Académique Documents
Professionnel Documents
Culture Documents
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 1
SUBSTRUCTURE
Information
A The work in this section comprises excavations,laterite fillings, strip and pad
foundation and other ancillary works up to and including ground floor slab
B The quantities are based on the architecturall and str uctural engineering
drawings provided as well as the assumptions stated below.
Soil Description
C The ground is assummed to be of firm bearing capacity and the ground
water level assumed to be below excavation
Location of Site
E The site is assummed to be free of bushes and shrubs. Certain items that
are unecessary have delibrately being left unquantified and priced.
Excavation
H Excavate1325mm deep pit for column bases 33 m3 536.49 17,704.17 536.49 17,704.17
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
SUBSTRUCTURE CONT'D
Filling
A 300mm Imported laterite filling to make up levels under ground floor slab,
deposited and compacted in150mm thick layer 35 m3 1,620.00 56,700.000 394.00 13,790.00 2,014.00 70,490.00
11trips (1trip= five cubic metre) @4500
F Lean concrete (1:5:10)in column base blinding 1 m3 14,002.00 14,002.000 6,606.06 6,606.06 20,608.06 20,608.06
52bags of cement @1550
0.82 trip (4.08cubic metre) of sand @ 10 000
trips ( 1.63 cubic metre) of local stone @ 35000
G Vertical sides of stub column 225mm x 225mm(Mat.rate assummes that) 24 m2 1,291.68 31,000.320 820.83 19,699.92 2,112.51 50,700.24
formwork in stub column is not reusable
H Edges of column base 300 mm high 17 m2 589.90 10,028.300 820.83 13,954.11 1,410.73 23,982.41
k Edges of 150mm ground floor bed 55 m 165.00 9,075.000 246.25 13,543.75 411.25 22,618.75
61 lengths of timber planks @ 630
9 length of 50 x 50 mm timber@ 200(1length=3.60m)
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
A 16mm diameter in stub columns(15lengths@2100:1length=11.7m) 0.28 Ton 136,582.16 38,243.005 37,430.00 10,480.40 174,012.16 48,723.40
B 8mm ditto(10 lengths@750) 0.04 Ton 195,117.38 7,804.695 37,430.00 1,497.20 232,547.38 9,301.90
C 12mm diameter in column bases(29lengths@1200:1length=11.7m) 0.28 Ton 138,750.14 38,850.039 37,430.00 10,480.40 176,180.14 49,330.44
D 6mm Steel wire fabric (to BSS 4483,1969.Ref A193 weighing 3.02kg/m2) 135 m2 391.20 52,812.000 113.04 15,260.40 504.24 68,072.40
Blockwork
225mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 86 m2 1,992.19 171,328.340 775.69 66,709.34 2,767.88 238,037.68
COLLECTIONS
SUBSTRUCTURE
CARRIED TO SUMMARY 1,109,060.82 505,958.10 1,615,018.92
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 2
FRAME , UPPER FLOOR AND STAIRCASE
Reinforcement:
High yield bar reinforcement to BS4449 in straight and
bent bars cut to length including hooks spacers,
distance blocks and tying wires in:
F 16mm Diameter in Columns (38 lengths@2100) 0.70 Ton 136,582.16 95,607.512 37,430.00 26,201.00 174,012.16 121,808.51
12mm Diameter ditto (12 lengths@1200) 0.12 Ton 138,750.14 16,650.017 37,430.00 4,491.60 176,180.14 21,141.62
N 8mm Diameter in columns (36 lengths750) 0.16 Ton 195,117.38 31,218.781 37,430.00 5,988.80 232,547.38 37,207.58
G 12mm Diameter in Suspended Slab (231 lengths 1200) 2.4 Ton 138,750.14 333,000.336 37,430.00 89,832.00 176,180.14 422,832.34
J 16mm Diameter in beams(76 lengths@2100) 1.39 Ton 136,582.16 189,849.202 37,430.00 52,027.70 174,012.16 241,876.90
L 12mm Diameter in ditto(3 length@1200 0.03 Ton 138,750.14 4,162.504 37,430.00 1,122.90 176,180.14 5,285.40
N 8mm Diameter in beams 78 lengths 750) 0.36 Ton 195,117.38 70,242.257 37,430.00 13,474.80 232,547.38 83,717.06
P 12mm Diameter in Staircase (29 lengths 1200) 0.30 Ton 138,750.14 41,625.042 37,430.00 11,229.00 176,180.14 52,854.04
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
A Vertical sides of 225 X 225mm X 3000m high columns(37nr) 97 m2 687.84 66,720.48 820.83 79,620.51 1,508.67 146,340.99
72 lengths of timber planks @ 630
27 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
Sawing timber with machine:=N=7178
B Soffit of upper floor slab 132 m2 877.66 115,851.12 985.00 130,020.00 1,862.66 245,871.12
35 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
124lengths of timber planks @ 630
79lengths of Bamboo props@140(1length=6m)
C Sides and soffit of beams 101 m2 917.11 92,628.11 985.00 99,485.00 1,902.11 192,113.11
31 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
101 lengths of timber planks @ 630
51 lengths of Bamboo props@140(1length=6m)
D Edges of upper floor slab 53 m 210.00 11,130.00 147.75 7,830.75 357.75 18,960.75
15 lengths of timber planks @ 630
E Soffit of stairflight and landing 13 m2 877.65 11,409.45 985.00 12,805.00 1,862.65 24,214.45
3 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
12 lengths of timber planks @ 630
6 lengths of Bamboo props@140(1length=6m)
F Sloping sides of stairflight with 150mm waist,300mm wide tread and 8 m 210.00 1,680.00 295.50 2,364.00 505.50 4,044.00
150mm risers
G Faces of risers 150mm high 26 m 114.54 2,978.04 147.75 3,841.50 262.29 6,819.54
COLLECTIONS
FRAME , UPPER FLOOR AND STAIRCASE CARRIED TO SUMMARY =N= 1,889,014.59 =N= 811,183.02 =N= 2,700,197.61
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 3
A 225mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 435 m2 1,992.19 866,602.650 709.20 308,502.00 2,701.39 1,175,104.65
B 150mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 51 m2 1,736.52 88,562.520 620.55 31,648.05 2,357.07 120,210.57
459 nr 150mm block@ 130
3915 nr 225mm blocks @ 140
81bags of cement @1550
3.18 trips(15.89 cubic metre) of sand @10000
C Reinforced in-situ concrete 1:2:4-20mm agg.)poured into formwork in lintels 4 m3 19,616.14 78,464.560 6,606.06 26,424.24 26,222.20 104,888.80
24bags of cement @1550
0.35 trips(1.76cubic metre) of sand @10000
0.70trips(3.53cubic metre) of sand @35000
D Sides and soffit of lintels 58 m2 502.98 29,172.840 820.33 47,579.14 1,323.31 76,751.98
74 lengths of 3.6m long timber plank @ 630
Reinfocement
E 12mm reinforcement in lintels 0.32 Ton 138750.11 44,400.036 37,430.00 11,977.60 176,180.11 56,377.64
31 lengths (1 length=11.7m long) @ 1170
F 8mm reinforcement in lintels 0.16 Ton 195,117.38 31,218.781 37,430.00 5,988.80 232,547.38 37,207.58
35 lengths@ 770
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 4
ROOF
Roof Trusses
Sawn,hardwood timber trusses
A 50 X 150mm Tie beams @1200mm c/c(30 lengths @1900; 1length=5.4m 159 m 422.22 67,132.980 212.76 33,828.84 634.98 100,961.82
long)
B 50 x 150mm Rafters@1200mm c/c(41 lengths) 220 m 422.22 92,888.400 212.76 46,807.20 634.98 139,695.60
C 50 x 150 mm Kingposts,struts and ties(106 lengths) 571 m 422.22 241,087.620 212.76 121,485.96 634.98 362,573.58
D 75 x 100mm Wall plate( 24 lengths;1length=3.6m) 84 m 111.11 9,333.240 212.760 17,871.84 323.87 27,205.08
E 75 x 50mm Purlins(92 lengths@ 250; 1length =3.6m) 329 m 69.44 22,845.760 212.760 69,998.04 282.20 92,843.80
F 50 x 50mm noggins@1200c/c( 137lengths@200;1length =3.6m) 492 m 55.56 27,335.520 212.760 104,677.92 268.32 132,013.44
G 75 x 100mm ridge board(3 lengths) 8 m 111.11 888.880 212.760 1,702.08 323.87 2,590.96
Roof Covering
0.55mm longspan aluminium corrugated roofing sheets with one and
a half corrugation side laps and 300mm end laps(measured net) fixed
to purlins with galvanized steel screws
ROOF
CARRIED TO SUMMARY =N= 921,271.82 =N= 565,240.72 =N= 1,486,512.54
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 5
WINDOWS
ITEM
Aluminium casement window
Supply and fix the following to plugged wall in aluminium casement windows
with cream colour foreign profile and 5mm thick tainted glass (Rate is
inclusive of "mosquito netting" )
B Projected window for stairhall size 600 x 1500mm high 4 Nr. 9,000.00 9,000.00 36,000.00
C Ditto size 900 x 1200 mm high overall 2 Nr. 21,600.00 21,600.00 43,200.00
13,200.00
D Ditto size 1200 x1200 mm high overall 12 Nr. 24,000.00 24,000.00 288,000.00
13,800.00
WINDOWS
CARRIED TO SUMMARY =N= 688,800.00
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 6
DOORS AND IRONMONGERY
Supply and fix the following doors and associated frames.Door and frame
shall be in approved hardwood and shall be finished with one coat sanding sealer
and two coats EU made Polygarde wood lacquer.
(Rates include all ironmongery and architraves) See doors schedule
F STEEL DOORS
G Locally fabricated mild steel solid panel security door fabricated with 8 Nr 37,200.00 37,200.00 297,600.00
2mm chequer plate
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 7
FLOOR, WALL AND CEILING FINISHINGS
Floor Finishings
B 300 x 300 x 6 mm thick non - slip ceramic tiles 45 m2 1200.00 54,000.00 689.50 31,027.50 1,889.50 85,027.50
Floor Finishings carried to Finishings Summary =N= 433,614.60 =N= 167,548.50 =N= 601,163.10
Wall Finishings
E Walls not exceeding 100mm width 140 m 14.50 2,030.00 427.50 59,850.00 442.00 61,880.00
38bags of cement@1550
1.65 trips(8.24m3) of sand@10000
200 x 300 x 6mm thick approved colour glazed ceramic tiles with grouted
joints laid to square pattern on cement and sand (1:4) backing on:
G 30mm floated backing to receive ceramic wall tiles 151 m2 392.00 59,192.00 392.00 59,192.00
32 bags of cement@1550
0.911trip(4.53m3) of sand@10000
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
Wall Finishings(contd.)
Walls exceeding 300mm width 287 m2 145.03 41,623.61 342.02 98,159.74 487.05 139,783.35
Walls not exceeding 100mm width 140 m 14.50 2,030.00 260.10 36,414.00 274.60 38,444.00
A 11bags of cement@1550
0.45trip(2.28m3) of sand@10000
B
COLLECTIONS
Wall Finishings carried to Finishings Summary =N= 341,784.63 =N= 515,378.92 =N= 857,163.55
Ceiling Finishings
PVC celing boards fixed to timber noggings (measured separately) 186 m2 1,440.00 267,840.00 689.50 128,247.00 2,129.50 396,087.00
Ceiling Finishings carried to Finishings Summary =N= 282,923.12 =N= 174,057.96 =N= 456,981.08
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
B Ditto, combined treads and risers average 450mm girth 20 m2 1080.00 21,600.00 689.50 13,790.00 1,769.50 35,390.00
F Ditto to waist and sides of steps 11 m2 145.03 1,595.33 440.49 4,845.39 585.52 6,440.72
44mm cement and sand (1:4) screeding to receive glazed vitrified tiles on:
G Staircase landing 4 m2 145.03 580.12 - 145.03 580.12
H Ditto, combined treads and risers average 450mm girth 20 m2 145.03 2,900.60 - 145.03 2,900.60
Staircase Finishing carried to Finishing Summary =N= 33,751.62 =N= 29,762.70 =N= 63,514.32
FINISHINGS SUMMARY
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 8
PAINTING
B Walls not exceeding 100mm width 140 m 12.96 1,814.40 80.15 11,221.00 93.11 13,035.40
10nr 20-litre drums of emulsion paint@7200
D Surfaces not exceeding 100mm girth 140 m 52.26 7,316.40 80.15 11,221.00 132.41 18,537.40
10nr 20-litre drums of textured paint @ 13000
F Soffit of stair flight and landing 19 m2 522.60 9,929.40 137.90 2,620.10 660.50 12,549.50
G Ditto to waist and sides of steps 11 m2 522.60 5,748.60 137.90 1,516.90 660.50 7,265.50
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR.8
PLUMBING AND SANITARY FITTINGS
Sanitary Wares
All fixtures and sanitary fittings shall be"Twyford"
or equal and approved.
A Allow a sum for the supply and instalation of all plumbing and sanitary fittings 253,584.00
Allow a sum for the construction of 1nr septic tank,1nr soakaway pit
and 4nr manholes Sum 177,943.72
ELEMENT NR. 10
ELECTRICAL INSTALLATIONS
Allow a sum of for the electrical works in the building Sum 983,800.00
ELECTRICAL INSTALLATIONS
CARRIED TO SUMMARY =N= 983,800.00
ELEMENT NR.9
Allow a sum for the fabrication and installation of finished mild steel
balustrades at balcony and stairhall. Sum 88,514.00
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
SUMMARY
ESTIMATED COST FOR SEMI DETACHED 3-BEDROOM DUPLEX =N= 6,553,448.78 =N= 3,497,909.69 =N= 13,310,451.04
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 1
SUBSTRUCTURE
Information
A The work in this section comprises excavations,laterite fillings, strip
foundation and other ancillary works up to and including ground floor slab
Soil Description
C The ground is assummed to be of firm bearing capacity and the ground
water level assumed to be below excavation
Location of Site
E The site is assummed to be free of bushes and shrubs. Certain items that
are unecessary have delibrately being left unquantified and priced.
Excavation
G Filling to make up level with surplus excavated material 7 m3 240.00 1,680.00 240.00 1,680.00
PREPARED BY 08038967752
SEPT. 2010 19
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
SUBSTRUCTURE CONT'D
Filling
A 300mm Imported laterite filling to make up levels under ground floor slab,
deposited and compacted in 300mm thick layer() 5 m3 900.00 4,500.000 250.00 1,250.00 1,150.00 5,750.00
C Plain in-situ concrete (1:3:6 - 20mm agg.) in 225mm thick ground floor bed 7 m3 14,040.00 98,280.000 4,191.66 29,341.62 18,231.66 127,621.62
Blockwork
D 150mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 39 m2 1,416.00 55,224.000 393.75 15,356.25 1,809.75 70,580.25
351nr 225mm blocks @ 130
5bags of cement@1550
0.21trip (1.05cubic metre)of sand @10000
COLLECTIONS
PREPARED BY 08038967752
SEPT. 2010 20
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 2
A 150mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 143 m2 1,416.00 202,488.000 324.00 46,332.00 1,740.00 248,820.00
B Reinforced insitu concrete 1:3:6-20mm agg.)poured into formwork in lintels 0.26 m3 14,040.00 3,650.400 4,023.99 1,046.24 18,063.99 4,696.64
C Sides and soffit of lintels 8 m2 771.75 6,174.000 360.00 2,880.00 1,131.75 9,054.00
Reinfocement
3 lengths@ 770
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 3
PREPARED BY 08038967752
SEPT. 2010 21
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ROOF
Roof Trusses
Sawn,hardwood timber trusses
A 50 X 100mm Tie beams @1200mm c/c(10 lengths @820; 1length=5.4m long) 53 m 151.85 8,048.050 129.60 6,868.80 281.45 14,916.85
B 50 x 100mm Rafters@1200mm c/c(13 lengths) 68 m 151.85 10,325.800 129.60 8,812.80 281.45 19,138.60
C 100 x 50mm Struts and Tie(21 lengths@820) 112 m 151.85 17,007.200 129.60 14,515.20 281.45 31,522.40
D 75 x 100mm Wall plate(5 lengths@550) 26 m 111.11 2,888.860 129.600 3,369.60 240.71 6,258.46
E 75 x 50mm Purlins(23 lengths@ 250; 1length =3.6m) 81 m 69.44 5,624.640 129.600 10,497.60 199.04 16,122.24
F 50 x 50mm noggins(45 lengths@200;1length =3.6m) 160 m 55.56 8,889.600 129.600 20,736.00 185.16 29,625.60
G 75 x 100mm ridge board(1 length) 3 m 111.11 333.330 129.600 388.80 240.71 722.13
Roof Covering
0.55mm longspan aluminium corrugated roofing sheets with one and
a half corrugation side laps and 300mm end laps(measured net) fixed
to purlins with galvanized steel screws
K Capping to hips and ridge 15 m 1,300.00 19,500.000 100.00 1,500.00 1,400.00 21,000.00
ROOF
CARRIED TO SUMMARY =N= 155,884.07 =N= 91,718.97 =N= 247,603.04
PREPARED BY 08038967752
SEPT. 2010 22
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 4
WINDOWS
Supply and fix the following to plugged wall in aluminium sliding windows
with cream colour profile and 5mm thick tinted glass (Rate is inclusive of .
"mosquito netting" ) See windows schedule
B Ditto size 600 x 600 mm high overall( W2) 1 Nr. 4,500.00 4,500.00 4,500.00
C Ditto size 1200 x 1425 mm high overall(W3) 4 Nr. 13,500.00 13,500.00 54,000.00
Metal Window
E Mild steel window fabricated with 25 x 25 1mm thick hollow steel pipe 1 nr 9,120.00 9,120.00 9,120.00
WINDOWS
CARRIED TO SUMMARY =N= 80,020.00
ELEMENT NR. 5
DOORS AND IRONMONGERY
Supply and fix the following doors and associated frames.Door and frame
shall be in approved hardwood
(Rates include all ironmongery ) See doors schedule
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
PREPARED BY 08038967752
SEPT. 2010 23
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ELEMENT NR. 6
FLOOR, WALL AND CEILING FINISHINGS
Floor Finishings
Ceramic Tile
A 300 x 300 x 6 mm thick non - slip ceramic tiles 8 m2 1000.00 8,000.00 345.60 2,764.80 1,345.60 10,764.80
C 44mm cement sand screeding trowelled smooth 28 m2 568.50 15,918.00 200.00 5,600.00 768.50 21,518.00
11bags of cement@1550
0.35trip(1.77m3) of sand@10000
Floor Finishings carried to Finishings Summary =N= 28,466.00 =N= 9,286.40 =N= 37,752.40
Wall Finishings
E Walls not exceeding 100mm width 32 m 12.86 411.52 249.99 7,999.68 262.85 8,411.20
8 bags of cement@1550
0.35trip(1.78m3) of sand@10000
200 x 300 x 6mm thick approved colour glazed ceramic tiles with grouted
joints laid to square pattern on cement and sand (1:4) backing on:
PREPARED BY 08038967752
SEPT. 2010 24
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
Wall Finishings(contd.)
A Walls eceeding 300mm width 74 m2 120.86 8,943.64 230.40 17,049.60 351.26 25,993.24
B Walls not exceeding 300mm width 32 m 12.86 411.52 249.60 7,987.20 262.46 8,398.72
5bags of cement@1550
0.20trip(0.98m3) of sand@10000
COLLECTIONS
Wall Finishings carried to Finishings Summary =N= 55,641.06 =N= 73,004.48 =N= 128,645.54
Ceiling Finishings
C Asbestos celing boards fixed to timber noggings(measured separately) 49 m2 1,050.00 51,450.00 231.49 11,343.01 1,281.49 62,793.01
34nr of 1.2x1.2m Asbestos boards
PREPARED BY 08038967752
SEPT. 2010 25
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
FINISHINGS SUMMARY
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
PREPARED BY 08038967752
SEPT. 2010 26
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ELEMENT NR. 7
PAINTING
B Walls not exceeding 300mm width 32 m 3.00 96.00 40.69 1,302.08 43.69 1,398.08
D Surfaces not exceeding 300mm girth 32 m 13.40 428.80 40.69 1,302.08 54.09 1,730.88
PREPARED BY 08038967752
SEPT. 2010 27
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR.8
PLUMBING AND SANITARY FITTINGS
Sanitary Wares
All fixtures and sanitary fittings shall be"Twyford"
or equal and approved.
A Allow a sum for the supply and instalation of all plumbing and sanitary fittings 30,000.00
ELEMENT NR. 10
ELECTRICAL INSTALLATIONS
D Allow a sum of for the electrical works in the building Sum 50,000.00
ELEMENT NR.9
ELEMENT NR.9
DEMOLITION
PREPARED BY 08038967752
SEPT. 2010 28
COST ESTIMATES FOR PROPOSED 2-BEDROOM BUNGALOW FOR Dr.MIKE EGBEBIKE
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
SUMMARY
L DEMOLITION 80,000.00
ESTIMATED COST FOR 2-BEDROOM BUNGALOW =N= 772,883.93 =N= 343,554.73 =N= 1,510,264.63
PREPARED BY 08038967752
SEPT. 2010 29
COST ESTIMATES FOR PROPOSED SEMI-DETACHED 6-BEDROOM DUPLEX FOR MR AMOBI T. OGUM
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 1
SUBSTRUCTURE
Information
A The work in this section comprises excavations,laterite fillings, strip and pad
foundation and other ancillary works up to and including ground floor slab
B The quantities are based on the architecturall and str uctural engineering
drawings provided as well as the assumptions stated below.
Soil Description
C The ground is assummed to be of firm bearing capacity and the ground
water level assumed to be below excavation
Location of Site
D The site is located in Awka.The rates are based on current market prices
of materials and labour within Awka Metropolis .
E The site is assummed to be free of bushes and shrubs. Certain items that
are unecessary have delibrately being left unquantified and priced.
Excavation
H Excavate1200 mm deep pit for column bases 49 m3 590.90 28,954.10 590.90 28,954.10
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
SUBSTRUCTURE CONT'D
Filling
A Filling to make up levels under ground floor slab with imported laterite
deposited and compacted in150mm thick layer to a depth of 450mm 70 m3 1,260.00 88,200.000 472.73 33,091.10 1,732.73 121,291.10
20 trips (1trip= five cubic metre) @4500
B Plain in-situ concrete (1:3:6 - local stone agg.) in 225mm thick foundation
footing . 19 m3 12,924.80 245,571.200 4,056.00 77,064.00 16,980.80 322,635.20
81bags of cement @1520
1.79 trips (9 cubic metre) of sand @ 10 000
3.60 trips ( 18cubic metre) of local stone @ 30000
E 350mm thick Column bases 25 m3 15,524.80 388,120.000 4,056.00 101,400.00 19,580.80 489,520.00
F 225 X 225mm Ground beams 6 m3 15,524.80 93,148.800 4,056.00 24,336.00 19,580.80 117,484.80
214 bags of cement @1550
3.16 trip (16cubic metre) of sand @ 10 000
6.17 trips ( 31 cubic metre) of local stone @ 30 000
G Vertical sides of stub column 62 m2 1,032.47 64,013.140 625.92 38,807.04 1,658.39 102,820.18
J Sides of ground beams(It is assumed that beams shall rest on blockwork) 51 m2 759.04 38,711.040 565.21 28,825.71 1,324.25 67,536.75
k Edges of 150mm ground floor bed 75 m 208.00 15,600.000 162.50 12,187.50 370.50 27,787.50
175 lengths of timber planks @ 630
62 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
B 8mm ditto (25 lengths@750) 0.11 Ton 173,000.00 19,030.000 24,700.00 2,717.00 197,700.00 21,747.00
C 12mm diameter in column bases ( 82 lengths@1200:1length=11.7m) 0.85 Ton 115,625.00 98,281.250 24,700.00 20,995.00 140,325.00 119,276.25
D 12mm diameter in ground beams (39 lengths@1200:1length=11.7m) 0.40 Ton 115,625.00 46,250.000 24,700.00 9,880.00 140,325.00 56,130.00
Blockwork
E 150mm Hollow sandcrete blockwork in cement and sand (1:6) mortar 23 m2 1,460.44 33,590.120 786.50 18,089.50 2,246.94 51,679.62
F 225mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 192 m2 1,736.36 333,381.120 786.50 151,008.00 2,522.86 484,389.12
COLLECTIONS
SUBSTRUCTURE
CARRIED TO SUMMARY 2,233,105.47 891,599.27 3,124,704.74
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 2
FRAME , UPPER FLOOR AND STAIRCASE
Reinforcement:
High yield bar reinforcement to BS4449 in straight and
bent bars cut to length including hooks spacers,
distance blocks and tying wires in:
F 16mm Diameter in Columns (120 lengths@2000) 2.21 Ton 108,399.00 239,561.790 24,700.00 54,587.00 133,099.00 294,148.79
N 8mm Diameter in columns (114 lengths750) 0.58 Ton 173,210.00 100,461.800 24,700.00 14,326.00 197,910.00 114,787.80
G 12mm Diameter in Suspended Slab (482 lengths 1200) 5.00 Ton 115,625.00 578,125.000 24,700.00 123,500.00 140,325.00 701,625.00
J 16mm Diameter in beams(62 lengths@2000) 1.14 Ton 108,399.00 123,574.860 24,700.00 28,158.00 133,099.00 151,732.86
L 20mm Diameter in ditto(6 length@1200 0.16 Ton 117,932.71 18,869.234 24,700.00 3,952.00 142,632.71 22,821.23
M 8mm Diameter in beams (64 lengths 750) 0.29 Ton 173,210.00 50,230.900 24,700.00 7,163.00 197,910.00 57,393.90
M 10mm Diameter in beams( 9 lengths ) 0.06 Ton 117,937.62 7,076.257 24,700.00 1,482.00 142,637.62 8,558.26
P 12mm Diameter in Staircase (30 lengths 1200) 0.30 Ton 115,625.00 34,687.500 24,700.00 7,410.00 140,325.00 42,097.50
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
A Vertical sides of 225 X 225mm X 3000m high columns(90nr) 243 m2 544.35 132,277.05 625.92 152,098.56 1,170.27 284,375.61
B Vertical sides of 450 X 450mm X 5900m high columns(4nr) 43 m2 544.35 23,407.05 625.92 26,914.56 1,170.27 50,321.61
C Soffit of upper floor slab 285 m2 868.70 247,579.50 650.00 185,250.00 1,518.70 432,829.50
274 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
268 lengths of timber planks @ 630
171 lengths of Bamboo props@140 (1length= 6m- 9m)
D Sides and soffit of beams 187 m2 762.00 142,494.00 650.00 121,550.00 1,412.00 264,044.00
58 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
187lengths of timber planks @ 630
187 lengths of Bamboo props@140(1length=6m)
E Edges of upper floor slab 103 m 303.13 31,222.39 361.14 37,197.42 664.27 68,419.81
43 lengths of timber planks @ 630
71 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
F Soffit of stairflight and landing 13 m2 762 9,906.00 650.00 8,450.00 1,412.00 18,356.00
3 lengths of 50 x 50 mm timber@ 200(1length=3.60m)
12 lengths of timber planks @ 630
6 lengths of Bamboo props@140(1length=6m)
G Sloping sides of stairflight with 150mm waist,300mm wide tread and 12 m 210.00 2,520.00 383.50 4,602.00 593.50 7,122.00
150mm risers
H Faces of risers 150mm high 20 m 114.54 2,290.80 192.08 3,841.60 306.62 6,132.40
COLLECTIONS
FRAME , UPPER FLOOR AND STAIRCASE CARRIED TO SUMMARY =N= 3,110,466.53 =N= 1,137,410.14 =N= 4,247,876.67
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 3
A 225mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 760 m2 1,736.36 1,319,633.600 786.50 597,740.00 2,522.86 1,917,373.60
B 150mm Hollow sandcrete blockwork in cement and sand (1:6)mortar 160 m2 1,460.44 233,670.400 786.50 125,840.00 2,246.94 359,510.40
1512 nr 150mm block@ 130
7182 nr 225mm blocks @ 150
176 bags of cement @1550
7.39 trips(37 cubic metre) of sand @10000
C Reinforced in-situ concrete 1:2:4-20mm agg.)poured into formwork in lintels 9 m3 15,524.80 139,723.200 4,056.00 36,504.00 19,580.80 176,227.20
55 bags of cement @1550
0.81 trips (4.06cubic metre) of sand @10000
1.58 trips (7.91cubic metre) of sand @30000
D Sides and soffit of lintels 119 m2 759.04 90,325.760 565.21 67,259.99 1,324.25 157,585.75
143 lengths of 3.6m long timber plank @ 630
Reinfocement
E 12mm reinforcement in lintels 0.62 Ton 115,625.00 71,687.500 24,700.00 15,314.00 140,325.00 87,001.50
60 lengths (1 length=11.7m long) @ 1170
F 8mm reinforcement in lintels 0.31 Ton 195,117.38 60,291.270 24,700.00 7,632.30 219,817.38 67,923.57
67 lengths@ 770
ITEM DESCRIPTION QTY UNIT MAT.RATE MAT.AMOUNT LAB.RATE LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 4
ROOF
Roof Trusses
Sawn,hardwood timber trusses
A 50X 150mm Tie beams @1200mm c/c( 62lengths @1700; 1length=5.4m 333 m 314.81 104,831.730 140.40 46,753.20 455.21 151,584.93
long)
B 50 x 150mm Rafters@1200mm c/c(83 lengths) 448 m 314.81 141,034.880 140.40 62,899.20 455.21 203,934.08
C 50 x 150 mm Kingposts,struts and ties(158 lengths) 855 m 314.81 269,162.550 140.40 120,042.00 455.21 389,204.55
D 75 x 100mm Wall plate( 36 lengths@700;1length=3.6m) 130 m 194.44 25,277.200 140.40 18,252.00 334.84 43,529.20
E 50 x 75mm Purlins(186 lengths@ 250; 1length =3.6m) 669 m 69.44 46,455.360 140.40 93,927.60 209.84 140,382.96
F 50 x 50mm noggins@1200c/c( 268lengths@200;1length =3.6m) 968 m 55.56 53,782.080 140.40 135,907.20 195.96 189,689.28
G 75 x 100mm ridge board(6 lengths) 20 m 111.11 2,222.200 140.40 2,808.00 251.51 5,030.20
H 300mm Fascia(25 lengths @1200) 91 m 399.99 36,399.090 140.400 12,776.40 540.39 49,175.49
Roof Covering
0.55mm longspan aluminium corrugated roofing sheets with one and
a half corrugation side laps and 300mm end laps(measured net) fixed
to purlins with galvanized steel screws
K Capping to hips and ridges 82 m 1,560.00 127,920.000 204.88 16,800.16 1,764.88 144,720.16
L Flat sheet cladding to fascia 91 m 250 22,750.000 325.00 29,575.00 575.00 52,325.00
ROOF
CARRIED TO SUMMARY =N= 1,683,755.09 =N= 751,045.88 =N= 2,434,800.97
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 5
WINDOWS
ITEM
Aluminium sliding window
Supply and fix the following to plugged wall in aluminium sliding windows
with cream colour foreign profile and 5mm thick tainted glass (Rate is
inclusive of "mosquito netting" )
B Projected window for stairhall size 1200 x 3000mm high (W6) 2 Nr. 26,750.00 53,500.00
C Ditto size 600 x 900 mm high overall (W2) 6 Nr. 7,490.00 44,940.00
E Projected window size 3000 x 1200 mm high overall (W4) 4 Nr 26,750.00 107,000.00
WINDOWS
CARRIED TO SUMMARY =N= 729,740.00
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 6
DOORS AND IRONMONGERY
Supply and fix the following doors and associated frames.Door and frame
shall be in Mahogany and shall be finished with one coat sanding sealer
and two coats EU made Polygarde wood lacquer.
(Rates include all ironmongery and architraves) See doors schedule
C Aluminium swing doors (2panels) glazed with 5mm thick glass using
foreign lightweight profile size 1800 x 2100 (D4) 2 Nr 96,300.00 192,600.00
STEEL DOORS
G Locally fabricated mild steel solid panel security door fabricated with Nr 65,000.00 0.00
2mm chequer plate(1800 X 2100)
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 7
FLOOR, WALL AND CEILING FINISHINGS
Floor Finishings
B 300 x 300 x 6 mm thick non - slip ceramic tiles in kitchen,store and toilets 80 m2 900.00 72,000.00 455.00 36,400.00 1,355.00 108,400.00
Floor Finishings carried to Finishings Summary =N= 788,924.40 =N= 253,435.00 =N= 1,042,359.40
Wall Finishings
E Walls not exceeding 100mm width 293 m 11.72 3,433.96 203.13 59,517.09 214.85 62,951.05
96 bags of cement@1520
4.15 trips(20 .76 m3) of sand@10 000
200 x 300 x 6mm thick approved colour glazed ceramic tiles with grouted
joints laid to square pattern on cement and sand (1:4) backing on:
F Walls in toilets and kitchen 230 m2 820.00 188,600.00 455.00 104,650.00 1,275.00 293,250.00
G 30mm floated backing to receive ceramic wall tiles 230 m2 379.20 87,216.00 379.20 87,216.00
48 bags of cement@1520
1.38 trip(6.9m3) of sand@10 000
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
Wall Finishings(contd.)
A Walls exceeding 300mm width 643 m2 117.20 75,359.60 169.00 108,667.00 286.20 184,026.60
B Walls not exceeding 100mm width 293 m 11.72 3,433.96 203.13 59,517.09 214.85 62,951.05
C 450mm wide surfaces of isolated columns 51 m2 117.20 5,977.20 407.85 20,800.35 525.05 26,777.55
59 bags of cement@1550
2.57 trip(12.83m3) of sand@10000
COLLECTIONS
Wall Finishings carried to Finishings Summary =N= 547,790.32 =N= 618,143.53 =N= 1,165,933.85
Ceiling Finishings
D PVC celing boards fixed to timber noggings (measured separately) 343 m2 1,250.00 428,750.00 494.00 169,442.00 1,744.00 598,192.00
17 bags of cement@1550
0.74 trip(3.71m3) of sand@10000
Ceiling Finishings carried to Finishings Summary =N= 462,152.00 =N= 250,359.20 =N= 712,511.20
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
B Ditto, combined treads and risers average 450mm girth 18 m2 850.00 15,300.00 455.00 8,190.00 1,305.00 23,490.00
F Ditto to waist and sides of steps 12 m 35.00 420.00 203.13 2,437.56 238.13 2,857.56
44mm cement and sand (1:4) screeding to receive glazed vitrified tiles on:
G Staircase landing 4 m2 559.20 2,236.80 - 559.20 2,236.80
H Ditto, combined treads and risers average 450mm girth 18 m2 559.20 10,065.60 - 559.20 10,065.60
Staircase Finishing carried to Finishing Summary =N= 32,946.00 =N= 16,131.76 =N= 49,077.76
FINISHINGS SUMMARY
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR. 8
PAINTING
B Walls not exceeding 100mm width 293 m 6.00 1,758.00 130.00 38,090.00 136.00 39,848.00
32 nr 20-litre drums of emulsion paint @ 3000
D Surfaces not exceeding 100mm girth 293 m 200.00 58,600.00 39.00 11,427.00 239.00 70,027.00
F Soffit of stairflight and landing 19 m2 60.00 1,140.00 130.00 2,470.00 190.00 3,610.00
G Ditto to waist and sides of steps 12 m 60.00 720.00 39.00 468.00 99.00 1,188.00
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR.8
PLUMBING AND SANITARY FITTINGS
Sanitary Wares
All fixtures and sanitary fittings shall be"Twyford"
or equal and approved.
A Allow a sum for the supply and instalation of all plumbing and sanitary fittings 453,829.80
Allow a sum for the construction of 1nr septic tank,1nr soakaway pit
and 10nr manholes(septic tank for a mximum of 16users) Sum 270,397.56
ELEMENT NR. 10
ELECTRICAL INSTALLATIONS
ELECTRICAL INSTALLATIONS
CARRIED TO SUMMARY =N= 1,026,772.00
ELEMENT NR.9
Allow a sum for the fabrication and installation of finished mild steel
balustrades at balcony and stairhall. Sum 300,456.00
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
ELEMENT NR 10
A Allow a sum for all works associated with the fencing and construction sum 1,116,303.52
of gates based on the following assumptions:
B Allow a sum for the supply and laying of 80mm thick paving stone Sum 1,727,767.52
on 350mm laterite filling and 50mm thick sharp sand
ITEM DESCRIPTION QTY UNIT MATERIAL MAT.AMOUNT LABOUR LAB.AMOUNT RATE AMOUNT
SUMMARY
ESTIMATED COST FOR SEMI DETACHED 6-BEDROOM DUPLEX =N= 11,773,514.66 =N= 5,627,138.08 =N= 25,800,563.13