Vous êtes sur la page 1sur 27

TRIBHUVAN UNIVERSITY 

INSTITUTE OF ENGINEERING 
DEPARTMENT OF ARCHITECTURE AND URBAN PLANNING 
PULCHOWK CAMPUS 
 

 
 
A SEMINAR ON  

  ECONOMICS OF 
 
  WATER ALLOCATION
 

MODULE: ECONOMICS 
 

SUBMITTED TO: 
DR. JIBGAR JOSHI 
 
 
SUBMITTED BY: 
KIRAN MAN JOSHI| 066‐MUP‐205 
MONICA MANANDHAR| 066‐MUP‐207 
SACHEEN MAHARJAN | 066‐MUP‐214 
SAMIR BYANJANKAR | 066‐MUP‐215 
SUCHITA BAJRACHARYA | 066‐MUP‐218 
Economics of Water Allocation 
 

CHAPTER 1| INTRODUCTION 

1.1 Background 
Water is rapidly becoming scarce in almost all countries and cities of the world with growing population on 
one hand and fast growing economics, commercial, industrial and developmental activities on the other. This 
scarcity  makes  water  both  social  &  economic  commodity.  Being  an  essential  component  of  life,  the  use  of 
water is independent of economic condition or occupation of the people although it may affect its demand.  

Tremendous  socio‐economic,  political,  commercial,  educational  and  other  activities  are  going  on  every 
moment. For all such activities, water is essential. But the rate of increase of supply of water is very low as 
compared  to  the  rate  of  population  growth  and  urban  expansion  coupled  with  hectic  social,  industrial, 
commercial and other activities. More than that, it is heart breaking to know that the total amount of water 
that  can  be  harnessed  inside  the  Kathmandu  Valley  in  no  way  will  be  able  to  meet  the  future  demand  of 
Kathmandu. Insufficiency in water supply meant further deterioration of the problem of wastewater. So, any 
delay  in  finding  a  solution  for  the  water  supply  and  waste  water  treatment  could  lead  to  a  serious 
environmental disaster in Kathmandu.   

1.2 Introduction ­ Water as economic commodity 
In addition to being a basic need and a non‐homogeneous good, water could be  excludable,  non‐excludable,  
rival  or  non‐rival,  depending  on  the  way  in  which  it  is packaged.    For  example,  rainwater  is  a  non‐
rival  and  non‐excludable  good;  a  private metered connection is rival and excludable.  A non‐rival good is 
one whose consumption by one person does not reduce the consumption by others.  A good is non‐excludable 
if  it  is  prohibitively  costly  to  exclude  someone  from  receiving  the  benefits  of  the  good  after  it  has  become 
available.  A public good is characterized by no rivalry in consumption.    

There are both excludable and non excludable public goods.    A non excludable public good is a good that is 
non  rival  in  consumption  and  that  cannot  be  denied  to  a  person  who  does  not  pay  for  it.    Therefore,  the 
benefit  derived  from  improved  water  supply  is  a  non  excludable.    Water  has  public  good  characteristics 
because  improved  water  services  to    households    translates    to    better    health    of    the    community,  
improvement  in  the workforce,  and  reduction  in  the  demand  for  health  care.    Using  water  that  is  
below standard  can  lead  to  water‐based,  water‐borne,  or  other  water‐related  diseases  such  as diarrhea,  
ring    worm.        In  many  developing  countries,  millions  of  dollars  are  spent  every  year  to  treat  outbreaks  of 
disease  most  of  which  are  water‐related.    Such    expenditures    are    usually    part    of    the    budget    of    the  
ministry    of    health    which    most  times  cannot  afford  these  costs.      To  satisfy  minimum  health  and  safety 
requirements, a sufficient quantity of water for consumption purposes must be at or above a certain quality 
level, to prevent water‐based illnesses.  Water for bathing must be of a certain quality to prevent skin‐related 
water‐borne diseases.  Other households in the community must satisfy these constraints as well to  prevent  
negative  externalities  resulting  from  water  borne  disease  spread  within  the neighborhood.    

Health  benefits  clearly  are  a  public  good  aspect  of  improved  water  quality. Reducing the time women 
and  children  spend  fetching  water  allows  them  to  engage  in  other  economic  activities  that  contribute  to 
2 | P a g e  
 
Economics of Water Allocation 
improved family well being and the economy at large. Provision  of  adequate  water  supply  will  also  reduce  
the  time  girls  spend  in fetching water allowing them more time for schoolwork.  Girls’ education yields a 
higher  rate  of  return  than  any  other  investment  in  developing  countries.  Educating  girls  has  large  social 
benefits  in  terms  of  savings  from  improved  hygiene  and  birth  control,  as  educated  women  choose  to  have 
fewer  children.  Bringing  water  closer  to  home  and  reducing  the  time  girls  have  to  spend  fetching  water 
therefore has a positive externality or benefit that accrues to society as a whole.  Arguments of whether these 
benefits  are  public  or  private  are  issues  of  concern  in  the  literature.    But  the  fact    that    improved    water  
supply  and  sanitation  provide  health  benefits  to  society  as  a whole is apparent and undisputable.  

1.3 Objectives 
• To know about economics factor involved in water Supply and its proper disposal 

• To understand the cost factor, economic and financial benefits involved in a water supply projects 

1.4 Scope and limitation 
• The  study  is  an  attempt  to  understand  the  economic  principles  behind  public  water  supply  system 
taking the reference of Melamchi Water Supply Project 

• The study is conducted within a very short period of time depending upon readymade data. 

• The  study  of  MWSP  project  has  been  done  taking  the  reference  of  financial  and  economic  analysis 
carried out at time of ADB’s funding of the project. The project has gone through several changes in 
policies, budget and strategy within that period. 

1.5 Methodologies 
The adopted methodologies are as follows: 

A. Selection of the Topic: 

Through the rigorous group discussion, the topic “Economics of water supply projects” for the seminar was 
selected. 

B. Literature Review: 

Reference  books  and  related  papers  were  studied  and  planning  was  done  for  the  interpretation  of  the  raw 
data. 

C. Data collection: 

The Secondary data was collected from the internet sources. 

D. Analysis: 

Analysis of data in terms of economics aspects 

E. Data Presentation: 

3 | P a g e  
 
Economics of Water Allocation 
The  raw  data  was  analyzed  and  developed  in  a  form  of  graphical  representation.  Conclusion  and 
recommendation are extracted from case study. 

CHAPTER 2 | WATER AND WATER SUPPLY 

2.1 Water sources 
2.1.1 Surface water 

These are open sources of water which includes river, ponds, streams etc. They are usually the main sources 
of  water  for  water  supply  system.  Since  they  are  exposed  to  air,  they  are  generally  polluted  and  should  be 
firstly  purified,  collected  before  distributing.  The  main  sources  of  water  in  Nepal’s  Context  are  rivers.  The 
presence of Himalayas makes Nepal rich in water resources. The rivers are fed through melting of snow in the 
Himalayas. Rivers are renewable source of water. Water is available from these rivers all the year round but 
during rainy seasons water level is higher. This makes the surface water most feasible for use in water supply 
water system.  

2.1.2 Ground Water 
Ground water can be a cheap and reliable source of water where it is available. Ground water can be obtained 
though well or deep boring (by hand pumps). Ground water is usually clean from impurities but it may contain 
dissolved  salts,  minerals  and  sometimes  harmful  metals  like  arsenic.  In  general,  ground  water  is  safer  from 
pollution  when  the  aquifer  is  deep  and  confined;  even  then  it  is  advisable  to  use  ground  water  for  general 
purpose other than drinking .i.e. non potable use. One drawback of ground water is that it is not renewable 
naturally in a short period and extreme reliance and use of ground water can cause geological disorder. One 
way to tackle this problem is by recharging ground water during rainy seasons by rain water. 

2.1.3 Rain Water 
Rain water is the ultimate source of water which feeds the entire secondary source including Surface water 
and  Ground  water.  Even  though  it  is  primary  source  of  water,  practical  implementation  of  rain  water 
harvesting was not seen until recently. Direct collection and use of rainwater is however, widely practiced at 
an informal level by householders. Although it cannot be considered as reliable source of water, the fact that 
it is renewable and free source of water makes it important source of water. 

2.2 Water supply system 

2.2.1 State owned system  
Since water supply system is extremely capital intensive, and the financial benefits achieved are also low but 
the economical benefits that the water supply projects provide are of major importance. It is the main reason 
why most water supply projects are mainly carried out by the government. 

The  main  goal  of  the  state  owned  system  is  to  provide  service  to  general  public.  It  is  however  usually 
inefficient, non‐flexible and non‐responsive.  

4 | P a g e  
 
Economics of Water Allocation 
2.2.2 Private system 
Being a profit based system, it is efficient, responsive and feasible. However private system may not look after 
environmental and sustainability factor because the main aim is profit.  

Example of Private system is Ground water supply in apartments through deep boring and other means. Since 
profit  is  main  factor,  environmental  issues  such  as  making  retention  pond  ,  ground  water  recharging  are 
usually not covered 

2.2.3 Public Private Partnership system 
PPP is the new model for implementing public projects. The main idea of PPP model is that the private sector, 
community  organizations  and  non  government  and  government  organizations  should  be  partners  in 
development.  The  Millennium  Development  Goal  (MDG)  Assessment  Study  for  Nepal  estimated  that  33  per 
cent  of  the  expenditure  necessary  to  achieve  the  MDGs  will  have  to  come  from  non‐government  sources. 
Public‐private partnerships are one of the means of achieving this. 

A. Definition of Public Private Partnerships 

There is no  clear agreement on what does and what does not  constitute a public‐private  partnership (PPP). 


Under a typical PPP scheme, the government specifies the services it wants the private sector to deliver, and 
then  the  private  partner  designs  and  builds  an  asset  for  that  purpose,  finances  its  construction,  and 
subsequently  operates  the  asset  and  provides  the  services  deriving  from  it.  This  contrasts  with  traditional 
public investment where the government designs and finances an asset and then contracts with the private 
sector to build it.  

In  most  cases,  the  government  then  operates  the  asset  once  it  is  built.  The  difference  between  these  two 
approaches  reflects  a  belief  that  giving  the  private  sector  combined  responsibility  for  designing,  building, 
financing, and operating an asset is a source of the increased efficiency in service delivery that justifies PPPs.  

B. Stakeholders of Public Private Partnership 

The  Partnership  generics  evolve  from  the  possible  linkages  among  the  stakeholders  involved  in  the  UWM 
System.  In  general,  there  are  three  major  groups  of  stakeholders  and  three  categories  of  partnerships 
linkages. The PPP is particularly known as partnership between the Government and the Private Sector. This 
category of partnership is the part of concern and will be discussed more in depth. 

The other two forms of partnership between the Government and the Communities, and partnership between 
the  Private  Sector  and  the  communities  or  Civil  Society  are  not  discussed.  The  partnership  between  the 
Government and the Civil Societies is based on the policy of the Government on particular sector to include 
and empower the Civil Societies when required. 

5 | P a g e  
 
Economics of Water Allocation 
The  partnership  between  Business  and  Civil  Societies  is  based  on  the  Social  and  Corporate  Responsibility 
policy adopted by the Business houses and becomes their internal matter. However, the latest two forms of 
partnership  are  more  conveniently  understood  based  on  the  modalities  discussed  for  Public  Private 
Partnership. 

C. Public Private Partnership Structure 

The  stakeholder  under  the  Government  category  included  the  Central  and  Local  Government  Bodies  as 
Ministries,  Departments,  Municipalities,  DDC  and  VDC.  The  Donor  Agencies  and  other  Government  Owned 
Agencies also fall under this category. The second category of stakeholder is the Formal and Informal Private 
Sector  comprising  of  profit  making  and  nonprofit  making  organizations  as  business  houses,  industries, 
companies, enterprises, service providers, NGO, CBO, and individuals. The third category of stakeholders is the 
consumers  comprising  of  service  users  from  Government  to  citizens  who  are  responsible  for  generation  of 
waste. 

D. Partnership Development Approach 

The approaches of Partnership Development are‐ 

Top Down Approach – where the Government takes initiatives and call for Partnership. 

Such initiatives are almost rare unless it is mediated and pressurized by the Civil Societies. 

Bottom  Up  Approach  –  This  requires  influence  on  Policy,  Plans  and  Programs  of  the  Government  and  very 
difficult to achieve. 

Lateral  Approach  –  This  approach  is  not  dependent  on  Government  Policy.  Mostly  it  is  carried  out  by  the 
Communities and Private Sector at grass root level following their Corporate and Idealistic Responsibility. The 
Lateral Partnership has very strong effect on Government Policy depending upon the strength and extends of 
spatial  coverage  of  membership  of  the  partnership.  The  recent  political  changes  in  Nepal  could  attribute  to 
this  form  of  partnership  where  the  communities  and  individual  informal  partners  united  for  achieving  a 
particular goal of political change. 

6 | P a g e  
 
Economics of Water Allocation 

CHAPTER 3.0 | ECONOMY BEHIND WATER SUPPLY 

3.1 Factors involved in water Supply 
Following factors are to be analyzed before making economical analysis of water supply system 

A. Water  supply  and  Sanitary  are  inter‐connected  with  each  other.  Once  water  is  delivered  to  house 
hold, it is bound to generate waste water. The water supply cost should include the provision and cost 
of removal and treatment of waste water generated.  

B. Water supply and sanitation services are broadly conceived as huge societal enterprise. Its day to day 
need and its requirement for lots of day to day activities for all sectors of society makes it a important 
part of urban ecology. Reliable and efficient water supply is good measure of a developed and healthy 
society. 

For an example if we compare the water supply and sanitation system of European cities and cities of 
developing nations like Kathmandu we can see huge difference in quality of service which reflects the 
development condition of society. 

C. The provision of water and sanitation services is very capital intensive. Moreover, in many cases there 
are  significant  economies  of  scale,  and  the  physical  capital  tends  to  be  long‐lived.  This  has  several 
important  implications.    It  is  critical  to  get  the  investment  planning  decisions  right  because  one  can 
make big mistakes by overbuilding, by building too far in advance of demand, by building facilities that 
no one wants, or by failing to maintain and operate such capital‐intensive facilities efficiently.   

For an example, in Kathmandu Valley, where water supply is intermittent, major cause for inefficient 
distribution of water is lack of effective valve system. Due to these households near the reservoir are 
always  getting  excess  water  while  those  away  from  it  are  getting  none  at  all.  Although  initial 
investment may be on higher end, using valve and two pipe systems may be a better choice here. 

D. Household  demand  for  very  small  quantities  of  drinking  water  is  extremely  price  inelastic  because 
people  must  have  water  to  live.      If  there  are  no  other  sources  of  water,  the  amount  of  money 
someone  will  pay  for  3‐4  liters  of  water  per  day  is  limited  only  by  his/her  income.  This  extremely 
inelastic demand for small quantities coupled with shortages of water supply can combine to create 
situations in the developing world that are beyond the experience of people in richer countries.   

For example, in some places in rural Tanzania a 20‐liter bucket of water can cost a day’s wages of an 
unskilled laborer.  You can take your choice: walk all day for water, or work all day in the fields and 
buy a bucket of water. 

E. The fact that the price inelasticity for small quantities of water is so low, and the provision of services 
is  very  capital  intensive,  the  water  supply  system  provides  large  opportunities  for  bribery  and 
kickbacks on construction contracts and equipment purchases.  These problems greatly increase the 
transaction costs of doing business, and thus the total cost of providing improved water and sanitation 
services in many developing countries. 

7 | P a g e  
 
Economics of Water Allocation 
For Example, one of the causes for cost increase and subsequent delay in construction of Melamchi 
Water Supply Project is due to corruption during various phases of construction. 

F. Water  is  very  different  than  electric  power  when  it  comes  to  storage  and  transport.  The  storage  of 
water is relatively easy, while transporting water long distances to urban centers is expensive because 
water is so voluminous.  With electricity, by contrast, storage is expensive and transportation is easy.  
Because water is typically expensive to transport long distances, it can be prohibitively expensive to 
provide customers with very high levels of service reliability. 

3.2 Financial and Economic Analysis 

3.2.1 With and Without‐Project Cases 
After choosing the best among alternatives, the next step is to test the financial  and  economic  viability  of  
the    project,    which    is    the    chosen,    least‐cost  alternative.    The  initial  step  in  testing  the  financial  and 
economic viability of a project is to identify and quantify the costs and benefits. 

To    identify    project    costs    and    benefits    and    to    compare    the    net    benefit  flows,  the  without‐project 
situation should be compared with the with‐project situation. The without‐project situation is different from 
the before‐project situation.  The without‐project  situation  is  that  one  which  would  prevail  without  the  
project  vis‐à‐vis factors like population increase. As water is getting scarcer, the water use pattern and the 
cost are also likely to change.  

3.2.2 Financial Vs Economic Analysis 
Financial  and  economic  analyses  have  similar  features.    Both  estimate  the  net  benefits  of  an  investment 
project based on the difference between the with‐project and the without‐project situations. 

However,  the  concept  of  financial  net  benefit  is  not  the  same  as economic net benefit.  While financial 
net benefit provides a measure of the commercial (financial) viability of the project on the project‐operating 
entity, economic net benefit indicates the real worth of a project to the country. 

Financial and economic analyses are also complementary.  For a project to be economically viable, it must be 
financially  sustainable.    If  a  project  is  not  financially  sustainable,    there    will    be    no    adequate    funds    to  
properly    operate,    maintain    and    replace  assets;  thus  the  quality  of  the  water  service  will  deteriorate, 
eventually affecting demand and the realization of financial revenues and economic benefits.  

It  has  sometimes  been  suggested  that  financial  viability  not  be  made  a concern because as long as a 
project is economically sound, it can be supported through government  subsidies.    However,  in  most  cases,  
governments  face  severe  budgetary constraints  and  consequently,  the  affected  project  entity  may  run  
into  severe  liquidity problems, thereby jeopardizing even its economic viability. 

The  basic  difference  between  the  financial  and  economic  benefit‐cost analyses of the project is that the 
former  compares  benefits  and  costs  to  the  enterprise  in    constant    financial    prices,    while    the    latter  
compares    the    benefits    and    costs    to    the  whole    economy    measured    in    constant    economic    prices.  
Financial    prices    are    market  prices    of    goods    and    services    that    include    the    effects    of    government  
intervention  and distortions in the market structure.  Economic prices reflect the true cost and value to the  
8 | P a g e  
 
Economics of Water Allocation 
economy    of    goods    and    services    after    adjustment    for    the    effects    of    government  intervention    and  
distortions    in    the    market    structure    through    shadow    pricing    of    the  financial  prices.    In  such  analyses, 
depreciation charges, sunk costs and expected changes in the general price should not be included. 

In  financial  analysis,  the  taxes  and  subsidies  included  in  the  price  of goods and services are integral parts 
of financial prices, but they are treated differently in economic  analysis.    Financial and economic analyses 
also differ in their treatment of external effects (benefits and costs), favorable effects on health and the UFW 
of a WSP. 

Economic analysis attempts to value such externalities, health effects and nontechnical losses. 

3.2.3 Financial vs. Economic Viability 
The steps in determining the financial viability of the proposed project include: 

(i)        Identifying and quantifying the costs and revenues; 

(ii)       Calculating the project net benefits; 

(iii)      Estimating the average incremental financial cost, financial net present value and financial internal rate 
of return (FIRR).  

The FIRR is the rate of return at which the present value of the stream of incremental net flows in financial 
prices  is  zero.  If  the  FIRR  is  equal  to  or  greater  than  the  financial  opportunity  cost  of  capital,  the  project  is 
considered financially viable.  Thus, financial benefit‐cost analysis covers the profitability aspect of the project. 

The steps in determining the economic viability of a project include the following: 

(i)        Identifying and quantifying (in physical terms) the costs and benefits; 

(ii)       Valuing the costs and benefits, to the extent feasible, in monetary terms; and 

(iii)        Estimating  the  EIRR  or  economic  net  present  value  (NPV)  discounted  at  EOCC  =  12%  by  comparing 
benefits with the costs. 

The  EIRR  is  the  rate  of  return  for  which  the  present  value  of  the  net benefit  stream  becomes  zero,  or  
at  which  the  present  value  of  the benefit  stream  is  equal  to  the  present  value  of  the  cost  stream.  For 
a project to be acceptable, the EIRR should be greater than the economic opportunity cost of capital. The Bank 
uses  12%  as  the  minimum  rate      of      return      for      projects;      but      for      projects      with      considerable  no 
quantifiable benefits, 10% may be acceptable.  

3.2.4 Procedures for Economic Analysis 
The    economic    analysis    of    a    Water  Supply  Projects    (urban    or    rural)    has    to    follow    a  sequence  of 
interrelated  steps: 

A. Defining the project objectives and economic rationale  

Under this will be defining the main goal of the project, why it is needed and how it will be achieved. 
To  acquire  the  knowledge  about  the  physical  features,  present  situation  regarding  existing  facilities 
9 | P a g e  
 
Economics of Water Allocation 
and their use constraints (if any) against their optimal use, the communities and their socio economic 
conditions, surveys and field visits need to be done. 

For  an  example  if  the  area  is  rural  or  based  on  economic  condition  of  the  household  in  the  area,  a 
community  taps  serving  few  household  may  be  more  beneficial  socio‐economically  than  providing 
individual taps 

B. Demand analysis and forecasting effective demand for project outputs.  

This    is    to    be    based    on    either    secondary    information    sources    or    socio‐economic  and  other 
surveys in the project area. Demand of water is depended on the tariff rate of water. The demand of 
water  also  fluctuates  with  season  and  on  the  time  of  a  day.    The  project  needs  to  access  the  peak 
demand. 

C. Establishing  the  gap  between  future  demand  and  supply  from  existing  facilities  after  ensuring  their 
optimum use. 

For example if the future demand of water of an area (as calculated from the survey) is expected to be 
16mlpd  and  existing  facilities  provides  around  5mlpd  with  their  optimum  use  then  water  supply 
system which can provide additional 11mlpd will be required. 

The  optimal  use  of  facilities  (if  applicable)  here  need  to  be  achieved  through  physical  and  policy 
related  measures.  The  physical  measures  are  like  leakage  control,  replacing  faulty  valves  and 
adequate maintenance and operation, (unless new network systems are proposed for water supply) 
etc;  policy  measures  can  be  charging  an  economically  efficient  tariff  and  implementing  institutional 
reforms. 

D. Identifying  project  alternatives  to  meet  the  above  gap  in  terms  of technology, process, scale and 
location through a least‐cost and/or cost‐Effectiveness analysis using economic prices for all inputs. 

This includes short listing and identifying the least‐cost alternative of achieving the required output. 
All the life‐cycle costs (market and non‐market) associated with each alternative are to be taken into 
account. 

The alternatives are not to be confined to technical or physical elements only, e.g., ground water or 
surface  water,  gravity  or  pumping,  large  or  small  scale,  etc.  They  can  also  include  activities  due  to 
policy  measures,  e.g.  leakage  detection  and  control,  institutional  reforms  and  managerial 
reorganization. 

For an example, we assume that cities near the seas can easily address it’s water need. But most of 
the time it is actually cheaper to use other sources of water than to purify and remove salt from the 
sea  water  (the  process  known  as  desalination)  and  distribute  the  desalinated  water  to  higher  level 
(since sea level lie below normal land level). The least‐cost analysis of different projects will reveal if 
the water supply project is feasible enough to implement or not.  

E. Identifying      benefits,      both      quantifiable      and      non‐quantifiable,      and  determining  whether 


economic benefits exceed economic costs. 

10 | P a g e  
 
Economics of Water Allocation 
For an example, when the dam was proposed for construction in the Narayani River in Chitwan, the 
financial study revealed that the project would really take a long time to attain the financial breakeven 
state. But the project was considered economically feasible due to following reason‐ 

• With the new irrigation network, the farmers will be able to produce more crops, which will result in 
increase  in  economic  activity  and  farmers  end  up  paying  more  taxes.  Also  as  a  social  benefit  nation 
will get more food yield. These non market, economic and social benefits cannot be easily quantified 
but these factors are considered for analyzing of economic benefits of the projects. 
• Generally, if the average income of the farmers in the area before the project is 5000 per month and if 
due to the project they could increase their crop yield and earn income of around 15000 per month 
then 10000 is considered as economic benefit of the project.  In the above case if the farmer earns 
10000  more  it  is  assumed  that  certain%  (say  10‐20%  i.e.  1000  to  2000)  of  the  earned  income  will 
return to government in the form of tax paid which is considered as financial gain in the case of state 
projects 

F. Assessing   whether   the   project’s   net   benefits   will   be   sustainable throughout  the  life  of  the  
project  through  cost‐recovery,  tariff  and subsidy  (if  any)  based  on  financial  (liquidity)  analysis  
and  financial benefit‐cost analysis. 

The benefits of the water supply projects are more economical and social than financial but given that 
it is the state which generally invests in water supply projects which low priority of financial return. 
But  for  water  supply  projects  to  be  sustainable,  the  operation  and  maintenance  cost  and  future 
upgrading  cost  has  to  be  provided  by  the  end  users.  Failing  to  achieve  this  will  make  the  project 
unfeasible even at cost of its social benefits.  

In  case  of  above  example  of  water  supply  for  irrigation  in  Chitwan  thorough  Narayani  river,  the 
farmers  has  to  pay  the  charges  for  using  water  for  irrigation.  Prices  are  charged  as  per  unit  of  land 
irrigated.  This cost collected should cover the O &  M cost of the project so the project is financially 
sustainable throughout the life of project. 

G. Testing for risks associated with the project through sensitivity and risk analyses. 

In calculating the EIRR or ENPV for WSPs, the most likely values of the variables are incorporated in 
the  cost  and  benefit  streams.  Future  values  are  difficult  to  predict  and  there  will  always  be  some 
uncertainty about the project results.  Sensitivity  analysis  is  therefore  undertaken  to  identify  those  
benefit  and  cost parameters that are both uncertain and to which EIRR and FIRR are sensitive.  

A sensitivity indicator shows the percentage change in NPV (or  EIRR)  to  the  percentage change  in  a  
selected variable. A high value for the indicator indicates project sensitivity to the variable. Measures   
minimizing  against  major  sources  of  uncertainty  are  incorporated  into  the  project  design,  thus 
improving it. 

For  an  example  some  of  the  variable  that  may  affect  the  water  supply  projects  includes  long  term 
reliability of water source, WTP (Willingness to pay) factors of the consumer, the government policies 
and economic ability of the government, political stability of the country which should be taken into 
account. 

11 | P a g e  
 
Economics of Water Allocation 
3.3 Cost involved in Water Supply System 
As said earlier, development of water supply system is extremely capital intensive. The treatment and delivery 
of water to the households and removal and treatment of the waste water generated cost serious money. The 
financial benefits achieved are also low but the economical benefits that the water supply projects provide are 
of  major  importance.  It  is  the  main  reason  why  water  supply  projects  are  mainly  carried  out  by  the 
government. The private sectors (whose main goal is profit) hence generally refrain for water supply projects 
unless low interest donations and grants are involved in the project.  

3.3.1 Market Costs 
The economic costs of providing a household with modern water and sanitation services are the sum of seven 
principal components:   

A. Opportunity costs of diverting raw water from alternative uses to the household (or resource rents)  
If, for example, a drinking water project uses  raw  water  diverted  from  agriculture,  the use of this 
water for drinking will result in a loss for farmers.  These costs are measured as the opportunity  cost  
of    water    which,    in    this    example,    equals    the    “benefits  foregone”  of  the  use  of  that  water  in 
agriculture.  

B. Storage and transmission of untreated water to the urban area   

This  includes  cost  in  construction  and  operation  of  infrastructure  used  for  trapping  and  storing 
(pumps, dams) the water source and transmission of the water to the area of distribution.  

C. Treatment of raw water to drinking water standards   

The most commonly adopted and cheap method here is sand filtration and chlorination.  

D. Distribution of treated water within the urban area to the household   

Making Supply Network and providing household connections of the treated water comprise a major 
cost component. 

E. Collection of wastewater from the household (sewerage collection)   

F. Treatment of wastewater (sewage treatment)   

G. Any remaining costs or damages imposed on others by the discharge of treated wastewater (negative 
externalities).    

12 | P a g e  
 
Economics of Water Allocation 
 

Table 1. Cost estimates: improved water and sanitation services  
No.  Cost component   US$ per m3  % of total  

1   Opportunity cost of raw water supply   0.05   2%  

2   Storage and transmission to treatment plant   0.15   6%  

3   Treatment to drinking water standards   0.15   6%  

4   Distribution  of  water  to  households  (including  0.75   30%  


house connections)  

5   Collection  of  waste  water  from  home  and  1.00   40%  
conveyance to wastewater treatment plant  

6   Wastewater treatment   0.35   14%  

7   Damages  associated  with  discharge  of  treated  0.05   2%  


wastewater  

  Total   2.50   100%  

Table 1 presents some illustrative average unit costs for each of these seven cost components, expressed in 
U.S. dollars per cubic meter.  The cost estimates in Table 1 include both capital expenses and operation and 
maintenance expenses.  The calculation of annual capital costs uses a capital recovery factor of 0.12, assuming 
a discount rate of 10% and an average life of capital equipment and facilities of 20 years. 

The unit costs of these different cost components could vary widely in different locations. For example, in a 
location with abundant fresh water supplies, item 1 (the opportunity cost of diverting water from existing or 
future  users  to  the  potential  target  group)  and  item  7  (the  damages  imposed  by  the  discharge  of  treated 
wastewater)  may,  in  fact,  be  very  low  or  even  zero.  However,  in  more  and  more  places  these  opportunity 
costs associated with water diversion and the externalities from wastewater discharge are beginning to loom 
large.  

Some  cost  components  are  subject  to  significant  economies  of  scale,  particularly  storage  and  transmission 
(item 2), the treatment of raw water to drinking water standards (item 3), and the treatment of sewage (item 
6). This means that the larger the quantity of water or wastewater treated, the lower the per‐unit cost. On the 
other  hand,  some  cost  components  are  experiencing  diseconomies  of  scale.  As  large  cities  go  farther  and 
farther away in search of additional fresh water supplies, and good reservoir sites become harder to find, the 
unit cost of storing and transporting raw water to a community increases. There are also tradeoffs between 
different cost components: one can be reduced, but only at the expense of another. For example, wastewater 
can receive only primary treatment, which is much cheaper than secondary treatment; but then the negative 
externalities associated with wastewater discharge will increase.   

13 | P a g e  
 
Economics of Water Allocation 
The opportunity costs of raw water supplies (item 1) are still quite low in most places, on the order of a few 
cents  per cubic meter.  Even in places  where urban water supplies are diverted from irrigated agriculture or 
valuable environmental assets, the unit costs will rarely be above US$ 0.25 per cubic meter. 

Raw water storage and transmission and subsequent treatment (items 2 and 3) will typically cost US$0.30 per 
cubic  meter.  Within  a  city,  the  water  distribution,  collection  and  conveyance  of  sewage  to  a  wastewater 
treatment plant (item 5) is even more expensive than the water distribution; this will cost about US$1.00 per 
cubic  meter,  40%  of  the  total  cost.  Secondary  wastewater  treatment  (item  6)  will  cost  about  US$  0.35  per 
cubic  meter.  Damages  resulting  from  the  discharge  of  treated  wastewater  are  very  site‐specific,  but 
environmentalists correctly remind us that that they can be significant.  

As shown, total economic costs comes to about US$2.50 per cubic meter in most location. However this value 
is bound to change depending on various factors. For example, in small communities in the mountainous areas 
of  Upper  Nepal,  cost  of  Water  and  Sanitary  services  can  easily  be  double  or  triple  these  amounts  per  cubic 
meter. (Source: Designing Optimal Water Supply System for Developing countries) 

Other factors which affect the economic cost of water includes the following: 

3.3.2 Non Market Costs 

Subsidies 
Generally in Developing Countries, the subsidies provided to consumers of water and sanitation services are 
not  only  huge,  but  also  regressive.  It  is  often  not  politically  “desirable”  for  the  majority  of  people  to 
understand  that  middle‐  and  upper‐income  households,  who  generally  use  more  water,  are  thus  actually 
receiving the most benefit from subsidies. Most fundamentally, poor households are often not connected to 
the W&S network at all and hence cannot receive the subsidized services. Even if they do have connections, 
the poor use less water than richer households, thus receiving lower absolute amounts of subsidy.   

For  an  example,  the  tariff  rate  of  water  for  Nepal  is  among  lowest  in  Asia  due  to  subsidy  provided  by 
Government which stand as Rs 80 for unmetered taps and maximum of 250 (Rs 50 for sewerage) for metered 
taps. The people of Kathmandu are unwilling to pay more tariffs for water supply due to unreliability of the 
service. This coupled with high ratio of loss due to existing use of old pipe is leading to failure of existing water 
supply system in its social goal and financially.  

Sustainability Cost 

It  can  be  referred  cost  added  to  ensure  the  future  availability  of  resource  and  ensure  its  sustainability.  This 
specially  applies  to  ground  water  whose  excessive  use  can  decrease  the  ground  water  table,  making  the 
ground water difficult to obtain or not available at all in the future. Hence, to cope with such situation, special 
cost called ‘Scarcity Premium’ is added to the resources. 

Environmental Cost 

This includes the cost to compensate for the environmental impact (if any) resulting due to use of water from 
the source and due to wastewater discharge.  

For an example, using water from the wetland for irrigation may disturb the ecosystem of the wetlands. The 
environmental cost helps to compensate for such impacts 

14 | P a g e  
 
Economics of Water Allocation 
 

3.4 Cost Recovery 
In  general,  the  cost  of  the  water  supply  project  is  expected  to  be  recovered  by  increasing  the  tariff  rate. 
Whereas  there  is  cost  recovery  in  most  of  the  countries  (Capital,  O  &  M,  Debt  services  etc),  in  developing 
countries  it  is  not  always  so.  The  greater  gap  between  cost  and  prices  leads  to  lower  service  reliability  and 
sustainability.  

Most  of  the  time,  in  developing  countries,  the  cost  of  the  project  is  not  expected  ot  be  recovered.  The 
government  invests  its  own  capital  for  the  project,  and  the  cost  collected  is  used  to  cover  the  present  and 
future  operation  and  maintenance  goals  only.  The  goal  here  is  to  achieve  economic  feasibility  rather  than 
financial. 

CHAPTER 4 | WATER SUPPLY SYSTEM IN KATHMANDU 

4.1 Water Supply 
In  KMC,  water  is  supplied  by  Nepal  Water  and  Sewerage  Corporation  (NWSC)  and  private  tanker  services. 
Besides  these  there  are  few  community  based  supply  system  for  specific  towns  and  villages.  For  example 
Siddhipur  Water  Supply  project  carried  out  by  combined  effort  of  NGOs,  Community  and  Local  level 
Governemnt. In addition to that, many industries, hotels, hospitals and a large number of households use a 
huge amount of ground water extracted by pumping.  

The  existing  water  pricing  policy  in  the  Kathmandu  is  partly  based  on  block  rate  tariff(BRT)  mechanism, 
although the users’s charge fails to cover the cost of services or to generate revenue for evvective treatment 
of  available  water  supply  and  augment  new  water  sources.  In  KMC,  the  tariff  rate  charged  by  NWSC  is  as 
follows 

4.2 Current drinking water tariffs 
Pipe  Minimum  Minimum tariff in NRs  Effective  from  17th September  2004  as  per  volume 
size   consumption  of water (price per 1000 Liters) 
(in  (ltr) 
inch) 
Household  Government, Commercial  Household Government,  Commercial 
Institutional &  &  institutional &   &  
public   industrial  public  industrial 
½”  10,000  50  50  50  15  15  15 
¾”  27,000  810  810  810  30  30  30 
1”  56,000  1,680  1,680  1,680  30  30  30 
1.5”  155,000  4,650  4,650  4,650  30  30  30 
2”  320,000  9,600  9,600  9,600  30  30  30 
3”  881,000  26,430  26,430  26,430  30  30  30 
4”  1,810,000  54,300  54,300  54,300  30  30  30 
For those household who doesn’t owe meter have to pay minimum Rs 552.00 /month. 

15 | P a g e  
 
Economics of Water Allocation 
Water supplied by NSWC or private tankers or extracted and used by various institutions or households are 
neither  controlled  by  a  uniform  law  nor  well  managed  by  the  existing  institutions.    It  was  nationally  and 
internationally accepted that the problem of water supply both in quantity and quality are basically due to the 
organizational  and  functional  weakness  of  the  major  supplier  of  water,  namely,  Nepal  Water  Supply  and 
Sewerage  Board  which  was  reorganized  as  Nepal  Water  Supply  Corporation  in  1989  (NWSC).  In  order  to 
improve the situation, donors expressed the opinion that HMG/Nepal should bring in a private operator (PO) 
to  manage  the  water  system  assets  and  made  this  a  condition  for  loans  and  grants.  Taking  this  fact  into 
consideration, His Majesty of Government of Nepal (HMG/N) then proposed three major reforms and decided  

• To bring in private company to manage the water supply staff and equipment  

• To repair, upgrade and expand the present water supply network; and  

• To construct a tunnel from the Melamchi valley to bring in more water.  

All these reforms required a huge amount of money. The total cost of the reform was estimated to be around 
US$ 468 million and is expected to be financed by loans (59%), grants (11%) and HMG/N (30%) to be spent 
between 2002 and 2007. This appears to be a very expensive project (US$ 300 per person in the valley). The 
roles of public and private sectors in the above reform process can be understood clearly from the following 
allocations of funds:  

• For private company US$ 4 million to be spent under certain condition  

• For system upgrading US$ 136 million  

• For Melamchi tunnel US$ 328million 

CHAPTER 5.0 | MELAMCHI WATER SUPPLY PROJECT 

5.1 Background  
In  1988,  the  Government  of  Nepal  decided  that  a  tunnel  should  be  built  from  the  Melamchi  Valley  to  the 
Kathmandu  Valley  to  improve  the  water  supply  in  Kathmandu,  Nepal’s  capital  city.  The  Melamchi  Water 
Supply Project (MWSP) was initially funded by a $71 million loan from the World Bank. However, seven years 
later the project stalled when it was revealed that a fraction of this amount had actually been spent.  

The World Bank demanded that an operator from the private sector be brought in before further funding was 
offered.  This  condition  remained  when  the  World  Bank  withdrew  and  the  Asian  Development  Bank  (ADB) 
became  the  main  donor.  By  2006,  Severn  Trent  Water  International  was  the  only  company  to  have  made  a 
valid bid for the project. 

The MWSP was an expensive project funded by an extensive foreign loan, which the government would have 
to  repay.  The  tunnel  was  taking  years  to  happen  and  there  was  concern  that  the  ordinary  people  of 
Kathmandu, especially the 40,000 poor citizens living without a water connection, would have no say in the 
design and planning of the project and no share in its potential benefits. 

16 | P a g e  
 
Economics of Water Allocation 
Since 1973, the government of Nepal has done several studies and implemented the schemes to find out the 
best solution to meet the water supply demand for the rapid growth of population in the Katmandu valley. In 
1988, more specific pre‐ feasibility studies were carried out for the water supply sources for the valley. Based 
on  these  studies,  the  Melamchi  scheme  was  identified  as  the  best  long‐term  solution  to  solve  the  constant 
water shortage in the valley. Subsequently, in 1997, the government established the Melamchi water Limited 
to  seek  funding  for  and  implement  the  Melamchi  Water  Supply  Project.  In  1998,  it  was  replaced  by  the 
Melamchi  Water  Supply  Development  Board  (MWSDB)  while  some  key  donors,  such  as  Asian  Development 
Bank,  Governments  of  Japan  and  Norway  took  interest  in  funding  the  project.  Currently  the  government, 
through MWSDB is implementing the project. 

5.2 Introduction 
Melamchi Water Supply Project is much‐debated 
mega project. The project was visualized in 1973. 
It  is  an  alternative  to  address  acute  water 
problems  of  Capital  Kathmandu.  The  Project  is 
located  in  Sindhupalchok  District,  but  covers 
Kavrepalanchok,  Kathmandu,  Lalitpur  and  
Bhaktapur. 5100 Million Litters water per day will 
be diverted from snow fed Melamchi,  Larke and  
Yangri rivers to KTM. In Kathmandu, per day 180 
Million Liters water is necessary.   

The  Melamchi  Water  Supply  Project  and 


institutional  reforms  were  carried  forward  in  the  period  in  accordance  with  the  government’s  two  pronged 
strategy to achieve sustainable and consumer oriented water supply and sanitation services in the Kathmandu 
Valley. 

The Melamchi Water Supply Project will be implemented with high priority to provide a long‐term sustainable 
bulk  water  supply  in  the  Kathmandu  Valley.  The  tunnel  excavation  works  will  be  carried  forward  and 
remaining  road  works  are  also  being  completed.  Preparatory  works  will  also  be  undertaken  towards  the 
construction  of  a  170MLD  Water  Treatment  Plant  in  Kathmandu  Valley.  The  operations  of  the  water  supply 
and sanitation services will be handed over to the Kathmandu Upatyaka Khanepani Limited (KUKL). A major 
program  for  repair,  replacement,  rehabilitation  and  expansion  of  the  age‐old  distribution  system  is  planned 
and being worked out to control leaks. Institutional efficiency will also be increased. 

5.3 Project Aims and Objectives 
With the starting of the project, it had following objectives: 

ƒ Solve the chronic water supply shortage and improve the water‐supply in Kathmandu (KTM)  Valley 

ƒ Rehabilitate and/or replace existing water supply network and associated equipment  

17 | P a g e  
 
Economics of Water Allocation 
ƒ Provide access to clean and safe water supply ensuring good health sanitation 

ƒ Establish efficient water supply networking system on a sustainable basis 

ƒ Reduce water pollution through establishment of sewer  and waste water treatment plants 

ƒ To improve river ecology,  religious sites, and cultural Ghats located at river banks by augmenting water 
flow at Bagmati and its tributaries  

ƒ To expand the depleting ground water sources of KTM 

5.4 MWSP: Cost Estimation 
The  total  project  cost  was  originally  estimated  at  US$  464  million;  JBIC,  Norway  and  Sweden  agreed  to  co‐
finance the project. Tunnel construction would cover 32% of the total cost, rehabilitation of the network, 46%, 
and  the  management  contract  plus  institutional  reforms,  4%.  The  World  Bank  earlier  agreed  to  provide 
financial support to the PSP process but pulled out in mid‐2002; ADB then came in to help prepare a 5‐year 
management contract. 

The main cost items (base costs) are the MDS ($74.29 million), WTP ($39.33 million), BDS ($48.47 million), and 
the distribution network improvements ($65.95 million). The following table gives a summary of the estimated 
costs: 

Foreign  Local 
Item  Total cost 
Exchange  Currency 
A.   Base          
1. Infrastructure Improvements  193.03  83.36  276.39 
2. Social and Environmental Support  2.10  10.34  12.44 
3. Institutional reforms  1.80  0.76  2.56 
4. Project Implementation Support  24.89  7.74  32.63 
Subtotal (A)  221.82  102.2  324.02 
B.  Contingencies 
1. Physical  22.20  10.20  32.40 
2. Price  21.40  9.40  30.80 
Subtotal (B)  43.6  19.6  63.2 
C.  Interest during Construction and Fees  7.60  33.20  40.80 
D.  Taxes and duties  0.00  36.00  36.00 
Total  273.00  191.00  464.00 
Percent  58.80  41.20  100 
 

Full cost recovery for urban water supplies is among the reforms instituted through the Melamchi project. In 
2004,  the  government  decided  to  increase  prices  annually  by  15%.  For  the  past  two  years  the  tariff  has 
remained the same, which means the next increase would be a whopping 30%. Consumers paying Rs 50 for 
10,000 liters, for instance, would have to pay Rs 66. 

18 | P a g e  
 
Economics of Water Allocation 
 

Available Budget   Budget Required as  Resource Gap 


Sector  per Three Year 
FY  000  Interim Plan    
2007/08  2316231  4270234  1954003 
Water and  2008/09  2547854  6618883  4071029 
Sanitation 
Sector  2009/10  2802640  6618883  3816243 
Total   7666725  17508000  9841275 
 

 
The  estimated  project  cost  is  US$  465  million.  The  Donors  for  the  project  are  ADB,  JBIC  (Japanese  Bank  of 
International  Cooperation),  NORAD  (Norwegian  Agency  for  International  Cooperation),  SIDA  (Swedish 
International Development Cooperation Agency. Asian Development Bank (ADB) is key donor and funding on 
following components: 

A. Construction  

B. Social and Environment  

C. Consultant  

The main loan for the project will be provided by Asian Development Bank. The loan of Special Drawing Right 
(SDR)    93,253,000.00  ($120.0  million  equivalent)  will  be  provided  with  a  term  of  30  years  including  a  grace 
period  of  8  years,  and  an  interest  charge  of  1%  per  annum  during  the  grace  period  and  1.5%  per  annum 
thereafter. The ADB funds for the Project as well as all other funds will be provided to the utility in an equal 
mix of loan and grant. Interest for the loan will be at 8% per annum repayable over 20 years including 7 years 
of grace. 

5.5 Financial Analysis

5.5.1 Cost Recovery Policy and Assumptions 

19 | P a g e  
 
Economics of Water Allocation 
During the preproject period, average tariffs are expected to rise from NRs6.9/m3 in 2000 to NRs12.8/m3 in 
2006 (in 2000 prices) to meet cash O&M costs as well as 
WTP and Cost recovery 
private  operator  and  regulatory  costs.  The  financial 
projections assume:  In  1989,  The  town  in  Indonesia  was  facing  with 
same problem as currently faced in Kathmandu. 
ƒ Improved collection efficiency;  
The  water  supply  system  was  unreliable, 
ƒ Metered standpipes charged at the lifeline rate;   inefficient  and  owning  to  these  facts  people 
ƒ Users meeting payment obligations;   were  unwilling  to  pay  more  tariff  for  water 
supply.  Although  water  use  was  38  m3  per 
ƒ Groundwater  charges  for  nondomestic 
household, there was large no of household not 
consumers;  
getting  water  at  all  and  those  getting  it  ware 
ƒ Wastewater charged as a 50% surcharge on the  misusing it owning to low tariff 
water  tariff.  Post‐project,  average  tariffs  will  be 
The  old  water  supply  system  was  becoming  a 
nrs23.0/m3  by  2008,  adequate  to  cover  O  &M, 
failure in its social goal and financial part too. 
debt  servicing,  regulatory,  and  private  operator 
costs.  All  nondomestic  use  of  groundwater  is  To  improve  this  situation,  the  government  after 
assumed to cease by 2008.  heavy  investment,  introduced  a  newer,  efficient 
and reliable water supply system to the city. The 
 
tariff  was  increased  by  115%  for  domestic  use 
  and  170%  for  non  domestic  use.  Given  the 
reliability  and  effectiveness  of  new  services  the 
5.5.2 Financial Internal Rate of Return 
people were willing to pay for it. 
The  overall  financial  internal  rate  of  return  for  the 
Project is 4.7%. This  may be compared with a weighted  The increase in tariff rate made the consumption 

average cost of capital for the Project of 0%, where the  of  water  per  household  to  drop  form  38m3  per 

onlending  rate  is  8%  and  domestic  inflation  is  8%  month  to  27  m3  per  month.  The  water  loss  in 

resulting  in  a  real  interest  rate  of  0%.  Similar  to  other  new  system  was  significantly  lesser  and  project 

urban water supply projects, the financial internal rate of  was  successful  both  economically  and 

return  showed  sensitivity  to  increases  in  capital  costs  financially. 

and revenues.  Hence  Willingness  to  Pay  (WTP)  factor  plays  a 


major  role  in  cost  recovery  of  project  and  price 
5.5.3 Financial Sustainability  
increase  with  proper  and  reliable  service 
There are mainly three aspects of financial sustainability  increases the people’s WTP factor 
in connection with MWSP: 
(Developing  optimized  water  supply  system  for 
(i)  Project  funding  and  fiscal  impact  on  government  developing countries by Grace Ukoli‐Onodipe) 
budget. WSPs are frequently funded by the government 
and  full  cost  recovery  especially  from  poor  water  users  may  not  be  possible  even  for  their  basic  minimum 
needs. 

(ii) Full or partial cost recovery of project costs from project beneficiaries. WSPs, like projects in other sectors, 
can hardly be sustained on government subsidy alone, without the revenue generation from the sector itself. 
Cost recovery and proper design of water tariff based on the costs of supply are required. 

20 | P a g e  
 
Economics of Water Allocation 
(iii) Financial incentives are necessary to ensure participation in the project of all stakeholders. In the context 
of a WSP, the participants include: 

ƒ lenders who lend money for capital investment 
ƒ guarantors  who  guarantee  the  loan  (In  public  projects  like  WSPs,  the  government  is  often  the  
guarantor) 
ƒ suppliers of inputs to the project 
ƒ users  of  project  output  (households/industries);  and  the  organization  which  sponsors  and  runs  the 
project (water enterprise) 
 

5.6 Economic Analysis 

5.6.1 with and Without the Project 
The  without‐project  option  offers  a  very  miserable  scenario  for  Kathmandu  Valley.  Since  NWSC  would  be 
unable  to  meet  demand,  piped  water  delivery  would  continue  to  be  limited  to  less  than  2  hours  every  two 
days,  pressures  and  water  quality  would  be  poor,  and  inequality  would  persist  for  water  distribution. 
Therefore, the economic price of water would rise from NRs 40/m3 currently to NRs 110/m3 in 2012. 

A  number  of  alternative  options,  including  in‐valley  storages  were  considered,  but  were  found  to  be 
impractical  because  of  various  shortcomings,  such  as  high  financial  and  social  costs,  low  yield,  and  other 
problems associated with population density and land use. The proposed design involves a low‐level tunnel, 
no  impoundment  storage,  and  no  hydropower,  and  was  considered  a  least‐cost  and  least  environmentally 
disruptive option. Furthermore, it retains the option for low‐cost gravity expansion of supply from the Yangri 
and Larke rivers and in valley storage in the future. 

5.6.2 Economic Internal Rate of Return 
The economic evaluation assumes base economic costs of $322 million and incremental O&M costs at 1% of 
total costs plus $0.04/m3 of water production. A standard conversion factor of 0.9 is assumed. Total costs are 
high because of the need to provide a sound basis for future expansion. Benefits are estimated at NRs1,500 
million/year initially and increase to about NRs6,000 million/year in subsequent years. 

The economic internal rate of return (EIRR) for the Project (with 170 MLD capacity) is 13.5%, while the EIRR for 
the full development is 15.3%. The EIRR was tested for sensitivity to tariff levels, water losses, income growth, 
nondomestic tariffs, and capital costs. The EIRR is estimated to be 10.1% at the current water loss figure of 
40%, 11.9% with real income growth reduced to 1% per year, 12.9% with a 50% decrease in the nondomestic 
tariffs, and 12.6% with a 10% increase in capital costs. 

21 | P a g e  
 
Economics of Water Allocation 
5.7 Project Benefit 
The Project’s primary target population is the 1.5 million people (180,000 households) living in the Kathmandu 
Valley.  The  urban  inhabitants  will  benefit  from  improved  water  supply  services  with  better  water  quality, 
increased  quantity,  improved  supply,  extended  service  areas,  more  equitable  water  distribution,  and  better 
customer services. These benefits will go hand in hand with raised public health, hygiene, and environmental 
awareness,  and  improved  sanitation  facilities  and  maintenance.  The  Project  will  also  accumulate  positive 
socioeconomic and poverty reduction benefits to the Melamchi Valley population (40,000). These will include 
increased  incomes  from  the  expanded  market  and  upgraded  skills,  reduced  workload  for  women,  better 
education for children, and reduced incidence of trafficking of girls. 

• Benefit to those people residing in the area by getting adequate supply of water 
• Water  supply  within  the  context  of  comprehensive  water  resource  management,  institutional  and 
sector administration responsibilities, 
• Levels of service including those to the urban poor 
• Capital investment mechanisms and development plans 
• Private sector participation 
• Subsidies and cost recovery objectives 
• Human resources development 
• Public awareness and hygiene education 
• Promotes  the  efficient  use  of  potable  water,  with  less  ground  water  extraction,  resulting  in 
environmental benefits 
• With the introduction of the project and the system upgrade, people would be willing to pay more for 
the facility, helping in economic feasibility. 

5.8 Other factors 

5.8.1 Issues in Melamchi Implementation  
• Breakeven point – will take many years to achieve 
• Expensive – consume 80% of total investment on water 
• Diversion of Melamchi river effects the livelihood of people and ecology of the area 

5.8.2 Impact on poverty 
Socioeconomic  surveys  conducted  during  project  preparation  suggest  that  about  20%  of  households  in 
Kathmandu Valley live in poverty, with incomes less than NRs 6,000 per month. The major project benefits are 
savings and incremental benefits accumulating to water users and to the economy, from the improved water 
supply and management. An examination of the demand curves indicates that the net benefit accruing to a 
poor household (benefit less tariff paid) is about the same as that accruing to a not‐so‐poor household, but 
the  composition  of  the  benefits  is  different.  The  poor  household  has  a small absolute  savings  benefit  and  a 
large  absolute  incremental  benefit.  Assuming  a  single  rate  tariff,  the  distribution  of  the  net  benefits  to 
consumers is about equal to the distribution of the population. However, the relative impact on the poor is 
better,  with  impact  ratios  of  net  benefit  over  income  estimated  at  1.6  for  the  poor  and  0.4  for  the  not‐so‐
poor. Assuming a stepped tariff structure, the impact ratio for the poor increases to 1.8, while that for the not‐
so‐poor decreases to 0.3. 

22 | P a g e  
 
Economics of Water Allocation 
5.11 Cost estimates 
The project is estimated to cost $464 million including contingencies, interest during construction, and taxes 
and duties. Foreign exchange costs are estimated at 59% of total costs, local currency costs at 41%.  

CHAPTER 6 | CONCLUSION 
ƒ The  benefits  achieved  from  water  supply  projects  should  be  measured  more  in  terms  of  social  and 
economical factors rather than financial 

ƒ Subsidies may be required for equity in water distribution, but not to the extent that this promotes 
misuse and increases burden on the system  

ƒ Participation  of  local  communities  during  both  design  and  implementation  is  crucial  for  project 
efficiency, sustainability and success. 

ƒ Project design should institute appropriate O & M mechanisms and properly delineate responsibilities. 

ƒ Good  governance  and  anticorruption  measures  contribute  to  a  more  favorable  project 
implementation environment. 

ƒ Private  sector  participation  should  be  encouraged,  especially  in  the  marketing,  distribution,  and 
maintenance of project outputs. 

23 | P a g e  
 
 

REFERENCES: 
1.  Planning approaches in Nepal  ‐  Dr. Jibgar Joshi 

2.  Handbook for the Economic Analysis of Water Supply Projects  ‐ Asian Development Bank 

3.  Report  and  recommendation  of  the  president  to  the  board  of  directors  on  a  proposed  loan  to  the 
kingdom of Nepal for the Melamchi water supply project   ‐ Asian Development Bank 

4.  Designing optimal water supply systems  for developing countries  ‐ Grace Ukoli Onodipe, B.Sc., M.S. 

5.  The  Economic  Costs  and  Benefits  of  Investments  in  Municipal  Water  and  Sanitation  Infrastructure:  A 
Global Perspective  ‐ Dale  Whittington and W. M. Hanemann 

6.  Lecture notes   ‐ Provided by Dr. Jibgar Joshi 

 
 
 
 
ACKNOWLEDGEMENT 
Our  sincere  appreciation  goes  to  Mr.  Jibgar  Joshi,  course  coordinator  of  Economics,  for  his 
encouragement  in  preparing  this  seminar  report.  His  valuable  guidance,  suggestions  and 
wholehearted support is highly appreciable.  

We highly appreciate timely assistance provided by guest lecturer, Mr. Tope Bahadur Basnet  for 
his valuable guidance and suggestions. 

We  would  also  like  to  thank  program  coordinator  Mr.  Ajaya  Chandra  Lal,  Mr.  Sudarshan  
Raghubanshi  ,  Mr.  Suresh  G.C  and  Mrs.  Leela  Pandey  for  their  valuable  supports  and 
cooperation. 

Last  but  not  the  least  we  would  like  to  express  our  sincere  gratitude  to  all  our  friends  who 
helped us to prepare this report. 

 
 
LIST OF ACRONYMS 
ADB    Asian Development Bank 

EIA    Environmental Impact Assessment 

NWSC    Nepal Water and Sewerage Corporation 

NWSC    Nepal Water Supply Corporation 

KMC    Kathmandu Metropolitan City 

HMG    His Majesty of Government 

WSP    Water Supply Project 

IRR    Internal Rate of Return 

FIRR    Financial Internal Rate of Return 

EIRR    Environmental Internal Rate of Return 

NPV    Net Present Value 

WTP    Willingness To Play 

MWSP    Melamchi Water Supply Project 

MWSDB  Melamchi Water Supply Development Project   

KUKL    Kathmandu Upatyaka Khanepani Limited 

JBIC    Japanese Bank of International Cooperation 

NORAD   Norwegian Agency for International Cooperation 

SIDA    Swedish International Development Cooperation Agency 

O & M    Operation and Maintenance 

PPP    Public Private Partnership 

BDS    Bulk Distribution System 

MLPD    Million Liters Per Day 

VDC    Village Development Committee 

PO    Private Operator 

 
 
 
 
 
 
 
 
 
 
Table Of Contents 
Chapter 1| INTRODUCTION ................................................................................................................................... 2 

1.1 Background .................................................................................................................................................. 2 

1.2 Introduction ‐ Water as economic commodity ............................................................................................ 2 

1.3 Objectives ..................................................................................................................................................... 3 

1.4 Scope and limitation..................................................................................................................................... 3 

1.5 Methodologies ............................................................................................................................................. 3 

Chapter 2 | WATER AND WATER SUPPLY .............................................................................................................. 4 

2.1 Water sources .............................................................................................................................................. 4 

2.2 Water supply system .................................................................................................................................... 4 

Chapter 3.0 | ECONOMY BEHIND WATER SUPPLY ................................................................................................ 7 

3.1 Factors involved in water Supply ................................................................................................................. 7 

3.2 Financial and Economic Analysis .................................................................................................................. 8 

3.3 Cost involved in Water Supply System ....................................................................................................... 12 

3.4 Cost Recovery ............................................................................................................................................. 15 

Chapter 4 | WATER SUPPLY SYSTEM IN KATHMANDU ........................................................................................ 15 

4.1 Water Supply .............................................................................................................................................. 15 

4.2 Current drinking water tariffs .................................................................................................................... 15 

Chapter 5.0 | MELAMCHI WATER SUPPLY PROJECT ............................................................................................ 16 

5.1 Background ................................................................................................................................................ 16 

5.2 Introduction ............................................................................................................................................... 17 

5.3 Project Aims and Objectives....................................................................................................................... 17 

5.4 MWSP: Cost Estimation .............................................................................................................................. 18 

5.5 Financial Analysis ....................................................................................................................................... 19 

5.6 Economic Analysis ...................................................................................................................................... 21 

5.7 Project Benefit ............................................................................................................................................ 22 

5.8 Other factors .............................................................................................................................................. 22 

5.11 Cost estimates .......................................................................................................................................... 23 

Chapter 6 | CONCLUSION .................................................................................................................................... 23 

References: ........................................................................................................................................................... 24 

 
 

Vous aimerez peut-être aussi