Académique Documents
Professionnel Documents
Culture Documents
Summary
This paper presents two major bridges in South America which have been designed and built in
record periods in geotechnical and seismically critical areas combining effectively local workforce
and international experience.
1. Introduction
Important waterways as the Panama Canal and the Orinoco River allow for long distance transport
and development along those. With the growth of local communities and industry the dividing
effect of these global connections need to be alleviated by an increasing number of fixed crossings.
Therefore between 2000 and 2006 two important links were designed and built in Panama and in
Venezuela.
The Panama Canal [1] had from the beginning only two narrow roadway crossings using the lock
gates. Later in the 60ies the so-called “Puente de las Americas” was built as a four-lane tied arch at
the south entrance to the canal. Increasing traffic and safety issues on the narrow bridge led to the
planning of a second fixed highway link. The new crossing is located 15 kilometres north of the
Pacific coastline close to Panama City, Fig. 1.
Fig. 3 Layout
Fig. 4 Superstructure: a) Cross-Section,
b) Anchorage at stay cables
2.5 Construction
The bridge was delivered the 15th of August 2004 to the client within an astonishing 22 months after
the commencement of foundation works. The development of effective operating sequences, the
investment of suitable equipment, the use of innovative techniques and exceptional efforts of all
parties were the key factors to complete the project successfully.
Piles: Since no experience relating to pile capacity in the Cucaracha formation was available, at
each of the three foundations a test pile was implemented, whose load carrying capacity was
examined with multi-level Osterberg tests. At P2 and P3, the test piles were integrated into the final
foundation. The results of the load-carrying capacity confirmed the theoretically determined
parameters.
Foundations: Both the pile caps and the raft foundations were cast in one pour for time reasons and
to avoid additional construction joints in the highly reinforced elements. The largest foundation (T1)
with a concrete volume of 4500 m³ was cast in 40 hours. An active cooling system was
implemented to control excessive temperatures.
Towers: Casting heights of 4.1 m were achieved with self-climbing jump forms. The 4 levels of
working platforms on the jump form enabled several work activities, and reduced cycle times of 4
to 6 days.
Bridge Deck: The superstructure was built concurrently from both sides of the canal using the CIP
balanced cantilever method. Due to the tight schedule, all operational sequences had to be
optimised as much as possible. The form travelers were designed in such a way that they could be
used first as an integral part of the pier table falsework which was separated later in two
independent form travelers. Early post-tensioning and cable stressing was achieved by usage of
precast elements in the anchorage areas of tendons and steel delta frames. Easy lowering of the
external formwork equipped with a simple launching mechanism permitted to move the traveler
within hours. After the initial learning curve, a constant 4-day cycle for segment production was
achieved. The initially planned concrete overlay of 4 cm was replaced by an integrated concrete
overlay cast with the segment pour and grinded to the final smooth surface at the end of
construction.
2.6 Conclusion
The project’s ambitious schedule required the close coordination of the designer and the contractor
early in the design phase. The true advantages of design / build configurations could be seen during
the last phase of construction. The close interaction between the site and the designer allowed for
both design and construction optimisation. An architecturally and structurally perfect solution could
be realised in time and in spite of basic changes within the process.
3. Second Bridge over the Orinoco
3.1 Description [4]
The length of this bridge, carrying a 4 lane highway and a single track centric railway, is divided
into
- the south approach with 2 x 2 sections of 300 and 360 m, a total of 1320 m
- the main bridge, a back to back cable-stayed bridge with 1200 m and
- the north approach composed of 2 sections of 300 m, Fig. 5.
The approaches as well as the main bridge have similar cross-sections, composed of single cell steel
box under the railway line with cantilevering cross girders supported by diagonals at 3 m distance
and an edge girder to support the roadway. The deck consists of a concrete slab in full composite
action with the steel box and steel grid of cross girders and the edge girders. For the suspended deck
the edge girders are strengthened to carry the cable forces and distribute the vertical component to
2 cross girders, Fig. 6.
Fig. 5 Layout
3.3 Construction
Almost 6 of 12 months of a year, piling and pile cap construction had to be interrupted due to high
water levels in the river. The mobilization of huge pontoons, which are generally used in coastal
areas, characterized this site. The execution of 370 piles with a total length of 13.100 m took 1 ½
years. By the help of GPS systems the piles could be placed with tolerances in the range of
centimeters.
The bottom scaffolding of the pile caps consisted of lost precast panels and the pour of the cap was
done in two or three stages. Temperature management was important due to generally high outside
temperatures and the mass of concrete.
All piers and towers were built with sliding formwork. For the piers with constant section and
without special embedded elements or connections this approach was very efficient. For the tower
construction the sliding had to be interrupted two times to place the cross girders.
All steel was imported from Brazil. Preassembled portions of the segments were shipped from Belo
Horizonte to Ciudad Guayana. In several shops in Ciudad Guayana the 12 m long segments were
assembled and transported to the site at 16 km distance.
Behind both abutments an assembling yard was prepared
to assemble in 3 lines approach sections of 300 and 360 m
length, as well as a portion of 210 m for the main bridge.
Each bridge section was provided with steel noses at the
front and at the end and was slid by means of teflon plates
into its final position.
The centre of the main bridge (120 m to both sides at the
delta pier) was erected by the help of auxiliary trusses and
partially by sliding to its final position. Both main spans
were erected by the free cantilevering method with 4
derricks in use, Fig. 8. Fig. 8 Free cantilevering erection
Construction terminated in August 2006, and in November Hugo Chaves Frías and Luis Lula da
Silva inaugurated the structure with the official name “Puente Orinoquía”.
3.4 Conclusion
An important second link has been built over the Orinoco, which will improve the possibilities for
development of the whole region. With the official start in 2001 only a 5 year period was needed to
design and build this link, for a bridge crossing such a big and difficult river an extremely good
performance.
4. Acknowledgements
A great deal of international cooperation was the basis for the successful completion of both
structures.
Bridge over Panama Canal Orinoco River
Client Ministerio de Obras Públicas Corporación Venezolana de
(MOP) Guayana (CVG)
Contractor Bilfinger Berger Constructora Norberto Odebrecht
Preliminary Design TY Lin, San Francisco Leonhardt, Andrä und Partner,
Stuttgart, Germany / BRAVE
Caracas / Sao Paulo
Detailed Design Leonhardt, Andrä und Partner, BRAVE Caracas / Sao Paulo
Stuttgart, Germany
Construction Leonhardt, Andrä und Partner, Leonhardt, Andrä und Partner,
Engineering Stuttgart, Germany Stuttgart, Germany
Checking COWI, Copenhagen, Denmark Leonhardt, Andrä und Partner,
Stuttgart, Germany
Cables Freyssinet, Spain Freyssinet, Spain
Joints Maurer, Munich, Germany ---
Bearings Schreiber Metallbau Mainhardt Freysinnet, Spain
Traveler URSSA, Victoria, Spain Usiminas Mecánicas, Belo
Horizonte, Brazil
Heavy Lifts Freyssinet, Spain Dorman Long, UK
We thank all people who have been involved and appreciate that even in difficult situations the
cooperation was always good and governed by the common goal.
5. References
[1] McCullough, D.: The Path between the seas. The Creation of the Panama Canal 1870 – 1914.
Simon & Schuster (2005), ISBN 978-0743262132.
[2] Lustgarten, P.: Puente sobre el Orinoco – Proyecto de la Superestructura Colgante. Boletin N°
11, Asociación Venezolana de Ingeniería Estructural.
[3] Saul, R., Humpf, K., Hopf, S. and Patsch, A.: Die zweite Brücke über den Panamakanal –
eine Schrägkabelbrücke mit 420 m Mittelöffnung und Rekordbauzeit (The second Bridge
across the Panama Canal – a cable-stayed bridge with 420 m main span and a record braking
construction time). Beton- und Stahlbetonbau 100 (2005), pp. 225 – 235.
[4] Humpf, K. Second Bridge over the Orinoco – Design, Construction and Operation.
Proceedings of the 5th International Cable-Supported Bridge Operators’ Conference
(ICSBOC), New York 2006.