Académique Documents
Professionnel Documents
Culture Documents
• Stone construction
Neolithic • Framed Structures – Timber & Stones
Age
• Invention of cement
• Invention of lift
WHY TO ADOPT A NEW CHANGE…??
•Technology is constantly evolving and rapidly changing the landscape of
many different industries.
• POPULATION
• HUMAN COMFORT
• TECHNOLOGY
• CLIMATIC CONDITIONS
• CULTURAL POLICIES
If we fail to adapt, we
fail to move forward.
- John Wooden
UPCOMING TRENDS IN CIVIL ENGINEERING
24
Advantages
Modular construction is a
form of off
site construction in which a
building's components,
or modules, are constructed
in a factory setting before
being transported to site for
assembly.
MODULAR CONSTRUCTION
-Joice Mayer
EMERGING TRENDS IN
FORM WORK
EMERGING TRENDS IN FORM WORK
• The walls and slab are poured simultaneously when using the
innovative tunnel form construction method.
•The focus is not only to keep bacteria alive but also to generate
much calcite to fill the cracks.
VALUE
ENGINEERING
46
VALUE ENGINEERING
• Value Engineering (VE) is a
structured and analytical process
that seeks to achieve value for
money by providing all necessary
functions at the lowest cost
consistent with required levels of
quality and performance.
HOW VE STARTS
• VE is based on a methodology
developed by Lawrence Miles, who
worked for the General Electric
Company in the USA
• Value Engineering began with a
creative, team-based approach
which allowed the generation of
alternatives to the existing solution.
48
The value of a function is defined as
the relationship of cost to
performance
49
FEATURES OF VE
• Using many widely accepted
analysis concepts and
techniques
• Systematic process following
job plan
• Providing the needed functions
safely, reliably, efficiently, and
at the lowest overall cost
51
PROCEDURE
CASE STUDIES OF VALUE ENGINEERING
56
Initial Proposal of Construction:
58
Load calculation with filling
• Weight of filling = 29500 t
• Weight of ground floor slab = 2535 t
• Live load = 2027.8 t
• S.I.D.L. (Floor finish & services) = 1824 t
• Weight of glazing = 101.5t
• Total weight = 35,989 t
59
60
PROPOSAL FOR STRUCTURAL SLAB AT
GROUND FLOOR
63
EFFECTIVE USE OF BASEMENT
FLOOR FOR PARKING
65
COST OF CONSTRUCTION WHEN
FILLING PROVIDED AND WHEN NOT
PROVIDED
Cost is compared when
Filling in basement floor and nominal slab above the filling
is provided
Structural slab provided at ground floor and basement floor
for car parking without filling
66
When structural slab is provided:
Cost of ground floor structural slab= 6759.6m2 x 0.35 m x Rs.20,000/m3
= Rs. 4,73,17,200/-
When filling considered :
Nominal
Area (m2) Cost/m3 Total (Rs/-)
Filling Slab above Volume(m3)
(Rs/-)
filling
5359.6 2.75 - 14738.6 1500 2,21,08,350
68
VALUE ENGINEERING IN OUR PROJECT
“Extra income@ 1
floor”
70
Continued . . . .
Therefore,
When 2 floors considered ,total additional income
per month
= 2 x 29,09,331
= Rs.58,18,663/-
71
“GEOSTRUCTURALS modification”
Incorporating value engineering into the project,
Even if the initial cost of construction will be high,
considering the long run it will be compensated within a
very short time
Additional 2 floors and basement can be added by replacing
equivalent weight of the filling and time saving and
sustainability by avoiding the red earth fill.
Additional substantial income in the long run from the
additional floors by utilizing them for office spaces.
72
Continued . . . .
Annual income from 2 extra office floors
= Rs 6,98,23,964/-
Basement floor can be used for parking for 150 extra
vehicles
73
PRESTIGE FORUM MALL
MASTER PLAN
CITYSCAPE APARTMENTS
LOADING DATA – TYPICAL FLOOR
LL-2KN/M²
FF-1KN/M²
FL-1.8KN/M²
LL-3KN/M²
FF-1KN/M²
LL-2KN/M²
FF-1KN/M²
A A
ELE
CITYSCAPE APARTMENT
A A
CITYSCAPE : 3D
CITYSCAPE : LG FLOOR
CITYSCAPE : TYPICAL FLOOR
LOADING DIAGRAM – TYPICAL FLOOR
ELE
LL-2KN/M²
FF-1KN/M²
FL-1.8KN/M²
LL-3KN/M²
FF-1KN/M²
C C
LL-2KN/M²
FF-1KN/M²
MASTER PILE LAYOUT
ARRIVAL OF PILE CAP CUTOFF LEVEL
11) PILE CUTOFF LEVEL FOR TRENCH SUPPORTING PILE = 91.975M
1) FOR HYPER MARKET & RETAIL PARKING
PILE CUTOFF LEVEL = 93.275M
R00 R01 R02 R03 R04 R05 R06 R07 R08 R09 R10 R11 R12 R13 R14 R15 R16 R17 R18 R19 R20
PILE CAP CUTOFF LEVEL CALCULATIONS
7800 5000 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800 10800
SP14
FOR HYPER MARKET
SP10
5400
2A PILE CUTOFF LEVEL = 93.0M
RP100
8A
3 4 4A 9
RL FOR HYPER MARKET
5A 9B RP99 PILE CAP CUTOFF LEVEL CALCULATIONS
9A RP94 RP95 RP96 RP97
RP93 RP98
RP92
10800
LIFT PILE CUTOFF LEVEL LIFT PILE CUTOFF LEVEL
14A 10 = 92.075 FOR HATCHED PORTION
LIFT PILE CUTOFF LEVEL = 92.075
PILE CAP CUTOFF LEVEL CALCULATIONS
= 92.075
10A
32 25A
362 359
10800
361
PILE CAP CUTOFF LEVEL CALCULATIONS FOR HYPER MARKET RETAINING WALL
44A 25B
4) FOR HYPER MARKET & RETAIL PARKING LIFT
PILE CUTOFF LEVEL = 92.075M
40 53 54 55 56 56A
36 38 39 41 43 44 50 51
37 42 45 46
47 49
53A
RJ
RP6 RP7 RP8 RP9 52 FOR LIFT
RP5 PILE CAP CUTOFF LEVEL CALCULATIONS
RP10
16) PILE CUTOFF LEVEL FOR RETAINING WALL PILE :-
44B
RP1 RP2 RP3
10800
58A 53B
PC1 PC2 LIFT PILE CUTOFF LEVEL
PC3 PC4 RP11 =92.075 PILE CAP CUTOFF LEVEL CALCULATIONS FOR HYPER MARKET RETAINING WALL
197
R1 59 60 61 62 63 5) FOR HVAC PLANT ROOM PILE CUTOFF LEVEL = 93.575M
64 65 66 70 72 73 74 75
RP13 RP4 PC5 PC6 PC7 PC8 RP12 67 68 71
88A 76
RH
200 FOR HVAC PLANT ROOM
4550
PILE CAP CUTOFF LEVEL CALCULATIONS
4450
PC9
77 78 79 80 81 PILE CAP CUTOFF LEVEL CALCULATIONS
R2 201 82 83 84 110A
88 108A 92 93 94
109A 95 RF 18) PILE CUTOFF LEVEL (SEWAGE TREATMENT PLANT
RP16 6) FOR HVAC PLANT ROOM PILE CUTOFF LEVEL = 93.275M -RESIDENTIAL BLOCK )
A) RU1,RU2,RU4,RU5 = 94.825M
PC16 PC17
TRAVLATOR PIT FOR HVAC PLANT ROOM
RETAIL PARKING PILE CUTOFF LEVEL PILE SUPPORTING TRAVLATOR PIT
9000
PC18 PC19 HYPER MARKET PILE CUTOFF LEVEL
R3 =93.275M
RP17 =93.275M
CUTOFF LVL
B) RESIDENTIAL U.G PUMP ROOM = 94.225M
=92.675M
100
PC20 96 97 98 99 107 108 109 110 111 95A
202 101
102 93A 94A RE
RP18 PILE CAP CUTOFF LEVEL CALCULATIONS
103
PC21 PC22 R4 C) PUMP ROOM COLLECTION SUMP = 93.225M
4450
FOR HATCHED PORTION 96A 7) FOR STAFF CANTEEN PILE CUTOFF LEVEL =92.525M
=91.775M
TRAVLATOR PIT
RP19 RD
PC23
FOR STAFF CANTEEN
D) RESIDENTIAL STP PUMP ROOM = 93.225M
4550
PC24 112A
PC25 123 124 125 127 129 129A
112 113 114 115 116 117 126
203 128
120 121
RC
118 119
122 MALL U.G SUMP ROOM
PC26 R5
RP20 RP21
PILE CAP CUTOFF LEVEL CALCULATIONS
PC27 PC28
RETAIL PARKING PILE CUTOFF LEVEL
10800
8) FOR STAFF CANTEEN PILE CUTOFF LEVEL =92.225M
RP22 = 93.0M LIFT PILE CUTOFF LEVEL
=92.075 A) FIRE WATER SUMP= 94.825M
FOR STAFF CANTEEN
PC29
PC30
204 130 134
RP23 142 147
PC31 140 141 143 144 146 148
132 138 139
131 133 136 B) RAFT TOP WATER SUMP= 92.875M
137 149 RB
PC32 150A 137A
PILE CAP CUTOFF LEVEL CALCULATIONS
RP24 131A
9) FOR RAMP PILE CUTOFF LEVEL WILL BE AS PER C) FIRE WATER SUMP= 93.225M
10800
172B LIFT PILE CUTOFF LEVEL RAMP SLOPE PROFILE
132A 136B 168A 172A = 92.075
R6 160B
136A 167A 157A
178A
205 10) PILE CUTOFF LEVEL FOR TRENCH SUPPORTING PILE
PC33 PC34 160
RP25
FOR HATCHED PORTION =93.275M
=91.775M
160A 19) PILE CUTOFF LEVEL FOR C56A = 99.575M
164 166 174 175 179
R7 162A PILE CAP CUTOFF LEVEL CALCULATIONS
167 173
177 181 RA
167B 168
PC35 162 163 169 177A
170
PC37 172
RP26 PC36
174A
331A
PC38 332A PILE CUTOFF LEVEL FOR TRENCH SUPPORTING PILE R4 29.01.15 GOOD FOR CONSTRUCTION
=92.70-0.4+0.075= 92.375M
331B R3 21-01-14 GOOD FOR CONSTRUCTION
RAMP IN FILLING
R8
RP27 331 R2 05-12-13 GOOD FOR CONSTRUCTION
PC40 206 333 334 335
RP45 208
PC39
PC42 209 210
211 212 213 214 R1 18.06.13 GOOD FOR CONSTRUCTION
R14 R15
PC41
207
RP41 RP42 RP43 RP44 RP88 RP89 RP90 RP91
R0 18.9.12 PILE LAYOUT
SP21 SP24
R9 SP22 SP23
RP28 SP20 R16 R17 RP39 RP40 215
SP25 SP26
RP46
SP30 SP27
SP28 216 217 218 219 220
SP29 SP32 SP33
SP44 HVAC PILE CUTOFF LEVEL STAFF CANTEEN PILE CUTOFF LEVEL
RP33 PC43 PC44 PC45 PC46 R11 SP34
SP36
PILE LAYOUT
RP29 = 93.575M = 92.525M
SP37 SP38 SP40 SP45
R10 SP35 SP42 SP46
SP47
PC47 PC48 SP39 SP41 SP43
R12 SP48
(MASTER PLAN)
PC49 PC50 RP47
SP50 SP51
RP30 RP31 RP32
SP56 SP57 SP58 SP59 SP60
R13 SP49 SP52 SP53 SP54 SP55
RP34 RP49 RP48 R18 R19 R20 R23 R24 R25 RP85 RP86 RP87
RP35 RP36 RP37 RP38
SP66A
SP61 SP62 R21 KEY PLAN
R22
78
LANDSCAPE ARCHITECT :-
360 93A
331B RP52
16 138
68 FOR HATCHED PORTION
16A 137A 357 PC58 = 91.775M
PC59 RP82
131A
359 RP53 PHE & FIRE CONSULTANT :-
361 150A
167A 168A 96
331
EXISTING PILE NEW PILE
PC60 PC61
RP54
163 RP56
110 PC65
77 40
10 RP80 = 750 DIA PILE = 750 DIA PILE
88A
112 RP81
25
10A RP57
32
PC66 PC67 PC68 PC69
PC70
32A 14A 14 RP79
RP58
93 172A 172B
5
130
216
RP78
PC75
RP67 RP71
RP77
RP68 RP69 RP70
RP76
RP72
8025/1/R4
PREVIOUSLY PROPOSED PLAN
PROVIDED PILES: CITYSCAPE
R21
R22
RP50 PC51
PC52 PC53 PC54
RP84
PC55
RP51
PC57
PC56
RP83
RP52
PC59 RP82
RP53
PC60 PC61
RP54
RP55
PC62 PC63
PC64
RP56
PC65
RP80
RP81
RP57
RP58
RP78
PC75
RP67 RP71
RP77
RP68 RP69 RP70
RP76
RP72
2750 6350 4250 4050 3700 7782 5074 7344 10800 7165 6935 5960 4515
1700
2P70 2P90
2P70 PILE SCHEDULE FOR INFORMATION ONLY
4475
6025
3300
3300
2P70
P70 700Ø 58
P70
250350
350
2P80
250
1100 1150 1250
2P70 2P70 P90 900Ø
P90
2P100 2P90 2P70
2P80 2P90 2P70 38 x 2 = 76
P90 700Ø
6025
3P80A 2P80 1750
P70 500 500
3P90A
2250
2250
2P80
2P100 2P80 800Ø 13 x 2 = 26
2P70
5000
1600 400 1200 1000 400600 650 1150 700 500700 500 800 1300
2P90 2P100 P70
3P90
16 x 2 = 32
500 500
6025
2P90
2P70
2P70 2P100 100Ø 11 x 2 = 22
3P100A 2P80
3P80A
5000
3P70 2P70
650 2500 650
2P70
P90 3P70 PRESTIGE FORUM MALL,KOCHI
400
700Ø
17
50
P70 P70 3x3=9 CITYSCAPE
50
P70
17
3P70 2P70 2P70 2P80 2P70 2P70
3680
P70 1750
2P90 2P90
400
2P70
5000
3P70A
1600
3680
2P90 2P90 2P90
2P70 2P70
P70 3P80A
P90 8-P90 P70 800Ø
P70 2x3=6
2P70 550 2000 2000 550
2P70 2P100 2P70
5000
2P70
1200 700
3680
3P70 2P70 RSP DESIGN CONSULTANTS(P)LTD
2P70
500
500
P70 P70 3P90 900Ø 2x3=6
2P70
1300 800
1300 800
2P70
P70
2P70 2P80
2P80 2P100 GEO STRUCTURALS (P) Ltd
3680
2P80
Geo technical & structural consultants
5000
2252
2252
2P100 3P80 3P90A
3P90 900Ø Phone: 2367824, 2368327 , Fax :2371643
P70 P70 600 2250 2250 600
2P70 E-mail : geostructurals@gmail.com
1250 1150 1098
3680
P70 P90 2P100
2P90
2P80 01
350250
2P90 P70
5000
P70
2P80 2P70
2P100 2P70 3P90A 2P90 1. This drawing should be read along with our general Notes,
2P90 2P100 Notes in this drawing, Architectural Drawings &
Specifications.
3300
3300
6350
P70 2. All dimensions should be checked by the architect and any
discrepancy found should be brought to our notice before
1x8=8 execution.
8P90 900Ø 3. All dimensions are in mm unless otherwise specified.
1700
1700
1700
2P70 2P70
5000
5000
7. The pile should be taken into pile cap by 75mm.
TOTAL 278 8. To ensure building up of pile upto the required level with good
150 150
1550 1500 2750 1300 2600 1050 1900 250 1850 950 1150 750 900 1900 1950 1700 4450 5250 3850 1100 concrete, pile has to be built up initially to a length more than
5000
2800 1700
that is required and this is to be cut off to remove all laitance
layer of concrete at its top.
P70 9. Initial load test on test piles and Routine Load Tests on working
piles should be carried out as per I.S 2911 (part IV)-- 1985.
7800 11700 7285 7565 5056 9000 4744 10. Clear cover to reinforcement a).Pile - 50mm.
P70 P90 P90 P90 11. Grade of steel shall be Fe500.
5000
P90 P90 P90 P90
2609
2609
12. Lap length is 55d, Where 'd' is the Diameter of bar.
13. Building is designed for B+LGF +UGF+18 Floors only
5000
P70
P70
P70
P70 P70 P70 FOR EXECUTION PURPOSE FOLLOW ONLY THE DRAWINGS
3509 4750 4750 3509 APPROVED & SIGNED BY THE STRUCTURAL CONSULTANT.
P70 P70 P70 P70 P70 P70
P70 4969 5000 5000 5000 4473 3832
A A
LAYOUT OF PILES
P70 ELE
1000
8mmØ@180mmc/c
SPACER
12mmØ@1500mmc/c
COST COMPARISON
SAVINGS
PROPOSED GEO
(RS)
NO OF
PILE 330 278
PILE 95644800 74518080 21126720
PILE CAP 53895290 16269110 37626180
TOTAL 149540090 90787190 58752900
TOTAL SAVINGS IN % 39.29%
GEOSTRUCTURALS MODIFICATION
• Instead of piled raft system planned, the new proposal of
individual pile caps under each column connected by grade
beams and slabs.
• Rs. 5,87,00000/- saved per tower.
• So, total about 11 crore rupees
where saved by value engineering.
88
Architect : JURONG CONSULTANTS/ WATG
Structural Consultants: JURONG CONSULTANTS/
Geostructurals Pvt Ltd
First Seven Star Hotel in Kerala
Area : About 8 lac 90 thousand sq. ft.
Resting on Reclaimed Land
1.Entire Dome area : 1.20m soil
fill (For Trees and Landscaping)
23 crores
Saving