Académique Documents
Professionnel Documents
Culture Documents
1
Quality System
2
Importance of Quality Systems
Quality Problems
System
Non
Adherence
70%
3
Reason for Defect ?
System failure
Adherence to Process :-
- Process Control standard (PCS)
- Maruti Inspection Standard (MIS-P)
Adherence to System:-
- Vendor Quality Assurance Manual (VQM)
Quality Systems Assessment by MSIL
MSIL QA-VSA conduct System Audit at Tier 1
Supplier periodically.
Total Clause in Check Sheet: 14
No. of Check Points: 79
Scoring:
Score Criteria
O (Circle) +3 System defined & Implemented
∆ (Traingle) 0 Minor deficiency either in system definition or implementation
X (Cross) -3 Major deficiency either in system definition or implementation
Key Clauses
1. 4M change Management
2. Tier 2 Control
3. Quality Abnormality Handling
4. Equipment Maintenance
5. Operator Training and Education
Quality Systems Status
Red Yellow Green Supplier Status
Clause 1
(Production Preparation)
2 Regarding 1 Do you implement follow-up to Master Timing plan as per APQP matrix
management / control the schedule and progress Customer events (sample approval, trial
implementatio of production preparation items? dates, SOP at customer end) and
n by production vendor's events (sample submission,
preparation pilot lot submission, SOP)
plan / report Plan Vs Actual updation
(master plan) Micro timing plan matching with
MACRO plan (wrt. timing)
Capturing delays in plan v/s actual in
timing plans.
3 Defect 2 Do you review and improve Procedure for FMEA with CFT
prevention on FMEA or Matrix diagrams when approach
the stage of any critical issue occurs after Rating of FMEA as per AIAG
process design SOP?
guidelines and having back up
by using
data for rating. Allocation of
FMEA/Matrix
diagram severity, occurrence & detection as
per AIAG manual
Cut off criteria for taking action as
per latest AIAG manual (Based on
Priority level decided by SOD
ratings)
Review of FMEA as per decided
criteria and at decided frequency
PFMEA
POTENTIAL
• What is It?
FAILURE MODE AND EFFECTS ANALYSIS
(PROCESS FMEA)
Process Step
• Objective or Purpose
Classification
Occurrence
Current Current
Detection
/ Function
Severity
Potential Potential Potential
RPN
Process Process
Failure Effect(s) Causes(s)
Mode of Failure of Failure Controls Controls
6
Clause 1 – Production Preparation
Quality 19 All PPAP documents prepared & varified as per actual process
Scope:
Initial flow control is applicable for newly developed parts or parts
developed after engineering change or after process change.
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
S Sub Clause S Check Point Requirement
No No
S
Sub Clause S No Check Point Requirement
No
Regulation ② How do you define items required Special controls (increased
2 for special control during initial inspection, increased sample size etc.
initial production control? Do you set at all stages - incoming, in-process &
production stricter inspection methods than the final)
control ordinal inspection?
IFC
IFC
IFC
Production preparation ECN PCN
IMPORTANT!
Always ensure implementation of
IFC in new part & post-SOP
ECN/PCN cases!
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
Special control during IPC period:
Increased or tightened inspection across all inspection stages within the process
Incoming, in-process, doubled inspection for FG parts (Addition Firewall/ IPC station)
Monitoring of Process capability for each product and process
OK . NG
OK . NG
OK . NG
IMPORTANT!
OK . NG
It is necessary to deploy stringent
checks at respective inspection OK . NG
stages
OK . NG
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
S
Sub Clause S No Check Point Requirement
No
1 Do you pick up issues and improve Do you record, analyze and improve
2 Implement them during initial production the issues reported during IFC
ation of control? period.
initial
production
control
② Do you control process capability Do you monitor Process capability,
and defect rate during initial defect rate during IFC period.
production control?
Clause 2 – Initial Production Control
Countermeasure:
Checkpoint when any defect occurs
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
Initial control period termination conditions:
Initial production control period can be terminated in case if following targets
are achieved:
Zero customer complaints
Zero Firewall/ IPC station defects
Inhouse rejection ppm (less than annual target)
Process capability Cpk>1.67 (or Process performance Ppk)
Effective implementation of countermeasure for production preparation issues
Effective implementation of countermeasure for issues observed during Initial production
control period
This means that the production can be resumed as per normal controls as specified in control plan.
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasures >> Exit
OK . NG
1 Customer complaints 0 OK . NG
Result of Initial Production Control OK . NG Initial control checks can be terminated YES . NO
If No, IPC period extended by _______ days, reason for extension ____________________________________________________________
___________________________________________________________________________________________________________________
(please use new sheet for extension period)
End of IPC (Termination)
ENGG PROD PUR PE HOD - QA
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 3
(4M Change Management)
Clause 3 –Change Management
S S No
Sub Clause Check Point Requirement
No
3.1 Definition and 1 Do you define List of changes that can occur
implementatio unexpected change in process related to 4M.
n of changing (unusual) and planned Distribution of changes into
management change clearly? planned and unplanned
Major Observation:-
4M changes related to man, method and material not
identified clearly.
No clarity on planned and unplanned.
Clause 3 –Change Management
Planned
Changes
4M
Change
Unplanned
Changes
Major Observation:-
Actions to be taken during 4M unplanned changes are not defined.
Usually set up part check is considered sufficient.
Operators are not aware of 4M changes
Clause 3 –Change Management
What are the
changes in 4 M
category
In-house and
Brainstorming Past Defect
customer end
session History
standards
Training
Document No:-
Revision No:-
4M CHANGE MANAGEMENT GUIDELINES Revision Date:-
Retro parts are the parts which are already produced when we come to know of change in process like m/c break down / pokayoke failure etc .
Part Inspection Containment Parts are the parts produced after change ( ex. part produced by lower skill operator , part produce at time of pokayoke bypass
If any NG part observed in Retroactive and Containment Inspection then 100% parts to be checked since last ok check(Setup/Periodic inprocess check)
Provi de trai ni ng before deputed and obs erved cl os el y ( A) (C-Vi s ual i ns pecti on 100%
4. New Operator YES Yes NO YES Supervi s or No Yes
by s upervi s or di m as per s ampl i ng pl an )
1 Man ( A)
( B) ALL PARTS SINCE LAST QA
Unpl anned Change 5.Operator not abl e to work due to
1.2 Operator of s ame s ki l l deputed NO Yes YES No Supervi s or INSPECTION TO BE CKECK No Yes
(Unexpected Change) s i cknes s or acci dent
VISUALY AND DIM CHECK AS PER
SAMPLING PLAN )
( A)
( B) ALL PARTS SINCE LAST QA
INSPECTION TO BE CKECK
Unpl anned Change 5.Operator not abl e to work due to
1.3 Operator unders ki l l deputed. YES Yes YES YES Supervi s or VISUALY AND DIM CHECK AS PER No Yes
(Unexpected Change) s i cknes s or acci dent
SAMPLING PLAN )
(C-Vi s ual i ns pecti on 100% di m
as per s ampl i ng pl an )
2.Change i n Mol d Start Producti on after s et up and FPA . NO Yes No No Supervi s or (A) No No
( A)
( B) ALL PARTS SINCE LAST QA
Producti on s hi fte d to othe r ma chi ne (Sa me
ca pa ci ty)Whe re the pa rt ha s be e n produce d e a rl i e r.
NO YES YES NO Supe rvi s or INSPECTION TO BE CKECK No No
VISUALY AND DIM CHECK AS PER
SAMPLING PLAN )
( A)
( B) ALL PARTS SINCE LAST QA
INSPECTION TO BE CKECK
Producti on s hi fted to hi gher / l ower capaci ty
NO YES YES YES Supe rvi s or VISUALY AND DIM CHECK AS PER No
machi ne.*
SAMPLING PLAN )
3.Machi ne/di e / TOOL /MOULDS
(C-Vi s ual i ns pecti on 100% di m
under breakdown
as per s ampl i ng pl an )
( A)
( B) ALL PARTS SINCE LAST QA
INSPECTION TO BE CKECK
Unpl anned(Unexpecte
2.2 VISUALY AND DIM CHECK AS PER
d Change)
machi n res tarted after temprary repai r.* NO YES YES YES Supe rvi s or SAMPLING PLAN ) No
(C-Vi s ual i ns pecti on 100% di m
as per s ampl i ng pl an ) to be
fol l owed up to parmanent
reapi r.
2 Machi ne/
( A)
( B) ALL PARTS SINCE LAST QA
4.Machi ne Parameter of out of Stop producti on and res tart producti on after
NO Yes YES NO Supervi s or INSPECTION TO BE CKECK Yes Yes
s pc.* res etti ng the parameters .
VISUALY AND DIM CHECK AS PER
SAMPLING PLAN )
( A)
( B) ALL PARTS SINCE LAST QA
Stop producti on and res tart producti on after
5.Checki ng Fi xture Breackdown* NO Yes YES NO Supervi s or INSPECTION TO BE CKECK Yes Yes
res etti ng the parameters .
VISUALY AND DIM CHECK AS PER
SAMPLING PLAN )
( A)
( B) ALL PARTS SINCE LAST QA
10.Power fel i or Operator i nform to s upervi s or, res tart the machi ne. NO YES YES no Supervi s or INSPECTION TO BE CKECK No Yes
VISUALY AND DIM CHECK AS PER
SAMPLING PLAN )
( A)
( B) ALL PARTS SINCE LAST QA
1)Ins pecti on to be s topped
11.Ins trument out of cal i berati on NO Yes YES no Supervi s or INSPECTION TO BE CKECK No Yes
2) Submi t i n l ab and i s s ue cal i berated verni er
VISUALY AND DIM CHECK AS PER
SAMPLING PLAN )
( A)
( B) ALL PARTS to be check SINCE
12.Poka Yoka Not worki ng (l eakage 1)Val i date the poka yoka
NO Yes YES no Supervi s or LAST ok veri fi cati on of pokayoke No Yes
tes t) 2) Rej ected parts s houl d be us ed
for the poi nt checked by
pokayoke of that machi ne )
Stop producti on and res tart producti on after ( A) (B-FOA/MOA ) (C-Vis ua l ins pection
14.Noi s e Level Hi gh NO Yes YES YES Supervi s or
100% & n=5 Dimens iona l )
No Yes
recti fyi ng the noi s e of machi ne.
Stop producti on & res tart producti on after correcti on ( A) (B-FOA/MOA) (C-Vis ua l ins pection
15. Ai r pres s ure l ow/hi gh NO YES YES YES Supervi s or
100% & n=5 Dimens iona l )
No Yes
i n ai r pres s ure.
Clause 3 –Change Management
S S No
Sub Clause Check Point Requirement
No
3.1 Definition and 3 Do you record product Records of quality of parts
implementatio quality check results to produced (Process and
n of changing ensure traceability? product parameters) during
management 4M change condition
Parts traceability through
identification(tag)?
4 Do you retroactively Checking records of parts
check about product produced before 4M change
quality when unexpected condition occurs(as per
change occurs? control plan)
Major Observation:-
Report contains part checked and found ok.
Content of inspection is not available.
Parts produced before breakdown (Retroactive parts) are not
checked.
Clause 3 –Change Management
Change item to be
recorded in
standard format
Clause 3 –Change Management
Clause 3 –Change Management
Clause 3 –Change Management
Abnormal conditions Criteria
Process Flow
Layout
Graph
Defect due to 4 M 50
change parts 600 parts 12000 Vehicles
X 1000X
S S No
Sub Clause Check Point Requirement
No
3.2 Definition and 1 Do you define initial part Procedure for First production
implementatio clearly? parts (FPP)
n of changing
management 2 Do you control initial Implementation of tags for
parts separately and various types of parts as per
make quality records manual.
about them? Proper storage system for
Initial parts to avoid mix-up.
System/Rule for Pre-ECN/PCN
parts disposition.
System/Rule for customer
information / approval before
implementation of planned
changes.
Major Observation:-
Procedure for FPP is generally not found.
Inspection & identification tags not defined for trail parts
IPP system not implemented for Tier-2
Clause 3 –Change Management
Clause 3 –Change Management
Clause 3 –Change Management
Clause 4
(Standard Management)
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
4.1 Procedure to 1 Do you make process Prepare control Plan for all the
make process control standards for all part manufactured by your
control products which is company
standards(QA shipped to SMC / MSIL?
process
charts)
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
4.1 Procedure to 2 Do you mention defined Mention both process & product
make process both characteristics of characteristic on control plan?
control quality and production
standards(QA control on the process
process control standards?
charts)
Observation (4.1.2)
Gaps in Standard management
All process characteristics not mentioned in control plan
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
Observation (4.1.3)
Gaps in Standard management
Poka Yoke, Limit sample reference not available in PCS
Not mention the details of Tier-2 & control characteristics
Clause 4 – Standard Management
PART ASSY ( Write part number of the VENDOR Write your company's name
NAME INDL
assembly)
( Write part number of the Process Control Standard Write serial no of Write total no. of pages
assembly) each page
(Write M UL, part number of Write A for and A and F for Functional parts
the assembly) MODEL
PART ASSY at the end of Part Number Write name (s) of mode (s) for
which this part is supplied
Page No.
(Write M UL, part number of
the assembly)
NUMBER INDL
Process Control Standard Control Inspectio Critical Control Sam pling R e c o rding
Process Description R e a m rk s
Machine Param ter Spec. Spec. n Method Characteri Incharge schem e/ Yes/ N o
Sl. No. stics frequency
Write check
Write the name of process/ Write For each For each Control Write A triangle Write Write if the For critical
Write frequency e.g.
operation e.g. incoming inspection, result of parameters
type, process control specificati briefly the should be R 100%. N=5
sequence
number
casting, machinging, plating etc. make w rite parameter on must method of marked if Am c=0. Start up Triangle to
checks are
recorded or
write action to
be taken in
control the W (I.e. check 5
checking
of the
For processes w hich are sub-
capacity
etc. of the parameter
w rite the
engineeri
be tighter
than the e.g. visual process P
pieces at the indicate Critical
not. It will be
better to also
case of
abnormally e.g.
process/ ti me of
mention the seggregation,
operation
contracted and for bought out
parts, w rite "sub-contracted"
machine s of both
products
ng standard w ith Go-
No Go
parameter
is critical
or
I
process
setting and
Process
way of scrap rework
used e.g. specificati specificati recording e.g. etc.
w ithing brackets below the Hydraulic (e.g. dia, on value on e.g. gauge, (See start if none is
defective).
Characteristics
name of report,
register, Z.R.
process name. Press 400 hardness w ith 250 + 7C, measurin legends N=3, c=0/Hr. chart etc.
Ton. etc) as tolerance 1.5 + 0.4 g w ith on bottom (I.e. check 3
For processes related to and w ell as or limits kg/cm2 45 micromete left pieces every
Functional items, w rite or process corner) hour and
e.g. 250, 55 r as per
continue if
respectively at the end of process (e.g. + 10C, 1.5 IS ….. none is
name. funace + 0.5 Etc. defective).
temp. kg/cm2 40- N=10, c=0;
Include sketch of the product pressure LOT (I.e.
60 HRC check 10
at each stage before and after etc.) pieces in each
each process lot and
accept the lot
if none is
defected).
R- Patrol Inspection Write briefly the reson for Date Prepared By Approved By
revision and referevce
AM - Automatic
Measurement Vendor
Legend for W- Operator
control P- Process Approval
Incharge I- Inspector
Write Revision Dates REV NO/DT Description Appd By MUL
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
Observation (4.2.1)
Gaps in Standard management
Retention period is not mentioned in procedure
Clause 4 – Standard Management
63
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
Observation (4.2.2)
Gaps in Standard management
Different process/ product characteristics in PCS, WI etc.
Clause 4 (Standard Management)
S No Sub Clause S No Check Point Requirement
4.2 Procedure to 3 Do you make use of lists Do you have the system to control
control to control preparation the revision details of any
standards and revision of document.
standards and share the
・Process updated information?
control
standards
・Inspection
specifications
・Operation
instructions
Observation (4.2.2)
Gaps in Standard management
Revision history not maintained properly.
Revision not captured in document.
Retrieval of old documents and distribution of new document
Clause 5
(Education & Training)
Clause 5 – Education & Training
Training Process
Skill Development
Work on
Station
Clause 5 (Education & Training)
Training schedule for new working associates
Duration Training after joining
1st day Joining formalities in HR
Briefing General Rules and Regulations
a. Explanation of standing orders
2nd day b. Canteen, dispensary and other medical facilities
c. Briefing on safe working in the shop floor
d. Fire & safety training
Week 1
Judgement
Clause 5 – Education & Training
Clause 5 – Education & Training
S S No
Sub Clause Check Point Requirement
No
5.2 Education for 1 Do you implement Status for training plan vs actual.
managers/Ins planned education to Training effectiveness check and
pectors/ supervisors for skill re-training criteria.
Special improvement ? Training content for planned
operators training should be adequately
defined.
Roles & responsibilities of
supervisors to be clearly defined.
Name of the
Category
Operator
No Instructions
Line No. Process Name
Problem Required
Checked by Designation O X
Classificati Sub Item Plan
Item No. Check Point Remarks
on No. Actual
Coherence between specification mentioned in
1
Operation Operation Standards condition & actual condition.
A
Conditions Whether operator is immediately reading the "display
2
value" and recording them in the check sheet or not?
Operation Is the operation being carried out as per decided
B 1
Sequence operation sequence or not?
are Quality checks being carried out and the finding are
1
Quality recorded in the check sheet or not?
C
Checks Checks in of "Initial Product" and "Proper display" for
2
Initial Production are being carried out or not?
Equipment Checking of Machine and Equipments is being carried
D 1
Checks out and check sheets are duly filled or not?
Working condition checks are being carried out in
regard to device in which Fool proofing are being
1
incorporated, entries are made accordingly in the check
sheets or not?
Equipment Working conditions checks are also being carried out
E 2
Testing for Dies and Jigs or not?
Working condition checks are being carried out in
3 regard to "Inspection Equipments, Measurement
purpose tools, Devices, Gauges etc. or not?
Is the grinding and changeover of the Cutting Tools,
Changeov 1 Grinding Stone, Electrodes etc. being timely carried out
er of or not? Are the records retained or not?
Clause 6
(Quality Audits)
Clause 6 – Quality audit and process verification
S S No
Sub Clause Check Point Requirement
No
90
Clause 7 – Tier 2 Control
S S No
Sub Clause Check Point Requirement
No
Observation:-
Gaps in Selection check sheet
S
Sub Clause S No Check Point Requirement
No
Observation (7.2.1)
Gaps in Audits
Audit not planned/ Conducted for all supplier
No re-plan available for the audits not conducted.
Observations are not captured in Supplier selection check sheet
No Action plan/ Follow up for open observations
Clause 7 – Tier 2 Control
S
Sub Clause S No Check Point Requirement
No
7.2 Management, 2 For outsourcing any Procedure to instruct suppliers
quality production, do you about Initial flow control at
evaluation and instruct them clearly supplier end.
instruction for about function and Implementation of Initial
suppliers important control items Supply control at supplier end
of products at the as per Procedure for
meeting ? new/ECN/PCN parts.
Observation (7.2.2)
Gaps in Development
Inspection Standard not decided with Sub Supplier.
Explanation of Part criticality not evident
Clause 7 – Tier 2 Control
S
Sub Clause S No Check Point Requirement
No
7.2 Management, 3 For outsourced process, Part development schedule
quality do you control the monitoring and capturing the
evaluation and progress of production delay reasons and making
instruction for preparation and action plan to meet the
suppliers confirmed issues ? timeline.
Monitoring the trial results at
supplier and prepare the
action plan based on CFT
approach.
Conducting PPAP at Suppliers.
Observation (7.2.3)
Gaps in Development
APQP Time plan Vs Actual not evident for Sub Supplier parts. Only
inspection reports available.
PPAP Approval not done / delayed
Clause 7 – Tier 2 Control
S Sub Clause S No Check Point Requirement
No
7.2 Management, 4 Do you make suppliers to Procedure to instruct suppliers
quality conduct initial about Initial flow control and
evaluation and production control and its monitoring.
instruction for decide department in
suppliers charge of conduct? Implement Initial Supply
control at supplier end as per
Procedure for new parts/
Change parts/ PCN cases.
Observation (7.2.4)
Gaps in Tier Initial flow control
IFC procedure not evident for Tier 2 Suppliers
Supplier Audit check sheet doesn’t contain related to IFC.
Clause 7 – Tier 2 Control
S Sub Clause S No Check Point Requirement
No
7.2 Management, 5 Regarding the parts Procedure to control the
quality which are shipped outsourced process where
evaluation and directly to the customers Delivery is done directly by
instruction for from outsourced Supplier to customer.
suppliers suppliers, do you have Adherence of Product Quality
method to assure checks as per procedure.
product quality
performance?
Observation (7.2.4)
Gaps in Outsourced process
No Gaps .
Clause 7 – Tier 2 Control
S Sub Clause S No Check Point Requirement
No
7.2 Management, 6 Do you make outsourced Procedure for Change
quality suppliers to conduct approval request from
evaluation and initial parts and 4M suppliers, control of initial
instruction for changing management parts & how have you
suppliers and is it possible to communicated your suppliers
trace? your requirements.
Does your supplier recording
the change situations
(summarized form) & ensuring
parts traceability and
submitting you at regular
interval.
Observation (7.2.4)
Gaps in Change management
Guidelines for changes is not prepared for Sub Suppliers.
Procedure for Change approval request from Sub Suppliers not
available.
Clause 8
(Handling abnormality in
quality)
Clause 8 – Handling abnormality in quality
S S No
Sub Clause Check Point Requirement
No
Major Observation:-
Major Observation:-
Major Observation:-
Major Observation:-
Major Observation:-
8.2 Prevention of 3 After corrective action are System for checking the
recurrence taken, do you conduct on- effectiveness of c/ms for
site checkup and evaluate customer, inhouse and
・Customer claims the effectiveness? supplier issue
・In process failure
・Suppliers failure
Major Observation:-
Major Observation:-
Observation (9.1.1)
Gaps in 5S
Observation (9.1.2)
Gaps in 5S
Identification tag not available. Similar parts kept together
Parts kept on floor, open environment etc.
Procedure for defining shelf life control, List of items with shelf life
and current status of monitoring not available.
Clause 9 – 5S Management
S No Sub Clause S No Check Point Requirement
Observation (9.1.3)
Gaps in 5S
Unidentified material at inspection table, Near machine etc.
Clause 9 – 5S Management
Observation (9.1.4)
Gaps in 5S
Lux level not defined as per IS: 6665
Lux level not monitored in B, C shift
No defined frequency & records for Lux monitoring.
Clause 9 – 5S Management
S No Sub Clause S No Check Point Requirement
9.2 Production 1 Do you keep condition Check condition of production
equipment's of production equipment's on shop floor. There
management equipment's, jigs and should be no equipment's
tools properly? damaged, clamps loose, oil
leakage from machine etc.
Check that production
equipment should not be fixed
with temporary non-standard
methods like packing with
scrap, tied with cloth etc.
Observation (9.2.1)
Gaps in 5S
Unclean machine, Air
Oil leakage from machine.
Clause 9 – 5S Management
S No Sub Clause S No Check Point Requirement
9.2 Production 2 Do you keep condition Check condition of inspection
equipment's of inspection equipment's on shop floor. There
management equipment's properly to should be no equipment's
ensure accuracy? damaged, checking fixture
clamps loose, datum pins
missing etc.
Observation (9.2.2)
Gaps in 5S
Pin missing/ Damage on inspection fixture
Validation of fixture not done as per time
No defined frequency for Pin replacement
Clause 10
(Equipment/ Inspection
equipment's
management )
Maintenance of Production Equipment
(Machine /die /tools /molds /jigs /fixtures)
119
Case Study - Improper Repair after machine
breakdown
Observation (10.1.1)
Gaps in Daily check sheet
Availability of Daily/ Periodic check sheet for all machines, dies,
tools/ Molds
Objective values are not captured in Daily check sheet.
Actual verification not done just putting √ on check sheet.
Checking Methods and Judgment criteria are not defined.
Clause 10 – Maintenance
S No Sub Clause S No Check Point Requirement
Observation (7.2.1)
Observation (10.1.1)
Gaps in replacement
Observation (10.1.1)
Gaps in Calibration
Calibration plan vs Actual not adhered
No judgement is taken based on calibration reports
Clause 10 – Maintenance
S No Sub Clause S No Check Point Requirement
Observation (10.1.1)
Gaps in boundary Samples
Boundary sample not stored adequately.
Clause 11
(Implementation of
Standards)
Clause 11 – Implementation of Standards
S No Sub Clause S No Check Point Requirement
11.1 Production 1 Do you use easy All process & station should
equipment's expression (visualizer, have operation standard / work
management onomatopoeia ,etc.) for instructions available.
operation instructions? All work instructions should be
So that operator can well defined with pictorial
easily understand display of instructions and
process and critical check points.
points. It is preferable to have work
instruction in local language so
that operators can easily
understand the content.
Observation (11.1.1)
Gaps in Implementation of Standards
Work instructions not available in English as well as regional
language.
Clause 11 – Implementation of Standards
S No Sub Clause S No Check Point Requirement
11.1 Production 2 Do you keep operation Work instructions should be
equipment's instructions on the kept at accessible place. For
management accessible place and Important information in work
post important quality instructions, highlighting is
points and critical recommended. .
operation points on the
place where operators
can see it easily?
Observation (11.1.2)
Gaps in Implementation of Standards
Clause 11 – Implementation of Standards
S No Sub Clause S No Check Point Requirement
11.1 Production 3 Do operators and Check that operators are
equipment's supervisors operate following the process as defined
management according to the in work instructions / OPS.
operation standards? Check that supervisor is
performing job as per his daily
work management sheet /
defined job responsibilities.
Check that inspectors are
following the process as defined
in work instructions / OPS.
Observation (11.1.3)
Gaps in Implementation of Standards
Observation (11.1.4)
Gaps in Implementation of Standards
Observation (11.1.5)
Gaps in Implementation of Standards
Major Observations:-
Major Observations:-
Major Observations:-
Observation (13.1.1)
Gaps in Handling Management
Approved packaging standard not available for child parts.
WIS not prepared for packaging std for FG parts.
Packing for FG was not done as per WIS.
Clause 13 – Handling Management
S No Sub Clause S No Check Point Requirement
13.1 Bins/ Trolley 2 Are the packaging style Check the bin / trolley and
Management & storage environment storage condition of work-in-
controlled with process, child parts and FG
consideration to parts. It should be able to
contamination control damage and
contamination to the parts.
Observation (13.1.2)
Gaps in Handling Management
Broken bins
Overloaded bins/ trolleys
Bins directly on shop floor
Bins found dirty/dusty.
Clause 13 (Handling Management)
S No Sub Clause S No Check Point Requirement
13.1 Bins/ Trolley 3 Do you have system to System defined at supplier for
Management maintain Bins /Trolleys in identification and periodic
Good Condition. maintenance of bins / trolleys
or BOP/WIP/FG.
Check if bins / trolleys are
cleaned at regular frequency
for BOP/WIP/FG.
Observation (13.1.3)
Gaps in Handling Management
Maintenance plan for Bins/ Trolleys
WIS not prepared for Bin/Trolley maintenance.
Bins replacement time needs to be standardized.
Bins cleaning to be ensured before keeping FG parts inside the
bins.
Clause 13 (Handling Management)
13.1 Bins/ Trolley 4 Does the Packaging Check for the proper packing
Management method prevent condition of parts to avoid
Transportation damage damage during internal
movement and also during
dispatch to customer.
Observation (13.1.4)
Observation (14.1.3)
Gaps in Critical parts management
Summary of Maru A parts Rework not captured e.g. Rework
record, Re-inspection, Batch code, Dispatch details of Rework part
etc.
Thanks