Vous êtes sur la page 1sur 3

0.

979818710449803

SITUATION SOUS-TRAITANCE : ABDELHADI AGAIGOU

(Gros oeuvre)
Situation N°1

Prix Avancement
Niveau U SURFACE T SURFACE REALISE decomposé % Prix partiel/ DH

Fondation
M2 176.44 176.44 200.00 100% 35,288.00
LA COUR -
M2 37.83 37.83 150.00 100% 5,674.50
SOUS SOL -
GROS OEUVRE M2 584.7 572.90 105.00 98% 60,154.50
MACONNERIE F 1 0.95 30,686.50 95% 29,152.18
ENDUIT F 1 0.95 30,686.50 95% 29,152.18
RDC -
GROS OEUVRE M2 686.38 472.23 105 69% 49,584.15
MACONNERIE F 1 0.80 36691.72 80% 29,353.38
ENDUIT F 1 0.00 36691.72 0% -
1 eme etage -
GROS OUEVRE M2 782.08 490.92 105.00 63% 51,546.60
MACONNERIE F 1 0.00 41059.2 0% -
ENDUIT F 1 0.00 41059.20 0% -
2 eme etage -
GROS OEUVRE M2 426.26 208.54 105.00 49% 21,896.70
MACONNERIE F 1 0.00 22378.70 0% -
ENDUIT F 1 0.00 22378.70 0% -
-
TOTAL TRAVAUX 311,802.18
LES AVANCE 328,040.00
AVANCE FERRAILLAGE 18,867.00
TOTAL AVANCE 346,907.00
10% DE GARANIE 31,180.22
- 66,285.04
572.90

280,621.96
- 66,285.04
328,040.00
322,400.00

Vous aimerez peut-être aussi