Académique Documents
Professionnel Documents
Culture Documents
:
À ?
During the govt. of PM Shaukat aziz (2006)
ECC in its decision of 16th august 2006 approved 150MW
Rental power plants proposal by WAPDA for the
installation at Piranghaib multan as emergency measure
subject to acceptance of tariff by NEPRA, stipulating the
WAPDA should only rent as much power as is absolutely
necessarily to be utilized with high load factors for
economics utilization of capacity.
During the caretaker Govt. of PM main Muhammad
Summro (15/02/2008) the ECC approved four rental power
plant each of 200-300mw (combine capacity 1000-
1200mw) as rental power plants in private sectors.
During PPP govt. (1/9/2008) ECC approved 1000MW
project for IPPs induction as M/s Karkey Rental project
Karachi. ECC latest decision (21/8/2009) approved a total
capacity (1500mw) for induction of rental power plant into
national gird, payment 14% mobilization advance against
bank guaranty by the sponsor and adjustable in monthly
rental payment according after commissioning of plant.
?
? .
Two rental power proposals received on 13/7/2006 from
GE & Alstom.
150 mw GE energy rental 10% advance payment against
advance bank guarantee .Monthly advance payment of 1%
for four rental months. Balance 86% in 36 equal monthly
rental services fee.
136mw Alstorm Power rental: 7% advance payment
against advance bank Guarantee balance 83% in 36
monthly rental services fee confirmed and irrevocable stand
by letter of credit.
??
Rental plants tariff is slightly different then normal IPPs
based on capacity return on capital, interest on loan and
repayment O$M and other variable cost components. RPPs
is simple cycle plant have different fuel consumption
pattern can be combined cycle ones over period of time
Gas-based RPPs required 92% availability guarantee RFO-
based RPPs required 85% availability guarantee.
The rental power generation costs between 12-13 cent per
KWh. Rentals have 3-5 years technical life span if they are
based on second hand machinery¶s installation for power
generation.
Its very important that 3-5 years term of contracts its not
feasible to procure brand new equipment due to long lead if
recovered over period of 3-5 years will push up the rental
payment exorbitantly high (2-3 time of present rate) most
of the RPP are almost new being of less then 10000 hours.
§ Registration fee US$ 100
§ RFP cost US$ 2,000
§ Banker¶s fee for issuance of Bid bond
§ Bid processing fee
§ Consultant fee $20,000 plus out of pocket expenses up to
bid submission
§ Capital Investment in Plant and other fee
§ 2% of the Lump-Sum Rental on successful issuance of
Letter of Award to
Type of Fuel =RFO
Total rental period = 5 years
Total rental payment in = $ 565 million
Payment made of 36 months = $ 339 million
Return after 36 months =167%
Annual return =61%
Fuel cost component = 6.344/kw
Annual rent =113
When we purchase the rental power plant at valued of cost.
The sum of economics depreciation and interest rate.
Interest rate means that financial return that could have
been earned had the money invested else where. The
interest rate of IMF in 11% per year.
Interest rate of $139*11% = $15.98million per year
Depreciation of plant $139/5 =$ 27.8 million
Interest rate and depreciation rate are for the 5years