Académique Documents
Professionnel Documents
Culture Documents
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) 20.04.2010 Slide 2 / 17
Pigments Business
Supply chain cost likely to Increasingly inflexible Production constraints Customer demanding more
increase supply responsiveness
Total supply chain cost Increasing number of Excess capacities are Customers reduce own
currently at about 5% of materials sourced globally reduced to minimise fix stocks, asking for more
sales with long lead-times cost base just-in-time deliveries
Cash focus in whole value Working capital priorities Additional demand or Customers placing orders
chain leading to smaller are driving raw material order changes cannot be on short-notice
order sizes, which stocks down absorbed as easily as in
increases transaction Reduced competition the past
costs
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) 20.04.2010 Slide 4 / 17
Improvement areas to achieve objectives
1 2
Demand planning Demand and inventory management
Improve S&OP
processes
3
Improve quality of planning Ensure that all relevant data for
Data quality
parameters in master data planning are available
4
Performance management Introduce Define clear
Train people
and capability building KPI reporting accountabilities
Source: CIP Planning Booster
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.)
Our effort to improve accuracy as the basis of
our Make-to-Forecast did not pay-back
Forecast Accuracy 2008 Despite substantial investment in process and
technology improvements we struggled to
100
maintain forecast accuracy above 60%
90
80
Percentage Accuracy
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 6 / 17
Completing the puzzle towards efficiency
1 2
Demand planning Demand and inventory management
3
Improve quality of planning Ensure that all relevant data for
Data quality
parameters in master data planning are available
4
Performance management Introduce Define clear
Train people
and capability building KPI reporting accountabilities
Source: CIP Planning Booster
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.)
From Push to Pull: Our Four Step Approach
1.
1. Use
Use the
the demand
demand forecast
forecast in
in the
the 2.
2. Decouple
Decouple production
production decisions
decisions
S&OP
S&OP toto ‘condition’
‘condition’ the
the supply
supply chain
chain from
from the
the forecast
forecast and
and MRP
MRP runs
runs
Plant
3.
3. Apply
Apply demand-pull
demand-pull planning
planning 4.
4. Operationalize
Operationalize these
these practices
practices into
into
techniques
techniques to
to replenish
replenish inventory
inventory our
our core
core processes
processes and
and SAP
SAP system
system
where
where possible
possible
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 8 / 17
1. Use the demand forecast in the S&OP to
‘condition’ the supply chain
“Supply Chain Conditioning”
Planning and Control Framework The Sales and Operations Planning
process sets the overall demand
Global
Demand Supply Monthly
C
o
n
g
itd
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 9 / 17
2. Decouple production from forecast and MRP
synchronizing the supply chain with actual demand
Triggered in line with Replenished from
consumption of the controlled primary global stocking
inventory held in the Primary point in line with actual
Distribution center consumption
Demand amplification throughout the supply chain is eliminated as the actual customer
demand is communicated using demand pull replenishment techniques
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 10 / 17
3. Apply demand-pull planning techniques to
replenish inventory where possible
Make To Order was used when the
customer lead time allowed
Volume-Variability Analysis
8.0
When supply from stock is required,
7.0 Annual Campaign planning techniques were identified
Normalised standard deviation
Planning
6.0
based on the volume and statistical
5.0 variability of each product
4.0
RoP
Demand Pull
3.0 Techniques Inventory levels were set as a function
2.0 of demand, lead time and required
Kanban
1.0 Rate Based customer service levels
0.0
0 500 1,000 1,500
Average demand in Kg
2,000 2,500
Products with predictable volumes
became ‘self managed’
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 11 / 17
The selection of planning scenarios is based on
volume and demand variability
Kanban is responsive to actual demand and
replenishes material in multiples of a fixed
quantity Provides self-management and flexibility
Planning Scenarios
High Re-order Point is also responsive to actual
Campaign demand but uses just one re-order quantity
management - Used when variability is too high for Kanban
DEMAND VARIABILITY
Re-order Point
Re-Order Point
Make to Order Campaign Management is used for very low-
volume materials
- Inventory may last a long time but is not significant
Kanban
Make to Forecast and Make to Order used for
Low High
special products
PRODUCT
MATERIAL VOLUME
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 13 / 17
4. Operationalize the operating practices into
our core processes and SAP system
Extensive training program sponsored by the Division Head with all stakeholders
Supply Chain Conditioning has been integrated into the S&OP process
– Planning parameters and the calculated inventory levels are reviewed quarterly and
replenishment technique selection is reviewed annually
A ‘Planning Cockpit’ has been developed in SAP with visual signals
Global KPI’s have been established to measure inventory, customer service and
operational compliance for each implementation
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 14 / 17
What about capturing market data?
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 15 / 17
Inventory reductions of up to 40% within the regional
distribution warehouses realised
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.) Slide 16 / 17
Summary of the experience
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.)
Confidential
Corp Comms
04.11.2009
Thank You!
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.)
Questions & Answers
Contact Information:
Matt Tichon/ Guillermo Fumero, Supply Chain and Procurement (Copyright Clariant. All rights reserved.)