Vous êtes sur la page 1sur 3

OBRA : AMPLIACION Y MEJORAMIENTO DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DEL MACRO PROYECTO

: PACHACUTEC DEL DISTRITO DE VENTANILLA - ETAPA 2

CONTRATISTA : CONSORCIO SADE COSAPI


SUPERVISIÓN : CONSORCIO SUPERVISOR PACHACUTEC

RESISTENCIA A LA COMPRESIÓN TESTIGOS CILINDRICOS (ASTM C 39)


f ' c = 280 kg/cm²
UBICACIÓN DE FECHA DISEÑO CARGA PROBETA RESISTENCIA PROMEDIO
Nº SLUMP EDAD
ESTRUCTURAS MOLDEO ROTURA f'c kg/cm2 Kg. Ø Área cm² Kg/cm² Prom.Kg/cm² % %

4.5 " 9/1/2016 9/8/2016 07 280 48700 15.30 183.9 264.9 94.6
4.5 " 9/1/2016 9/8/2016 07 280 53070 15.25 182.7 290.5 273.3 103.8 97.6
Cruce Rio Chillon Prog.5+255-5+262 4.5 " 9/1/2016 9/8/2016 07 280 47990 15.20 181.5 264.5 94.5
4.5 " 9/1/2016 9/29/2016 28 280 64130 15.25 182.65 351.1 125.4
4.5 " 9/1/2016 9/29/2016 28 280 63710 15.10 179.08 355.8 354.6 127.1 126.6
4.5 " 9/1/2016 9/29/2016 28 280 63930 15.10 179.08 357.0 127.5
4.75 " 9/7/2016 9/14/2016 07 280 53560 15.10 179.1 299.1 106.8
4.75 " 9/7/2016 9/14/2016 07 280 53610 15.20 181.5 295.4 299.4 105.5 106.9
Cruce Rio Chillon Prog.5+262--5+277/5+284-5+291 4.75 " 9/7/2016 9/14/2016 07 280 54030 15.05 177.9 303.7 108.5
4.75 " 9/7/2016 10/5/2016 28 280 62360 15.10 179.1 348.2 124.4
4.75 " 9/7/2016 10/5/2016 28 280 63210 15.20 181.5 348.3 350.5 124.4 125.2
4.75 " 9/7/2016 10/5/2016 28 280 63140 15.05 177.9 354.9 126.8
4.5 " 9/7/2016 9/14/2016 07 280 54080 15.20 181.5 298.0 106.4
4.5 " 9/7/2016 9/14/2016 07 280 54110 15.20 181.5 298.2 297.2 106.5 106.2
Cruce Rio Chillon Prog.5+262--5+277/5+284-5+291 4.5 " 9/7/2016 9/14/2016 07 280 53970 15.25 182.7 295.5 105.5
4.5 " 9/7/2016 10/5/2016 28 280 64620 15.00 176.7 365.7 130.6
4.5 " 9/7/2016 10/5/2016 28 280 63720 15.10 179.1 355.8 359.6 127.1 128.4
4.5 " 9/7/2016 10/5/2016 28 280 63570 15.05 177.9 357.3 127.6
5" 9/10/2016 9/17/2016 07 280 52070 15.25 182.7 285.1 101.8
5" 9/10/2016 9/17/2016 07 280 52230 15.30 183.9 284.1 287.1 101.5 102.5
Cruce Rio 5+277-5+284/5+291-5+297/5+304-5+311 5" 9/10/2016 9/17/2016 07 280 51980 15.05 177.9 292.2 104.4
5" 9/10/2016 10/10/2016 30 280 70350 15.10 179.1 392.8 140.3
5" 9/10/2016 10/10/2016 30 280 70840 15.10 179.1 395.6 396.6 141.3 141.6
5" 9/10/2016 10/10/2016 30 280 70910 15.00 176.7 401.3 143.3
5.5 " 9/10/2016 9/17/2016 07 280 49550 15.10 179.1 276.7 98.8
5.5 " 9/10/2016 9/17/2016 07 280 49810 15.05 177.9 280.0 285.0 100.0 101.8
Cruce Rio 5+277-5+284/5+291-5+297/5+304-5+311 5.5 " 9/10/2016 9/17/2016 07 280 54140 15.20 181.5 298.4 106.6
5.5 " 9/10/2016 10/10/2016 30 280 65280 15.10 179.1 364.5 130.2
5.5 " 9/10/2016 10/10/2016 30 280 65390 15.20 181.5 360.4 362.8 128.7 129.6
5.5 " 9/10/2016 10/10/2016 30 280 65970 15.20 181.5 363.6 129.8
4.5 " 9/12/2016 9/19/2016 07 280 53960 14.95 175.5 307.4 109.8
4.5 " 9/12/2016 9/19/2016 07 280 55580 15.25 182.7 304.3 305.4 108.7 109.1
Cruce Rio Chillon Prog.5+297 - 5+304 4.5 " 9/12/2016 9/19/2016 07 280 53110 14.90 174.4 304.6 108.8
4.5 " 9/12/2016 10/10/2016 28 280 59230 15.20 181.5 326.4 116.6
4.5 " 9/12/2016 10/10/2016 28 280 60120 15.10 179.1 335.7 331.0 119.9 118.2
4.5 " 9/12/2016 10/10/2016 28 280 60050 15.20 181.5 330.9 118.2
4.5" 9/16/2016 9/23/2016 07 280 54120 15.35 185.1 292.4 104.4
4.5" 9/16/2016 9/23/2016 07 280 53630 15.30 183.9 291.7 295.0 104.2 105.4
Cruce Rio Chillon Prog.5+311 - 5+318 4.5" 9/16/2016 9/23/2016 07 280 53510 15.05 177.9 300.8 107.4
4.5" 9/16/2016 10/14/2016 28 280 65510 15.20 181.5 361.0 128.9
4.5" 9/16/2016 10/14/2016 28 280 66220 15.15 180.3 367.3 365.0 131.2 130.3
4.5" 9/16/2016 10/14/2016 28 280 66070 15.15 180.3 366.5 130.9
5" 9/20/2016 9/27/2016 07 280 45810 15.25 182.7 250.8 89.6
5" 9/20/2016 9/27/2016 07 280 45040 15.05 177.9 253.2 250.7 90.4 89.5
Cruce Rio Chillon Prog.5+318 - 5+325 5" 9/20/2016 9/27/2016 07 280 44740 15.15 180.3 248.2 88.6
5" 9/20/2016 10/18/2016 28 280 0 2.00 3.14 0.0 0.0
5" 9/20/2016 10/18/2016 28 280 0 14.90 174.37 0.0 0.0 0.0 0.0
5" 9/20/2016 10/18/2016 28 280 0 14.90 174.37 0.0 0.0
5" 9/23/2016 9/30/2016 07 280 44210 15.10 179.1 246.9 88.2
5" 9/23/2016 9/30/2016 07 280 43950 15.10 179.1 245.4 247.1 87.7 88.3
Cruce Rio Chillon Prog.5+325-5+332/5+338.5-5+341 5" 9/23/2016 9/30/2016 07 280 44890 15.15 180.3 249.0 88.9
5" 9/23/2016 10/21/2016 28 280 0 2.00 3.14 0.0 0.0
5" 9/23/2016 10/21/2016 28 280 0 14.90 174.37 0.0 0.0 0.0 0.0
5" 9/23/2016 10/21/2016 28 280 0 14.90 174.37 0.0 0.0
4.5 " 9/28/2016 10/5/2016 07 280 44730 15.10 179.1 249.8 89.2
4.5 " 9/28/2016 10/5/2016 07 280 43870 15.10 179.1 245.0 248.0 87.5 88.6
Cruce Rio Chillon Prog.5+343 - 5+349 4.5 " 9/28/2016 10/5/2016 07 280 45220 15.20 181.5 249.2 89.0
4.5 " 9/28/2016 10/26/2016 28 280 0 2.00 3.14 0.0 0.0
4.5 " 9/28/2016 10/26/2016 28 280 0 14.90 174.37 0.0 0.0 0.0 0.0
4.5 " 9/28/2016 10/26/2016 28 280 0 14.90 174.37 0.0 0.0
4.75" 9/30/2016 10/7/2016 07 280 43680 15.00 176.7 247.2 88.3
4.75" 9/30/2016 10/7/2016 07 280 43920 15.10 179.1 245.3 242.9 87.6 86.8
4.75"
Cruce Rio Chillon Prog.5+332-5+338.5/5+341-5+343/5+349-5+356 9/30/2016 10/7/2016 07 280 42880 15.20 181.5 236.3 84.4
4.75" 9/30/2016 10/28/2016 28 280 0 2.00 3.14 0.0 0.0
4.75" 9/30/2016 10/28/2016 28 280 0 14.90 174.37 0.0 0.0 0.0 0.0
4.75" 9/30/2016 10/28/2016 28 280 0 14.90 174.37 0.0 0.0
OBRA : AMPLIACION Y MEJORAMIENTO DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DEL MACRO
: PROYECTO PACHACUTEC DEL DISTRITO DE VENTANILLA - ETAPA 2

CONTRATISTA : CONSORCIO SADE COSAPI


SUPERVISIÓN : CONSORCIO SUPERVISOR PACHACUTEC

ANALISIS ESTADISTICO DE LOS ENSAYOS DE ROTURA DE CONCRETO


f ' c = 280 kg/cm²
Resistencia PROMEDIO
Nº UBICACIÓN DE ESTRUCTURA RANGO (x - prom Rango) (x - prom) (x - prom) 2
28 dias(kg/cm2) CORRIDO
1 Cruce Rio Chillon Prog.5+255-5+262 354.6 6 125 15678
2 Cruce Rio Chillon Prog.5+262--5+277/5+2 351.6 6.6 122 14940
3 Cruce Rio Chillon Prog.5+262--5+277/5+2 356.6 354 1.5 127 16174
4 Cruce Rio 5+277-5+284/5+291-5+297/5+3 398.4 369 5.7 169 28567
5 Cruce Rio 5+277-5+284/5+291-5+297/5+3 362.0 372 3.2 5 133 17569
6 Cruce Rio Chillon Prog.5+297 - 5+304 333.3 365 4.8 4 104 10799
7 Cruce Rio Chillon Prog.5+311 - 5+318 366.9 354 0.8 3 138 18912
8 Cruce Rio Chillon Prog.5+318 - 5+325 0.0 233 0.0 3 -229 52627
9 Cruce Rio Chillon Prog.5+325-5+332/5+33 0.0 122 0.0 2 -229 52627
10 Cruce Rio Chillon Prog.5+343 - 5+349 0.0 0 0.0 1 -229 52627
11 Cruce Rio Chillon Prog.5+332-5+338.5/5 0.0 0 0.0 0 -229 52627

2523 333148
n………….. 11
Número de Ensayos
S x………… 2523
Sumatoria
S x/n……… 229.4 Promedio, Km/cm²
S (xn-n)²…. 333148
s1²……….. 33315
s1………… 182.52 Desviación
v1………… 79.6 Varianza
Determinación de ocurrencia por debajo del limite inferior
f'cR = f'c + 1.34 s1 524.6 kg/cm2
f'cR = f'c -35 + 2.33 s1 670.3 kg/cm2
Se empleara f'cR = 670.3 kg/cm2
t = (f'cR - f'c)/s1 2.138
f'cR1 = u+t s1 619.7 kg/cm2
f'cR2 = u-t s1 -160.9 kg/cm2
OBRA : AMPLIACION Y MEJORAMIENTO DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DEL MACRO PROYECTO
: PACHACUTEC DEL DISTRITO DE VENTANILLA - ETAPA 2

CONTRATISTA : CONSORCIO SADE COSAPI


SUPERVISIÓN : CONSORCIO SUPERVISOR PACHACUTEC

GRÁFICOS DE RESISTENCIA DE CONCRETO f ' c = 280 Kg/cm²


R E S IS T E N C IA K g /C M ²

580

480

380

280

180
0 1 2 3 4 5 6 7 8 9 10 11 12
Resistencia 28 dias(kg/cm2) f'c = 280 Kg/cm²
N ÚM ER O DE PRUEBA Promedio Kg/cm²
R E S IS T E N C IA K g /C M ²

480.0

380.0

280.0

180.0
0 1 2 3 4 5 6 7 8 9 10 11 12
NÚ M ERO D E PRU EB A

PROMEDIO CORRIDO f'c = 280 Kg/cm² f'c = S x/n - 1.34 s1 f'c = S x/n + 35 - 2,33 s1
P r o m e d io d e R a n g o

20

15

10

0
4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0
NÚM ER O DE PR UEBA
(x - prom Rango) 0,05 f'c 0,10 f'c