Additional of BAÑOS IV Hydroelectric Plant H55


Description: The project is a run-of-river hydropower plant located in the province of Huaral, department of Lima. The Project’s purpose is renewable
electricity generation to be supplied to Animón’s mining unit. The capacity installed will be 3.3 MW and the estimated yearly average generation
will be 20.7 GWh.
Current Status: Projects Benefits:
Earliest project start date: April 2007. Number of direct and indirect jobs generated:
Operation start date: May 2009. Employing local workforce in construction and plant management
Project lifetime: 40 years. (500 indirect jobs).
Current Status: Feasibility study completed. PIN is already develop. Sustainable development contribution:
PDD is under development. The project construction is in the finaliza- The project will create a source of renewable energy in a sustainable
tion process. way. Helping the country develop the hydrocarbon trade balance
through the reduction of oil imports to be used for electricity gene-
Estimated Annual Emission Reductions (tCO2/year): ration. Enabling SEIN to reserve thermal power plants only for stand-
An average of 11,323 tCO2-equivalent per year. by power generation, thus displacing expensive generation fuelled by,
while reducing GHG emissions.
Project Participant and Financing CER´s negotiation: Open.
Total project cost: US$ 6,000,000
Contact Information:
Sources of finance to be sought or already identified: Name: José Estela
Equity: 100% Company: Administradora Chungar S.A.
Debt: 0% Title: Energy Manager
Phone: (511) 219- 4000
E-mail: jestela@volcan.com.pe

CHANCAY Hydroelectric Plant H56


Description: Description: The project is a run-of-river hydropower plant located in the province of Huaral, department of Lima. The Project’s purpose
is renewable electricity generation to be supplied to Animón’s mining unit. The capacity installed will be 108.1 MW and the estimated yearly average
generation will be 550.4 gigawatts hour (GWh).
Current Status: Projects Benefits:
Earliest project start date: January 2012. Number of direct and indirect jobs generated:
Operation start date: January 2016. Employing local workforce in construction and plant management
Project lifetime: 40 years. (1,000 indirect jobs).
Status: Feasibility study completed. PIN is already developing. PDD is Sustainable development contribution:
under development. The construction of the project is planned to be- Helping the country develop the hydrocarbon trade balance through
gin on 2012. the reduction of oil imports to be used for electricity generation.
Enabling SEIN to reserve thermal power plants only for stand-by power
Estimated Annual Emission Reductions (tCO2/year): generation, thus displacing expensive generation fuelled by heavy fuel
An average of 294,143 tCO2equivalent per year. oil, diesel, coal and natural gas, while reducing GHG emissions.
CER´s negotiation:
Project Participant and Financing Open
Total project cost: US$ 185,000,000
Contact Information:
Sources of finance to be sought or already identified: Name: José Estela
Equity: 40% Company: Administradora Chungar S.A.
Debt: 60% Title: Energy Manager
Phone: (511) 219- 4000
E-mail: jestela@volcan.com.pe