WIDENING AND METALING OF 65 M ROAD FROM RANIO CHILAS TO NARAN VIA BOTAH VALLEY
BILL NO - 8 : DISMANTELING
ESTIMATED PWD RATE
ITEM NO CODE DESCRIPTION UNIT AMOUNT (RS) Premium QUANTITY (Feet)
Dismanteling stone masonary in lime or cement
morter in foundation,plinth and ground floor 3 123 including stacking salvaged material (serviceable) Cft 209486.14 22.75195 4766218.20709007 45% and disposing surplus stuff as directed within three chains (91.5).
Dismanteling RCC including separating
15 123 reinforcement from concrete in foundation plinth and Cft 2511.82 25.716475 64595.2651009108 45% ground floor including stacking at site and disposing of unserviceable material within three chains (91.5). Dismantelling of C.C work cast in situ in 16 123 foundation ,basement,plinth and ground floor Cft 5651.60 31.32406 177031.199237372 45% including disposing of the material as directed with in 3 chains (91.5 m)
TOTAL OF BILL NO - 8 5,007,844.67
DISMANTELLING OF EXISTING CULVERTS AND RETAINING WALLS RCC WORKS S.No Description Nos Length Width Thickness Quantity 1 Slabs 25 22.967 6.562 0.667 2511.8242 Total (Cft) 2511.82423 PCC 1:3:6 S.No Description Nos Length Width Thickness Quantity 1 Culvert walls 50 22.967 6.562 0.5 3767.7364 Culvert Bed 25 22.967 6.562 0.50 1883.8682 Total (Cft) 5651.60453 STONE MASONARY S.No Description Nos Length Width Thickness Quantity 1 Culvert walls 50 22.967 0.8 6.562 6028.3782 Retaining walls 1 4500 3.44505 13.124 203457.76 Total (Cft) 209486.141