Vous êtes sur la page 1sur 1

Condensed Construction Schedule

Meadow Creek Interceptor Upgrade Projects
Updated December 22, 2010
Estimated Start Estimated Finish Status
Contract A Work Areas
Notice to Proceed April 1, 2010 Complete
Pen Park Lane to Holmes Ave June 10, 2010 January 30, 2011 Clearing, benching and E&S complete.  Bypass pumping equipment and pipe are in 
operation at the old wastewater treatment plant site.  Pipe laying operation is on‐going 
and 800 feet of 48" has been installed.  Stream crossing is complete.  Production blasting 
is nearly complete at the old wastewater treatment plant site.  The bypass system will be 
moved to Locust Meadows/St. Charles after Christmas and production blasting and pipe 
laying will begin in those areas in the new year.    

Pen Park Golf Course to Pen Park Lane December 15, 2010 February 28, 2011 Contractor has mobilized to the Golf Course.


Holmes Ave to Rio Road January 15, 2011 April 1, 2011 Neighborhood meeting and easement delineation anticipated in Janurary
Rio Road to Melbourne Rd March 15, 2011 June 1, 2011
Boring Below Rio Rd August 1, 2010 February 28, 2011 Approximately 152 feet are complete of the 317 foot tunnel.
Boring Below Melbourne Road January 15, 2011 February 15, 2011
Close out and Final Completion June 30, 2011 August 14, 2011

Contract B Work Areas
Notice to Proceed April 1, 2010 Complete
Kenwood Lane to Brandywine Dr. June 1, 2010 January 30, 2011 Clearing, benching and E&S complete.  Bypass pumping equipment and pipe are 
operational.  Pipe installation is on‐going with approximately 2,200 feet installed.  
Contractor has installed pipe under railroad and the stream crossing.  
Brandywine Dr. to Pepsi Place October 25, 2010 February 15,2011 Clearing is complete.  Contractor is stockpiling materials in the easement.
Pepsi Place to Hydraulic Rd November 1, 2011 May 15, 2011 Clearing is complete.  
Hydraulic Rd to Emmet Street April 15, 2011 June 30, 2010
Boring Below Norfolk Southern September 17, 2010 October 22, 2010 Bore is complete.

Boring Below Hydraulic Road TBD
Boring Below Route 250 Bypass November 15, 2010 January 15, 2010 140' of 156' is complete
Close out and Final Completion June 30, 2011 August 14, 2011

Notes:   The above schedule is subject to change based on the Contractor's progress and will be updated accordingly. Within each area, the work will include surveying, clearing, geotechnical 
investigations, erosion and sediment control, grading, delivery of equipment and materials, sewer installation, final seeding and grading.  An overlap in work is anticipated when 
transitioning from one work area to the next.  Tunneling operations under railroads and roadways will be conducted independent of the posted schedule for each work area; further 
information will be posted as the final schedule for these activities becomes available.  The landscape restoration work will follow in the next planting season.   

Vous aimerez peut-être aussi