Académique Documents
Professionnel Documents
Culture Documents
Working Group
37.27
December 2000
AGEING OF THE SYSTEM
IMPACT ON PLANNING
PREPARED BY
WORKING GROUP 37-27
M. Ahmadi-Pour (Iran), K. Bakic (Slovenia), B. Bakka (Norway), G. Balzer (Germany), T. Davies (Canada), A.
Davriu (France), R. Gilbert (Northern Ireland), J. C. Hygebjerg (Denmark), C. Kelleher (Ireland), K. Kreβ
(Germany), L. Marketeg (Sweden), A. Nakazato (Brazil), A. Nourai (United States), J. Rimell (United
Kingdom), P. Smith (Ireland), B. Stirk (United Kingdom), L. Twardy (Poland), J. Williams (United States).
TABLE OF CONTENTS
1. INTRODUCTION..............................................................................................................................3
2. STATISTICS ......................................................................................................................................6
6. CONCLUSIONS ..............................................................................................................................40
In the past, the driving force for system modernisation has been load growth: equipment
was replaced because its rating or characteristics were no longer compatible with the
changing requirements due to steady and considerable load growth. Nowadays, in the
low growth environment that prevails in many countries, many assets are rated
sufficiently to fulfil their roles in electricity transmission up to the expiry of their
lifetimes. Furthermore, the very large groups of assets installed during high growth
periods are all likely to reach the end of their lives at about the same time.
In this context, CIGRÉ Working Group 37-27 was established with the following scope
of work:
• Describe the age of equipment in different systems and different types of locations.
• Identify and where possible quantify system problems due to ageing.
• Identify equipment types subject to deterioration due to ageing and equipment types
subject to technical obsolescence.
• Consider the range of options available to deal with ageing equipment in the system.
• Formulate guidelines for selecting the appropriate option.
The Working Group’s full Terms of Reference are given in Appendix 2.
This report summarises the work of WG 37-27 that successfully accomplished the scope
originally proposed. The statistics presented (Section 2) in this report show that many
companies and countries have significant blocks of network assets that will approach the
ends of their estimated lives in the coming years. The report (Section 3) indicates some
of the possible consequences of ageing on the system. The scale of the problem of
ageing assets facing many companies in the coming years requires the selection of one
or more overall strategies, rather than addressing the issue on a case by case basis. A set
of alternative generic strategies is presented (Section 4). A process is proposed for the
selection of an appropriate strategy and identification of the factors that may dictate the
eventual choice of strategy (Section 5).
This report does not cover details of total life management of equipment, specific life
extension methods, etc. These issues have been and continue to be addressed by the
relevant CIGRÉ study committees. Some of the relevant CIGRÉ activities are listed in
Appendix 1.
The age profile for transmission equipment shows the growth in systems at 110 kV and
above during the 1950’s and continuing throughout the 1960’s, gradually falling to
today’s investment levels, which again approximate to those of the late 1950’s. Based
on the information presented in this report, the population peak will enter the window of
2.1 Introduction
Ageing is an issue because all assets within an electricity network are subject to ageing
and wear-out during their service life. Indeed, each asset has its own individual useful
lifetime, but for simplification, utilities commonly apply generic lifetime figures to
groups of similar assets with similar individual asset duties or operating regimes.
Oil 110-199 42 (30 to 50) 6 Rating requirements, fault duty changes, maintenance
200-275 41 (30 to 50) 6 costs, spares obsolescence, mechanical wear, safety,
≥345 38 (30 to 45) 5 seal problems
Gas 110-199 43 (30 to 50) 6 Rating requirements, fault duty changes, maintenance
200-275 42 (30 to 50) 6 costs, spares obsolescence, mechanical wear, safety,
≥345 42 (30 to 50) 6 seal problems, seen as “less robust”, environmental
concern re SF6
Bay Assets
Earth switches
& disconnectors ≥110 42 (30 to 50) 8 Rating requirements, maintenance costs, corrosion,
mechanical wear
CTs – Oil ≥110 39 (30 to 50) 7 Design weaknesses, seals
Transformers ≥110 42 (32 to 55) 8 Design, loading, insulating paper & oil degradation,
system faults, spares, rating requirements, high
temperature, moisture levels
ACSR-OHL
“Normal” ≥110 54 (40 to 80) 14 Climate, environment, corrosion, conductor grease
environment levels, creep, mechanical fatigue, insulator failures,
wind, precipitation, ice loading, pollution levels,
“Heavily ≥110 46 (30 to 70) 15 material quality, high temperatures due to loading,
polluted” joints, design
Towers
Steel lattice ≥110 63 (35 to 100) 21 Climate, environment, corrosion, maintenance, poor
galvanising, ground conditions, concrete spalling,
grillage corrosion, steel/concrete junction
Wood Poles ≥110 44 (40 to 50) 4 Preservation treatment, rot, woodpeckers, insects,
wind, precipitation
Cables ≥110 51 (30 to 85) 20 Environmental concerns (oil leaks), backfill, sheath (oil
Oil Filled reinforcing tape) corrosion,
electrical/thermomechanical stress, loading, crystalline
lead sheath
50000
40000
30000
20000
10000
0
0-5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Age in 1998 (Years)
25000
Circuit km
20000
15000
10000
5000
0
0 to 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
5
Age in 1998 (years)
60
50
40
30
20
10
0
Bsh Csb Cfa Cfb Dfb
Hot/Wet CLIMATE Cold/Wet
Fig. 2.3 Anticipated Life for ACSR in Different Climates (Köppens Classification)
Conductor corrosion and fitting wear are the main ageing mechanisms that impact on
ACSR conductor, rather than technological obsolescence, though replacement offers the
opportunity to utilise the latest advances and often enables a higher technical rating to be
achieved with the same supporting structures.
25000
Population
20000
15000
10000
5000
0
0 to 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95
5
Fig. 2.4 Age Distribution and Life Estimates for Lattice Steel Towers
14000
12000
Population
10000
8000
6000
4000
2000
0
0 to 5 10 15 20 25 30 35 40 45 50 55 60
Age in 1998 (years)
Fig. 2.5 Age Distribution and Life Estimates for Wood Poles
Deterioration due to the ageing effects of environment and attack from woodpeckers
apply to this plant type rather than technical obsolescence, as the long service history
proves.
500
Circuit km
400
300
200
100
0
0 to 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85
Age in 1998 (years)
Fig. 2.6 Age Distribution and Life Estimates for Underground Cables
Concerns about the impact of oil leaks on the environment also raise the profile of this
group as well as the high replacement costs involved. 36% of the cables are now within
the mean asset life window but the end of life scenarios are varied enough to distribute the
replacement impact over a significant period.
Technical obsolescence can render some cable systems redundant, particularly small
populations of old gas filled designs, but for oil filled cables, the ageing effects of
reinforcing tape and sheath corrosion, or electrical and mechanical stresses are the
dominant end of life scenarios.
2.4 Substations
10000
Range of Asset
9000 Life Estimates
8000
7000
Population
6000
5000
4000
3000
2000
1000
0
0-5 10 15 20 25 30 35 40 45 50 55 60 65
Age in 1998 (Years)
Gas CB Oil CB Air CB Bay Assets
Transformers Indoor GIS E/mech Prot
1600
1400
1200
Population
1000
800
600
400
200
0
0 to 5 10 15 20 25 30 35 40 45 50 55 60
Fig. 2.8 Age Distribution and Life Estimates for Circuit Breakers
A life expectancy of 41 years (standard deviation 6 years) is anticipated for the whole
population of circuit breakers, with only a slight life increase between early air technology
and the latest SF6 gas technology (Fig 2.8). Variances in asset lives are a result of
variations in mechanical wear, maintenance costs, problems with spares obsolescence and
potential safety concerns. System rating or fault duty requirements can also result in
variations in replacement requirements. Life extension has been undertaken on a small
population of assets with 3% in the 45 – 60 year age bands.
Circuit breakers are subject to deterioration due to ageing mechanisms, such as seal
deterioration, component breakdown etc. as well as technical obsolescence, as a result of
advancing technology or the inability to satisfy developing system requirements.
6000
5000
Population
4000
3000
2000
1000
0
0 to 10 15 20 25 30 35 40 45 50 55 60 65
5 Age in 1998 (years)
Fig. 2.9 Age Distribution and Life Estimates for Bay Equipment
(CT’s, VT’s, Disconnects, Earth Switches)
Ageing is the main driver leading to direct replacement of this plant type, with insulation
deterioration, seal deterioration, and corrosion taking effect, though a large population are
replaced as a consequence of strategies employed to deal with other plant types.
2.4.3. Transformers
The age distribution for transformers (Fig. 2.10) shows that 4% of the population is in the
50 – 80 year old age band, 20% of the population is in or beyond the anticipated mean
asset life window, (i.e. over 35 years old) and in the next 10 years over 50% of the
population will be within the asset life window. Variation about the mean anticipated life
of 42 years (standard deviation 8 years) is mainly attributable to the design and service
regime the transformer has been exposed to. Ageing of transformers will undoubtedly
have a major impact on planning, requiring careful consideration of the strategy required
to tackle the growing population potentially nearing end of life.
Whilst transformers are subject to ageing processes, and technical advances with respect
to lower losses etc. lead to improved designs, the main drivers leading to replacement are
severe operating conditions, resultant insulation breakdown, initial design or inadequate
system rating.
1000
800
600
400
200
0
0 to 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
5
Age in 1998 (Years)
Fig. 2.10 Age Distribution and Life Estimates for Transformers
250
200
Population
150
100
50
0
0 to 5 10 15 20 25 30 35 40 45 50 55 60 65
1200
Population
1000
800
600
400
200
0
0 to 5 10 15 20 25 30 35 40 45 50 55 60
Fig. 2.12 Age Distribution and Life Estimates for Electro-Mechanical Protection
Installation Replacement
40
50
60
70
80
90
00
10
20
30
40
50
19
19
19
19
19
19
20
20
20
20
20
20
3.2.1. Deterioration
Deterioration is the process whereby a material degrades to a point where it is no
longer able to satisfactorily comply with its original specification as determined by
the operator. The nature and extent of deterioration of a particular piece of equipment
will depend on the manner of the deterioration process for that equipment. In general
the rate of deterioration may depend on the passage of time, on the usage (loading,
number of operations) of the equipment, or on the maintenance history of the
equipment.
Deterioration processes related to corrosion, for example, are largely dependent on the
passage of time and on maintenance. Loading, leading to increased temperatures can
accelerate corrosion processes.
Deterioration processes related to internal insulation are more likely to depend on
operating temperature and are therefore related to the usage of the equipment.
For some deterioration processes, correct maintenance should reduce the rate of
deterioration. For example, paint, provided it is correctly applied before any
corrosion, should protect equipment from corrosion.
3.3.4. Switchgear
Switchgear ageing results in two major problems: mechanical deterioration and
insulation problems. Mechanical deterioration of contacts and movable parts is
strongly related to their usage history: number of operations and current flow. The
main consequence is not only overheating of the parts concerned, but also changes in
operating times.
Insulation problems increase with time and the most common problem is the perishing
of seals and gaskets that leads to leakage of SF6 insulating gas. Oil circuit breakers
suffer from water ingress and air leaks.
3.1.1 Reliability
Falling reliability is a major consequence of the ageing process. The familiar bathtub
curve suggests that as assets age, their failure rates generally increase. For asset
managers and planners, the key is to try to pre-empt the onset of these age-related
failures and make the appropriate decisions to deal with them. Failure to deal
effectively with future age-related failures can lead to a gradual decline in reliability
and increase in operation and maintenance costs.
Increased unreliability leads to an increase in revenue expenditure to deal with the age
related failure modes. In addition, unreliability leads to a non-optimal use of the
system and can further lead to the cancellation of planned work to enable work on
faults. This non-optimal use of system puts increased operational pressure on affected
assets thus leading to their increased unreliability. With increased unreliability comes
a decrease in plant availability. This places constraints on the system, which affects
system security, availability for outages to effect asset replacements and new
connections. This ultimately increases risk of disruption to the end customer.
The issue of the timing of and availability to effect asset replacement can be a
dilemma for system planners and asset managers. A decision to delay asset
replacement or alternatively an attempt to recover by increasing asset replacement at a
later stage, can ultimately lead to lower availability and further fault outages. This is
illustrated by the ‘spiral of decline’ shown in Fig. 3.2.
3.4.1. Performance
On certain assets, an increase in age can lead to inefficiencies in operation. This can
affect its loading capability and in some cases lead to downrating. The loss of
performance can influence the decision on whether to replace or refurbish the assets
particularly if additionally influenced by system requirements. In today’s operating
regime with increased regulatory pressures to obtain the maximum from the assets,
performance is a key issue to the decision process.
3.4.2. Compliance
The issue of compliance is an important one especially where asset replacement is
concerned. As time progresses, changes in legislation and technical standards can
render some assets outside these requirements. Assets which do not comply with
legislation are obvious candidates for asset replacement. Some companies may be
able to determine to what degree they wish to apply changes to equipment standards,
which are dynamic by nature, retrospectively. Developments in environmental and
safety standards and legislation are increasingly influencing the decisions on dealing
with aged equipment.
3.4.3. Environmental
Increased awareness and developments in legislation relating to a range of
environmental issues such as pollution, visual impact, waste, SF6 gas, electric and
4.1 Introduction
In the preceding sections we have introduced the problem of ageing and the problems that
ageing poses for transmission systems. In this section we begin the consideration of strategies
to meet the challenges of ageing.
A strategy or solution may be developed and implemented at one of a number of levels:
• It may be applied to a network as a whole
• It may relate to particular assets
• It may relate to individual components only
The distinction between “asset” and “component” is not absolute, but depends on the context,
as shown in Table 4.1.
Table 4.1. Assets and components
Asset Examples of components
Overhead line Foundation, tower, conductor etc.
Main power cable Sealing ends, pressure system etc.
Power transformer Fan, cooling, bushings, tap changer etc.
Substation Bay
Bay Circuit breaker, disconnect, CT, VT, earthing switch,
surge arrestors, foundations, structures
Circuit breaker Contacts, seals, drive mechanism
Control and protection Relays, cabling, SCADA
Renewal by replacement means that all components of the asset are replaced. The
network is unchanged. In most cases the opportunity will be used to achieve some
form of Upgrading (See below).
Renewal by refurbishment means that some components of the asset are replaced to
restore the asset to “as new” condition. The network is unchanged. As with renewal
by replacement, the opportunity will often be used to achieve some upgrading.
Upgrading or renewal is an action taken at the circuit level. The network is enhanced
in some way, e.g. by increasing the current-carrying capacity.
Re-design network is a system level action. This could involve a complete re-
configuring of a part of the network such as the gradual planned elimination of a
voltage level, or could be more localised, such as the re-configuring of a substation.
As an alternative to implementing one of the above strategies, deferral or life-extension
techniques may be used to postpone a decision until the company is ready to select a longer-
term strategy. Examples of deferral techniques are shown in Table 4.3.
Table 4.3. Deferral techniques
System Operation/ Plant Perspective
Planning Perspective
Life extension Increased maintenance.
Increased monitoring.
”Wait and see”.
Action when breakdown occurs.
Table 4.5 gives some examples of individual solutions to the problems posed by the ageing of
particular plant items. Such individual solutions must of course be part of or be consistent
with an overall strategy.
5.1 Introduction
The statistics presented in Section 2 of this report show that many companies and countries
have significant blocks of network assets that will approach the ends of their estimated
lives in the coming years. Section 3 indicates some of the possible consequences of ageing
on the system. The scale of the problem of ageing assets facing many companies in the
coming years requires the selection of one or more overall strategies, rather than addressing
the issue on a case by case basis.
Section 4 of this report presents a set of alternative generic strategies and solutions.
Section 5 describes a process for the selection of an appropriate strategy and identifies the
factors that may dictate the eventual choice of strategy.
In an electricity supply industry, the System Planner is responsible for preparing plans for
the development of the networks to satisfy projected future requirements for transmission
capacity. The Asset Manager is responsible for maintaining the network assets in a safe
and serviceable condition. These functions are typically separated organisationally to a
greater or lesser extent from one another. Indeed with the introduction of concepts such as
the Independent System Operator, these groups may not even be in the same company. (As
the structure of the electricity market evolves in different countries and jurisdictions, it may
not always be clear who is fulfilling the roles of System Planner and Asset Manager.
However it must be accepted that the roles are fulfilled somewhere in the industry.)
The choice of a strategy to deal with the problems of ageing assets involves both the
System Planners and the Asset Managers. Exchanges of information between these
functions are very important in the process of strategy selection. To ensure selection of
optimum strategies, there must be exchanges of relevant information across organisational
boundaries.
Throughout this section a process to choose one or more appropriate strategies is described
by means of process flow diagrams. These diagrams show uni-directional processes that
flow from a starting point to a final decision point. In reality there will be many loops and
iterations in the process. These loops are not shown in the diagrams.
The process is illustrated by a diagram showing a general overview (Fig. 5.1), followed by
more detailed diagrams dealing with the different parts of the process (Figs. 5.2 and 5.3).
Prepare composite
Implement Chosen renewal and
Strategy development plan
Other Factors
•Cost
•Land Use
•Technology
•Safety
•Environment
•Availability of outages
Business Drivers
Technical Drivers
EFFECTS OF TIME External Drivers
INTERNAL FACTORS
ASSET CONDITION
Deterioration ASSESSMENT
KEY CONDITION
INDICATORS
reliability
On-line Set Indicators ACTION
performance
diagnostic
efficiency assessment
GENERATE OPTIONS
EXTERNAL FACTORS Renew by Refurbishment
Inspection &
Acceptable Outside
Plant related: limits of Renew by Replacement
maintenance
spares Condition Upgrade
obsolescence
Re-design Network
safety
Performance Inside
Non- Plant related: history
environmental
land use
financial constraints
Effects of Time
The processes concerned with the effects of time (ageing) have already been described in
Section 3. These are, in summary, deterioration, where the equipment changes and
eventually no longer satisfies requirements, or obsolescence, where it is not practical or not
economical to retain the equipment in service. Additionally, with the passage of time,
constraints on finance, on environmental impact and on land use will also change.
Choose preferred
option
5.5.1. Triggers
The main initiating factors that require actions to be taken in relation to system planning
and development, may be described as follows:
1. Change in requirements leading to demand for increase/ decrease of transmission
capacity.
2. New authority requirements related to existing assets.
3. Asset condition not satisfactory in relation to legal or company requirements.
The consequences of ageing require actions to be taken in relation to item 3 above. But the
action has to take into account consequences of item 1 and 2.
5.5.2. Implementation
An implementation plan must take account of the following
• What is the precise scope of the renewal work?
5.5.3. Prioritisation
Prioritisation, selecting the order in which equipment should be renewed or refurbished,
can be done on the basis of one of a number of alternative strategies:
• An incident-based strategy, where priorities are set on the basis of actual instances of
failure
• A time-based strategy, where priorities are set on the basis of the age of the
equipment
• A condition-based strategy, where priorities are based on the results of condition
assessment activities,
• A system reliability-centred strategy which takes account of the two aspects of
condition and importance to the system.
A reliability-centred asset management strategy uses the following procedure:
• The condition of the equipment has to be determined.
• The importance of the equipment for the network as a whole must be determined, e.g.
the influence of equipment failure on the reliability of supply.
• Both information inputs must be combined and evaluated in order to specify the
optimum sequence of replacement or refurbishment for the individual devices
(equipment, substation).
The condition can be evaluated on the basis of different criteria such as age, service history,
results of inspection and diagnostic tests, knowledge and experience of maintenance staff
etc.
Defining a piece of equipment's importance and assessing the consequences of a failure
basically constitute a practical but also subjectively influenced exercise. In this context,
there are numerous different parameters to be considered. These include:
• non-availability of the circuit
• failure rate of the circuit
• system configuration
• interrupted active power
Index C
condition of
circuit
Index O
Refurbishment /
overall sequence of
Σ refurbishment /
replacement
strategy
replacement
Index I
importance of
circuit
The values for the "c" (condition) and "i" (importance) parameters can be can be calculated
in such a way that the "c" and "i" values can assume a maximum value of 100. A large
value for "i" signifies that the equipment concerned is of high importance in the network.
A large vale for “c” signifies that the equipment is in poor condition.
Another way to illustrate this concept is drawn in Figure 5.5. The results (crosses) can be
listed in an X, Y system of co-ordinates as shown in the Figure. The vertical axis
represents the condition of the item of equipment concerned, while the horizontal axis
reflects its importance in the network. A cross in the top left-hand corner corresponds to an
item of equipment that, although in poor technical condition, would not cause any major
consequences if it were to fail. In contrast, a cross in the bottom right-hand corner
designates an item of equipment that is in very good condition. A failure of this device
would entail substantial consequences for network operation. The distances d1 to d5
illustrate the sequence in which the individual equipment items must be serviced or
replaced.
2 3
cR 1
4 5
d1 d2
d3
cM
d4
d5
100 i
Fig.
5.6 Impact of Pre-investment and Life Extension on Replacement Profile
The availability of suitably qualified skilled staff to maintain obsolescent equipment may
dictate the need to opt for a strategy based on upgrading rather than a deferral option based
on maintenance and monitoring. This is especially true in the case of protection equipment,
where there is an increasing shortage of staff with the skills to maintain and repair
electromechanical relays.
1
See also "Developing medium to long-term strategies to manage your business safely into the 21st century"
V. Jonas, IEE Colloquium on tools and techniques for dealing with uncertainty, London, January 1998.
5.6.7. Safety
Although many changes in laws and regulations are not applied retrospectively to existing
plant, changing safety requirements may well have to be taken into account immediately.
The statistics presented in Section 2 show clearly that in many countries large amounts of
transmission plant installed during periods of high growth are approaching the end of their
useful lives. The resulting technical, financial, resource and other consequences need to be
addressed in an integrated and timely manner.
Problems associated with ageing manifest themselves in terms of plant deterioration and / or
technical obsolescence. These plant-related issues can eventually lead to system wide
problems such as reduced reliability / availability, and non-compliance with changing
technical, environmental and safety standards. However, as a result of the application of
planning criteria such as n – 1 or n – 2, there is little evidence that ageing has impacted on
system performance. If ageing plant is not refurbished or replaced there is a risk of
deteriorating system performance in the longer term.
The development of the most appropriate strategy is a complex issue and will involve both the
system planner and the asset manager. In developing system development plans, system
planners must take account of the fact that certain assets will reach the end of their lives.
Future system requirements are central to the development of plans for the retirement,
refurbishment or replacement of life-expired assets. The selection of the optimum strategy
will therefore require close liaison and the exchange of relevant information between system
planners on the one hand and asset managers on the other hand.
In developing options the planner must be aware that many of the issues associated with the
modification of existing plant will differ from those associated with new developments.
Some issues will favour the modification of existing plant over new construction e.g.
availability of a route corridor. Others may favour new construction e.g. unavailability of
outages to modify existing plant.
Five broad generic strategies to deal with ageing have been identified. These are:
• Renewal by refurbishment: some components of an asset are replaced to bring the asset to
an as-new condition
• Renewal by replacement: all components are replaced i.e. like-for-like replacement of the
asset.
• Upgrading or renewal: the ageing assets are replaced or refurbished to a standard which
provides an enhanced asset
• Network redesign: the opportunity is taken to implement a redesign (and hence an
enhancement) of the system.
• Life-extension or deferral: increased maintenance and/or monitoring of existing
equipment until other strategies can be implemented.
CIGRÉ Sessions
2000
Group 13, preferential subject 1
Consequences of economic constraints on switchgear
13-103: Balzer, Strnad, Neumann, Halfmann, Orlowska, Life cycle management of
circuit breakers by application of reliability-centred maintenance
13-104: Janssen, Lanz, Peelo, De Radigues, Makareinis, Life management of CBs a
summary of the studies of CIGRÉ WG 13.08
1998
Group 12, preferential subject 2
Life management of power transformers and reactors: failure analysis, monitoring and
diagnostics, refurbishment and processing.
12-202: Kazimerski, Sobocki, Olech, Selected elements of life management of large
power transformers, a Polish experience
12-204, Pettersson, Fantrana, Sundermann, Life assessment, ranking of power
transformers using condition based evaluation. A new approach,
12-207, Aschwanden, Hässig, Fuhr, Lorin, V. Der Houhanessian, Zaengel, Schenk,
Zwelacker, Piras, Development and application of new condition assessment
methods for power transformers.
12-210, Jarman, Lapworth, Wilson, Life assessment of 275 kV and 400 kV transmission
transformers.
1990
Group 22. preferential subject 2, Long term performance of components
22-201, Amm, Havard, Horrocks, Horrocks, Macedo, Development of a high voltage
transmission line refurbishment program at Ontario Hydro.
22-203, Crouch, Swift, Parraud, De Decker, Ageing mechanisms of AC energised
insulators.
CIGRÉ Symposia
110-22 Darveniza, Saha, Hill, Le, Studies of the condition of insulation in aged
transformers and predicting its remaining life
Technical Brochures
Maintenance and Management of Protection Systems, Brochure 87, 1994
Electra Articles
Lifetime evaluation of transformers, WG12. 09 (Thermal aspects of transformers )
Electra 150, October 1993
Terms of Reference
The following tables and associated histograms show the age statistics supplied by each
of the companies surveyed. For commercial confidentiality reasons, the identity of each
company is not shown.
The histograms show above the x-axis the asset populations in 5-year age bands for each
plant type. Each colour represents the volume of plant in different companies. The
colour used to represent each company varies from one histogram to another. Likewise,
the order of the columns of data from different companies varies from one table to the
next.
Each company's estimate of asset life is shown below the x-axis. In most cases the
companies provided their estimates of shortest, mean and longest anticipated asset life
for each type of asset. The heights of the bars representing asset life estimates do not
have any particular significance. Larger blocks represent estimates of mean life, and
smaller blocks represent estimates of shortest or longest life.
A3 - 1
List of Data Sets
A3-1 Overhead Lines – ACSR – Normal Environment.....................................................................3
A3-2 Overhead Lines - ACSR Fully Greased – Polluted/Wind Exposed Environment .................4
A3-3 Overhead Lines - ACSR Fully Greased – Heavy pollution / Ice loading ................................5
A3-4 Overhead Lines > 110 kV – Wood Poles - .................................................................................6
A3-5 Lattice Steel Towers - >110 kV...................................................................................................7
A3-6 Cables - Oil Filled, >110kV .........................................................................................................8
A3-7 Cables - XLPE, >110kV ..............................................................................................................9
A3-8 Submarine DC Cables ...............................................................................................................10
A3-9 110-145 kV Air Blast Circuit Breakers....................................................................................11
A3-10 110-170 kV Oil Circuit Breakers..............................................................................................12
A3-11 110-170kV Gas Circuit Breakers..............................................................................................13
A3-12 200 – 275 kV Air Blast Circuit Breakers .................................................................................14
A3-13 200-275kV Oil Circuit Breakers...............................................................................................15
A3-14 200-275 kV Gas Circuit Breakers.............................................................................................16
A3-15 345 kV and above Oil Circuit Breakers...................................................................................17
A3-16 345 kV and above Air Blast Circuit Breakers.........................................................................18
A3-17 345 kV and above Gas Circuit Breakers..................................................................................19
A3-18 Earth switches/Disconnectors ...................................................................................................20
A3-19 Switch Disconnectors.................................................................................................................21
A3-20 Surge Arrestors -Gapped/Gapless............................................................................................22
A3-21 Current Transformers - Oil filled ............................................................................................23
A3-22 Combined Current and Voltage Transformers.......................................................................24
A3-23 Voltage Transformers - Capacitor ...........................................................................................25
A3-24 Gas-Insulated Switchgear - Indoor ..........................................................................................26
A3-25 Transformers .............................................................................................................................27
A3-26 Shunt Reactors...........................................................................................................................28
A3-27 Electromechanical Protection, Signalling, Control and Intertripping Equipment..............29
A3-28 Synchronous Compensators .....................................................................................................30
A3-29 Static VAR Compensators ........................................................................................................31
A3-30 Capacitor Banks ........................................................................................................................32
A3 - 2
A3-1 Overhead Lines – ACSR – Normal Environment
15000
CIRCUIT km
10000
5000
0
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
ASSET LIFE
Age - YEARS
A3 -3
A3-2 Overhead Lines - ACSR Fully Greased – Polluted/Wind Exposed Environment
4000
CIRCUIT km
3000
2000
1000
0
ASSET LIFE
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Age - YEARS
A3 -4
A3-3 Overhead Lines - ACSR Fully Greased – Heavy pollution / Ice loading
5000
4000
3000
CIRCUIT km
2000
1000
0
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80
ASSET LIFE
Age - YEARS
A3 -5
A3-4 Overhead Lines > 110 kV – Wood Poles -
15000
10000
Population
5000
0
5 10 15 20 25 30 35 40 45 50 55 60 65 70
Asset Life
Age - YEARS
Age Range
(Years)
0-5 7200 111 341 462
5-10 7400 304 100 497
10-15 4900 280 425 600 8
15-20 6100 1146 750 493 115
20-25 9000 1690 1100 503 1035
25-30 6000 850 700 302 667
30-35 10400 1882 1525 27 798
35-40 5100 686 2800 739 1101
40-45 6100 1011 366 344 1062
45-50 5800 1940 966 607 0
50-55 3000 3816 268 0
55-60 4000 730 396
60-65
A3 -6
A3-5 Lattice Steel Towers - >110 kV
30000
Population
20000
10000
0
5
15
25
35
45
55
65
75
85
95
105
115
Asset Life
Age - YEARS
Age Range
(Years)
0-5 5084 37 392 734 235 35 220 85
5-10 3697 301 1853 2997 235 1250 253 8
10-15 7080 86 2598 1479 235 2925 327 50
15-20 5345 254 3368 2648 416 2480 1679 198
20-25 12092 1145 2400 3124 284 228 4450 1942 530
25-30 5686 4313 4014 5538 103 157 4560 1296 396
30-35 2298 7587 3368 2144 703 430 4390 1401 112
35-40 30 4780 1892 2179 80 334 4350 172 409
40-45 1792 907 3103 142 1883 253 692
45-50 1 0 7897 380 7623 485 69
50-55 450 2250 867 2233 71
55-60 0 13911 22
60-65 11
65-70 121
70-75 300
A3 -7
A3-6 Cables - Oil Filled, >110kV
500
400
300
CIRCUIT km
200
100
0
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85
ASSET LIFE
Age - YEARS
A3 -8
A3-7 Cables - XLPE, >110kV
250
200
150
100
50
0
ASSET LIFE
5 10 15 20 25 30 35 40 45 50 55 60
Age - YEARS
A3 -9
A3-8 Submarine DC Cables
500
400
300
CIRCUIT km
200
100
0
5 10 15 20 25 30 35 40 45 50 55 60 65 70
ASSET LIFE
Age - YEARS
A3 -10
A3-9 110-145 kV Air Blast Circuit Breakers
600
500
400
300
Population
200
100
0
5 10 15 20 25 30 35 40 45 50 55
Asset Life
Age - YEARS
Age Range
0-5 1
5-10
10-15
15-20 1
20-25 5 3 9
25-30 5 1 12 84 6
30-35 5 29 6 110 16 347 44
35-40 5 4 8 70 496 4
40-45 9 10 58 1
45-50 2 11 22 41
Estimated life
Earliest 25 35 35 40 40 40 30 25
Mean 30 40 40 45 50 45 45 40 35
Latest 35 45 50 50 60 50 50 50 40
A3 -11
A3-10 110-170 kV Oil Circuit Breakers
1500
1000
Population
500
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
(Years)
0-5 77
5-10 47 7
10-15 22 1 1 1
15-20 14 981 36 2
20-25 47 1255 49 13 13 120 7 52
25-30 49 1376 81 9 19 12 59
30-35 46 731 55 73 45 9 2
35-40 49 137 26 41 2 9
40-45 39 7 24 14
45-50 64 2 19 1
50-55 40
55-60 6
A3 -12
A3-11 110-170kV Gas Circuit Breakers
2000
1500
Population
1000
500
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
0-5 29 1899 2 43 5 6 23 160 22
5-10 13 1841 44 61 3 27 48 50 13
10-15 25 1258 15 26 2 14 30 50
15-20 45 630 14 14 4 8 74
20-25 3 9 2 3 12
25-30 1
A3 -13
A3-12 200 – 275 kV Air Blast Circuit Breakers
500
400
300
Population
200
100
0
5 10 15 20 25 30 35 40 45 50 55
Asset Life
Age - YEARS
Age Range
(Years)
0-5 1
5-10
10-15 10
15-20 2 12 1 48 15 4
20-25 6 20 4 110 20 12 9
25-30 1 85 10 2 204 5 6 41
30-35 57 16 22 166 15 207
35-40 5 10 40 76 55
40-45 26 44 4
45-50 2
A3 -14
A3-13 200-275kV Oil Circuit Breakers
300
Population
200
100
0
Asset Life
5 10 15 20 25 30 35 40 45 50 55
Age - YEARS
Age Range
(Years)
0-5 4 50
5-10 5 100
10-15 20 42 100
15-20 20 7 144 21 2 50
20-25 15 14 178 105 32 2
25-30 2 3 34 131 43 17 18
30-35 7 74 22 10 70
35-40 8 34 34 1 15
40-45 12 7
45-50 22 13
50-55 21
A3 -15
A3-14 200-275 kV Gas Circuit Breakers
600
500
400
300
Population
200
100
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
(Years)
0-5 2 41 400 12 10 111 18 6
5-10 18 70 13 150 19 20 75 21 15
10-15 2 28 75 41 20 57 37 11
15-20 3 25 40 6 8 29 5
20-25 2 22 59 7
25-30 1
30-35 1
A3 -16
A3-15 345 kV and above Oil Circuit Breakers
200
150
Population
100
50
0
5 10 15 20 25 30 35 40 45 50 55
Asset Life
Age - YEARS
Age Range
0-5 20
5-10 10 30 3
10-15 40 60 1 66
15-20 40 60 4 2 124
20-25 30 27 91
25-30 30 8 19
30-35 14 5
35-40 19 3
A3 -17
A3-16 345 kV and above Air Blast Circuit Breakers
300
Population
200
100
0
Asset Life
5 10 15 20 25 30 35 40 45 50 55 60
Age - YEARS
Age Range
(Years)
0-5
5-10
10-15 15 68
15-20 34 2 15 3 54 42 59
20-25 9 41 12 18 72 81
25-30 23 161 14 5 72 45
30-35 150 5 5 72 14
35-40 55 8 9
40-45 4
A3 -18
A3-17 345 kV and above Gas Circuit Breakers
400
300
Population
200
100
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
(Years)
0-5 70 86 3 20 3 16 19
5-10 4 30 83 51 40 153 23 33 41
10-15 23 15 20 2 40 6 81 26
15-20 49 5 15 3 40 9 14
20-25 21 26 36
A3 -19
A3-18 Earth switches/Disconnectors
Disconnectors/Earth Switches
5000
4000
3000
2000
Population
1000
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
(Years)
0-5 1 22 10 444 130 125 46
5-10 27 96 2 363 290 10 121
10-15 33 91 229 550 213 4
15-20 13 171 359 550 285 14
20-25 12 186 12 1162 650 249
25-30 31 88 12 3457 210 534
30-35 82 40 42 2119 130 165 2
35-40 57 57 15 533 32 2
40-45 8 16 100 139 198
45-50 6 16 7 1
50-55 2 0
55-60 0
60-65 8
A3 -20
A3-19 Switch Disconnectors
Switch Disconnectors
200
150
100
Population
50
0
5 10 15 20 25 30 35 40 45 50 55 60 65
Asset Life
Age - YEARS
Age Range
(Years)
0-5 5
5-10 47 77
10-15 3 28
15-20 7 12 87
20-25 21 8 33
25-30 2 36 109
30-35 97 6
35-40 66 2
40-45 19
45-50 27
50-55
55-60 3
A3 -21
A3-20 Surge Arrestors -Gapped/Gapless
Surge Arrestors
1200
1000
800
600
Population
400
200
0
Asset Life
5 10 15 20 25 30 35 40 45 50 55 60 65 70
Age - YEARS
Age Range
(Years)
0-5 6 18 5 4 636 272
5-10 178 12 33 9 8 474 304
10-15 143 12 4 36 282
15-20 127 12 15 1 33 513
20-25 12 3 6 307
25-30 18 12 7 2 124
30-35 12 1 1 6
35-40 12 192
40-45
45-50 270
A3 -22
A3-21 Current Transformers - Oil filled
300
200
100
0
5 10 15 20 25 30 35 40 45 50 55 60 65
Asset Life
Age - YEARS
Age Range
(Years)
0-5 12 58 30 239 39
5-10 28 18 60 155
10-15 167 125 49
15-20 4 143 125 29
20-25 57 125 191
25-30 184 95 334
30-35 1 105 30 524 12
35-40 1 0 240 111
40-45 12 139 15
45-50 14 5
50-55 11
55-60 3
A3 -23
A3-22 Combined Current and Voltage Transformers
800
600
Population
400
200
0
Asset Life
5 10 15 20 25 30 35 40 45 50 55 60 65
Age - YEARS
Age Range
(Years)
0-5 30 1 12
5-10 895 27
10-15 2 33 45
15-20 13 132
20-25 12 48
25-30 31 204
30-35 82 48
35-40 57 78
40-45 8 48
45-50 6 21
50-55
55-60 2
A3 -24
A3-23 Voltage Transformers - Capacitor
800
600
400
Population
200
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
(Years)
0-5 30 30 200 5
5-10 60 121 18
10-15 110 52 1 5
15-20 110 24 78 3
20-25 110 126 55
25-30 80 287 225
30-35 30 678 1 55
35-40 96 125 1
40-45 43
A3 -25
A3-24 Gas-Insulated Switchgear - Indoor
250
Population ( bays)
200
150
100
50
0
Asset Life
5 10 15 20 25 30 35 40 45 50 55 60
Age - YEARS
Age Range
(Years)
0-5 24 3 146
5-10 9 2 63 1 0 176 1
10-15 28 1 2 1 42 206 2
15-20 20 8 2 7 198 3
20-25 5 1 256 1
25-30 142
30-35 5
A3 -26
A3-25 Transformers
Transformers, >110kV
2000
1500
1000
Population
500
0
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Asset Life
Age - YEARS
Age Range
(Years)
0-5 124 3 2 4 25 6 11 1 77 7 166
5-10 124 3 14 13 51 4 7 8 1 93 96 443
10-15 116 20 17 16 31 15 1 7 78 21 389
15-20 100 18 5 4 27 37 2 5 68 45 631
20-25 100 30 9 45 22 13 4 124 111 839
25-30 95 19 15 5 115 19 36 2 156 152 812
30-35 46 19 68 2 251 19 27 1 3 76 89 654
35-40 2 20 31 4 92 9 11 46 78 549
40-45 3 5 19 30 13 108 75 72
45-50 2 5 3 2 3 93 122
50-55 4 2 42 62
55-60 30 142
60-65 12
65-70 3
70-75 7
75-80 6
A3 -27
A3-26 Shunt Reactors
Shunt Reactors
50
40
30
Population
20
10
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
(Years)
0-5 1 9 1 2
5-10 15 12
10-15 2 1 25 12 1
15-20 2 9 17 3
20-25 3 8 1 5 2
25-30 2 2 3 5 3
30-35 15 1
35-40 1
A3 -28
A3-27 Electromechanical Protection, Signalling, Control and Intertripping Equipment
150
%Population
100
50
0
5 10 15 20 25 30 35 40 45 50 55 60
Asset Life
Age - YEARS
Age Range
(Years)
0-5 0% 5%
5-10 0% 14% 3% 5%
10-15 2% 28% 18% 21% 5%
15-20 0% 28% 28% 22% 5%
20-25 17% 50% 14% 5% 3% 21% 10%
25-30 43% 50% 9% 0% 28% 15% 10%
30-35 27% 5% 1% 58% 7% 10%
35-40 12% 48% 8% 3% 10%
40-45 2% 3% 6% 11%
45-50 1% 9%
50-55 22%
A3 -29
A3-28 Synchronous Compensators
Synchronous Compensators
14
12
10
Population
0
Asset Life
5 10 15 20 25 30 35 40 45 50 55 60
Age - YEARS
Age Range
(Years)
0-5
5-10
10-15 1 1
15-20 1
20-25 4
25-30 1 1 1
30-35 7 4 1
35-40 8 2
40-45 1
A3 -30
A3-29 Static VAR Compensators
10
6
Population
0
5 10 15 20 25 30 35 40 45 50
Asset Life
Age - YEARS
Age Range
(Years)
0-5 9 2
5-10 1 7 1
10-15 2 1 1 2
15-20 1 1 3
A3 -31
A3-30 Capacitor Banks
Capacitor Banks
200
150
100
Population
50
0
5 10 15 20 25 30 35 40 45
Asset Life
Age - YEARS
Age Range
(Years)
0-5 4 4 33 44 2
5-10 1 4 41 108 2
10-15 1 11 2
15-20 7 7 5
20-25 4 1
25-30 2 8
30-35 11 3
A3 -32
Appendix 4.
Case Studies
Case Studies
No. Country Company Plant Particular Strategy Adopted
/ General
1. Canada Ontario Hydro 115 kV Overhead line P Upgrade by replacement
2. Denmark Eltra 150 kV Grid G Redesign network
3. England and Wales National Grid Co. 275 kV Overhead line P Upgrade by refurbishment
4. England and Wales National Grid Co. 275/66 kV Transformers P Renew by replacement
5. England and Wales National Grid Co. 275 kV London network G Redesign network
6. France Electricité de France 225 kV Overhead line P Upgrade by refurbishment
7. Germany Deutsche Verbundgesellschaft 220 kV Network G Redesign network
8. Ireland ESB National Grid 110 kV Overhead lines G Renew or upgrade by refurbishment
9. Ireland ESB National Grid 110 kV Stations G Renew or upgrade by refurbishment
10. Northern Ireland Northern Ireland Electricity 110 kV Overhead lines G Renew by refurbishment
11. Northern Ireland Northern Ireland Electricity 33 kV Circuit breakers G Renewal by refurbishment or replacement
12. Poland Polish Power Grid Corporation 220 kV Overhead lines G Upgrade by refurbishment
13. Poland Polish Power Grid Corporation 220 kV Substations G Upgrade by refurbishment
14. Poland Polish Power Grid Corporation 220 kV Network G Redesign network
15. Slovenia Electroinstitut Milan Vidmar 220 kV Network G Redesign network
16. Slovenia Electroinstitut Milan Vidmar AAC Conductor G
17. United States 230 kV Circuit breakers P Redesign network
CASE STUDY: 1
COUNTRY: CANADA
COMPANY: ONTARIO HYDRO
PLANT: 115 kV OVERHEAD LINE
1. RESULT TO BE DELIVERED
2. BACKGROUND
In the development of the Transmission Line Refurbishment & Replacement (TLR&R) program,
candidate lines for the TLR&R 1999 program were developed and prioritised using the drivers
stated in the Overhead Transmission Line Refurbishment & Replacement Strategy document dated
October 2, 1998. The conductors of circuit A1N are 58 years old and are at the end of its life as
shown by the laboratory test results. In addition, the results of the condition assessment of the
wood poles, insulators and hardware shows that they are also approaching the end of life. The
condition of the wood poles have degraded to the point that under expected adverse weather
conditions there is a significant risk that the poles will fail and present a hazard to the public and a
lengthy customer interruption. All the 90 wood poles in the line section Vanessa Jct. to Norfolk TS
must be replaced.
The 115 -27.6 kV, 75 MVA Norfolk TS is supplied radially from Allanburg TS via 95 km of 115
kV double circuit line (A8N/A11N) and then a 12 km continuation of 115 kV single circuit wood
pole line (A1N), built in 1940, from Vanessa Jct. to Norfolk TS.
Study indicates that 115 kV supply is the most economical long-term supply for Norfolk TS.
This is a radial supply and a temporary by-pass would be needed to provide an uninterrupted
supply to Norfolk TS during the construction phase. Building a by-pass is very costly. Live line
construction methods will be used to avoid the need to build a temporary by-pass line. Live line
construction methods requires higher poles to be used in order to provide safe working clearances.
New steel poles were considered for this project. Installed costs of steel poles are estimated to be
similar to wood poles. However, development work to date has not produced acceptable safe work
procedures for live-line installation of steel poles. Steel poles will be used if this issue is
successfully addressed in the interim.
The 12-km radial line section passes through a rural high use area. Consequently a broken
conductor would result in customer supply interruptions and would endanger public and employee
safety.
Alternative #1:
Do Nothing; maintain the ageing transmission lines on an as required basis (repair as they fail).
Public safety and reliability to the customers would be compromised. Component failures require
A4 - 2
emergency restoration and will cause customer supply interruptions. The average cost of
emergency restoration is over 300% of the cost of identical planned work.
In the event of a failure of radial circuit A1N the Norfolk TS supplying the Town of Simcoe and
a large load-sensitive industrial customer will have no source of supply which is an unacceptable
option.
This alternative was eliminated because it does not meet the required results and it does not satisfy
concerns about the risk to public safety, system security or reliability of supply to the customer
load in the Simcoe load area and OH retail area load. OHSC has an obligation to continue
providing a reasonable level of service, including capacity, reliability and security.
4. ALTERNATIVES CONSIDERED:
Alternative #2:
Refurbish 12 km of 115 kV single wood pole radial line (A1N), Vanessa Jct. to Norfolk TS.
Replace the conductor with energy efficient conductor sized to meet the required 500 Amp maximum
emergency summer ampacity. Replace all wood poles, insulators, hardware and shield wire.
Alternative #3:
Build a new 230 kV single circuit wood pole line to Norfolk TS from the nearest available 230kv
line (21 km) and convert the station to 230-27.6 kV operation. Remove circuit A1N from service
and dismantle and remove conductors, poles, etc.
Alternative #2 is recommended:
It provides a proactive management of safety concerns from ageing lines in the Simcoe load area.
It contributes to customer satisfaction and their retention as TNAM’s long term customers, in
particular large industrial customers, in the competitive environment.
It is the lowest cost alternative that meets the results to be delivered.
5. FINANCIAL EVALUATION
There are no other future costs which distinguish Alternative 2 from Alternative 3, other than the
initial capital. The financial evaluation has been carried out for Alternatives #2 and #3. The
estimated NPVs for Alternatives #2 & #3 have been calculated and Alternative #2 is recommended
based on least cost.
7. RISK ANALYSIS
Not proceeding with the recommended work would result in increasing risk to public and
employee safety from component failures and to continuity of supply to the Simcoe loads.
A4 - 3
The recommended work will minimise impact of construction activities on public by
completing refurbishment work in a single project.
There is little risk of stranding this investment because these facilities are the only supply
facilities in the area. Opportunities for establishing alternative transmission lines to supply the
area loads would be economically, technically and environmentally impractical; and
opportunities for NUG development in the area would not eliminate the need for this supply
line. The total load supplied is QMW. The projected load growth in the Simcoe load area is
estimated to be X% per annum.
The work will be carried out by NWS staff who are experienced in this type of work.
8. MONITORING
Scope, cost, schedule, performance, results and legislative/regulatory compliance will be
monitored through standard project management practices.
A4 - 4
CASE STUDY: 2
COUNTRY: DENMARK
COMPANY: ELTRA
PLANT: 150 kV GRID
A4 - 5
3. FACTORS INFLUENCING CHOICE:
System requirements:
The 400 kV grid is still missing some lines to close the 400 kV loops, and thereby providing a rigid
supergrid for transmission. The completion will improve the transmission capacity considerably
and allow for almost full exploitation of the interconnections to Norway, Sweden and Germany
and at the same time give improved grid access to the new and most efficient power stations.
In the coming years Eltra and Elsam in co-operation will construct two offshore wind farms as
demonstration projects for a large-scale development of 2000 MW offshore wind farms. This will
stress the transmission system further, since surplus electricity production during hours with high
winds and low load will have to be exported.
Cost:
Acceptable costs for the reconstructing of the 150 kV grid while at the same time completing the
400 kV grid. Saving costs for refurbishment and instead retire old lines.
Planning permission:
Regional authorities often link together/connect new 400 kV projects with the removal of 150 kV
lines. This has in several cases been advantageous in the political process of obtaining permissions.
Technology:
Overhead lines are the most reliable technique.
Outages:
One disadvantage is forced outages for all systems in connection with a few types of maintenance
and repair works. However, this can often be scheduled for periods with low load or co-ordinated
with other outages.
Financing:
Refurbishment is a cost to the line owner. The regional transmission companies own the 150 kV
lines. New lines are generally constructed with a 70% contribution from Eltra.
4. THE PROJECT
New 400 kV lines are planned together with the reconstruction of 150 kV lines. This makes it
possible to retire 150 kV lines from residential areas and areas of conservation value. The 400 kV
grid is expected to be completed by the year 2010.
A4 - 6
CASE STUDY: 3
COUNTRY: ENGLAND AND WALES
COMPANY: NATIONAL GRID
PLANT: 275 kV OVERHEAD LINE
2. CHOICE OF STRATEGY
A number of alternative strategies to address the deterioration of the line were considered:
• Retirement – redesign system to be adequate without the line
• Rebuild and enhance the line – uprate to 400kV, increase rating.
• Refurbish like for like retaining the existing conductor, with the option of increasing current
carrying capacity by increasing conductor size and strengthening tower steelwork and
foundations.
• Extend life with enhanced maintenance.
System requirements:
The line is required to meet existing system needs and transfers from Scotland. Expectations of
greater future Scottish transfers would require a 400kV or uprated route.
A4 - 7
Cost:
Refurbishment with larger conductors at 275kV giving over 40% increase in rating is more
expensive than like for like but is cost beneficial in reducing requirements for SVC installations
and produces a less brittle system.
Consents:
Rebuilding the existing line to 400kV would require new consents and wayleaves, which could
take at least 4 to 5 years to obtain with a public inquiry being necessary. This timescale would not
be acceptable as the line deterioration before eventual rebuilding would be unacceptable.
Environment:
Uprating the existing line with larger conductors does not require new consents or wayleaves, and
in an area that is classed as an agreed World Heritage site will be more acceptable to the
community than a new 400kV route with larger towers.
Technology:
Replacing the existing Aluminium Conductor Steel Reinforced (ACSR) line with conductors of
All Aluminium Alloy Conductor (AAAC) with slightly larger diameter but greatly increased rating
capacity, whilst requiring significant tower and foundation strengthening reduces the need to
uprate the line to 400kV.
Outages:
Outages for refurbishment are available but need to be arranged with those necessary for the
commissioning of another new 400kV route South of this area that is under construction and will
enable greater Scottish transfers.
Financial:
Line refurbishment may be treat as capital but as the route will be uprated the project will attract a
significant higher level of taxation.
Safety:
Refurbishment enables the required level of safety to be maintained.
4. THE PROJECT
Refurbishment with larger AAAC conductors is recommended for this particular route given the
potential request from the Scottish Companies to increase transfers. It will provide the most
economical and environmentally acceptable system for the UK supply industry, with an overall
Net Present Value cost saving if anticipated transfers are required. It provides a less brittle
transmission system and reduces losses, though it will involve significantly more work on the
towers and foundations and increases scheme costs.
A4 - 8
CASE STUDY: 4
COUNTRY: ENGLAND AND WALES
COMPANY: NATIONAL GRID
PLANT: 275/66 kV TRANSFORMERS
1. RESULTS TO BE DELIVERED.
2. ASSESSMENT CRITERIA
The following criteria are used to determine whether or not the transformers at a particular grid
supply point require modification or replacement.
• The transformer installation must meet the obligations to comply with the transmission
Licence by meeting planning and operational standards within the Grid Code.
• The reliability of the individual transformers at the site must together meet the requirements
for the overall reliability of the supply point.
• In the case of failure of one transformer, there must not be an unacceptable risk of failure of
the whole supply point to meet demand due to a second failure within the time it takes to
replace the first transformer.
• It must be possible to take a planned outage for maintenance or construction works without
incurring an unacceptable risk of losing demand due to the failure of one of the transformers
remaining in service.
• The transformers must meet NGC safety performance criteria and its duty to comply with
Health and Safety legislation.
• The transformers must meet NGC environmental performance criteria and its duty to comply
with Environmental legislation.
• The present installation or any proposed modifications must meet the business requirements of
NGC and its customers. Requirements will include the consideration of full life time costs
including the cost and practicality of maintenance and the requirements for outages.
3. BACKGROUND
The 275 kV substation was originally commissioned in the late 1960's to feed a Regional
Electricity 66 kV grid supply point which supplies a predominantly rural and light industrial
demand. There is an ongoing requirement for supplies at 66 kV on the site into the foreseeable
future.
Transformers 1 and 2 are identical in terms of manufacturer, age and loading history.
The expected long term reliability of these transformers was reviewed and options for
improvements considered.
A4 - 9
4. SPARES COVER
One spare 275/66 kV 120 MVA transformer is currently available.
This spare covers a population of 24 such units in service.
Current experience indicates the expected time for replacement of a failed transformer with the
spare, assuming the spare is available is normally up to 12 weeks.
6. ANALYSIS
Since two of the three transformers at the supply point ( SGT1 and SGT3 ) have uncertainties
about their long term reliability, all three have limited overloading capabilities, and one ( SGT3 )
shows signs of accelerated deterioration at current loadings, the supply point must be considered to
have a higher than normal probability of transformer failure, and also a higher than normal
probability of a second transformer failure.
During winter intact conditions ( 3 SGTs in service), loss of one SGT results in no loss of demand.
However, a second failure or loss with one unit on outage would result in approx. 100MW of
demand having to be rota disconnected until additional SGT capacity is restored.
In summer with one unit on outage loss of one of the remaining SGTs incurs approx. 40MW
demand lost ( auto load shed ). REC would transfer as much demand to the adjacent supply point
as their network will allow to protect as far as possible against a second transformer fault. This
transferred demand is at risk to single fault outages (66kVnetwork fully loaded).
There is therefore a strong case for considering options for improving the expected long term
reliability of the transformers at the substation.
7. OPTIONS
The standard options and their likely impact are:
a. Do nothing beyond carrying on with existing NGC maintenance policy and the associated
functional/work specifications.
Will not improve expected reliability.
b. Increase the frequency of maintenance and inspection.
Not expected to improve reliability significantly, and may even increase the probability of
transformer failures by increasing the loading on the transformers not on outage.
c. Refurbish/repair to give life extension/increased reliability.
Remedial action unlikely to be economic/successful for SGT1 dielectric fault and life
extension unlikely to reduce SGT3 insulation ageing.
d. System rationalisation (NGC or REC ).
May not be feasible, but any reduction of site demand or improvement in site transfers
would be expected to reduce probability of transformer failures, particularly probability
of loss of second transformer.
A4 - 10
e. Increase spares holding.
The availability of a second spare would reduce the duration of loss of demand on second
transformer failure, but would not reduce likelihood of such failure
f. Carry out a replacement programme.
Replacement of one transformer ( preferably SGT1 ) would virtually eliminate the
enhanced probability of second failures and therefore loss of demand.
8. RECOMMENDATIONS
Due to the condition and age of the SGTs and their associated auxiliary equipment, replacement of
SGT1 is recommended by the year 2003/4 to ensure the long term integrity of supplies to the 66
kV GSP.
A4 - 11
CASE STUDY: 5
COUNTRY: ENGLAND AND WALES
COMPANY: NATIONAL GRID
PLANT: 275 kV NETWORK IN LONDON
LONDON INFRASTRUCTURE
National Grid has commenced upon one of its most complex projects to ensure it is able to meet
the demand for improved and secure electricity supplies to London for the next century. This case
study gives an overview of the project, which includes building of new substations and a linking
400kV cable.
2. CHOICE OF STRATEGY
Alternative strategies to address the situation were considered:
1) Like for like replacement at 275kV
2) Development to 400kV
System requirements:
Demand growth in central London is expected to rise, particularly due to computerisation and air
conditioning, and with no generation to support this, security of supply is dependant upon the NGC
and London Electricity network.
Cost:
Consideration of various options and the associated incidence of expenditure was taken into
account to decide the final strategy.
Consents:
A new 20 km tunnel with associated wayleave requirements is required for the chosen option, but
severe congestion would occur if roads were to be excavated for in-situ cable replacement.
Environment:
To minimise disturbance a tunnel was chosen for the cable route and to minimise noise an indoor
substation has been specified.
Technology:
Both options would allow the adoption of modern technology switchgear and cables, with
consequent improvements in reliability and availability.
Outages:
Outages for future like for like replacement work would be extensive, putting demand at risk over
several years and therefore options to reduce this requirement were investigated.
A4 - 12
4. THE PROJECT
By overlaying the existing 275kV system with a new 400kV system, outage requirements have
been minimised, and reliability will be increased as existing assets are replaced in a controlled and
phased manner. The 400kV option also provides for long-term demand growth and ensures
demand shortfall in the short term is not encountered.
A4 - 13
CASE STUDY: 6
COUNTRY: FRANCE
COMPANY: ÉLECTRICITÉ DE FRANCE
PLANT: 225 kV OVERHEAD LINE
The electric supply of the Dôle area (French Jura) relies on the 225 kV EHV transmission network.
The peak load of this area is about 350 MW. The overhead line that ensures the main supply is
overloaded under normal operating conditions (N status) and in case of line tripping (N-1 status).
Furthermore, this line includes several lengths of conductors from the 1930’s with low cross-
section. The Asset Manager considers this line as an ageing asset.
The problem is therefore to propose the best middle range plan for supplying the considered area
while solving the question of ageing asset.
2. CHOICE OF STRATEGY
Four alternative plans have been considered in order to provide an answer to this problem:
- retirement and advancement of a 400 kV overhead line with a regional 400/225 kV supply,
- retirement of the line and expansion of the regional 225 kV network, the regional supply
relying on an existing 400/225 kV existing source,
- rebuild and enhance the line, the regional supply relying on an other existing 400/225 kV
source,
- refurbish the line, changing the existing conductors, in order to improve the current carrying
capacity.
A4 - 14
- no need to significantly improve the current carrying capacity of the line because of the
slowing down of load growth and the expansion of local generation (cogeneration).
- environmental issues : the building of a new line or the rebuilding of the existing line with
improved current carrying capacity have turned to be impossible. It would have been very
hard to get the planning permission because of the sensitivity of the area to environmental
issues.
- cost : the implementation of a new national policy in order to reduce the transmission costs
which results in the need to drastically cut the capital investments for regional transmission
networks.
- Technology: complementary in-depth investigations performed by asset managers have shown
that most of the towers could support conductors with a standard 366 mm2 cross-section (a few
towers require to be slightly reinforced).
4. THE PROJECT
Refurbish the line and improving the maximum current capacity by changing the conductors,
changing conductor supports and mechanically reinforcing some towers
A4 - 15
CASE STUDY: 7
COUNTRY: GERMANY
COMPANY: DEUTSCHE VERBUNDGESELLSCHAFT
PLANT: 220 kV NETWORK
1. PREFACE
The development of the high voltage network is determined by the increasing demand of the
electrical energy in the past. The operation of the network will be done using the 220 kV and 380
kV voltage level. The 110 kV voltage level belongs nowadays to the distribution area.
The tasks of the voltage levels are as follows:
380 kV:
- national and international transmission tasks
- connection to power plants up to 1300 MW
- feeding the 220 kV and 110 kV voltage levels
- connection to big cities and industries
220 kV:
- national and international transmission tasks
- connection to power plants up to 700 MW
- feeding the 110 kV voltage level
- connection of big cities and industries
110 kV:
- regional distribution of electrical energy and regional transmission in rural areas
- connection of power plants up to 700 MW in general
- feeding the medium voltage networks
- connection to big communities
- connection to industrial customers
- reserve function of the 220 kV and 380 kV networks.
The possible development of the high voltage network was investigated by several studies in the
past. The result was that the 380 kV voltage level will be the most important high voltage grid in
the future, while the importance of the 220 kV grid will be reduced. This assumption is confirmed
by the decreasing of the relative proportion of the 220 kV voltage level in the high voltage grid. In
1970 the 220 kV proportion was more than 82 %, 1980 about 66 % and 1991 this proportion was
only 58 % (West Germany).
This development is referred according to the technical, operational and economical advantage of
the 380 kV voltage level as:
- greater transmission capacity
- better voltage stability
- connection to larger power plants
- lower transmission losses
- lower specific right of ways
A4 - 16
compared to the 220 kV voltage level. Whereas the first installation of the 220 kV grid was started
in Germany in the twenties of this century, the first installation started at the end of the fifties.
According to the age of several 220 kV equipments these elements has to be replaced in the future.
As the tasks of the 380 kV and 220 kV networks are more or less equal and there will be no
increasing of the energy demand in the future the question has to be solved, if the change over to
the 380 kV voltage level will be wise according to the planning, technical and economical reasons.
This was the reason of the DVG (German Transmission Company) to perform a study concerning
the tendency and development of the 220 kV voltage. The basis of this study was as follows:
- proportion of the 220 kV voltage of the transmission network today
- development of the 220 kV and 380 kV voltage level (development up to now, future
tendency)
- age of the 220 kV equipments
- average technical lifetime of the 220 kV elements
- reasons for changing, reducing or keeping up the 220 kV voltage level.
The result of the evaluation will be summarised in the following chapters.
A4 - 17
4. AGE OF THE 220 kV VOLTAGE LEVEL
The time range between the introduction of the 220 kV and the 380 kV level is about 30 years. On
this reason the average age of the 220 kV equipment is remarkable higher than those of 380 kV.
The age of the 220 kV equipment can be derived from table 1.
Table 1: Structure of the 220 kV equipments (number of elements)
Equipment ≤ 30 years > 30 years
380/220 kV network transformers 81 3
220/110 kV network transformers 454 83
220 kV power plant transformers 110 19
220 kV substations 217 98
220 kV couplings (national) 19 17
220 kV couplings (international) 14 8
1) system length in km
The elements, which are older than 30 years, is between 3 % (380/220 kV network transformers)
and about 47 % (national couplings). More than 67 % of the overhead lines are older than 30 years.
The comparison with the today structure of the age comes to the conclusion, that 220/110 kV
network transformers, power plant transformers, and overhead lines will reach their end of the
lifetime and should be upgraded or replaced.
A4 - 18
Eight of nine German transmission utilities are operating the 220 kV network. Four of eight
explain to replace the 220 kV in the future. One company intends to reduce the network whereas
one company will it keep up. Two companies wish to replace the 220 kV network, but due to
several constraints, they have to keep up these equipments in the future too. Five utilities intend to
use the 220 kV overhead lines by changing to 110 kV. The change to 380 kV is also intended.
Table 3: Reasons for the replacement, reducing or partial maintenance of the 220 kV
level
7. CONCLUSION
The relative part of the 380 kV level has constantly increased in Germany over the last three
decades. This happens mainly during the time of high increase of energy consumption in the sixties
and seventies, which is reduced in the past and should not be expected in the future. For the reason
of the high lifetime many 220 kV elements need to be refurbished or replaced, what is combined
with high investment costs. Therefore the existing standard and the future development of the 220
kV level was evaluated taken into consideration planning, technical and economical aspects. The
nine German transmission utilities make the data available.
The result is, that the 220 kV and 380 kV voltage levels have more or less the same importance.
The today importance of the 220 kV level can be derived from the number of national and
international couplings and feeding substations to important customers. According to the age of the
220 kV level it can be expected that many equipments reach the borderline of their statistical and
technical lifetime and should be refurbished or replaced.
The decision regarding replacement or reduction of the 220 kV equipments can not be done by one
single utility but has to be a common decision of the neighbouring utilities and customers due to
the connecting constraints. Therefore some utilities have to keep up the 220 kV equipments in the
future.
A4 - 19
Four of eight utilities, which use 220 kV elements, intend to change the 220 kV level. This process
will take about 20 to 30 years. One company will reduce the 220 kV network, whereas one will
keep it up. Two companies want to change the 220 kV level, but their are forced by different
reasons to use some parts over a long time. Five companies are planning new 220 kV elements on
a small scale. And five will change 220 kV overhead lines to 110 kV. The technical and
economical reasons for the changing, the reduction, and partial maintenance respectively of the
220 kV level are equal.
In the whole the 220 kV voltage level will lose importance whereas the 380 kV level will win. Its
part (relative and absolute) will be reduced. In a long time it will be stabilised at a lower level than
today.
A4 - 20
CASE STUDY: 8
COUNTRY: IRELAND
COMPANY: ESB NATIONAL GRID
PLANT: 110 kV OVERHEAD LINES
ESB National Grid has approx. 3,600 km of 110 kV transmission lines, of which over 1,000 km or
30% was constructed before 1960.
In recent years, a programme of refurbishing older 110 kV wood-pole transmission lines has been
initiated. The programme involves the replacement of poles and pole-top hardware. The line
conductor is not being replaced. Much of the work is carried out live.
• Maintenance activities are based on data from line patrols (air/ground), pole strength tests and
hardware inspection
• There was a perception that condition was rapidly deteriorating. There was an increasing
incidence of pole/hardware replacement. It was becoming clear that normal maintenance
would not be adequate unless it was significantly increased.
• Special condition assessments were carried out on selected lines to determine their true
condition.
Thus the assessment of asset condition was based on performance history, routine inspection and
maintenance and special inspection and diagnostic assessment.
The overall condition assessment showed that the condition of the 110 kV lines was outside
acceptable limits.
• Many poles had residual strengths outside safety limits.
• Maintenance resources required were becoming unsustainable in terms of cost, availability of
skilled staff and availability of outages.
• Conductors, steel towers and foundations were generally in good condition.
Thus the concept of refurbishment programme was born.
2. CHOICE OF STRATEGY
A number of alternative strategies to address the deterioration of the 110 kV lines were considered:
• Retirement – redesign system to be adequate without the line
• Rebuild the line like for like
• Rebuild and enhance the line – add earthwires, add optical fibre, increase current carrying
capacity, use heavier conductor or larger poles
• Refurbish like for like retaining the existing conductor, with the option of increasing current
carrying capacity by increasing ground clearances.
A4 - 21
transmission lines.) The planning permission might be refused, or might incorporate expensive
conditions. The fact of applying for planning permission might provide an opportunity for
objections to existing lines that have received general public acceptance.
Technology: The fact that the existing conductor is in acceptable condition limits the range of
options.
Outages: Long-term outages for refurbishment are not available. This limits he refurbishment to
work that can be carried out live.
Financial: Full line refurbishment may be treated as a capital project. A capital project is more
acceptable than increased expenditure on maintenance.
4. THE PROJECT
Refurbish lines and uprate to maximum current carrying capacity of conductor by increasing
ground clearances.
Carry out using live using live line techniques
Prioritise the work on basis of input from Planning and Operations Departments
Capitalise the work
A4 - 22
CASE STUDY: 9
COUNTRY: IRELAND
COMPANY: ESB NATIONAL GRID
PLANT: 110 kV STATIONS
2. CHOICE OF STRATEGY
A number of possible options are available to deal with this issue
• Retirement : redesign the network to be adequate without the station.
• Rebuild the station on a separate though adjacent site.
• Refurbish with enhancements – In a situation such as this refurbishment with enhancement is
the only option as like for like refurbishment cannot be carried out as the older equipment
being removed is no longer available and newer equipment has more features than the older
plant.
A4 - 23
3. FACTORS INFLUENCING CHOICE
System Requirements : Power System Planning will be consulted before each individual project
is undertaken to confirm the need for the station.
Cost : Refurbishment is a significantly cheaper option than rebuilding partly due to the fact that
some existing plant in all stations can be retained.
Planning Permission : A station rebuild would require planning permission. This might be
difficult to obtain and could provide a focus for objections against stations which to date have
received public acceptance.
Technology : Refurbishment provides the opportunity to introduce new technologies such as
integrated control and protection schemes etc.
Outages : There would be long-term outages associated with changing over to a new substation. In
the case of the refurbishment option, a mobile bay, complete with full protection facilities is used
to bypass individual bays meaning that the refurbishment can be carried out with disrupting
supply.
Financial : Refurbishment may be treated as a Capital Project.
4. THE PROJECT
Refurbish the Substations based on the requirements identified in the earlier survey
Carry out using mobile bypass bay to minimise outages
Confirm with Planning Department the long-term need for the substation and any short-term
developments planned for the station.
Capitalise the work.
A4 - 24
CASE STUDY: 10
COUNTRY: NORTHERN IRELAND
COMPANY: NORTHERN IRELAND ELECTRICITY
PLANT: 110 kV OVERHEAD LINES
• Patrols by both helicopter and foot where supplemented by targeted climbing inspections of
suspect structures.
• Detailed inspection led to the grading of decay present in poles and a prioritising of pole
replacement on a line.
• Problems with outages and access at ground level mean that it may take four years to complete
a line
• Some lines needed to be re-strung due to system requirements.
• Small amounts of ungreased conductor exist at this voltage and urgent replacement is required
due to condition.
Condition, criticality and age were all taken into account when prioritising work
2. STRATEGY
Strategies considered and the factors influencing the strategy are similar to the ESB’s refurbishment
programme. However the limited outages available on the network did not affect the decision to
continue with current working practices, as they do not require any additional expenditure on tools or
training.
3. PROJECT
Refurbish the 110kV single circuit overhead lines that are in poor condition based on an order
allowing for condition, criticality and age.
A4 - 25
CASE STUDY: 11
COUNTRY: NORTHERN IRELAND
COMPANY: NORTHERN IRELAND ELECTRICITY
PLANT: 33 kV CIRCUIT BREAKERS
1. INTRODUCTION
The Northern Ireland Electricity rural network has a variety of circuit breakers on the 33kV
distribution system. By far the most prevalent is the South Wales Switchgear E01 large oil volume
circuit breaker.
• The age profile is as detailed below. All the circuit breakers were installed between 1955
and 1976 i.e. are 23 to 44 years old.
140
120
100
Number
80
60
40
20
0
1955-60 1961-65 1966-1970 1971-1976
Year
• The E01 breaker accounts for 90% of the total population of outdoor 33kV oil circuit
breakers.
• The circuit breakers are on a 4 year cycle for maintenance.
• The current NIE policy for asset replacement for outdoor circuit breakers at 33kV is a
normal life expectancy of 40 years with no units expected to remain on the system beyond
45 years.
• The condition of most of the breakers is good however there are ongoing problems with:
- moisture absorption from tank oil on the bushings and leakage of bushing oil
- unit becoming obsolete due to lack of spares
3. CHOICE OF STRATEGY
Two strategies were considered in dealing with these particular units:
• Refurbishment: replacement of original copper breaker contacts with hardened tungsten
tipped contacts.
• Replacement: Phased replacement of selected units.
A4 - 26
4. FACTORS INFLUENCING CHOICE:
Performance : The level of post fault maintenance on many units had been particularly high as a
result of the frequent outages during winter storms. An investigation was carried out to identify
potential suppliers of hardened contacts for retrofit/ refurbishment, such as those used in current
SF6 technology.
Environmental: NIE have been pursuing a policy of replacement of outdoor 33kV meshes with
alternative arrangements in specific areas for purely environmental considerations. The options
include replacement with indoor 33kV switchrooms and low profile ground mounted reclosers
Technology: Technology has influenced the refurbishment and replacement decisions. In the case
of refurbishment, the ability to satisfactorily upgrade contacts by ‘defusing’ of tungsten tips has
allowed this increased performance. In the case of replacement, compact 33kV SF6 switchboards
have been incorporated in ‘barn’ type switchrooms thus eliminating the outdoor mesh
arrangement. In addition, by cabling out of the substation to a distance of 200m or more, the hub
and spoke effect presented around a substation by incoming overhead lines is reduced. The use of
33kV ground mounted reclosers in place of E01 breakers has also reduced the visual impact of
transformer feeder substations.
Age: A replacement programme of aged outdoor 33kV breakers is underway in rural areas where
the meshes will remain and there is sufficient existing stock of outdoor 33kV circuit breakers.
5. PROJECT:
Refurbishment:
• A number of units were re-type tested at CESI, Italy with original and hardened contacts.
Tests carried out to IEC56 (30% and 60% short circuit duty). This bandwidth covered 90%
of the substations where these breakers are installed.
• Based on the results of testing, the superior performance of the hardened contacts resulted
in pushing post fault maintenance from 4 fault operations to 15 operations.
• Maintenance interval now dependent on mechanism requirements rather than contacts. Trip
coil profiling being introduce to impact on time based maintenance interval.
• To date, approximately 30% of all E01 units have had their tips replaced. The programme
started with breakers with high fault levels and high number of operations. The remaining
units are being upgraded when maintained but also taking into account any proposed asset
replacement.
• As a result of this initiative, no post fault maintenance has been carried out over the past 3
years. The confidence levels of operational and control staff in the equipment’s
performance have also been increased.
Replacement:
• The replacement of E01 circuit breakers is based on system need, environmental issues and
age.
• In conjunction with system development, indooring of outdoor meshes is common in areas
where the impact on the local environment is can be reduced.
• Replacement of E01 breakers with new SF6 units is progressed in rural areas based on age
and condition to utilise existing stock.
• Replacement of the remainder will be dependent on age, condition and system
development.
A4 - 27
CASE STUDY: 12
COUNTRY: POLAND
COMPANY: POLISH POWER GRID CORPORATION
PLANT: 220 kV OVERHEAD LINES
2. CHOICE OF STRATEGY
A number of alternative strategies to address the deterioration of the 220 kV line were considered
mainly:
• Redesign for 400 kV on the same route.
• Rebuild and enhance the line; replace conductors, earthwires add optical fibre, increase
current capacity, replace insulators, in some places increase ground clearances and improve
foundations.
A4 - 28
Outages: The outages required for refurbishment are much shorter that those required for the re-
construction of the line for 400 kV. (3 – 4 months )
Financial: Full line refurbishment may be treated as a capital project. A capital project is more
acceptable than increased expenditure on maintenance.
4. THE PROJECT
Refurbish line and uprate the maximum current carrying capacity with larger conductor and by
increasing ground clearances. Replacement of insulators will increase the reliability of line and the
adding of optical fibre will increase general value of interconnection.
A4 - 29
CASE STUDY: 13
COUNTRY: POLAND
COMPANY: POLISH POWER GRID CORPORATION
PLANT: 220 kV SUBSTATIONS
2. CHOICE OF STRATEGY
A number of alternative strategies to address the deterioration of the 220 kV substation were
considered, mainly:
• Retirement.
• Rebuild the station like for like.
• Rebuild and enhance the substation in the same voltage level but much modern configuration,
change transformers, circuit breakers, disconnectors, current and voltage transformers, add a
new protection and control system which gives the possibility of remote control.
• Refurbish using majority of equipment..
A4 - 30
Outages: The refurbishment activity was continuing during operation of main transforms. The
outages was temporally for minimum time. The period of refurbishment was 2.5 years.
Financial: Full substation refurbishment may be treated as a capital project. A capital project is
more acceptable than increased expenditure on maintenance and consequences of forced outages of
big refinery. This refurbishment was expensive because there was needed to set down the old
equipment and supporting construction.
4. THE PROJECT
Refurbish substation and furnish with new equipment to improve the operation conditions and
reliability and permit remote control from the dispatching centre.
A4 - 31
CASE STUDY: 14
COUNTRY: POLAND
COMPANY: POLISH POWER GRID CORPORATION
PLANT: 220 kV NETWORK
A4 - 32
• Disassembly of the existing single circuit 220 kV lines and using the relieved routes to
construct multi-circuit and multi-voltage 400 and 220 kV lines;
• Rebuilding 220/110 kV substations into 400/110 kV substations with possible utilisation
of the existing 110 kV switching stations and rebuilding 220 kV switching stations into
400 kV switching stations;
• The need and possibility of considering various unconventional technical solutions (small
dimension lines, overhead NN switching stations with decreased isolation gaps).
3. The strategy of diversified approaches to the degree of limitation and further utilisation of the
220 kV grid in various regions of the country, together with predicting the zones of its
complete liquidation, zones of its full utilisation (and even moderate expansion) and mixed
zones (with partial overlap of 220 and 400 kV grids), was recommended as the preferred
strategy.
The work under consideration, after seminar examination at the beginning of 1997, was accepted
as the general guidelines to perform a series of more detailed works concerning individual regions
of the country.
The works have already been started and will be continued this and next year.
Their complicated and comprehensive character following from the necessity of parallel
consideration of several different problems such as: the assessment of the technical condition of
investigated equipment, system analyses, new design solutions, costs and economic comparisons,
should be emphasised.
Considerable practical difficulties in finding the most effective strategy for the reconstruction and
maintaining the operation of the 220 kV grid are mainly due to:
• Uncertainty regarding the future tasks of the KSP (Domestic Transmission Grid) within the
international exchange program. This fact depends on the determination of future means of
connecting and future co-operation principles of UCPTE and CENTREL systems with the
power systems of Russia. (Relevant works conducted in appropriate international groups are
not finished yet.)
• “Failing to meet” in time more remote needs of partial rebuilding of the domestic 220 kV grid
into 400 kV grid and the urgent need of modernisation of a considerable amount of older
equipment of the grid. The modernisation (for prolonged operation at 220 kV) and, on the
other hand, the change to 400 kV operation represent, to a considerable degree, alternative
undertakings to be harmonised to avoid spending the financial means for short-term useful
solutions.
Particularly complicated situation can occur for 220 kV equipment for which the need for urgent
modernisation within two next years was established. During this period the studies of justified
(necessary) liquidation of 220 kV equipment and their replacement with new 400 kV equipment
will not be completed.
In such a situation it is proposed to adopt the following additional procedure verifying the scope
and schedule of modernisation of 220 kV equipment within two next years:
1. The procedure should concern only equipment located on sites containing the existing 220 kV
grid and expected to be closed down (or reconstructed into 400 kV grids) following the work
cited above .
2. For the equipment mentioned above – the assumption of conducting, within next two years,
only the most urgent modernisation activities (concerning directly the operation, breakdown
hazards with catastrophic consequences) and to defer the remaining activities; in particularly
justified cases (far advanced realisation, large intermediate costs of interrupting the works) –
further continuation of works with aiming to minimise the costs of modernisation of these
objects (taking into consideration their not fully clarified perspective usefulness).
CONCLUSIONS
1. The most important network which will be developed is 400 kV grid.
A4 - 33
2. 220 kV network will be gradually changed but slowly.
3. A long range plan for the activities proposed in item 2 is needed.
A4 - 34
Table 1
The increase of length of 220 and 400 kV line circuits in the domestic transmission grid during
consecutive 5-year periods in the years 1965 - 1996.
Fig 2
The increase of length of 220 and 400 kV line circuits in the domestic transmission grid during
consecutive 5-year periods in 1965 - 1997.
3000
Lenght increase of line circuit
2500 400 kV
220 kV
2000
1500
1000
500
0
to 1964 1965-1970 1971-1975 1976-1980 1981-1985 1986-1990 1991-1996
-500
A4 - 35
Table 2
Characteristic of network assets of PPGC by the end of 1997.
Table 3
Statistic data on the age of network assets of PPGC.
Time diaposons
Specification Units More than Less than
25 - 20 20 - 15 15 - 10 10 - 5
25 years 5 years
years years years years
Length of 400 kV km 533 1095 562 1631 735 0
lines % 11,5 24 12,5 36 16 0
Length of 220 kV km 6541 788 730 162 0 0
lines % 79,5 9,5 8,5 2,5 0 0
Transformer MVA 1320 2550 0 930 1800 0
capacity 400/220 kV % 20 40,5 0 13 26,5 0
Transformer MVA 0 250 2750 1250 2750 330
capacity 400/110 kV % 0 3,5 37,5 17 37,5 4,5
Transformer MVA 8860 3083 3620 800 277 890
capacity % 50,5 17,5 20,5 4,5 1,5 5,5
220/110 kV
Number of breaker 6 31 21 52 54 10
400 kV % 3,5 18 12 30 31 5,5
Number of breaker 209 100 72 23 0 42
220 kV %. 47 22,5 16 5 0 9,5
A4 - 36
Table 4 Disadvantageous features of the 220 kV domestic grid (at the end of 1997, from the point
of view of its future use in the Domestic Power Grid – KSE)
Pos. Specification Reasons of appearance Consequences
1. Small usability from the point Progressing limitation of the Due to the expected
of view of serving transit and range of the 220 kV grid in intensification of the tasks
foreign exchange functions neighbouring countries following from the
participation of KSE in
the international power
exchange further
development of the 400
kV grid is indispensable
2. Disadvantageous structural
2.1. features a) Underestimation of increasing a) Insufficient (low) use of
Dominance of single circuit difficulties in getting new land per 1 MW of the
lines routes and permissions for transmission capacity.
(only 33% of 220 kV line constructing new lines NN b) Limited possibilities of
circuits on double circuit b) Grid development under the rebuilding 220 kV line
poles/supports) circumstances of short into 400 kV line (double
financial means circuits only).
2.2. Small cross-section c) Relatively large
working/active conductors As above transmission losses, small
constitute 40% of the whole transmission capacity
line length reserves against future
load increases
3. Improper technical condition a) From the very beginning, the a) The need of performing
of considerable part of elder part of the equipment of 220 extensive modernisation
220/110 kV stations kV stations installed in ( even by the end of the
previous years was technically standard life period of
outdated and of bad quality devices)
b) Premature use of simplified b) Large scope and high cost
switching station schemes, of modernisation works
with relatively deceptive
automatics
c) Lack of monitoring of the
level of the shorting power (at
the design stage)
4. Uneven loading of 220 and
400 kV lines operating in
4.1. parallel a) Inappropriate (too high) load a) Excessive transmission
Too high power of the electric increase prognosis for the losses in 220 kV grid,
power station in the 220 kV regions supplied by the 220 local overloads in 220 kV
grid kV grid grid in the states n-1
b) Limited financial means
(1965-1990)
4.2. Relatively low loading of the c) Existing 220/110 kV stations a) 220/110 kV stations,
400/110 kV station have very good localisation located nearer to customer
with respect to the main groups, have a te
customer groups ndency to overloading
A4 - 37
CASE STUDY: 15
COUNTRY: SLOVENIA
COMPANY: ELECTROINSTITUTE “MILAN VIDMAR”
PLANT: 220 kV NETWORK
1. INTRODUCTION
500
Circuit lenght (km)
400
300
200
100
0
59 55 50 45 44 40 38 34 33 31 30 29 28 26 25 24 22 21 20 19 18 17 16 12 11 10 9 8 7
Age (years)
A4 - 38
existing 220 kV lines, possibilities for transiting and loading, operation risk level, and alternative
replacement with 400 kV lines.
Compared with its size, the Slovenian transmission network is with its three voltage levels, i.e.
110 kV, 220 kV and 400 kV, and the intermediary 400/220 kV transformation, over complicated.
On the other side, there is only one production source connected to the 220 kV voltage in the
overall electric power system and no new sources are likely to be included on this voltage level in
the foreseeable future.
2. STUDYING MODEL
The above problems are comparable with cases as experienced in some European Electricity
Supply Companies where it has been established that the 220 kV voltage has, due to similar
constraints, no long term perspective. Furthermore, it was already over a decade ago that they
started abandoning the 220 kV network, or having it replaced with the 400 kV one, and the newly
constructed lines are of the 400 kV voltage level.
1 ,6
1 ,4
1 ,2
∆f [m
0 ,8
0 ,6
0 ,4
t= 5 0 y e a rs
t= 3 0 y e a rs
0 ,2 t= 1 0 y e a rs
t= 1 ye a r
t= 1 00 h
t= 1 0 h
t 1 h
0
50 150 250 350 a [m ] 4 5 0
A4 - 39
Possible variants for the 220 kV network
Owing to the above described problems that are expected to take place in the next 20 years, it is
necessary that the destiny of the 220 kV system is decided upon already now. Recently, the “Milan
Vidmar” Electric Power Research Institute implemented a techno-economic study4 in which an
analysis was made of two possible strategies of the further development of the 220 kV or 400 kV
transmission systems of Slovenia:
a/ 220 kV network refurbishment + monitoring
b/ replacement of 220 kV networks with the 400 kV one
For the two strategies the Institute elaborated technical solutions for the long term development for
the future 30 years taking into consideration uniform criteria for the network planning so as to
assure, on the long term basis, an equal quality and reliability of the consumption supply.
A4 - 40
the present-value rate and dynamics of the 220 kV system abolition on the final economic impact
is for each of the variant expressed in the index form as shown in Table 1. A comparison of the
overall present-value costs indicates that the variant with the transition to the 400 kV system (2A)
is, when compared to the variant of the 220 kV system preservation (1A), economically more
favourable between 7% and 13%, depending on the observed present-value rate. Fig. 3 makes a
comparison between the overall present-value costs of the 2A and 1A variants for the 8% present-
value rate. Following the above, it is quite evident that due to economic reasons it is quite
reasonable to seriously scrutinise the suitability of the gradual abolition of the 220 kV system and
its replacement with the 400 kV one.
100000 2A
-7%
80000
DEM x 1000
40000
20000
0
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030
leta
A4 - 41
4. CONCLUSION
The techno-economic analyses brought to light advantages and disadvantages of the abolition of
the 220 kV network and its transition to the 400 kV voltage.
Advantages:
- increase of transport capacity of the transmission network
- space exploitation rationalisation (environmental aspect)
- simplification of the network structure and smaller number of elements
- greater operation reliability level
- abolition of the 400/220 kV transformation and transformation directly to 400/110 kV
- smaller number of transformer stations, transformers and installed power
- smaller transportation losses
- smaller demand of the reactive power
- lower maintenance expenses
Disadvantages:
- high initiation investment expenses
- abolition of the 220 kV voltage level necessitates preliminary 110 kV system reinforcement
- increase of short circuit currents on the 110 kV level - installation of the switching
equipment of a greater capacity
- possibilities of administrative difficulties in the processes of permit and consent provision
owing to the public unfavourableness resulting from their fear of an increased effect of the
electromagnetic radiation
- necessity of reaching agreements with the neighbouring electric power systems as to the
dynamics of the 220 kV interconnection lines abolition.
Having assessed the technical, economic and not the least but the last environmental aspects of the
above advantages and disadvantages, we can draw the conclusion that despite the numerous listed
difficulties the development perspective of the Slovenian transmission system is in having its 220
kV voltage gradually abolished, reinforcing its 400 kV, and transition to the direct 400/110 kV
transformation. The planned dynamics of the 220 kV voltage level abolition and the scope of the
400 kV network construction are shown in Fig. 4.
900
800
upgrading and 400 kV
new constructions
700
Circuit lenght (km)
400
300
220 kV
200
abolition of the
100 220 kV network
0
1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020
Year
A4 - 42
5. REFERENCES
/1./ Study of thermal loading of conductors for OHL, 2. part, Electroinstitute “Milan
Vidmar, Ref No 1256, Ljubljana, 1994 (in Slovenian)
/2./ F Jakl, K Bakic, L Valencic, Combined use of the air monitoring system in
production and transmission of electricity, IEEE Transactions on Power Systems, Vol
12, No 4, August 1997, pp 1068-1075
/3./ Monitoring system supporting thermal loading of OHL in Slovenia, Electroinstitute
“Milan Vidmar, Ref No 1319, Ljubljana, 1994 (in Slovenian)
/4./ Technical and economical valorisation of 220 kV network in the long-term
development strategy of Slovenian EPS, Electroinstitute “Milan Vidmar, Ref No
1391, Ljubljana, 1997 (in Slovenian)
Summary
The paper analyses the issue of the further destiny of the 220 kV Slovenian transmission network.
The fact that the average age of the 220 kV network elements is some 30 years faces the electricity
transmission utility with the dilemma whether to have the 220 kV network further preserved and to
have it, upon the termination of its life period, refurbished, or to have it abandoned. A techno-
economic study that was made at the “Milan Vidmar” Electric Power Research Institute, led to the
conclusion that it would be technically and economically reasonable to have the 220 kV network
in the forthcoming 20 years gradually abandoned and replaced with the 400 kV one.
Paper prepared by
Kresimir Bakic and Joze Perme,
Electroinstitute Milan Vidmar
A4 - 43
CASE STUDY: 16
COUNTRY: SLOVENIA
COMPANY: ELECTROINSTITUTE “MILAN VIDMAR”
PLANT: AAC CONDUCTOR
AGEING STUDY OF CONDUCTORS AAC 500 MM2 AFTER FORTY YEARS OF
OPERATION1
Abstract
The paper is focused on the creeping phenomenon as observed in 500mm2 aluminium
(AAC) conductors of a 110 kV overhead transmission line in Slovenia. Results of an
investigation are shown providing a solid basis for a comparison between two forty years
old conductors; one having been in operation for thirty-five years and the other
inoperable. Values obtained with a prestress method employed at the line construction in
1955-1957 and thirty-five years later, i.e. in 1994, are analysed.
1. Introduction
The very first proposals of homogeneous conductors which were not reinforced date back to the
fifties. At that time, Prof. Milan Vidmar, the nestor of Slovenian Electric Power Engineers,
presented at the 13th International CIGRE Conference in Paris his idea about the mechanical
equivalence between copper and aluminium in the overhead transmission line technique /1/. In
accordance with this Vidmar’s conception, a 110 kV line with AAC 500 mm2 conductors, the
Pekre-Kidricevo line, was constructed in 1953-1955. In the course of time, the line has been given
the name the “Vidmar’s line”. The design of these conductors included 91 aluminium wires of the
2.65 mm radius. Later, it was realised that the Vidmar’s idea of unreinforced aluminium
conductors was only a partial solution as far as its long term aspect was concerned. While the level
of losses was satisfactory, mechanical properties of conductors were soon found to be quite
critical. The problem was their inadequate elasticity which exhibited itself in unacceptably great
sags for which reason several tightening ups of the line have been necessary. After forty years of
its operation, an analysis of the conductor creeping effect and its comparison with an inoperable
conductor of the same age were made. The interest of the investigation was laid in the
determination of differences between the ageing of the transmission conductor (rope) that has been
thermally stressed and the one that has not been submitted to such stressing.
As in the fifties the creeping phenomenon of conductors of overhead transmission lines was not yet
known, the today’s technique of special line erection was not practised. Moreover, even today
there are instances that the conductors creeping is not compensated at their construction.
Creep is defined as mechanical elongation of materials leading into the conductor prolongation,
increased sags or decreased safety ground clearance. In other words, this is the phenomenon of the
material deformation caused by long duration mechanical and thermal stressing.
In addition to the state of the observed AAC 500 conductors, a comparison will be shown with
some other conductor types as currently used in the world practice
2. Conductor creep on »Vidmar's line«
Immediately upon the construction of the line, increased sags resulting from the creeping effect
were observed. As this phenomenon was not adequately investigated at the time, Prof. Vidmar did
not pay due regard to the problem. Records of the building company which constructed the line
show that after a certain time of operation increased sags were detected and that conductors were
erected to their maximal tensile strength of 60/Nmm2, irrespective of the ambient temperature.
After 48 hours, this strength was decreased down to the conductors rated tensile strength. This
measure, which was taken in 1957, mechanically stabilised the conductor and sags were set up
1
Franc Jakl, Univercity of Maribor, Faculty for electricity 2000 Maribor, Slovenia
Kresimir BakicElectroinstitute Milan Vidmar Hajdrihova 2, 1000 Ljubljana, Slovenia
A4 - 44
according to the values defined in assembly tables. Thereafter the line operated with no problems
for quite many years.
After forty years of the line operation, new instances of increased sagging have been noted for
which reason an analysis of the state was envisaged.
A laboratory analysis (by Dalekovod, Zagreb, Croatia) was made at a constant temperature θ=25.5
∀0.5 ΕC and at a constant tensile strength for:
a) a new conductor σEDS 18.4%=27.52 N/mm2
b) an old conductor σEDS 18.3%=27.39 N/mm2
Figure 1 shows results of the laboratory creep analysis for different conductor samples.
Legend: 1 – AAC 500 – Unused conductor , sample 1 (25 ºC, 18% EDS)
2 – AAC 500 – Used conductor, (25 ºC, 18% EDS), 34 years in operation
3 - ACSR 490/65 (24 ºC, 18.3% EDS)
4 – AC/ACS 475/25 (27 ºC, 14% EDS)
5 – AAAC 185 – (27 ºC, 22.9% EDS)
6 – AAC 500 – Unused conductor, sample 2 (24ºC, 18% EDS)
7 – UTAL (230ºC, 20% EDS)
8 – ZTAL (230ºC, 20% EDS)
9 – ZTAL (20ºC, 20% EDS)
10 – Steel wire 4.5 mm (150ºC, 14% EDS)
11 – Invar steel wire 4.5mm (240ºC, 20% EDS)
12 – Invar steel wire 4.5mm (20ºC, 20% EDS)
The employed algorithm for the calculation of the permanent AAC 500 conductor coefficient of
expansion (conductor no 2 in Fig. 1) was:
Єm= 0.00041 t0.0189 m/m
The value of the permanent expansion for the operational period of forty years (from the first
conductor strengthening up in 1956 until the last one made in 1996) was 521 µm/m. Figure 2
shows the details of testing two AAC 500 conductors.
A4 - 45
Fig.2: Detailed curve of creeping for a) 35 years in operation conductor AAC 500 and
b) unoperated conductor AAC 500 both with age of 40 years
3. Determination of the value of the permanent expansion for the AAC 500
conductor after forty years of operation
Site reports prepared by the maintenance personnel warned about the decreased safety heights that
were observed particularly during hot summer days. For this reason geodesic measurements of
sags and safety ground clearance - the first ones were carried out by the maintenance personnel
and the second ones by designers - were made on the most critical parts of the line (at crossings
with heavily burdened roads). Their common conclusion was that ground clearance had been
decreased by 0.9 - 1.1 m (at the mean span of 250 m) and the tensile strength by 13.8%.
An example of measured and calculated sags or tensile strengths of the AAC 500 type conductor
for the span between towers no. 22 and 23 is shown in Fig. 3.
A4 - 46
For the observed span a = 258.2 m, the prolonged length of conductors lδ was at decreased tensile
strength from σ1= 60 N/mm2 down to σ2 = 51.7 N/mm2 at the conductor creeping
8 2
lδ = (f 2 − f12 )
3a
A4 - 47
CASE STUDY: 17
COUNTRY: UNITED STATES
PLANT: 230 kV CIRCUIT BREAKERS
2. CHOICE OF STRATEGY
Alternative strategies to address the situation were considered:
1) Refurbishment of existing breakers (replace leaking bushings)
2) Replacement of existing breakers (replace like for like)
3) Retirement of existing breakers (remove breakers and do not replace)
Technical Obsolescence:
Refurbishment was considered to repair the heavy-leaking SF6 circuit breaker. Since this was one
of only two breaker types on the transmission system and spare parts were becoming difficult and
expensive to obtain, it was decided that investments in major refurbishments could not be justified
for this breaker type.
Cost:
Replacement cost was weighed against the predicted savings in SF6 expense. Although
replacement of the heavy-leaking circuit breaker had a valid business case, it would not necessarily
receive funding due to budget constraints and prioritisation of other projects for the transmission
infrastructure.
Environment:
Reduction or elimination of SF6 leaks was strongly desired due to the potent nature of this
greenhouse gas.
System requirements:
The substation was originally designed and built for future expansion and the 230 kV bus was a
breaker-and-half configuration. However, future expansion turned out not to be needed over the
years and is not predicted to be needed in the near future. The two breakers considered for
technical obsolescence only serve the purpose of redundancy at the station and could be opened
without interrupting the flow of energy during normal conditions. The removal of these breakers
was proposed and the new configuration was evaluated by system planners and system operators
and determined to be acceptable.
A4 - 48
4. THE PROJECT
Removal of the two 230kV circuit breakers completely removes a circuit breaker population that
had a technical obsolescence problem in addition to removing a problematic SF6 piece of
equipment. There are minimal costs associated with this option (relay changes, removal costs,
reduced reliability) and extensive benefits (elimination of obsolete design, reduced SF6 costs, extra
free-standing CTs and gang switches for stock). The solution for this application was very unique
and only applicable to the particular station studied. Other “obsolete” circuit breakers were
evaluated in terms of breaker position elimination, but this solution could not be implemented at
these locations.
A4 - 49
Appendix 5.
The RCM method considers the condition of the equipment as well as its importance
in the system. Therefore this method can be used as a valuable tool for planing of
renovation measures. In the following three different types of 420 kV circuit-breakers
are considered. The aim of the investigation is to prove the practicability and ability
of the computer based RCM-method and the exactness of the assessment.
For definition of importance of the breaker in the system different options are
available. The definition applied in these investigations takes into account the non-
availability of the equipment and the loss of power caused by the outage of the
breaker in question. The non-availability is ascertained from the outage time and the
statistical outage and failure rate respectively. The outage time of the breaker
depends on the scheme and the layout of the substation and the location of the
breaker in the station. The loss of power is evaluated from the real load flow via the
breaker in concern. For comparison the value is normalised and related to the
maximum value in the network configuration under consideration.
The first type of breaker under investigation is a minimum oil circuit-breaker with
eight units per pole. These breakers with a spring drive mechanism were taken into
service between 1973 and 1978. The second type, a double pressure SF6 breaker
with four units per pole, belongs to the first generation of SF6 circuit-breakers and
were equipped mainly with hydraulic drive mechanisms, but some with pneumatic
drives. These breakers were installed in 1972 and 1973. The third type counts to
first generation of SF6 puffer-breaker. It is a four unit breaker with an hydraulic drive
mechanism taken into service in the period from 1975 to 1978.
The importance is mainly in the region below 50 %. But four breakers are classified
in the range above 90 %. All these latter breakers are installed in generator feeders.
From these results one can derive a renovation strategy in four stages. First the
three breakers of the before mentioned generator feeders and the two other
breakers in a highly exploited substation have to be exchanged. Secondly the
breakers in the 50 % range and at last those in the 30 - 40 % range have to be
considered. Because of the low importance a renovation of the breakers below the
30 % range can be disregarded and reconsidered when a new inventory of condition
and importance for this type of breaker is carried out after a certain period of time.
minimum oil breaker
100
80
condition c
60
40
20
0
0 20 40 60 80 100 120
importance i
The population of this type of breaker consists of 21 pieces. The results are
presented in figure 2. Since only breakers of two subsequent years of manufacture
are installed the condition varies only in a small range. Compared to the condition
level of the minimum oil breakers the average is some what higher, i.e. the condition
of this breaker in general is worse which is also in accordance with the overall
service experience. The renovation suggested is to exchange all these breakers in a
defined sequence beginning with the breakers in the range of importance of 60 %
and above. The second section contains the 30 % up to 60 % range and the last the
section below 30 %. Because of the reduced reliability, these breakers have to be
observed thoroughly, e.g. by yearly recording of the condition.
SF6 breaker, dual pressure type
100
80
condition c
60
40
20
0
0 20 40 60 80 100
importance i
The population under investigation of this type comes to 38 breakers. The results
can be taken from figure 3. The importance of the population in concern is to more
than one half below 35 %. Only a small amount is above 60 %. One of these
breakers with 90 % importance belongs to a generator feeder.
100
80
condition c
60
40
20
0
0 20 40 60 80 100
importance i
The condition in total is considerably better compared to the breakers dealt with
before. It is in the range between 45 % and 55 %. With regard to the condition even
the worst breaker of this type is better than the best minimum oil breaker of the
same year of manufacture. This proves the superiority of the puffer-type breaker
technology and complies with the service experience in general. The small range of
variation depends on the years of manufacture close together without any particular
change in technology.
The results with this breaker show that in the foreseeable future no renovation
measures will be necessary. They can also be used to adapt the limit value between
normal maintenance activities and renovation. Based on the comparison between
the three breaker types under investigation the condition limit value was assumed to
60 %. By means of some more detailed tests and measurements of the breakers’
condition and consideration of the failures rates of breakers which will be renovated
soon the limit value can be fixed more precisely.
2 Evaluation of a network
2.1 Circumstances
2
A German utility (approximately 6,000 km service area, 1.6 million private and
commercial clients, 1,150 staff members) which had realised the importance of
optimising maintenance processes wanted in 1999 to audit, evaluate and optimise
the existing assets as well as to analyse and optimise the maintenance processes in
co-operation with an internationally active consultancy company within the scope of
Auditing the available equipment and comparing them to the existing data bases
was the first necessary step for achieving the goals of the project - firstly because
until then the maintenance and archiving of data depended largely on the person
who conducted it, and secondly because certain data (such as condition and degree
of maintenance) was not available for all equipment.
The results of the analysis were evaluated and compared to reference values from
the internal data bases of the utility. At the end of this phase of the project, a
complete "finger-print" of all the significant equipment in the network was available.
In the next step, the information acquired in the analysis phase was used for
developing alternative maintenance strategies. In TBM strategies, the equipment are
replaced after a hypothetical period of service life and maintenance is carried out
continuously after specific time intervals. A maintenance budget based on this
approach corresponds to an index value of 100.
However, this was not enough for achieving the goal of the project. Assessing the
possibilities of approaches using modern Reliability Centered Maintenance (RCM)
was an even more important task. Such approaches distinguish themselves through
the fact that they not only take the technical condition of the assets into
consideration but also their importance in the overall network.
The result of the total assessment of the 123 kV and 245 kV circuit-breakers is listed
in figure 4. In addition to that, customer specific critical values for the technical
condition of the equipment are defined. In the example shown in figure 8, the critical
value for a maintenance measure (cM) is fixed at c = 40 whereas the critical value
for a replacement or retrofitting measure (cR) is fixed at c = 60. For example
according figure 10 an extremely important circuit breaker (i = 100) is in a critical
position (c = 56) and must be maintained urgently. Furthermore, a general order for
maintenance measures can be derived from the figure.
In the same way further h.v.-equipment are assessed, for example transformers,
which are listed in figure 4, and instrument transformers. Furthermore complete
substations and h.v. overhead lines are considered. The main difference is, that
several items have to combine to a single statement. For example, the substation
consists of:
- bays - cicuit-breakers
- instrument transformers - disconnectors
- secondary equipment - civil works and so on.
condition c
importance i importance i
This different items have to assess according to their condition and the cverall
condition of the complete substation is evaluated considering the investment costs
and amount of the several items.
3 Conclusion
The reliability of Transmission Assets over their lifetime follow the familiar bathtub
curve : relatively high infant mortality in the early stages followed by a long period of
normal reliable operation. Reliability again decreases as the asset approaches the end
of its useful life.
Transmission asset managers or maintenance managers will want to ensure that the
asset remains in the high reliability zone for as long as possible. In order to ensure
reliable operation the assets must be maintained. Traditionally, this involved removing
the asset from service to carry out regular maintenance activities.
In an ideal world the transmission system would have sufficient spare capacity to
enable plant to be removed when required and for as long as required to carry out the
required maintenance. However in many utilities, particularly mature utilities, demand
growth continues while increasingly greater restrictions are placed in the way of new
plant construction. The result is that maintenance outages are becoming more difficult
to obtain, in particular long outages for major overhauls.
This situation needs to be addressed on two fronts :
• Maintenance managers must put in place policies and methodologies which
will continue to provide the required level of reliability with reduced
maintenance outages.
• for future plant, the maintenance manager must be involved in the
design/specification stage of new assets and he must ensure that assets which
are installed have minimum maintenance requirements.
In relation to the former, the following techniques have the potential to
minimise/optimise outages :
• Acceleration of the work, e.g. using additional labour or resources,
• Use of parallel construction of circuits, e.g. utilising either circuit by-pass
facilities, mobile by-pass switchgear bays.
• Temporary protection panels or relay rooms.
• Pre-wired protection cubicles or suites.
• Temporary by-pass towers on OHL routes or in substations.
• Off line cable, transformer or substation replacement.
• Use of temporary control operating points as control facilities are replaced.
• Construction of new circuits before retirement of assets to be renewed
The Asset Replacement Planner is a method used by one company to ensure that resultant
asset replacement plans are communicated widely, and in particular to the system planner,
is by representing the plans on a bar chart over a 20-year timeframe. This 20 year “Asset
replacement Planner” supports the more usual representation of plans on System
Development Diagrams and allows the “Big Picture” to be seen. Copies of the planners
are also made widely available within the company by placing them on the company
Intranet.
Asset Replacement proposals affecting "Main Distribution Company" Portfolio sites For further information, contact ………….. MAIN Dist. Co
Business Plan
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12 Yr 13 Yr 14 Yr 15 Yr 16 Yr17 Yr18 Yr19 Yr20
Substation Connectee Site built 00/01 01/02 02/03 03/04 04/05 05/06 06/07 07/08 08/09 09/10 10/11 11/12 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20
Footham 66 MQ 1965
380, 480 and bays replacement - Indoor ABCB's AEI GA6W4 (AR01567372)
Footham 275 MQ 1968
4sw mesh AEI GA10's - whole S/S replacement (AR05643173)
Kirk 132 MQ 1962
l XOPR60's & bays (AR0054620)
Kirk 275 MQ 1965
KEY
Cependant, le CIGRÉ ne pourra en aucun cas être tenu responsable des préjudices ou dommages de quelque
nature que ce soit pouvant résulter d’une mauvaise utilisation des informations contenues dans cette brochure.
Copyright © 2000
Toute reproduction, même partielle, par quelque procédé que ce soit, est interdite sans autorisation préalable.
Cette interdiction ne peut s’appliquer à l’utilisateur personne physique ayant acheté ce document pour
l’impression dudit document à des fins strictement personnelles.
Pour toute utilisation collective, prière de nous contacter à sales-meetings@cigre.org
The greatest care has been taken by CIGRE to produce this digital technical brochure so as to provide you with
full and reliable information.
However, CIGRE could in any case be held responsible for any damage resulting from any misuse of the
information contained therein.
Published by CIGRE
21, rue d’Artois
FR-75 008 PARIS
Tel : +33 1 53 89 12 90
Fax : +33 1 53 89 12 99
Copyright © 2000
All rights of circulation, translation and reproduction reserved for all countries.
No part of this publication may be produced or transmitted, in any form or by any means, without prior
permission of the publisher. This measure will not apply in the case of printing off of this document by any
individual having purchased it for personal purposes.
For any collective use, please contact us at sales-meetings@cigre.org