1 Factory 1 Damage Panel / KTTD Oct.15, 2018 Oct.12, 2018


QC Room Skratches

2 Factory 1&2 Flashing not proper fix KTTD


Typical Small
Canopy

3 Factory 1&2 Flashing for Door KTTD


Typical Over Head Opening Not yet Install
Dor

4 Link Way Flashing for Link Way KTTD


connection to column

5 Factory 2 Gap between Plastering KTTD


Shower Room wall and EPS Wall Panel

7 Factory 2 Unproper fixing of Panel KTTD


Office Area Flashing

8 Factory 2 Painting of Canopy KTTD


Office Area Support

9 Factory 2 Flashing Not Fix KTTD


Office Area

10 Factory 2 Missing Bottom base KTTD Oct.15, 2018


Office Area flashing

11 Factory 2 Gap of EPS Panel KTTD

12 Factory 2 Gap of EPS Panel KTTD


UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018


12 Factory 2 Gap of EPS Panel KTTD

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks
UP DATE INITIAL PUNCH KTTD
LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

13 Factory 2 Gap between EPS panel KTTD


Office Area and roof purlins

14 Factory 2 EPS panel have Gap KTTD


Office Area from M&E pipe line
need flashing

15 Factory 2 EPS panel need corner KTTD


Office Area need to repair

16 Factory 2 Water Leaking of Roof KTTD


GL. X20 / Y5-Y6 Gutter

17 Factory 1 Welding connection KTTD


Storage Room need to repair

18 Factory 1 EPS panel Corner KTTD


Storage Room flashing Missing

19 Factory 2 Damage the panel need KTTD Oct.15, 2018


to repair

20 Road Typical Crack on road KTTD Oct.15, 2018


surface

21 Road Typical Splattered KTTD Oct.15, 2018


concrete need to
remove

22 Factory 1 Typical: Oct.15, 2018


Ponding Water Make
proper slope of Gutter

23 Factory 1&2 Typical: Oct.15, 2018


Incomplete seam under
Monitor Area

24 Factory 1&2 Typical: Oct.15, 2018


Add screw ridge roll
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

25 FACTORY 2 Cutting the roof sheet Oct.15, 2018


FAÇADE and provide flashing for
wall panel protection

26 MAIN ENTRANCE Typical: Top of Oct.15, 2018


CANOPY Aluminum flashing not
straight need to repair

27 MAIN ENTRANCE Typical: Top of Oct.15, 2018 Oct.12, 2018


CANOPY aluminum composite Complete
for canopy not proper
fixing

28 Typical: Make proper Oct.15, 2018 Oct.12, 2018


good application of Complete
silicon

29 FACTORY 1&2 Typical : Unproper Oct.15, 2018


application of silicon for
ridge roll

30 FACTORY 1 & 2 Typical: Down spout Oct.15, 2018


GL. X10 & X11 support not align

31 FACTORY 1 Typical : Ceiling EPS Oct.15, 2018


QC ROOM panel support removed
the vinyl protection

32 MAIN ENTRANCE Aluminum composite Oct.15, 2018 Oct.12, 2018


CANOPY for canopy not vertical Complete
need to repair

FACTORY 1 : QC ROOM
33 Gap of partition wall KTTD Oct.10, 2018

34 Retouching paint KTTD Oct.10, 2018

35 Provide Door access for KTTD Oct.15, 2018 Oct.12, 2018


electric Maintinace Complete
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

KTTD Oct.15, 2018 Oct.12, 2018


Complete
DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO
ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

FACTORY 1 : TOOL STORAGE & SPARE PARTS


36 Gap between Panel wall KTTD Oct.15, 2018 Oct.12, 2018
and bottom base of Complete
column

37 Reyouching paint KTTD Oct.10, 2018


different color

38 Provide Panel cover for KTTD Oct.15, 2018 Direct Worker


Steel Column and aircon make it due to
pipe line additional
( Additional works ) works
due to additional
airconditioner units

39 Corner flashing not fix KTTD Oct.10, 2018

40 Retouching paint KTTD Oct.10, 2018

41 Retouching paint KTTD Oct.10, 2018

FACTORY 1 ELECTRIC ROOM

42 Retouching Paint at KTTD Oct.10, 2018


entry door

43 Gap of wall panel KTTD Oct.10, 2018

FACTORY WORK SHOP

44 Gap between flashing & KTTD Oct.10, 2018


panel

45 Flashing bended, big KTTD Oct.10, 2018


gap with wall

46 Wall panel was KTTD Oct.10, 2018


damaged
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

47 Flashing bended, big KTTD Oct.10, 2018


gap with wall

48 FACTORY 1 There is a gap between


QC Room wall panels

49 FACTORY 1 Need silicon for bottom


QC Room panel

50 Conner flashing not


length enough
QC room

51 Remove wooden

GL X10 factory 1

52 Clean alumium frame


additon silicon at
conner flashing
Spare room

53 Clean paint in alumium


falshing for windown
Roof monitor
factory 1&2

54 Additon screw every


0.5m
Gutter factory 1&2

55 Additon and repair


screw for gutter cover
Roof monitor every 0.5m
factory 1&2

56 addition screw every 2


rib
Roof monitor
factory 1&2

57 Addition screw for roof


of monitor every 2 rib
Roof monitor
factory 1&2

58 Addition screw for wall


of monitor every 2 rib
Roof monitor
factory 1&2
INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: September 25, 2018

DEFECT PHOTOS DEFECT PHOTOS


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY Notes Remarks

24 Factory 1 Welding connection not FUJI Co.Ltd.


GL. X11 / Y1-Y5 proper

25 Factory 2 Welding connection not FUJI Co.Ltd.


GL. Y6 / X11 proper

26 Factory 2 Rectification paint for FUJI Co.Ltd.


GL. X11 / Y6-Y7 beam

27 Factory 2 Cross bracing bolts need FUJI Co.Ltd.


GL. X11 / Y6-Y7 to paint

28 Factory 2 Tightining for Cross FUJI Co.Ltd.


GL. X11 / Y6-Y7 bracing

29 Factory 2 Cover palstiv make good FUJI Co.Ltd.


GL. X11 / Y6-Y7 surafce

30 Factory 2 Welding conection not FUJI Co.Ltd.


GL.. Y9 / X11 enough

31 Factory 2 Rectification paint for FUJI Co.Ltd.


GL. Y11 / X13-X14 beam

32 Factory 2 Rectification paint for FUJI Co.Ltd.


GL. Y11 / X13-X14 beam

33 Factory 2 Rectification paint for FUJI Co.Ltd.


GL. Y11 / X5 sika grouting surface

34 Factory 2 Bottom base of sub FUJI Co.Ltd.


GL. Y11 / X5-X6 frame need to paint
INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: September 25, 2018

DEFECT PHOTOS DEFECT PHOTOS


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY Notes Remarks

35 Factory 2 Rectification paint for FUJI Co.Ltd.


GL. Y11 / X6 Column

36 Factory 2 Rectification paint for FUJI Co.Ltd.


GL. Y11 / X16-X17 Sub Frame

37 Factory 2 Rectification paint for FUJI Co.Ltd.


GL. Y20 / X8 Column

38 Factory 2 Clean up of panel / Stain FUJI Co.Ltd.


GL. Y20 / X7-X8

39 Factory 2 Rectification paint for FUJI Co.Ltd.


Column

40 Factory 2 Rectification paint for FUJI Co.Ltd.


under steel deck

41 Factory 2 Rectification paint for FUJI Co.Ltd.


Column

42 Factory 2 Welding conection not FUJI Co.Ltd.


Stair No.02 proper at land floor in
Stair 2
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 24, 2018

ITEM NO. LOCATION


DEFECT PHOTOS DEFECT PHOTOS
DESCRIPTION ACTION BY
SCHEDULE TO Notes
( BEFORE ) (AFTER ) COMPLETE Remarks

1 Factory 2 Cut the exposed rebars Kien Nam Oct.15, 2018


GL. X16 / Y1

2 Factory 2 Repair bottom of Wall Kien Nam Oct.15, 2018


Shower Room by plastering

3 Factory 2 Removed the hard Kien Nam Oct.15, 2018


Toilets No. 05 concrete on floor

4 Factory 1&2 Gap between sub frame Kien Nam Oct.15, 2018 Pending slow
Boundary Wall and plastering action Factory
need to repair 2 not
complete

5 Factory 2 Fill mortar the hole and Kien Nam Oct.15, 2018 No Action
GL. Y11 / X15-X16 make good suface

6 Factory 2 Repair edge corner of Kien Nam Oct.15, 2018 No Action


GL. Y20 / Y9-Y10 wall

7 Factory 2 Removed the hard Kien Nam Oct.15, 2018


Toilet 5 mortar palster on top

8 Factory 2 Repair entry door Kien Nam Oct.15, 2018


GL. X17 / Y1 plaster wall
DONE

10 Factory 2 Palstering work Kien Nam Oct.15, 2018


GL. X11 / Y1-Y2 between curtainwall
frame and brick wall

11 TOILET 3 Plastering bottom wall Kien Nam Oct.15, 2018


need to repair

12 Factory 2 Clean up & Make Good Kien Nam Oct.15, 2018 No Action
Near at Toilet 3 surface of Corner Wall

13 Factory 1 Clean up & Make Good Kien Nam Oct.15, 2018 No Action
Near at Toilet 2 surface of Corner Wall
14 There is a gap between
aluminum frame and
wall

15 Retouching Paint for Kien Nam Oct.20 2018


wall

GUARD HOUSE
16 Silicon missing line Kien Nam Oct.20 2018

17 Fill the gap by silicon Kien Nam Oct.20 2018

18 Fill the gap by silicon Kien Nam Oct.20 2018

19 Fill the gap by silicon Kien Nam Oct.20 2018

20 Fill the gap by silicon Kien Nam Oct.20 2018

21 Repair silicon around Kien Nam Oct.20 2018


the window make make
surface

22 Repair silicon good Kien Nam Oct.20 2018


surface

23 Repair silicon good Kien Nam Oct.20 2018


surface

24 Repair silicon good Kien Nam Oct.20 2018


surface

25 Repair silicon good Kien Nam Oct.20 2018


surface
DONE

26 Repair silicon good Kien Nam Oct.20 2018


surface
MOTOR BIKE
27 Clean Up of Roof Purlins

28 Repair the Crack

29 Ponding Water

30 Make Straightness of
bounday slab

GARBAGE HOUSE
31 Bad surface of
Clean Up before floor finish affect
Painting bottom wall to liquid hardener
bad surface of Floor
finish

32 Bad surface of
Clean Up before floor finish affect
Painting bottom wall to liquid hardener
bad surface of Floor
finish

33

Need plastering
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 24, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY
COMPLETE Notes Remarks

1 Factory 1&2 Typical Gap between HDOOR Oct.15, 2018


frame of Hanging door

2 Factory 1&2 Typical Retouching HDOOR Oct.15, 2018


paint the welding mark

3 Factory 1&2 Treshold of Steel door HDOOR Oct.15, 2018 On going


not complite and need
to repair

4 Factory 2 Gap bet. Door frame HDOOR Oct.15, 2018


and sub frame

5 Factory 2 Retouching Paint of HDOOR Oct.15, 2018


Door frame

6 Factory 2 Gap bet. Mortar plaster HDOOR Oct.15, 2018


and door frame

7 Factory 2 Bottom stoper defect HDOOR Oct.15, 2018 80%


COMPLETE

8 Factory 2 Hanging Door Roller HDOOR Oct.15, 2018 DONE


have rusty

9 Factory 2 Clean Up of Treshod of HDOOR Oct.15, 2018 On going


Steel door

10 Factory 1 Window Glass Missing HDOOR Oct.10, 2018

11 Storage Room / DONE Gap of Aluminum HDOOR Oct.15, 2018


QC Room Factory window frame
1&2

12 Storage Room / DONE Typical Gap of HDOOR Oct.15, 2018


QC Room Factory Aluminum window
1&2 frame
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 24, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY
COMPLETE Notes Remarks

FACTORY 1 : QC ROOM
13 Screen net and window HDOOR Oct.15, 2018
handle are missing

14 Panel Door touching to HDOOR Oct.15, 2018


floor Tiles

15 Typical Fill the Gap of HDOOR Oct.15, 2018


Fixed Door

FACTORY 1 : TOOL STORAGE & SPARE PARTS


16 Window screen and Hdoor Oct.15, 2018
window handle not yet
installation

17 Window gasket are not Hdoor Oct.15, 2018


proper installation

FACTORY 1 : TOILET 1
18 Window glass not Hdoor Oct.10, 2018
installed

FACTORY 1 TOILET 2

19 Window glass missing Hdoor Oct.10, 2018

FACTORY 1 ELECTRIC ROOM

20 Door Handle make good HDOOR Oct.15, 2018


surface of silicon
Entry door from factory

21 Door Frame have big HDOOR Oct.15, 2018


gap need to repair
Entry Door from
Compressor room

22 Fill the gap of window HDOOR Oct.15, 2018


frame

23 Window handle & HDOOR Oct.15, 2018 On Going


Screen net not yet
installed
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 24, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY
COMPLETE Notes Remarks

24 Fill the gap of window HDOOR Oct.15, 2018


frame

25 Damage of Steel Door HDOOR Oct.15, 2018

26 TOILET 1,2,3&5 DONE TYPICAL PROVIDE DOOR HDOOR Oct.15, 2018


STOPER FOR ABS DOOR

27 Stair 1 Exposed the steel HDOOR Oct.27, 2018


Office area bracket for cutain wall

28 Factory 2 Treshold for Steel Door HDOOR Oct.27, 2018 On Going


GL. Y11 / X18 Not yet Install Installed
October 31,
2018

CANTEEN
29 Glass Door not install Oct.27, 2018

Canteen

30 Alumium Door not HD Oct.27, 2018


install
Canteen

31 Typical Fill the Gap Hdoor Oct.27, 2018 Done


outside face of window
frame
Canteen

32 Provide cover end of Oct.27, 2018 Done


flushing of Glass Door
Canteen

33 Silicon not yet complete Hdoor Oct.27, 2018 On Going


at edge of window
frame
Canteen

34 Gap between wall and Hdoor Oct.27, 2018 Done


SUS Frame
Canteen

35 Gap between Ceiling Hdoor Oct.27, 2018 Done


and SUS Frame
Canteen
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 24, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY
COMPLETE Notes Remarks

36 Gap of Door frame Hdoor Oct.27, 2018 Done

Canteen

37 Done

Aluminum frame of
Factory 2 window is dented

38 Window joints do not Done


work
Factory 2

39 Window joints do not Done


work
Factory 1

40 The gap between wall On Going


and aluminum frame
need being reprocessed
Canteen

41 Lighting for barracade


not yet installation
Barracade

41 Removed Plastic and


make good surface of
FACTORY 2 steel door
X20 / Y4 Silicon not complete

41 Gap of Door frame


notproper fill of silicon
Inside Compressor
Room & Electric
Room

41 Gap of Door frame


notproper fill of silicon
Electric Room

41 Gap of Aluminum frame


need silicon
Toilet 3 Done

41 Steel door perimeter


door frame need silicon
FACTORY 2
Done
X20 / Y8

41 Typical Exposed Screw


at Curtain wall frame
OFFICE CURTAIN
WALL
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 24, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY
COMPLETE Notes Remarks

41 Typical Expoesed steel


bracket at Curtain Wall
OFFICE CURTAIN
WALL

41 Archtive of abs door


have gap must be one
cut
Toilet 5

41 Silicon not proper


application
Toilet 5

41 Hanging Door panel


have need to rectify
Hanging Door at
link way
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

1 FACTORY 1&2 Typical Nhat Thanh Oct.27, 2018 On Going


( 4 Location ) Retouching Paint of sub Phat
frame for steel ladder

2 CANTEEN SUS trench not Nhat Thanh Oct.27, 2018 On Going


complete Phat

3 Garbage House Steel Ladder not yet Nhat Thanh Oct.27, 2018
install Phat

4 Main Gate DONE Sub Gate not yet paint Nhat Thanh Oct.27, 2018
Phat

5 Sub Gate in Motor Sub Gate at Motor Bike Nhat Thanh Oct.27, 2018
Bike not yet install Phat

6 FENCE Typical Oct.15, 2018 On Going


Retouching Paint of
Steel Fence

7 FENCE Typical Oct.30, 2018 On Going


Retouching Paint of
Steel Fence

8 Typical Oct.30, 2018 On Going


Retouching Paint of
Steel Fence

9 Align the entire fence Oct.30, 2018 On Going


line

10

`
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

DEFECT PHOTOS DEFECT PHOTOS


ITEM NO. LOCATION ( BEFORE ) (AFTER ) DESCRIPTION ACTION BY Notes Remarks

1 Factory 1 Clean Up of stain paint Thanh Quan


( Toilet 2 ) from Cable ladder cover Phat

2 Factory 2 Clean Up of stain paint Thanh Quan


( Toilet 3 ) from Cable ladder cover Phat

3 Pump Room Painting of Down Spout


same color of wall

4 GARBAGE HOUSE Incomplete painting Thanh quan


outside Wall phat

5 Incomplete painting Thanh quan


outside Wall phat

6 GARBAGE HOUSE Incomplete painting Thanh quan


outside Wall phat

7 FACTORY 1&2 Typical Bottom of wall Thanh quan


outside face noy phat
complete

8 FACTORY 1&2 The bottom line of wall


hasn't been painted

9 FACTORY 1&2 The bottom line of wall


has not been painted

10 CANTEEN The bottom line of wall


has not been painted
11 Garbage House Painting of base of steel
column
Up Date INITIAL PUNCH LIST

PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

FACTORY 1 : QC ROOM
1 Clean up of Floor Tiles NHAT ANH TUAN Oct.15, 2018
and make good surface
more apply white
cement

2 Clean up of Floor Tiles NHAT ANH TUAN Oct.15, 2018


and make good surface
more apply white
cement

3 Make good surface of NHAT ANH TUAN Oct.15, 2018


application of white
cement

FACTORY 1 : TOOL STORAGE & SPARE PARTS


4 Ceiling board missing NHAT ANH TUAN Oct.15, 2018

5 Ceiling board missing NHAT ANH TUAN Oct.15, 2018

6 Gap of Ceiling Frame to NHAT ANH TUAN Oct.15, 2018


ceiling board / Unlevel

FACTORY 1 : TOILET 1

7 Silicon around the NHAT ANH TUAN Oct.15, 2018


lavabo

8 Silicon around the NHAT ANH TUAN Oct.15, 2018


lavabo

9 Door Stoper not NHAT ANH TUAN Oct.10, 2018


installed

10 Ceramic tile need to NHAT ANH TUAN Oct.15, 2018


change make good
surface

11

12 DONE OTHERS: NHAT ANH TUAN Oct.15, 2018


Clean up
Rectification of White
Cement
Up Date INITIAL PUNCH LIST

PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 26, 2018

NHAT ANH TUAN Oct.15, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

FACTORY 1 TOILET 2
13 Door stopper not yet NHAT ANH TUAN Oct.15, 2018
installed

14 Floor tiles damage / NHAT ANH TUAN Oct.15, 2018


Replace

15 Wall Tile have damage / NHAT ANH TUAN Oct.15, 2018


Replace

16 Floor tiles damage / NHAT ANH TUAN Oct.15, 2018


Replace

17 Typical Gap of Wall tile NHAT ANH TUAN Oct.15, 2018


to window frame

18 OTHERS: NHAT ANH TUAN Oct.15, 2018


Clean up
Rectification of White
Cement

FACTORY 2 TOILET 3
19 Plastering bottom wall NHAT ANH TUAN Oct.15, 2018
need to reapir

20 Silicon for joint Nhat Quan Phat Oct.15, 2018


connection

21 Ceramic cutting hole NHAT ANH TUAN Oct.30, 2018


need to repair

22 Ceramic cutting hole NHAT ANH TUAN Oct.30, 2018


need to repair

23 Typical Gap of Wall tile NHAT ANH TUAN Oct.30, 2018


to window frame

24 Typical Silicon not NHAT ANH TUAN Oct.30, 2018


proper need to repair
Up Date INITIAL PUNCH LIST

PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

25 Typical Silicon not NHAT ANH TUAN Oct.30, 2018


proper need to repair
Up Date INITIAL PUNCH LIST

PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

CANTEEN
26 White Ciment not NHAT ANH TUAN Oct.27, 2018
good typical wall and
floor
Canteen

27 Gap celling NHAT ANH TUAN Oct.27, 2018

Canteen

28 Make black color of NHAT ANH TUAN Oct.27, 2018


edge of stone
Canteen

29 Fill the gap between pvc NHAT ANH TUAN Oct.27, 2018
and floor tiles
Canteen

30 Ceramic Tiles Need to NHAT ANH TUAN Oct.27, 2018


repair
Canteen

31 Skirting Make Good NHAT ANH TUAN Oct.27, 2018


Surface
Canteen

32 White cement not finish NHAT ANH TUAN Oct.27, 2018

Canteen

33 Make Black color of NHAT ANH TUAN Oct.27, 2018


edge of granite stone
Canteen

34 White cement not finish NHAT ANH TUAN Oct.27, 2018

Canteen

35 NHAT ANH TUAN Oct.27, 2018


The wall need being
Canteen replastered and
repainted

SIGNAGE / FLAG POLE / SUB GATE


36 SIGNAGE Joint connection make NHAT ANH TUAN Oct.27, 2018
good surface

37 SIGNAGE Edge of granite stone NHAT ANH TUAN Oct.27, 2018


make good surface

38 SIGNAGE Granite Stone different NHAT ANH TUAN Oct.27, 2018


color
On Going

39 Ramp Granite stone have gap NHAT ANH TUAN Oct.27, 2018
Up Date INITIAL PUNCH LIST

PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY
COMPLETE Notes Remarks

40 Flag pole Granite stone for NHAT ANH TUAN Oct.27, 2018 On Going
pedestal not finish
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 30, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

1 Factory 2 More polishing works Dai Vu Oct.15, 2018 Done


Along boundary
wall

2 All Steel door Entry Door Not polish Oct.15, 2018 Done

Dai Vu
3 Along Y14 Factory Removed the concrete Dai Vu Oct.15, 2018 Done
2 stain in column

4 Office Area Removed the Stain Dai Vu Oct.15, 2018 Done


Factory 2 concrete for under deck
plate

5 Removed the Stain Dai Vu Oct.15, 2018 Done


concrete for under deck
plate

6 Factory 2 Make Good Surface Dai Vu Oct.15, 2018 Done

7 Factory 1&2 Corner not sanding Dai Vu Oct.15, 2018 Done

8 Factory 1&2 Make Good Surface at Dai Vu Oct.15, 2018 Done


column corner

9 Near boundary Rough surface near Dai Vu Oct.15, 2018 Done


wall boundary wall

10 Under steel door Dusty and rough surface Dai Vu Oct.15, 2018 Done
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 30, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

11 Near boundary Incorrect fixing hole on Dai Vu Oct.15, 2018 Done


wall slab

12 Liquid hardenner Dai Vu Oct.15, 2018 Did not touch


WS 1 the other area
2 differ colour in one of cold joint
area

13 Around column Dai Vu Oct.15, 2018 Done


pad
Not yet done

14 Around steel door Dusty and rough surface Dai Vu Oct.15, 2018 Done

15 Near boundary Rough surface Dai Vu Oct.15, 2018 Done


wall

16 FACTORY 1 Rough surface & dusty Dai Vu Oct.15, 2018 Done


Near boundary
wall

17 FACTORY 1 Not yet done Dai Vu Oct.15, 2018 Done


Conner of wall,
column pad & slab

18 FACTORY 1 Not yet done Dai Vu Oct.15, 2018 Done


Conner of wall,
column pad & slab

19 FACTORY 1 Not yet done Dai Vu Oct.15, 2018 Done


Conner of wall,
column pad & slab

20 FACTORY 1 Not yet done Dai Vu Oct.15, 2018 Done


Conner of wall &
slab

21 FACTORY 1 Not yet done Dai Vu Oct.15, 2018 Done


Conner of wall &
slab
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 30, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

22 FACTORY 1 Under Remove rebar & chip Dai Vu Oct.15, 2018 Done
hanging door then finish
frame

23 FACTORY 1 Rough surface Dai Vu Oct.15, 2018 Done


Under hanging
door frame

24 FACTORY 1 Not yet done Dai Vu Oct.15, 2018 Done


Around column
pad

25 FACTORY 1 Not yet done Dai Vu Oct.15, 2018 Done


Around column
pad

26 FACTORY 1 Dai Vu Oct.15, 2018 Done


Around column
pad

27 FACTORY 1 Clean & grind again Dai Vu Oct.15, 2018 Done


Around column
pad

28 FACTORY 1 Make Good surface of Dai Vu Oct.15, 2018


Floor Slab connection joint

29 FACTORY 1 Make Good surface of Dai Vu Oct.15, 2018


Floor Slab connection joint
Cold Joint already
repair but client did
not satify due see
the line of different
color
30 GARBAGE HOUSE Unproper sanding of Dai Vu Oct.15, 2018 Could not
floor slab repair due to
bad surface of
concrete floor
slab by KIEN
Nam
31 GARBAGE HOUSE Unproper sanding of Dai Vu Oct.15, 2018
floor slab

32 GARBAGE HOUSE Unproper sanding of Dai Vu Oct.15, 2018


floor slab
Could not
repair due to
bad surface of
concrete floor
slab by KIEN
Nam
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 30, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

33 GARBAGE HOUSE Unproper sanding of Dai Vu Oct.15, 2018


floor slab

34 GARBAGE HOUSE Unproper sanding of Dai Vu Oct.15, 2018


floor slab

35 ELECTRIC ROOM & Not enough application Oct.25, 2018 Done


PUMP ROOM of Hardener and
polishing

36 ELECTRIC ROOM & Not enough application Oct.25, 2018 Done


PUMP ROOM of Hardener and
polishing

37 ELECTRIC ROOM & Not enough application Oct.25, 2018 Done


PUMP ROOM of Hardener and
polishing

38 Factory 1&2 Foot Marking on floor Could not


slab repair due to
more damage
of floor slab
surface

39 Factory 1&2 Joint filler have damage Oct.25, 2018 Done


TYPICAL need repair

40 Factory 2 / Y1 / Putty already but not Oct.25, 2018 Done


X14-X15 polish and hardener

41 Factory 2 Putty already but not Oct.25, 2018 Done


X14 / Y4-Y5 polish and hardener

42 Factory 2 Putty already but not Oct.25, 2018 Done


X16-X20 /Y3-Y5 polish and hardener

43 Factory 1&2 Trowel Machine Oct.25, 2018 Not Avaiable


Marking on floor slab to repair
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 30, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

44 Rebar of slab is emerged Oct.30, 2018 Done

45 Oct.30, 2018 Done

Need to be repainted

46 Floor near column is Oct.30, 2018 Done


dirty

47 Oct.30, 2018 Did not touch Refer to comments


the other area at Item 29
The joint between two of cold joint
pieces of concrete is
imcompatible
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 30, 2018

ITEM NO. LOCATION


DEFECT PHOTOS DEFECT PHOTOS
DESCRIPTION ACTION BY
SCHEDULE TO Notes
( BEFORE ) (AFTER ) COMPLETE Remarks

1 Factory 1 along Fill the hole of electric 226 Co.Ltd Oct.15, 2018
GL. X1 Outlet

2 Factory 1&2 rear Cut the Exposed Tie Rod 226 Co.Ltd Oct.15, 2018
side elevation and make good fill to
avoid water leak

3 Factory 1&2 Signage not fix and 226 Co.Ltd Oct.15, 2018
typical make good alignment of
pipe

4 Factory 1&2 Retouching Paint 226 Co.Ltd Oct.15, 2018


typical

5 Factory 1&2 Retouching Paint 226 Co.Ltd Oct.15, 2018


typical

6 Factory 1&2 Done Fill the hole of electric 226 Co.Ltd Oct.15, 2018
typical outlet

7 QC ROOM Done Exposed Pipe on Inside 226 Co.Ltd Oct.15, 2018


panel wall ned to repair

8 QC ROOM Done Exposed Pipe on Inside 226 Co.Ltd Oct.15, 2018


panel wall ned to repair

9 Factory 2 Fire Alarm moved up to 226 Co.Ltd Oct.15, 2018


Office area 5mm

10 GARBAGE HOUSE DONE Exposed Electric Pipe 226 Co.Ltd Oct.15, 2018
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 30, 2018

Oct.15, 2018

ITEM NO. LOCATION


DEFECT PHOTOS DEFECT PHOTOS
DESCRIPTION ACTION BY
SCHEDULE TO Notes
( BEFORE ) (AFTER ) COMPLETE Remarks

FACTORY 1 : TOOL STORAGE & SPARE PARTS


11 Electric PVC pipe not 226 Electric Oct.10, 2018
Proper installation Loss
Connection

12 Electric Outlet line and 226 Electric Oct.10, 2018


plate are missing

13 Electric Outlet line and


plate are missing

FACTORY 1 : TOILET 1
14 Make proper materials 226 Oct.10, 2018
for cover the future
electric outlet

FACTORY 1 : TOILET 2
15 Make proper materials 226 Oct.10, 2018
for cover the future
electric outlet

16 Fil the Gap of Electric 226 Oct.10, 2018


Outlet

FACTORY 1 : TOILET 3
17 Electric Outlet missing 226 Oct.10, 2018

ELECTRIC PANEL
18 Provide Marking level Oct.27, 2018 DONE

19 Not Enough Cover Oct.27, 2018 DONE


UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 30, 2018

ITEM NO. LOCATION


DEFECT PHOTOS DEFECT PHOTOS
DESCRIPTION ACTION BY
SCHEDULE TO Notes
( BEFORE ) (AFTER ) COMPLETE Remarks

20 Insert Fire stop Oct.27, 2018 DONE

21 Factory 2 Electric cable ladder is Oct.30, 2018 No Action


not straight

22 Factory 2 Cable line is not straight Oct.30, 2018 No Action

23 Factory 1 Electric cable ladder and Oct.30, 2018 No Action


pvc pipe are curved

24 Factory 1 Oct.30, 2018 No Action

Cable ladder is not


straight
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 09, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

1 Pump room Water leak BG Oct.25, 2018

2 Pump room Filling opening BG Oct.25, 2018

3 Pump room Cleaning welding point BG Oct.25, 2018


SUS pipe

4 Pump room Cleaning welding point BG Oct.25, 2018


SUS pipe

5 Toilet - Fac 2 Install mirror BG Oct.25, 2018

6 Toilet- Fac 2 Silicon around Lavatory BG Oct.25, 2018

7 Toilet- Fac 2 adjust Urinal BG Oct.25, 2018

8 Toilet- Fac 2 Water leak BG Oct.25, 2018

9 Canteen Install drain pipe for sus BG Oct.25, 2018


sink

10 Factory 2 Addition support for BG Oct.25, 2018


water supply pipe

11 External Addition support for BG Oct.25, 2018


trunking
12 External Addition support for BG Oct.25, 2018
trunking and cutting
foam

13 External Addition support for BG Oct.25, 2018


trunking and cutting
foam

14 External Install garden faucet BG Oct.25, 2018

15 External Install garden faucet BG Oct.25, 2018

16 External Filling opening BG Oct.25, 2018

17 External Chain for maintenance BG Oct.25, 2018


pump lost? Painting
support

18 External Extension trunking and BG Oct.25, 2018


fill up foam

19 External Extension trunking and BG Oct.25, 2018


fill up foam

20 Factory 2 Air compressor pipe is Oct.30, 2018


curved

21 Factory 2 Pvc pipe is curved Oct.30, 2018

22 Factory 2 Cleaning up panels Oct.30, 2018

23 Factory 1 Air compressor pipes Oct.30, 2018


are curved

Toilet 5 Women Damage of Mirror at


Toilet 5
UP DATE INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: OCTOBER 26, 2018

DEFECT PHOTOS DEFECT PHOTOS SCHEDULE TO


ITEM NO. LOCATION
( BEFORE ) (AFTER )
DESCRIPTION ACTION BY Notes Remarks
COMPLETE

1 Pump room Cover opening for HKN Oct.25, 2018 Oct.25, 2018
suction pipe.

2 Pump room Cover panel foot HKN Oct.25, 2018 Oct.25, 2018

3 Moto bike park Painting of colume KHN Oct.25, 2018 Oct.24, 2019
same color.

4 Factory Painting of colume HKN Oct.25, 2018 Oct.24, 2019


same color.

5 External Painting of Bulong HKN Oct.25, 2018 Oct.24, 2019

6 Cover opening for drain HKN Oct.25, 2018 Oct.25, 2018


pipe

7 Guard House Oct.30, 2018

Retouching Paint for


wall

8 Guard House Oct.30, 2018


Fill the hole and make
proper installation of
wiring
INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

ITEM NO. LOCATION


DEFECT PHOTOS DEFECT PHOTOS
DESCRIPTION ACTION BY
SCHEDULE TO Notes
( BEFORE ) (AFTER ) COMPLETE Remarks

1 Typical Mahole Trash Screen and clean THANH TRI Oct.15, 2018
up of Manhole

2 Typical Road Curb Typical Grinding works THANH TRI Oct.15, 2018 On Going
for concrete curb

3 Typical Mahole Move up the Manhole THANH TRI Oct.15, 2018


cover to make same
level of top of curb

4 Typical Mahole Clean Up and Make THANH TRI Oct.15, 2018 On Going
same level of cover

5 Typical Mahole Clean Up THANH TRI Oct.15, 2018

6 Typical Mahole Trash Screen and clean THANH TRI Oct.15, 2018 On Going
up of Manhole
Make good surface of
slope

7 Typical Mahole Trash Screen and clean THANH TRI Oct.15, 2018 On Going
up of Manhole
Make good surface of
slope

8 Typical Mahole Clean Up and Make THANH TRI Oct.15, 2018


same level of cover

9 Pump Pit Cover of Pump Pit THANH TRI Oct.15, 2018


Missing

10 Typical Mahole Trash Screen and clean THANH TRI Oct.15, 2018 On Going
up of Manhole
Make good surface of
slope

11 Pump Pit PVC Pipe not connect to THANH TRI Oct.15, 2018
Pump Pit
INITIAL PUNCH LIST
PROJECT: CTR VINA Project, Tam Ky, Quang Nam

Date: October 26, 2018

ITEM NO. LOCATION


DEFECT PHOTOS DEFECT PHOTOS
DESCRIPTION ACTION BY
SCHEDULE TO Notes
( BEFORE ) (AFTER ) COMPLETE Remarks

12 THANH TRI Oct.30, 2018

Concrete curb is broken


and damaged

13 The cover is THANH TRI Oct.30, 2018


imcompatible

14 THANH TRI Oct.30, 2018

The manhole need to be


plastered

15 The manhole is broken THANH TRI Oct.30, 2018


and damaged

16 THANH TRI Oct.30, 2018

Soil and stone fill the


manhole