Académique Documents
Professionnel Documents
Culture Documents
PRN: 19020241091
IB - B
Assignment 7: Operations Research
Chapter 13
Solution: 9
a)
Activity Earliest start (ES) Earliest Finish (EF) Latest Start (LF) Latest Finish (LF)
A 0 9 0 9
B 0 6 9 15
C 9 15 9 15
D 9 12 12 15
E 15 15 15 15
F 6 9 16 19
G 9 11 19 21
H 15 21 15 21
I 21 24 21 24
c) The opening date of six months after the start of the project appears to be feasible as the above
calculations show that the longest time taken for the completion of the project is 24 weeks, i.e. 6
months.
Solution 13
Activity Expected Time Variance
A 5 0.11
B 3 0.027
C 7 0.11
D 6 0.44
E 7 0.44
F 3 0.11
G 10 0.44
H 8 1.78
Assuming that the distribution of the project completion time T follows a normal distribution, we
complete the following probabilities.
T=21 weeks
Z = (21-22)/√2.44 = -0.64
T = 22 weeks
Z = (22-22)/√2.44 = 0
T = 25 weeks
Z = (25-22)/√2.44 = 1.92
Solution 21
Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack
(ES) (EF) (LF) (LF)
A 0 3 0 3 0
B 0 2 1 3 1
C 3 8 3 8 0
D 2 7 3 8 1
E 8 14 8 14 0
F 8 10 10 12 2
G 10 12 12 14 2
Total project cost using normal times = 800 + 1200 + 2000 + 1500 + 1800 + 600 + 500 = $8400
Case Study: RC Coleman
Variance = [(b-a)/6]2
Let's derive expected time and variance for each activity as follows:
A 6 0.44
B 9 2.78
C 4 0.44
D 12 7.11
E 10 1
F 6 0.44
G 8 7.11
H 6 0.44
I 7 2.78
J 4 0.11
K 4 0.44
Activity ES LS EF LF Slack
A 0 3 6 9 3
B 0 0 9 9 0
C 9 9 13 13 0
D 13 17 25 29 4
E 13 13 23 23 0
F 23 23 29 29 0
G 13 21 21 29 8
H 29 29 35 35 0
I 29 32 36 39 3
J 35 35 39 39 0
K 39 39 43 43 0
0.84 = 40 - X / 5.651/2
X = 38 weeks
If we want 80% of the project completion by 40 weeks, then the expected project time should be
reduced to 38 weeks.
MIN 450Ya+400Yb+600Yc+300Yd+1000Ye+650Yf+750Yg+700Yh+800Yi+400Yj+500Yk
S.T.
1) 1Ya+1Xa>6
2) 1Yb+1Xb>9
3) 1Yc-1Xa+1Xc>4
4) 1Yc-1Xb+1Xc>4
5) 1Yd-1Xc+1Xd>12
6) 1Ye-1Xc+1Xe>10
7) 1Yf-1Xe+1Xf>6
8) 1Yg-1Xc+1Xg>8
9) 1Yh-1Xd+1Xh>6
10) 1Yh-1Xf+1Xh>6
11) 1Yh-1Xg+1Xh>6
12) 1Yi-1Xd+1Xi>7
13) 1Yi-1Xf+1Xi>7
14) 1Yj-1Xh+1Xj>4
15) 1Yk-1Xi+1Xk>4
16) 1Yk-1Xj+1Xk>4
17) 1Xk<38
18) 1Ya<2
19) 1Yb<2
20) 1Yc<2
21) 1Yd<4
22) 1Ye<3
23) 1Yf<2
24) 1Yg<3
25) 1Yh<2
26) 1Yi<3
27) 1Yj<1
28) 1Yk<1
OPTIMAL SOLUTION
Activity Weeks
B 7
C 3
E 10
F 6
H 6
J 3
K 3