Académique Documents
Professionnel Documents
Culture Documents
1. INTRODUCTION:
The transformer is a vital apparatus in the electrical equipment in every stage viz.
Generation, transmission, distribution and utilization of electricity. Failure of a transformer in
the chain causes interruption in electricity supply and dislocation of all the works going on.
Care and maintenance of the transformer therefore requires attention from time to time to
avoid sudden, unpredicted failure. If a developing defect is detected early, remedial action
can be taken immediately and service continuity of the transformer maintained.
The troubles which would occur in service, methods of detecting them early and remedies
& repairs to bring back the transformers in service are described below.
The transformer in service may fail according to nature of troubles developed in the
transformer itself or due to some external causes. The external causes may be excessive
overloading on the transformer, short circuits near the transformer, failure of other auxiliary
equipment nearby, failure of its controlling breaker, failure of protection to operate and so on.
Internal causes of failure are failures of transformer insulation, failure of winding due to
excessive heating, internal short circuits, failure of winding joints, ingress of moisture in the
oil and insulation, deterioration of insulating oil, and failure of other auxiliary internal equipment,
such as reactor of the tap changer, contacts of the tap changer etc.
Failure of transformer can also take place if proper care has not been taken during its
erection. While receiving the transformer, unloading, storing and assembling, the instructions
of the manufacturer should be followed strictly. If the transformer is received with oil inside,
all care as if the transformer is in service, is required with nitrogen gas. A very strict watch is
required on maintenance of pressure and purity of gas, all the time the transformer is stored.
The auxiliary equipment such as radiators, conservator, piping, explosion vent are to be stored
with proper care. Conservator and radiators should be maintained airtight. The HT and LT
bushings should be immediately tested and H. T. bushings stored vertically. Similarly while
assembling the transformer every equipment such as H. T. & L. T. bushings of the transformer
windings, oil tap changer, diverter tank, connections of lead with bushing etc. should be
tested separately according to standards specified.
If the erection and commissioning is done properly, maintenance is required on the
transformer to judge the performance in service. It consist of regular inspection, testing and
reconditioning wherever necessary.
2. Factors affecting the life of the transformer : (i.e. factors responsible for degradation
of insulation.)
The normal expected life of a power transformer is about 35 years. Life of a power
transformer essentially means life of its insulation system comprising mainly :
i) Solid dielectric [paper, varnish, cloth, pressboard];
ii) Liquid dielectric [mineral oil].
A. Effect of Moisture
Transformer oil readily absorbs moisture from the air. This water in oil decreases the
dielectric strength of the oil as well as that of the insulating paper which absorbs and stores
the moisture due to higher affinity of water to paper than to oil.
254
B. Effect of Oxygen
Oxygen may be present inside the transformer due to air remaining in oil, air pockets
trapped in the winding etc. The oxygen reacts on the cellulose of the insulating paper, and the
decomposition products of the cellulose lead to the formation of organic acids which dissolve
in oil and consequently form sludge. This sludge blocks the free circulation of the oil. Thus the
adverse effect of oxygen, which may be aggravated by catalytic action between hot oil and
bare copper, increases the operating temperature.
D. Effect of Varnishes
Some varnishes, particularly of the oxidizing type, enter readily and react with the
transformer oil and precipitate sludge on the windings. Synthetic varnishes having acid-
inhibiting properties generally delay the natural formation of acid and sludge in the oil. This
factor needs consideration during maintenance.
F. Aging of Insulation
The aging of insulating materials is defined as “irreversible negative change of pertinent
property”. The quality of insulation declines during the aging process, to different extents,
depending upon various operating conditions, due to both physical and chemical effects. The
dielectric strength of the conductor insulation deteriorates extremely slowly. If the same is
not mechanically disturbed much. However, mechanical properties (tensile strength) deteriorate
more significantly in the course of time, and are hence taken as the criteria to determine
aging of paper.
G. Operating Temperature
If the sustained operating temperature of the insulation exceeds the normal operating
temperature limit of 980C (hot spot temperature), there will be a shortening of life of the
transformer. In this condition, loading procedure as per IS-1972 define the life of material in
the insulating system as influenced by temperature alone, which may also be affected by
mechanical and electrical stresses.
3. MAINTENANCE OF TRANSFORMERS
i) Transformers require only a little care as far as day to day work is concerned Maximum
temperature of oil corresponding to load and atmosphere condition, oil level in the
255
conservator, condition of silicagel in breather, leakages of oil if any, explosion vent
diaphragm, cleanliness of bushings, proper working of cooling system of the transformer,
electrical load conditions, and transformer hum etc. are the factors requiring regular
observation.
ii) The transformer in service should not be subjected to overvoltage and overload. Incoming
voltage, and taps should be correctly adjusted.
iii) Every transformer has a cooling system to limit the temperature rise of the transformer.
The loading of transformer in KVA depends on the temperature rise and therefore the
cooling system should be maintained in good condition. If ventilation fans do the cooling
they must be available at the set value of temperature as recommended by the
manufacturer. For the transformer oil systems, cooled by water, sufficient quantity of
clean water should be available. Coolers also should be maintained clean. Watch should
be kept for leakage if any in the oil cooler. Alarms for stoppage of oil and water flow
should be maintained in working order. Instructions available for the ventilation and
cooling of the transformer should be strictly followed. All small naturally cooled
transformers should be installed at well ventilated places. Permissible continuous
overloading for a short period and overloading during emergency is determined by the
normal running temperature and therefore the transformer should be run at temperature
as low as possible.
iv) General maintenance of the transformer demands cleanliness of the surrounding yard
and the transformer with all its auxiliaries, leakages of oil should be attended as quickly
as possible. Silicagel in breathers should be replaced as soon as it indicates wetness by
change of colour. All the silicagel breathers are provided with sealing oil and the latter
should be replaced from time to time. Foundation and fixing should be checked for
firmness. Checking performance of radiators, cooling system equipment, earthing of the
transformer, temperature-indicating instruments, signals and protection equipment of
transformers should be done regularly.
v) The current transformer, potential transformer lightening arrestor, isolators, circuit
breakers installed for the transformers should also be maintained in order. Current
transformers and potential transformers also require equal care as the main transformer.
Contact resistance of isolators & circuit breaker will also effect the performance of the
transformer. All these equipment should be maintained in order.
vi) Due to leakage in the transformer, oil topping up is necessary. Lot of research and
experiments are going on, regarding mixing of oils. The results indicate that the oil of
two different sources though conforming to the same standards should not be mixed as
the sludging properties of the oil are considerably affected by mixing. Topping up of oil
should therefore, be done by the original grade of the oil as far as possible. If the mixing
up of two grades is unavoidable, the two grades of oils should be tested thoroughly
before mixing. Topping up with mixed oil should be undertaken only when oil topped up
is small in comparison to total transformer oil content, if the results of test show similarity
of characteristics.
B. Transformer oil:
Oil level should be checked at frequent intervals and if necessary conservator should
be topped up. Oil for topping up should be clean fresh filtered and complying with IS 335 and
should preferably be from the same source as the original oil.
For maintenance of oil reference may be made to Indian Standard Specification IS:
1866, which gives detailed recommendations for maintenance of insulating oil. Sample of oil
should be taken at regular intervals and tested. It may be mentioned that normal method of
oil purification only maintains dielectric strength of oil. However the dielectric strength does
not give a true indication of the correct condition of the oil. Even oil, which is highly deteriorated,
may give high dielectric strength, if it is dry. Therefore, it is necessary to carry out chemical
tests and other test as given in IS: 1866 in addition to the above tests.
It may be noted that reconditioning by centrifugal separator or filtration does not
remove the acidity from the oil but will remove only sludge, dust etc. and will tend to retard
the process of deterioration. Filters with fullers earth will help to reduce the acidity in the used
oil and in addition improve the resistivity.
D. Silicagel Breather :
Breathers should be inspected frequently especially in a situation where temperature
and humidity changes are considerable and when transformer is subjected to fluctuating
loads. So long as silica gel is in active stage, its colour changes to pale blue/pink/white.
Heating it upto 110-1300C for about 8 hours should reactivate silica gel.
The oil level in the oil seal must be maintained at the level marked in the cap. Renew
the oil when necessary. When two silica gel breathers are connected one below the other, oil
seal is provided only on the lowest breather. Breathers should be checked for clear air passage.
It can be confirmed by unscrewing the vent screw on breather. If air passage is clear, on
257
unscrewing the vent screw, oil level comes in gauge glass centre otherwise remains unbalance.
The air pipe be made clear.
E. Buchholz relay:
Routine operation and mechanical inspection tests should be carried out as
recommended. During service, if gas is found to be collecting and giving alarm, the gas
should be tested and analysed to find out the probable nature of the fault. Sometimes, it may
be noticed that the gas collected is only air. The reason for this may be that the oil is releasing
absorbed air due to change in temperature. The absorbed air is released only in initial period
on charging and loading, when no vacuum is applied during filling of oil in transformer. The
nature of internal faults can be identified to a great extent by a chemical analysis of gas.
Buchholz relay will also give alarm or trip the breaker due to oil level falling below the
Buchholz relay. Isolating valve between the conservator and Buchholz relay facilitates removal
of Buchholz relay for repairs/checking without lowering the oil level in conservator. A dummy
flanged pipe is also supplied for fitting it in place of Buchholz relay for keeping the transformer
in operation without Buchholz relay. It should be ensured that isolating valves on either side
of Buchholz relay are kept fully open for unhindered oil flow. The jamming of float pivot in the
fulcrum may be caused due to sludge & sedimentation. It should be removed and cleared by
operating the float with little uplifting from the drain hole by rodding to float gently.
F. Explosion vent:
The diaphragms fitted at the exposed end and inner end of the vent should be inspected
at frequent intervals and replaced if damaged. Whenever lower diaphragm ruptures, oil rises
inside the explosion vent pipe and is visible in the level indicator on explosion vent, Failure to
replace the outer diaphragm quickly will allow ingress of moisture which will contaminate the
oil. If diaphragm is broken because of fault in the transformer, an inspection should be carried
out to determine the nature and cause of the fault.
G. Temperature indicators:
At each yearly maintenance inspection, the level of oil in the pockets holding the
thermometer bulbs should be checked and the oil be replenished, if required. The capilary
tubing should be fastened down again if it has become loose. Dial glasses should be kept
clean and if broken replaced as soon as possible to prevent damage to the instrument.
Temperature indicators found reading incorrectly should be calibrated with standard
thermometer immersed in hot water bath. Thermometer pockets should be filled with oil. Also
check the pocket/s for presence of water and if found, clean the pocket and refill with fresh oil
and seal the opening properly. If armoring of capillary is exposed, then retaping must be done
by PVC tape of good quality to prevent further damage to the armoring or capillary.
H. Bushings:
Porcelain insulators and connectors should be cleaned at convenient intervals and
minutely examined for any cracks or other defects. Small or narrow cracks are difficult to
detect. However, they are likely to develop rapidly. All such bushings should be replaced.
Similarly oil inside the oil communicating type bushings should be checked by unscrewing air
release screws provided on bushing top. The cause of any serious loss of oil should be
investigated. In case of any sign of oil leakage in the bushings, the matter should be referred
to manufacturer. In case of capacitance bushing, Tan delta I.R. value and capacitance be
258
checked for satisfactory level. Test tap be kept earthed after the test is over. Bushing arcing
horn gap be adjusted properly as per operating voltages. Oil level in bushing gauge glass be
properly maintained with transformer oil of the same grade and quality.
J. Gasket:
Check the transformer for leakages periodically. The bolts should be tightened evenly
around the joints to avoid uneven pressure. Broken or leaking gaskets should be replaced as
soon as possible with proper jointing & fixing.
K. Rollers:
After the transformer has been in service for a long period, roller should be examined
carefully. They should be greased and rotated to see that they turn freely.
L. Paint work:
During storage and service, the paint work should be critically inspected atleast once
a year and where necessary painting and retouching be carried out. If the metal surface is
exposed and becomes rusty or greasy due to delay in touching work, the surface must be
thoroughly cleaned before repainting with primer and final paint. Paint as mentioned in the
General Arrangement drawing of transformer should be used. In case paint of another chemical
base is to be used, paint manufacturer should be consulted for compatibility with existing
paint.
N. Maintenance Schedule:
The maintenance schedule given in “Annexture” is a good indication of the attention
required to be given to the transformer under normal conditions.
259
vii) Flash over of bushing;
viii) Buldge in tank;
ix) Choke in radiator tubes;
x) Deteriorated oil.
REMEDIES:
It is generally observed that damage to HT winding is found in a vast majority of failed
transformers. Inadequate protection on LT side can be compensated by the provision of moulded
case circuit breakers (MCCBs) which afford better protection than fuse wires. Dry type
transformers will do away the need for supervision and maintenance of oil and associated
problems like breather maintenance, provided it is cost effective. Completely self protected
transformers have lightning arrestors LA closer to HT bushings unlike conventional transformers
where LA are installed separately. Fail safe transformers have protection features based on
thermal sensing and hence are considered to be far superior. LT phase separators would
prevent midspan clashing of LT line conductors and thus reduce frequent stressing of windings
in transformers and their consequential failures.
260
xvi) Remove the air through vent plug of the diverter switch before you energize the
transformer.
xvii) Check the oil level in the diverter switch and if found less, top up with fresh oil conforming
to IS: 335.
xviii) Check the gearbox oil level, if less, top up with specified oil.
xix) Examine and replace the burnt or worn out contacts as per Maintenance Schedule.
xx) Check all bearings and operating mechanism and lubricate them as per schedule.
xxi) Open the equalizing valve between tank and OLTC, wherever provided at the time of
filling the oil in the tank.
xxii) Connect gas cylinder with automatic regulator if transformer is to be stored for long, in
order to maintain positive pressure.
xxiii) Fill the oil in the transformer/ reactor at the earliest opportunity at site and follow
storage instructions.
xxiv) Check the door seals of marshalling Box. Changes the rubber lining if required.
xxv) Equalize the diverter compartment of the OLTC by connecting equalizing pipe between
flange joints provided on the tap changer head.
261
xxi) Do not allow dirt and dust deposits on bushings, they should be periodically cleaned.
xxii) Do not allow unauthorized entry near the transformer/ reactor.
xxiii) Do not leave ladder unlocked, when the transformer/ reactor is ‘ON’ in service, in case
it is provided.
xxiv) Do not change the sequence of valve opening for taking standby pump and motor into
circuit.
xxv) Do not switch on water pump unless oil pump is switched on.
xxvi) Do not allow water pressure more than oil pressure in differential pressure gauge.
xxvii) Do not mix the oil, unless it conforms fully to IS : 335.
xxviii) Do not allow inferior oil to continue in transformer/ reactor. The oil should be immediately
processed and to be used only when BDV/ ppm conforms to IS : 1866.
xxix) Do not continue with pink silicagel, this should immediately be changed or regenerated.
xxx) Do not leave secondary terminal of an unloaded CT open.
xxxi) Do not store transformer/ reactor for long after reaching sit. It must be erected and
commissioned at the earliest.
xxxii) Do not keep the transformer/ reactor gas filled at site for a longer period.
Unauthorized additions to existing loads as well as illegal tapping of power and loads
not yet sanctioned, lead to overloading of the transformers.
Whenever the cumulative expenditure towards rectification of damages in failed
transformer exceeds 50% of its original cost, the transformer itself is considered as
uneconomical for repair and disposed off. This is also the case when the core and yoke parts
of the transformer had got damaged.
262
ANNEXTURE
263
NO. FREQ. OF ITEMS TO BE INSPECTION ACTION REQUIRED
INSPECTION INSPECTED NOTES IF INSPECTION SHOWS
UNSATISFACTORY CONDITIONS
264
NO. FREQ. OF ITEMS TO BE INSPECTION ACTION REQUIRED
INSPECTION INSPECTED NOTES IF INSPECTION SHOWS
UNSATISFACTORY CONDITIONS
Note :
1) In addition to the above instructions given in this manual reference should also be made
to IS 1886 Code of practice for installation and maintenance of transformers.
2) In case of anything abnormal occurring during service, advice from Supplier should be
obtained, giving them complete particulars as to the nature and the extent of occurrence,
together with the name plate particulars in order to assist identification of the transformer.
3) Dielectric strength of oil be maintained as given in IS: 335/1972 with latest revision, on
completion of periodical inspection maintenance of the transformer, the tests as below
may be carried out with a view to confirm healthiness of transformer prior to charging.
265
TESTS ON TRANSFORMERS
No. TEST *W *C *M
1 Ratio Ö Ö Ö
2 Windind resistance measurement (At all taps) Ö Ö Ö
3 Insulation resistance & polarisation Index. Ö Ö Ö
4 Polarity, vector Group Ö Ö -
5 Separate sources withstand voltage. Ö - -
6 Measurement of No load losses. Ö Ö -
7 Load losses and Measurement of impedance (at all taps) Ö Ö -
8 Temperature rise test Ö Ö -
9 Impulse withstands test. Ö - -
10 Switching surge withstand test. Ö - -
11 Induced voltage withstand & partial discharge measurement. Ö - -
12 Measurement of iron losses (after all type tests) Ö Ö -
13 Measurement of insulation resistance and polarization index. Ö Ö Ö
14 Measurement of capacitance & tan delta of windings Ö Ö Ö
& bushings too.
*W At manufacture’s work
*C while Commissioning
*M Periodical Inspection Maintenance.
266