METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
CONTENTS:
1. Scope of works
2. Access / Egress
3. Lighting
4. Plant & Equipment
5. Hazardous Materials & Substances
6. Waste Management
7. Special Control Measures
1|Page
PROJEK PEMBINAAN SEKOLAH BAHARU 30 BILIK DARJAH DAN
LAIN LAIN KEMUDAHAN DI SEK. MEN. KEB. PERMAI,
KEMAMAN, TERENGGANU
MECHANICAL & ELECTRICAL
METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
1. Scope of Works
Scope of Activities
Site Procedure
i. Site mobilization shall be done with real time monitoring the conditions & progress of
builder works.
ii. Before commencement of the work, carry out examination of the physical condition
of the area.
iii. Photographs should be taken where necessary, prior to commencement and during
works.
2|Page
PROJEK PEMBINAAN SEKOLAH BAHARU 30 BILIK DARJAH DAN
LAIN LAIN KEMUDAHAN DI SEK. MEN. KEB. PERMAI,
KEMAMAN, TERENGGANU
MECHANICAL & ELECTRICAL
METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
Method Statement
- Preparation Stage
a. Selection and sample submission of material as per specification by consultant and
JKR specification (CKE.LS.01.01.(02).2011).
c. For concealed or cast-in conduits must be complete with proper fittings and
accessories for either PVC or G.I. conduits.
d. For surfaced-run conduits, most widely used is G.I. conduits complete with fittings
and accessories.
e. Accessories used for the support of conduit both G.I. or PVC varies with method of
support. The most common being the conduit saddles. The spacing between
supports must comply with specifications by engineers, foreman and sub-contractor.
g. Preparation of detail shop drawings for the proposed mounting method including
support system by Engineer.
h. Conduit samples of the correct class must be subscripted for approval by consultant
prior to purchase of Engineer.
3|Page
PROJEK PEMBINAAN SEKOLAH BAHARU 30 BILIK DARJAH DAN
LAIN LAIN KEMUDAHAN DI SEK. MEN. KEB. PERMAI,
KEMAMAN, TERENGGANU
MECHANICAL & ELECTRICAL
METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
- Installation stage
a. Site survey of the proposed cable routing based on approved CSD by foreman /
sub-contractor together with Engineer.
b. Installation shall be carried out based on approved shop drawings & material used
shall be of approved brand.
c. Mark the exact position of the conduit route with the blue marker string and then
install conduit saddles.
d. Install the correct size of the conduits, by clamping with saddles by foreman / sub-
contractor.
e. Check to ensure no sharp edges within the conduit joints for surfaced conduit and to
ensure proper bonding for all conduit joint for concealed PVC conduit by foreman /
skill worker / sub-contractor.
f. Conduits shall run vertically or horizontally only for surfaced run conduits.
g. After installation of conduit, Engineer-in-charge shall check the complete works and
complete the Inspection checklist for Electrical conduit installation works
h. Engineer-in-charge shall arrange and request for inspections with the Client’s
representative M&E clerks of works (COW) using approved Main Contractor
Request for Inspection (RFI) form
i. Where installed within switches, distribution boards, control panels and the like,
wiring shall be neatly and carefully bunched, being adequately supported and held
in position by means of supports or brackets or insulating material as necessary.
4|Page
PROJEK PEMBINAAN SEKOLAH BAHARU 30 BILIK DARJAH DAN
LAIN LAIN KEMUDAHAN DI SEK. MEN. KEB. PERMAI,
KEMAMAN, TERENGGANU
MECHANICAL & ELECTRICAL
METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
- Approved Materials
For non-metallic conduits and fittings, they shall be of rigid high impact
PVC grade Heavy Duty Code No 4421 and shall be under Product
Certification Scheme. The colour of the conduit for concealed wiring
shall be of orange. Unless otherwise for purposes of identification or
distinguishing from another services, white coloured conduit shall be
Conduit PVC
used for surface wiring. Rigid high impact PVC conduits shall comply
with MS 1534:PT.1, MS 1534:PT2:Sec1, IEC 60614-1, IEC 60614-2-2,
IEC 60423, BS EN 61386-2, BS EN 50086-1 and fittings shall comply
with MS 1534:PT.1, MS 1534:PT2:Sec1., IEC 61035-1 and IEC 61035-
2-2..
5|Page
PROJEK PEMBINAAN SEKOLAH BAHARU 30 BILIK DARJAH DAN
LAIN LAIN KEMUDAHAN DI SEK. MEN. KEB. PERMAI,
KEMAMAN, TERENGGANU
MECHANICAL & ELECTRICAL
METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
2. Access / Egress
i. Proper step ladders shall be provided for access and egress into trenches as
applicable.
ii. All workers working at height shall equip themselves with proper attire including full
body harness if height >2 meters and additional with shock absorbers if height >4
meters. The harness lanyard shall be secured to the various secure points.
3. Lighting
Adequate temporary/task lighting shall be provided if work to be carried at night or at
dark places.
4 Electrical drill & Hacker (only for surface installation works) 1 lot
*The above machinery & Equipment used quantity will be varied depending on site conditions and production
rate.
6. Waste Management
i. The rubbish which would be created from our scope of works will be disposed to the
designated dumping ground.
ii. All waste materials to be placed at the designated waste bins according to types.
6|Page
PROJEK PEMBINAAN SEKOLAH BAHARU 30 BILIK DARJAH DAN
LAIN LAIN KEMUDAHAN DI SEK. MEN. KEB. PERMAI,
KEMAMAN, TERENGGANU
MECHANICAL & ELECTRICAL
METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
iii. The general waste will be collected / disposal periodically by licensed waste collector.
General Notes:
7|Page
PROJEK PEMBINAAN SEKOLAH BAHARU 30 BILIK DARJAH DAN
LAIN LAIN KEMUDAHAN DI SEK. MEN. KEB. PERMAI,
KEMAMAN, TERENGGANU
MECHANICAL & ELECTRICAL
METHOD STATEMENT:
INSTALLATION OF ELECTRICAL CONDUIT
1. The contents of this method statement should be communicated with the site workforces
who are involved with the activities.
2. An “Accepted” copy of this method statement should be available at the work locations
at all times during work.
8|Page