0.009"
f. Crank Shaft end play? (Please mention the value)
a. Check inlet restriction at full load (It should not exceed 30" of water) 10"of water
✔
b. Check air intake piping arrangement, clamps & supports ---Yes/No
c. Exhaust piping diameter 6 "of
water
d. Exhaust pipe length :
Horizontal 1MTR Vertical 1MTR
e. Number of bends in exhaust piping STD
h. Exhaust system adequately supported & free to expand when hot ✔ Yes/ No
I Rain protection (rain cap) provided ✔ Yes I No
j. exhaust piping lagged with suitable high temperature insulation to
prevent heat radiation within genset room Yes/ No ✔
k. Exhaust back pressure (back pressure limits to be got from CAT) _ _15_ _ " of water
I. Room temp. (difference from ambient to DG room not to exceed 5 deg) 34 Degree C
Sign
Gmrrco l@i Alternator Start-up Checklist
Customer Name: PATWARI BAKERS PVT LTD DATE: 19/05/2020
Rating Information
Engine serial number: SKK00129
SKK00129 I Arrangement number: 5655028
5655028
Alternator serial number: K6C002610
K6C002610 I Alternator model: LC6124C
LC6124C
Generator Name Plate Information
Voltage : 415 I Rating (Prime, Continuous, Standby) PRIME
Amperage: 556 jRatin_gkVA : 400
Environment
Ambient temperature: 35 Room temperature: 34
Atmospheric Condition I Salty I Dusty I Wet I Clean I Comments
Alternator gr_easing procedure & grade explained to the Customer: Yes I No YES
Insulation test
MeggerTest 1 MIN reading 10 MIN reading P.I Value= 10 Min I 1 Min * Comments
Main Stator 200 150 50 Should not be
Main Rotor 200 140 60 less than 5M Ohms
Exciter Stator 220 170 50 [ MEGGER with
Exciter Rotor 220 160 60 500VD.C]
**=This value should be greater than '1' for LT M/C 's for HT not less than
1.5. P.I (Polarization Index)-Difference between lmin & 10min readings
Electrical Yes No Comments
Unit properly grounded ✔
Check diodes with Varistor ✔
Alternator alignments Provide Face & run out
SINGLE BEARING ALTERNATOR
readings and crank end play
Tighten all Cable Bolts [At
✔
Alternator and Breaker]
Check Cable flexibility and No Check after tightening of all
✔
stress on Alternator Terminal. cable mounting & gland bolts
Check for shorting I opening of
✔
control cables AVR & EMCP control cables
Check for Space heater ON/OFF
✔
operation
Automatic Voltage Regulator Measure NO- LOAD
✔
operation Excitation voltage
Set Over-current protection and Available m EMCPil + (Std.
check ✔
fitment on & above 725 kva)
Set Over-voltage protection and Available in EMCPII + (Std.
✔
check fitment on & above 725 kva)
Set Reverse-power protection and
✔
Available in EMCPII + (Std.
check fitment on & above 725 kva)
Set Electronic Earth fault relay I ✔
ELR and check
Set Under-voltage protection
✔
and check
1 of2
Set Over speed protection and ✔
Available in all EMCP-II
check &II+
Check for loose wiring and tighten ✔
Check that correct cable size/ lugs Refer sales manual for correct
✔
& glands are used size of cable
Check cable crimping is proper If not correct it before
✔
commissioning the Genset
Installation and Load Information
Neutral grounding system YES UPS 10
Enclosure type STD Size STD
Motor ( Lar2est capacity ) Other loads - %
Total hp 200 Lighting 20
Total SKVA (largest capacity) 380 Computers. 5
Type of Starter DOL / STAR DELTA / VFD Welding 5
Non-Linear 5
Type of operation Solo ✔ Parallel Others 55
Maximum running
load 250 kW
Full Load Data ✔
Note:
1. After meggering do not forget to discharge the coils.
2. If insulation value is less than 5M ohms, dry the alternator with lamp & re-check
3. Alternator alignment procedure and specification please refer manual
4. Tighten all mounting bolts with torque wrench
5. DO-NOT use alternator fan for rotating D.G Set
6. Check Phase sequence.
7. Record Vibration level at DE and NDE side
8. Check and ensure that neutral is grounded properly
9. Check Circuit Breaker ON I OFF operations
10. Check control supply for relays and C.B
11. Check grease at NDE bearing. If alternator is stored I not running for six months
and above, Re-grease bearing. Bearing generated - yes I no
12. Set alarm and trip for winding and Bearing in case ofRTD and BTD.
13. Ensure that Test Certificate and Maintenance Manual is available.
Remarks: DG Set Commissioned as per customer urgency during lockdown period and it was connected to existing AMF panel of 320 KVA DG set.
Also used existing power cables. Suggested customer to complete pending installation work like exhaust cladding, Cable glands
and upgrade AMF panel with recommended rating ACB and power cable size.