CARBON PORTFOLIO - PERU 2010

Energy, Industry and Others

SANTA CRUZ I Hydroelectric Power Plant H21


Description: Description: The plant will have an installed Capacity of 5.9 MW and a yearly average generation of 35.8 GWh. It is located in the north
east of Lima, basin of Blanco River (Santa Cruz), in the district of Colcas, Province of Caraz, Department of Ancash, Peru.

Current Status: Projects Benefits:


Earliest project start date: June 2007. Number of direct and indirect jobs generated:
Operation start date: February 2009. 150 jobs during construction and 6 permanent jobs in the operation
Project lifetime: 40 years. phase to the local people.
Current Status: EIA was approved by the Ministry of Energy and Mines. Sustainable development contribution: It displaces expensive generation
Concession and permission granted. PDD was registered at the EB. Pro- by fossil fuel while reducing greenhouse gas emissions.
ject obtained the National Letter of Approval from peruvian DNA. It supports local development by providing electricity and direct inves-
tment.
Estimated Annual Emission Reductions (tCO2/year): It purifies and cleans the water for irrigation.
An average of approximately 18,150 tCO2-equivalent. It contributes to Peru’s fiscal account through the payment of taxes.
CER´s negotiation:
Project Participant and Financing Sell Commitment.
Total project cost: UD$ 7,500,000

Contact Information:
Sources of finance to be sought or already identified:
Name: Guillermo Cox
Equity: NA. Company: Hidroeléctrica Santa Cruz S.A.C.
Debt: NA. Title: General Manager
Phone: (51-1) 242-4935
E-mail: gcox@gczingeniros.com

Rehabilitation of the CALLAHUANCA Hydroelectric Power Station H22


Description: The project consists of improving the hydroelectric use of the Santa Eulalia River, increasing the installed capacity of Callahuanca power
station in 7.5 MW. Currently the plant has a total installed capacity of 72.7 MW. This refurbishment will increase the plant’s capacity up to 82.5 MW.
It is located in the department of Lima, province of Huarochiri.
Current Status: Projects Benefits:
Earliest Project Start date: July 2005. Sustainable development contribution: Part of Callahuanca’s earnings
Operation Start date: October 2007. will deriver to reforestation of vulnerable-to-erosion mountain areas
Project lifetime: 20 years. with autochthonous species which will allow sustainable exploitation
Current Status: Financing negotiations are closed. The letter of appro- by local communities; specific training for plant’s remote control ope-
val was issued in January 2005 by the Designated National Authority rators; and increase of taxes paid to Peruvian Government.
on CDM. Environmental lmpact Assessment is not required. The project
has been registered as a CDM project. Awating issuance of CERs for pe- CER´s negotiation:
riod January 2008 to December 2008. Closed
CERs will be sold to ENDESA, mayor share holder of EDEGEL, the owner
Estimated Annual Emission Reductions (tCO2/year): company.
An average of approximately 18,189 tCO2-equivalent per year.

Project Participant and Financing


Contact Information:
Total project cost: US$ 13,800,000
Name: Jorge Castañeda Sánchez
Company: EDEGEL
Sources of finance to be sought or already identified: Title: Environmental auditor
Equity: NA Phone: (51-1) 2156369 Fax: (51-1) 445-4270
Debt: NA E-mail: jcastaneda@edegel.com

www.fonamperu.org