Académique Documents
Professionnel Documents
Culture Documents
CONTENTS
Preface vii
Index 152
vii Preface
PREFACE
1
APPLICATION OF CONCURRENT
ENGINEERING (CE) FOR
CONSTRUCTION INDUSTRY
Mohamad Ibrahim Mohamad
Andrew Noel Baldwin
Khairulzan Yahya
1.1 INTRODUCTION
Concurrent Engineering (CE) is a management philosophy
originated from manufacturing industry. There are many
definitions of CE that can be found in the literature but most of
them are similar. The term “Concurrent Engineering” was
originally devised by Institute for Defense Analysis (IDA), a
working group set up by US Defence Advanced Research Project
Agency (DARPA) in their Report R-138 (Winner et al., 1988). The
IDA definition of CE is the most widely accepted by the
manufacturing community as follows:
“Concurrent engineering is a systematic approach to
the integrated, concurrent design of products and their
related processes, including manufacture and support.
This approach is intended to cause the developers, from
the outset, to consider all elements of the product life
cycle from concept through disposal, including quality,
cost, schedule, and user requirements”.
The rationale for the application of CE to construction derives
from the similarity of the basic construction/manufacturing process
as well as the nature of the problem faced by both industries, as a
result of the traditional approach practised in its work process.
Many aspects of CE are not actually new to construction. Some of
2 Issues in Construction Industry
1.2 BACKGROUND
CE is a widely accepted design management philosophy in several
industries especially in manufacturing. However, despite the claim
made by Love and Gunasekaran (1997), there is no research
evidence to support that it has been fully applied in construction to
the same extent as in other industries. The topic of the application
of CE and its fundamental elements to construction has generated
some interest in research literature such as De La Garza et al.
(1994), Baxendale et al. (1996), Evbuomwan and Anumba (1996),
Houvilla et al. (1997), Love et al., (1998) and Kamara (1999). The
main focus of the discussion can be categorised in two key areas,
the application specific CE tools and modelling technique to
support data integration in a CE environment and the managerial
perspective of CE implementation as a complete process. However
the literature relating to construction application is far more
limited compared to those in manufacturing.
1.3.2 Teamwork
The use of teamwork is a common feature approach in today's
management practice. It is also a common practice to organise a
project team prior to the execution of the construction project.
However the basic feature of the teamwork is different from one
application to another. The concept of teamwork used in CE
principles is based on collaborative teamwork system or more
appropriately known in CE practices as Cross Functional Team
(CFT).
creates synergy for project success. However the author argues that
the ability of the partnering approach to develop a teamwork
concept parallel to CE principles depends on several factors.
Among the factors are: who are in the partnering parties; the real
objectives of partnering (because it is intended to pursue a business
goal); the involvement of the clients in the partnership; and the
type of procurement approach used to deliver the project.
The role of the each participant must be recognised and also their
contribution toward the project design development. The
contractor, or their subcontractors, material and equipment
suppliers who have knowledge on the constructability aspect of the
project and material usage must be recognised for their role to
influence or review the design. In CE, they will be given the role
to contribute during the conceptual and detail design phase of the
project. This will be achieved within the multifunctional
8 Issues in Construction Industry
REFERENCES
2
CONSTRUCTABILITY IN
CONSTRUCTION
Rosli Mohamad Zin
2.1 INTRODUCTION
weather
Lack of consideration to storage
*
needs
Lack of consideration to problem of
*
traffic control
Lack of consideration to existing
Design-related problems
*
Issues in Construction Industry
*
equipment or manpower
Poor techniques/sequence of
construction forced upon by the
*
design
Lack of consideration to accessibility
*
*
needs
*
*
Improper construction tolerance
*
*
Unpractical design details
*
Lack of standardisationn
*
Poor design information
*
Incomplete design details
*
Unsafe design
*
Complex design
Rowing and
Navon et al.
Alshawi and
Fisher and
Ghanah et
O’Connor et
Tatum et al.
Griffith and
King (1987)
Underwood
References
al. (1987)
al. (2000)
Ferguson
Sidwell
Jargeas
Adams
Kasper
CIRIA
(1983)
(1985)
(1986)
(1989)
(1989)
(1989)
(1994)
(1991)
(1995)
(1996)
(2000)
Rajan
Anon
20
Constructability in Construction 21
Average Index = ∑ ai xi
∑ xi
Where, ai = constant expressing the weight given to i
2.4 RESULTS
Frequency
Percentage
Percentage
Valid
Percentage
Cumulative
Owner 9 28.1 28.1 28.1
Consultant 4 12.5 12.5 40.6
Contractor 19 59.4 59.4 100.0
Total 32 100.0 100.0
Percentage
Percentage
Valid
Percentage
Cumulative
Frequency
Percentage
Percentage
Valid
Percentage
Cumulative
Architects 12 37.5 37.5 37.5
Engineers 20 62.5 62.5 100.0
Total 32 100.0 100.0
Percentage
Percentage
Valid
Percentage
Cumulative
0-5 years 19 59.4 59.4 59.4
6-10 years 12 37.5 37.5 96.9
> 10 years 1 3.1 3.1 100.0
Total 32 100.0 100.0
Constructability in Construction 25
Frequency
Percentage
Percentage
Valid
Percentage
Cumulative
0-5 years 16 50.0 50.0 50.0
6-10 years 14 43.8 43.8 93.8
> 10 years 2 6.3 6.3 100.0
Total 32 100.0 100.0
Average Indices (Owner)
Average Indices (Contractor)
Average Indices (Consultant)
(H)
Kruskall‐Wallis Significance
No. DESIGN-RELATED
PROBLEMS
2.5 DISCUSSION
In the questionnaire survey the design-related problems gathered
through literature were used to test the degree of occurrence of
those problems among architects/engineers in the Malaysian
construction industry. The results obtained indicate that there is not
much difference in term of ratings of the degree of occurrence of
design-related problems regardless of the respondents’
characteristics i.e. type of companies, specialisations, design
experience and construction experience. Survey results confirmed
that the design-related problems exist during construction but at
varying degree of occurrence. In section 2.0 it was highlighted that
these problems are encountered during construction but the origin
of which can be traced back to the design process. These problems
arise due to poor constructability consideration during the design
works. In order to improve design constructability, certain
requirements must be achieved. Researchers used various terms
for those requirements such as constructability concepts,
constructability principles, constructability commandments, or
constructability improvement types. Nevertheless, “constructability
principles” has been used quite widely among researchers. The
constructability principles should be considered or applied by the
designers during the design works. The followings are eighteen
principles of constructability that are applicable at the design stage
(CIRIA 1983; Tatum et al. 1985; CII 1986; O’Connors et al. 1987,
Adams 1989; Griffith and Sidwell 1995):
28 Issues in Construction Industry
3. Encourage Standardisation/Repetition
Constructability is improved when standardisation and repetition
of design elements are maximised. The design of building elements
should encourage appropriate repetition and standardisation, so as
to reduce learning time and speed of construction. Many
construction project elements have potential for standardisation.
Building systems, material types, construction details, dimensions,
and elevations are examples of project elements that may be
standardised for increased field efficiency.
2.5 CONCLUSIONS
Design-related problems are common issue in the construction
industry especially among contractors. The impact of design-
related problems can sometimes be quite significant to project
performance. Quite often projects are delayed or costs are
increased as a result of poor design solutions produced by the
designers. This study identified fourteen types of design-related
problems that are common in the local construction projects. It is
recommended that constructability should be properly
implemented at the design stage in order to minimise the design-
related problems.
REFERENCES
3
ECO-COSTS OF SUSTAINABLE
CONSTRUCTION WASTE
MANAGEMENT IN MALAYSIA
Khairulzan Yahya
A. Halim Boussabaine
Zaiton Haron
Rozana Zakaria
3.1 INTRODUCTION
Sustainable development is a development that taken the issue of
environment as a priority besides on making whatever planning
into reality. One of the key themes of 'sustainable development' is
managing a waste (Williams, 1998). Sustainable waste
management encourages the generation of less waste, the re-use,
recycling and recovery of waste that is produced. Farmoso et al.
(1999) defines waste as any losses produced by activities that
generate direct or indirect costs but do not add any value to the
product from the point of view of the client. While Symond (1999)
define wastes as any substance or object, which the holder discards
or intends, or is required, to discard. Construction activity requires
and consumes a large amount of natural resources. Beside of
negative impact to the environment due to depletion of natural
resources, it may increases the amount of waste and pollution if no
measurement to tackle the problem is taken. In Malaysia, the
construction waste has cause a significant impact on the
environmental and also increasing the concern of the society
(Beguma, Siwar et al. 2006). Hence, this paper, review
construction waste minimisation strategies, addresses the issues
that are attributed to construction waste management and presents
36 Issues in Construction Industry
REDUCTION
REUSE
RECOVERY
DISPOSAL
industry, waste may arise from any activity or process from one or
more of the following (Wyatt, 1974); manufacturer, designer,
construction process and client (the use of building). Gavi1an and
Berno1d (1994) and Craven et.a1 (1994) described the main causes
of the waste generation which among other including error in
contract document, changes to design, ordering error, accident,
lack of site control and lack of waste management, damage during
transportation and off cuts from cutting materials to length.
However, Chen et al. (2002) emphasised that construction waste is
still beyond controlled because of these three factors, construction
firms reluctant to adopt low-waste technique as it is expensive to
use; design coordination has a major impact of waste generation;
on-site construction waste. In the handling and distribution of
components from the manufacturer or supplier to site, potential of
loss or damage the materials may not be able to avoid.
Winning of raw
recycling
Recyling to Manufacturing
other dispose
Recycling to
manufacturing Designer
industry recycling
Recyling to Construction
other dispos
Recycling to
Client (use of
construction
b ildi / ti
Recyling to Demolition
other dispose
Direct costs are defined cost that gives direct impact on the
construction process (McGrath and Anderson, 2000). In adequate
consideration at design stage may lead to various level of waste;
excessive cutting, rejection of poor quality materials, excessive
excavation and many more. This was also identified as one of the
factors influencing generating of waste onsite.
Risk
Cost Process
Construction
Waste
Management Policy
Impact
Technology
Risk
Σ Cost saving of recycling and reuse, Crr = Crr1– (Crr2+ Crr3) (3)
Where,
Crr1 = cost of implementation/operation
Crr2 = cost of saving of recycling strategies
Crr3 = cost of saving of reuse strategies
Total of Eco-costs =
Cwc + Cwt + Cwd + Cep + Ce + Crr + Ct + Ci + Cr (8)
3.5 CONCLUSION
The research is part of contribution in construction industry
towards sustainable development in Malaysia. The research aims is
to develop a sustainable waste quantification eco-costs model
based on empirical study approach in construction stage. The
implementation of the above eco-costs algorithm will be made in
each of the activities during the construction processes. Based on
literature review and it is shown that data availability on material
waste in building industry in Malaysia was relatively scarce and
most of the current research focused fairly limited number of
material in a few construction sites. Past research shows that,
construction waste management area has a broad and unique
problem to be solved in order to make our development sustainable
in the future.
REFERENCES:
Alfredo Serpell and Luis Fernando Alarcon (1998), Construction
Process Improvement Methodology for Construction Projects,
International Journal of Project Management, Vol 16 No.4, pp
215-221, Pergamon.
Beguma, R. A., C. Siwar, et al. (2006). "A Benefit-Cost Analysis
On The Economic Feasibility of Construction Waste
Minimisation: The Case Of Malaysia." Resources,
Conservation and Recycling 48: 86-98.
Bossink, B.A.G., and Brouwers, H.J.H. (1996), “Construction
Waste: Quantification and Source Evaluation”, J. Constr. Eng.
Management, 122(1), pp 55-60
Carlos Torres Farmoso, Eduardo Luis Isatto and Ercillia Hitomi
48 Issues in Construction Industry
http://aplikasi.kpkt.gov.my/ucapan.nsf/8521d968204e8b45482
5697400224ca6/f0039c303ee60fe7482571ab000de3c6?OpenD
ocument, visited on 30/12/2008
Lau, H. H., A. Whyte, et al. (2008). "Composition and
Characteristics of Construction Waste Generated by
Residential Housing Project." International Journal of
Environmental Research 2(3): 8
Senthil Kumaran. D, S. K. Ong and A. Y. C. Nee (2000), Tool to
Incorporate Environment Costs Into Life Cycle Assessment,
Environmentally Conscious Manufacturing Conference,
Boston, Massachusetts, U.S.A. November 6-8, 2000.
Skoyles E.R. and Skoyles J.R. (1987), Waste Prevention on Site,
Mitchell, London.
Symonds Group Ltd, ARGUS, COWI and PRC Bouwcentrum
(1999), Construction and Demolition Waste Management
Practices, and their Economic Impact, Report to DGXI,
European Commission.
Wen-Ling Huang, Dung-Hung Lin, Ni-Bin Chang and Kuen-Song
Lin (2002), “ Recycling of construction and demolition waste
via a mechanical sorting process”, Journal of Resource,
Conservation and Recycling, Elsevier Science, 37, pp 23-37
Zhen Chen, Heng Li and Conrad T.C. Wong (2002), Journal of
Automation in Construction, Elsevier Science
240 Advances in Manufacturing and Industrial Engineering (2008)
4
CONSTRUCTION SITE NOISE
MODELLING USING STOCHASTIC
TECHNIQUES
Zaiton Haron
Khairulzan Yahya
David Oldham
4.1 INTRODUCTION
The prediction of noise arising from an construction activities
represents a problem when a number of different processes are
carried out at different times in the course of the working day.
These typically involve the use of powerful machines that have
correspondingly high sound power levels[1]. The nature of the
sources, coupled with the limited opportunities for the screening of
neighbouring sensitive locations from the noise generated, means
that complaints often arise from such activities. Problems can be
avoided if noise levels arising from these activities can be
controlled to comply with the noise limits specified by the local
authority at the planning stage. This requires the application of a
suitable noise prediction technique, however, the noise
experienced at a receiver is affected by factors such as movement
of machinery around the site, the operational characteristics of the
machinery, distance from the site, ground cover, screening and
meteorological conditions. At the planning stage the data regarding
these factor are very granular[2].
where ,
Lm is band noise level for distribution 1
Ln is band noise level for distribution 2
m=1,2,3…..i and n=1,2,3…..,j
Source Location
Centre of
Receiver
These two values, together with the source height, zs, define its
location.
Wij (8)
I ij =
2πrij
2
Assuming that, for far field radiation from a finite source, the
sound pressure level is equal to the intensity level yields the
following expression for the sound pressure level.
W (10)
I (i , j ) =
2πr( i , j )
2
Area
Element
Source
Receiver
Figure 4.2 Division of site into small area elements for the
probabilistic method
Construction Site Noise Modeling Using Stochastic Techniques 59
0.25
0.15
0.1
0.05
0
65 70 75 80 85
Level ((dB)
B
PDFB %idle = .( PDF100%idle ) (11)
100
C
PDF C % on = .( PDF100 % on )
100 (12)
where
• P100% idle is the probability distribution for the machine
idling for 100% of the time.
• P100%on is the probability distribution for the machine on
full power for 100% of the time
• PB% idle is the contribution to the probability distribution for
the machine idling for Z% of the time.
• PC%on is the contribution to the probability distribution for
the machine on full power for Y% of the time
A
PDF = + PDF B % idle + PDF C % on (13)
100
0.25
0.1
Probability method
0.05
055 60 65 70 75 80
Level, dB
0.25
(d=225m,std=0.9)
Frequency distribution
0.2
(d=125m,std=1.1)
0.15
(d=75m,std=1.9)
0.1
(d=50m,std=2.6)
0.05
0
35 40 45 50 55 60 65 70
Level, dB
50 80
60 x 50
50
45°
70 60
45
64
°
20
Receiver
0.2
0.18
0.16 E xcavator (C)
0.14
Excavator(A)
0.12
Frequency
0.1
Truck (B)
0.08
0.06
0.04
0.02
0
35 40 45 50 55 60 65 70 75 80
Level, dB
1
Cumulative Distribution
0.8
0.6
0.4
0
45 50 55 60 65 70 75 80
Level, dB
4.7 CONCLUSIONS
This chapter has described the basis of stochastic modelling using
a e Monte Carlo and probability approach to obtain the
distribution of noise levels arising from open site operations. The
results obtained have shown that this method is capable of
predicting the probability distribution of the noise level due to
either individual noise sources or a combination of noise sources
to a similar degree of accuracy to the Monte Carlo method.
REFERENCES
5.1 INTRODUCTION
ECONOMIC ENVIRONMENT
SOCIETY
ECONOMIC ENVIRONMENT
SOCIETY
ENVIRONMENT
SOCIETY
ECONOMIC
9.20% by the year 2020. The total land use of this area is
16,180.00 hectare.
The land use pattern for MPAJ as indicated MPAJ
Structure Plan stated that landscaping of the neighbourhood
will be stressed. It is also suggested that enough buffer
zone will be provided between other facilities in
neighbourhood area.
• Environmental
Urban • Social
Neighbourhood • Economical
Quality of Sustainable
Life Neighbourhood
REFERENCES
6
INTEGRATING ABC INTO PROJECT
OVERHEAD MANAGEMENT
Al-Ojaili Ammar
Aminah Md Yusof
6.1 INTRODUCTION
6.2.1 Cost
As mentioned earlier, cost is a main criterion against which a
project is gauged. Properly investigating cost requires defining it,
establishing its significance, and reviewing its main classes.
91 Issues in Construction Industry
6.2.2 Overhead
The focus of this paper is improving cost management of project
overhead. To establish a proper context for the discussion this
section defines overhead, substantiates its significance, reviews its
main categories, and justifies focusing on project overhead.
6.4. ABC
This paper has explored the issues of cost management, cost,
overhead, and cost accounting. It investigated some of the
101 Issues in Construction Industry
From the above definition, one can observe the main differences
between ABC and TCA. ABC relies on analyzing the activities
needed by a cost object to establish a causal link for assigning
costs to it, particularly overhead charges. TCA, on the other hand,
relies on establishing rates for applying overhead costs using
simplistic allocation bases (Hoshower 1996). Not only such a
difference in philosophy allows ABC to accurately handle
overhead, it gives it great value and potential for all companies,
including construction ones.
Resource Costs
Resource Cost
Drivers
Direct
Assignment
Activity Cost
Drivers
Cost flow, cost pools, and cost drivers are all tools for
predicting cost behavior through a cost model. Hicks (1999)
describes the working of an ABC cost model by stating that it
begins with the volume and mix of products or services an
organization provides; accumulates the cost of activities involved
in furnishing that volume and mix of products or services; and then
converts that cost into a set of rates that can be used to cost
individual processes as well as the products or services. The
volume and mix of products or services is translated into the
volume and mix of measurable activities that are required, which
are then used to generate the cost required for providing the
volume and mix of products or services. Once the total costs are
accumulated, they are first distributed to the activities that made
them necessary. The cost of the various activities are then
converted into rates that can be attributed to the products and
services that were used to drive the cost model in the first place.
layers. They are divided into production and delivery cost layers.
Production cost layers include site-sustaining, process-sustaining,
product-sustaining, batch volume costs, and product volume costs.
Delivery cost layers comprise market segment-sustaining,
customer-sustaining, produce volume-driven, sales order-driven,
and delivery pattern-driven costs (Morrow 1992).
6.5. CONCLUSIONS
Cost is usually one of the most important project considerations.
In construction, cost management is the process used to assist
efficient project execution through controlling all aspects relating
to cost. It applies to all cost types, including overhead. However,
this paper has shown that the methods of cost management are
deficient. It also demonstrated that the use of traditional cost
accounting negatively affects the management of cost and both
general and project overhead. Further, the paper highlighted some
shortfalls in some new cost accounting methodologies. Through
examining literature relating to the above issues and ABC, this
paper established the potential of ABC in rectifying many of the
current cost management problems, particularly those relating to
project overhead. It also examined the basic working of ABC.
Despite such great promise, ABC is rarely applied in construction.
This paper provided some insight into the value and methodology
of ABC. However, deeper investigation of ABC in construction
that is supported with proper data is needed to facilitate its use in
improving the management of cost and project overhead.
Integrating ABC into Project Overhead Management 108
REFERENCES
7
AN OVERVIEW OF CONSTRUCTION
ACCIDENTS IN MALAYSIA
Abdul Rahim Abdul Hamid
Muhd Zaimi Abd Majid
Bachan Singh
7.1 INTRODUCTION
from 10.4 in 1993 to 8.3 in 2004 but the statistic show it has
increased from the year 1995 until 2002. We need to bring down
this rate to remain competitive or be at par with the developed
nations which have low fatality rate such as Sweden (1.2), United
Kingdom (1.3), Netherlands (1.9), Denmark (2.0), Finland (2.0),
Australia(2.0), Japan (2.6) and Singapore (4.9) (Jaafar. 2005).
from 4,207 cases in 1993 to 4,445 cases in 2004. The fatality rate
as shown in Figure 7.2 has increased by 51 per cent from 51 cases
in 1993 to 77 cases in 2004. Meanwhile, the cases for permanent
disablement have increased by 46.1 per cent from 305 cases in
1993 to 566 cases in 2004.
3,000
2,000
1,000
0
2003 2002 2001 2000 1999 1998 1997 1996 1995
YEAR
PERMANENT
CONSTRUCTIONACCIDENT SEVERITY
DISABLEMENT
FATALITY
400
300
200 159 146
104 116
95 88 89 81
100 60
0
2003 2002 2001 2000 1999 1998 1997 1996 1995
YEAR
Year Registered Total Accident Permanent Death Acc Rate per Fatality Rate
Workers Employment Reported Disablement 1,000 per 100,000
3.5
3.3
3.1
3
% F a ta litie s 2.5
2 2 2
1.8
1.5
1 1 1
0.7 0.7 0.7 0.7
0.6 0.6 0.6 0.6
0.5
0
1999 2000 2001 2002 2003
Year
Year/ 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004
Amount
Cases 114,134 107,635 86,589 85,338 95,006 92,074 85,869 84,810 73,858 69,132
Compens 289 316 384 445 497 609 638 722 754 836
ation RM
- Million
Yearly % 9 22 16 12 22 5 13 5 11
change
7.7 SUMMARY
REFERENCES
kempen.html.
European Agency for Safety and Health at Work (EU ASHW)
(2002), Inventory of Socioeconomic Costs of Work
Accidents, Luxembourg, pp5.
European Agency for Safety and Health at Work (EU ASHW)
(2004), European Week for Safety and Health at Work
2004: Why Construction - Financial Costs. available
http://osha.eu.int/ew2004/static/whyconstruction/index_en.
htm
Everett, J.G. and Frank, P.B. 1996. Costs of Accidents and Injuries
to the Construction Industry. Journal of Construction
Engineering and Management, ASCE, Vol 122, No. 2,
Paper No. 10616.
Heinrich, H.W., Petersen, D. and Roos, N. 1980. Industrial
Accident Prevention: A Safety Management Approach,
Fifth Edition, McGraw Hill Book Co: New York.
HSE. Press Release E207:99-25 Oct. 1999 Work Accident and Ill
Health Cost Society Billions – New HSE Report Estimates.
available http://www.hse.gov.uk/press/e99207.htm
HSE. 29 April 2001. Levels and Trends in Workplace Injury:
Reported Injuries and the Labour Force Survey 1997/1998.
available http://www.hse.gov.uk/laborsurvey.
ILO. 22 April 1996. Press Release: ILO Highlights Growing Risks
to Worker Health and Safety. Available
http://www.ilo.org/public/english/bureau/inf/pr/96-13.htm.
International Labour Organization (ILO). 2005. Prevention: A
Global Strategy – Promoting Safety and Health at Work,
The ILO Report for World Day for Safety and Health at
Work Geneva, 2005, pp3.
Levitt, R.E. and Samelson, N.M. 1993. Construction Safety
Management. Second Edition. John Wiley & Sons,
Inc.:USA
123 Issues in Construction Industry
8
THE ROLE OF CONSULTING
ENGINEERS IN PROJECT
DEVELOPMENT
Wan Zulkifli Wan Yusof
Bachan Singh
Abdul Rahim Abdul Hamid
Ngang Shue Ming
8.1 INTRODUCTION
The objectives of this study are : to study the role of the consulting
engineers in the construction project, to study the factors affecting
the success of the management consulting projects, to identify the
client’s level of satisfaction regarding the services rendered by the
consulting engineers and to identify the problems faced by the
consulting engineers in managing the project.
8.3 METHODOLOGY
8.5 RESULTS
In this study, a sample size of forty respondents is identified. There
were thirty-eight out of the forty employees who responded to the
survey indicating the participation rate of 95%.
From Table 8.2 below , it can be seen that the level of cooperation
between contractors and consulting engineer is on the average.
(Average index = 3.36).
Table 8.2: The View of the Contractors on the Level of Cooperation between
the Contractors and Consulting Engineers
1= Totally cooperative 5= Totally uncooperative
Level of cooperation Average
Index
Level of cooperation between contractors and consulting engineers 3.36
Table 8.3: The View of Contractors and Clients on the Level of Satisfaction on
Consulting Engineers’ Services
1= Totally satisfied 5= Totally unsatisfied
Level of satisfaction on consulting engineers’ services Average Index
By Clients 3.20
By Contractors 3.18
8.6 DISCUSSIONS
From Table 7.1, most of the consulting engineers conduct their site
visit weekly or monthly. This complied with the agreement in
BEM Form A (Revised 1/83) : Memorandum of Agreement
Between Client and Consulting Engineer for Professional Services;
Part A. Most of the respondents felt that the frequency of the site
visit conducted by the consulting engineers depends on the types
of project.
from the clients, it was found that the clients were a bit concerned
on the consulting engineers’ site experience. They felt that most of
the consulting engineers could not provide very good design due to
the lack of site experience. (See Table 8.3)
Besides, the results revealed that the second critical problem was
the shortage of manpower. Most of them felt that this problem was
relevant to the first problem (ie. too many projects in hand). Due to
the shortage of manpower, a consulting engineer usually needs to
handle more than two or even three projects at the same time.
131 Issues in Construction Industry
8.7 CONCLUSION
REFERENCES
9
SYSTEMIZATION OF PROJECT
EVALUATION AND MONITORING IN
CONSTRUCTION
M. Mustaffar, Z.A. Memon & M.Z. Abd Majid
9.1 INTRODUCTION
The need has long existed for tools to streamline the job of
systematic evaluation and monitoring for management of
construction activities. Although manual, paper-based information
flow on construction projects still dominates. Nonetheless,
135 Issues in Construction Industry
and analyzing site data. In practice little has been done to address
this problem; most of the research efforts in the field of project
control still focus on the development of cost control models.
9.7. CONCLUSIONS
REFERENCES
Chang, C.-C. and Lim, C.-J. 2001. LIBSVM: a library for support
vector machines. Software available at
http://www.csie. ntu.edu.tw/~cjlin/libsvm.
Cohen, A.M and Hersh, W.R. 2005. A Survey of Current Work in
Biomedical Text Mining. Briefings in Bioinformatics,
6(1): 57-71.
Couto, F.M., Martins, B. and Silva, M.J. 2004. Classifying
Biological Articles using Web Resources. Proceeding of
the 2004 ACM Symposium on Applied Computing, pp.111-
115.
Dollah, R. and Aono, M. 2008. Classifying Biomedical Text
Abstracts using Binary and Multi-class Support Vector
Machine, The 22nd Annual Conference of the Japanese
Society for Artificial Intelligence, Hokkaido.
Ho, C. Y. and Lam, W. 1998. Automatic discovery of document
classification knowledge from text databases. available at
http://citeseer.ist.psu.edu/310941.html.
Leonard, J.E. Colombe, J.B. and Joshua, L.L. 2002. Finding
Relevant References to Genes and Proteins in Medline
using a Bayesian Approach. Bioinformatics, 18(11): 1515-
1522.
151 Issues in Construction Industry
INDEX
modeling, 142
monitoring, 134-138, 140-
144,0146
objectives, 125
Reporting mechanisms
digital, 136, 138, 140, 143-144,
146
Sustainable
construction, 35, 41, 48
development, 35-36, 47, 68-69,
71, 73-74, 76, 79, 85
living, 68-70, 74-78, 83-84
neighbourhood, 68, 71-73, 76,
84
waste, 35, 47
Systemization, 134
Teamwork
cross functional team, 4, 12
characteristic of collaborative
team, 6-7
objectives of team, 5, 7, 11, 13
teamwork in construction, 5
Visualization tools, 29