Fabrication and Installation Sequence of Works

1. Pre Fabrication off Corrugated Walls for Switchgear/MCC R , Electrical-Instrument,


and Battery Room in Workhsop

2. Stud pin shooting on the walls, can be executed on the ground or after installations
of walls at the deck
3. Blasting and painting of the walls for Room (on the ground or on the deck)

Blasting and
Stud pin Painting

4. Stacking Cellar Deck


5. Installation of column and braces, then complete welding & NDE

E&I and Battery Rooms Switchgear/MCC Rooms

6. Stacking and install of walls for the Switchgear/MCC, Electrical-Instrument, and


Battery Rooms.

Notes

E&I and Battery Rooms

 Notes :
- All Equipment with more then 2.1 m height must be installed first inside
the room before closing this Structural Wall Panel
- Hold identified structural wall panel prior to equipment installation.
- Wall Panel at Double Door “HOLD” for Equipment’s Installation
7. Stacking Mezzanine Deck with Roof Deck for Switchgear/MCC Room.

Roof Deck

Switchgear/MCC Rooms

8. Welding of structural wall panels of all Building Rooms.


9. Installation of doors strutural frames of all Building Rooms.

Door frame
Door frame

E&I and Battery Rooms


Door frame
Door frame

Switchgear/MCC Rooms

10. Installation of HVAC Duct Penetrations at Building Room Walls

Switchgear/MCC Rooms

11. Installation of Supports for Switchgear/MCC, Electrical-Instrument, and Lighting


Supports of all Bulding Rooms
12. Complete of welding of Supports for Switchgear/MCC, Electrical-Instrument, Cable
Trays and Lighting Supports of all Bulding Rooms below Mezzanine Deck.
13. Complete of welding of Supports for Switchgear/MCC, Electrical-Instrument, Cable
Trays and Lighting Supports of all Bulding Rooms above Roof Deck.
14. Installation of MCT’s and Completion of all remaining welding works on Cellar Deck
below Building Rooms Areas.
Switchgear/MCC Rooms

E&I and Battery Rooms

15. Installation of floor and architectural wall supports.


16. Installation of HVAC ducting supports in all Building Rooms.
17. Installation of Insulation on the wall in all Building Rooms
- Cutting of insulation
- Installation of first layer insulation
- Installation of alumunium foil and wire mesh
- Installation of second layer (final layer).
Insulation

Insulation

Insulation Insulation

E&I and Battery Rooms

Insulation

Insulation Insulation

Switchgear/MCC Rooms

18. Installation of Insulation on the roof in all Building Rooms.


19. Installation of steel plate floor deck with stringer support gird in all Building Rooms.
20. Installation canopy on each Building Rooms on the of double hinge door.
Steel plate floor

Steel plate floor

E&I and Battery Rooms

Steel plate floor Switchgear/MCC Rooms

21. Installation of cable tray and cable ladders

Switchgear/MCC Rooms

E&I and Battery Rooms


22. Installation of Electrical-Instrument, MSS/Switchgear, and Battery Equipments in
each Building Rooms.
23. Installation of fire rated doors in on each Building Rooms.
24. Installations of HVAC ducting, dampers, exhaust/supply fans in all Building Rooms.

Electrical & Instrument


HVAC
Battery Equipments

HVAC

E&I and Battery Rooms

Switchgear

Switchgear/MCC Rooms
25. Installations of furnitures in all Building Rooms.

E&I and Battery Rooms

Furnitures

Switchgear/MCC Rooms

26. Other works to complete the Building Rooms.