Vous êtes sur la page 1sur 6

ICST241 - Data Comm.

and Networking Technologies


Second Semester SY 2010-2011
Froilan B. Rojano, MS

Project #1
Due Date: January 28, 2011

A new IT building, a Graduate School Building, and a building for two-year courses will be
constructed. Your task is to provide a budget proposal to install a network for the three
buildings. The three new buildings must be interconnected. The proposal should contain the
one-time costs and the monthly fixed costs. You are also tasked to come up with a preliminary
documentation of the entire network. This document should contain everything from user
requirements to user security policy.

You may use relevant assumptions to some items that are not clear but this has to be explicitly
noted.

75 meters

IT Building 25 meters

ROAD (15 meters wide)

Graduate School Building


Building for the 25 meters
25 meters
2-Year Courses

40 meters
50 meters

1
ROAD (15 meters wide)

IT Building
Floor Area: 75 meters x 25 meters
Distance between floors: 5 meters

S 7 Classrooms S
Administrators’ t t
Room and a a
Faculty Cubicles
Secretaries Area i i
r 7 Classrooms r
s s

Stairs Stairs Network Administration Room

First Floor Second Floor

4 Lecture Labs S 4 Research Labs S


t t
a a
i i
4 Lecture Labs r 4 Research Labs r
s s

4 Lecture Labs 4 Research Labs


Stairs Stairs

Third Floor Fourth Floor

First Floor
• 40 cubicles for the faculty
• 5 rooms for the administrators

2
• 5 tables for the secretaries
Second Floor
• Divided into 14 classrooms and a Network Administration Room
Third Floor
• Divided into 12 lecture laboratories
Fourth Floor
• Divided into 12 research laboratories

Laboratory and Classroom Specifications

Ground Floor
• each cubicle for faculty, administrators and secretaries must have a workstation
• print and save, internet access, and email
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS

Network Administration Room


• houses all servers, and network equipment
• all servers and equipment must be connected to a UPS
Lecture Laboratories
• each lab has 40 workstations + 1 for the instructor
• print and save, internet access and email
• must be video conferencing enabled
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Research Laboratories
• each lab has 20 workstations
• print and save, internet access and email
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Classrooms
• each classroom has a workstation and a projector
• must be video conferencing enabled
• presentation software, anti-virus software, and a UPS

3
Graduate School Building
Floor Area: 40 meters x 25 meters

1 Lecture Lab 2 Research Labs

3 Classrooms

Grad School Director’s Room


Secretary’s Area

Laboratory and Classroom Specifications

Room for the Graduate School Director and the Secretary


• 2 workstations, 1 for the director and 1 for the secretary
• print and save, internet access, and email
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Lecture Laboratory
• each lab has 40 workstations + 1 for the instructor
• print and save, internet access and email
• must be video conferencing enabled
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Research Laboratories
• each lab has 20 workstations
• print and save, internet access and email
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Classrooms
• each classroom has a workstation and a projector
• must be video conferencing enabled
• presentation software, anti-virus software, and a UPS

4
Building for the 2-Year Courses
Floor Area: 50 meters x 25 meters
Distance between floors: 5 meters

3 Classrooms S 3 Lecture Labs S


t t
a a
i i
r r
3 Classrooms s 3 Research Labs
s

Director’s Room and


Stairs
Stairs Secretary’s Area

First Floor Second Floor


First Floor
• director’s room and secretary Area
• 6 classrooms
Second Floor
• Divided into 3 lecture laboratories and 3 research laboratories

Laboratory and Classroom Specifications

Room for the Director and the Secretary


• 2 workstations, 1 for the director and 1 for the secretary
• print and save, internet access, and email
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Lecture Laboratories
• each lab has 40 workstations + 1 for the instructor
• print and save, internet access and email
• must be video conferencing enabled
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Research Laboratories
• each lab has 20 workstations
• print and save, internet access and email

5
• each workstation must have a word processor, worksheet, presentation software, anti-
virus software, and a UPS
Classrooms
• each classroom has a workstation and a projector
• must be video conferencing enabled
• presentation software, anti-virus software, and a UPS

Vous aimerez peut-être aussi