Vous êtes sur la page 1sur 1

CARBON PORTFOLIO - PERU 2010

Energy, Industry and Others

HUASAHUASI I-II Hydro power Plant H59


Description: The project is a new hydroelectric power plant located in the province of Tarma, department of Junin. The Project’s purpose is re-
newable electricity generation to be supplied to the electric grid. The total installed capacity will be 15.86 MW and the estimated yearly average
generation will be 85 gigawatts hour (GWh).
Current Status: Projects Benefits:
Earliest project start date: 2010 Sustainable development contribution:
Operation start date: April 2012 It utilizes domestic and renewable resources, thus contributing to fuel
Project lifetime: 40 years diversification and resource independence for the Peruvian electricity
Current Status: Pre-Feasibility study completed. Concession granted by sector.
Ministry of Energy and Mines. PDD at validation. It supports local development through an annual contribution to be-
nefit local communities.
Estimated Annual Emission Reductions (tCO2/year): It displaces expensive generation fired by heavy fuel, diesel, coal and
An average of 60,613 tCO2-equivalent per year. natural gas, while reducing GHG emissions.
CER´s negotiation:
Project Participant and Financing
Sell Commitment.
Total project cost: US$ 30,810,000

Contact Information:
Sources of finance to be sought or already identified: Name: Guillermo Cox
Equity: NA. Company: Hidroeléctrica Santa Cruz S.A.C.
Debt: NA. Title: Presidente de Junta
Phone: (51-1) 2424935
E-mail: gcox@gczingenieros.com

NUEVO IMPERIAL Hydroelectric Power Plant H60


Description: The project is a new hydroelectric power plant located in the province of Cañete, department of Lima. The Project’s purpose is renewa-
ble electricity generation to be supplied to the electric grid. The total installed capacity will be 3.97 MW and the estimated yearly average generation
will be 25 gigawatts hour (GWh).

Current Status: Projects Benefits:


Earliest project start date: 2010 Sustainable development contribution:
Operation start date: May 2012 It utilizes domestic and renewable resources, thus contributing to fuel
Project lifetime: 40 years diversification and resource independence for the Peruvian electricity
Current Status: Pre-Feasibility study completed. Concession granted by sector.
Ministry of Energy and Mines. It supports local development through an annual contribution to be-
nefit local communities.
Estimated Annual Emission Reductions (tCO2/year): It displaces expensive generation fired by heavy fuel, diesel, coal and
An average of 15,285 tCO2-equivalent per year. natural gas, while reducing GHG emissions.

Project Participant and Financing CER´s negotiation:


Total project cost: US$ 6,000,000 Open

Sources of finance to be sought or already identified: Contact Information:


Equity: XX % Name: Alfredo Len Alvarez
Debt: XX % Company: Hidrocañete S.A.
Title: General Manager
Phone :
E-mail:

www.fonamperu.org

National Environmental Fund - Peru