ITP-I-11
1_2 Related Installation insturuction Document review Vendor Procedure R H N/A N/A Vendor Procedure
1_3 Installation Method of Statement Document review Contractor Procedure R H N/A N/A Method of Statement
1_4 Shop Drawing Document review Contractor Drawing R H N/A N/A Shop Drawing
2 Execution
Specification and
2_3 Check support arrangement visual inspection approved shop drawing. I I N/A N/A Visual Inspection+RFI
Specification and
2_4 Check cable glands as specified. visual inspection I I N/A N/A Visual Inspection+RFI
approved submittal
2_5 Verify J.Box Tag visual inspection Specification and Drawings I I N/A N/A Visual Inspection+RFI
DESCRIPTION:
REPORT No:
CHECKED DISPOSITION
SL.No INSPECTION TO BE PERFORMED
YES NO N/A
REMARKS:
WITNESSED/REVIEWED BY: CONTRACTOR (NEGEMCO) ENGINEER (DAR) EMPLOYER APC (If Requiered)
SIGNATURE:
PRINT NAME: