Académique Documents
Professionnel Documents
Culture Documents
MM-40
Book No. Rev 2017–09–01
Published By:
Alfa Laval Tumba AB
SE-147 80 Tumba, Sweden
Remark :
These are supplied by request of ship owner.
Contents
1 Ship specific information 7
2 Introduction 9
2.1 Safety information 9
2.2 System overview 10
5 Mechanical installation 17
5.1 General requirements 17
5.2 Ex zones 18
5.3 UV reactor 18
5.3.1 General requirements 18
5.4 Filter 20
5.5 CIP module 21
5.6 Flow meter (FIT201-1) 22
5.7 Pressure monitoring device 25
5.8 Valves 25
5.9 Electrical cabinets 28
5.10 Ancillary equipment and functions 28
5.10.1 Sampling devices (Q201.1 and Q201.2) 28
5.10.2 Booster pumps 29
5.10.3 Tank stripping 29
3
6 Pipe design 31
6.1 Water types 31
6.2 Valves outside PureBallast 31
6.3 Pipe dimensions and material 32
6.4 Pressure and flow 34
6.5 Pressure and flow – backflush 34
6.5.1 Calculate pressure and flow for backflush 34
6.5.2 Calculate value for backflush parameter setting 35
7 Electrical design 37
7.1 Basic technical data 37
7.2 Installation requirements 38
8 Ex protection 41
8.1 Ex components 41
8.1.1 UV reactor 43
8.1.2 CIP module 44
8.1.3 Filter 44
8.1.4 Pipe net 45
9 Pneumatic design 55
4
10.5 External components 62
10.6 GPS 66
11 System approval 69
11.1 Alfa Laval’s responsibilities 69
11.2 Installing party’s responsibility 69
11.2.1 Approval planning 69
11.2.2 Design approval 69
11.2.3 Installation survey 70
13 Start-up procedures 77
14 Drawings 79
14.1 Graphic symbols used in drawings 80
14.2 General drawings 81
14.2.1 Flow chart 81
14.2.2 Technical data 82
14.2.3 Connection list 83
14.2.4 Electrical system layout (3 pages) 89
14.2.5 Instrument air distribution 92
14.2.6 Quality specification / Instrument air 93
14.2.7 Quality specification / Fresh water 94
14.2.8 Quality specification / CIP liquid 95
14.2.9 Material data sheet / UV lamp 96
14.2.10 Safety data sheet / CIP liquid 106
5
14.3 Dimension drawings including technical
data 114
14.3.1 UV reactor (previously called AOT reactor) 114
14.3.2 Filter 115
14.3.3 CIP module (2 pages) 116
14.3.4 Flow transmitter FIT201-1 118
14.3.5 Pressure monitoring device 6 bar system (Incl.
PT201-16, PI201-18, RV201 and 201-15) 119
14.3.6 Pressure monitoring device high pressure system
(Incl. PT201-16, PI201-18, RV201 and 201-15) 120
14.3.7 Valve V201-3 and V201-9 121
14.3.8 Valve V201-32 and V403-35 122
14.3.9 Valve V212-31 (Optional in scope of supply) 123
14.3.10 Control valve V201-8 125
14.3.11 Backflush valve V309-1 126
14.3.12 Check valve CV201 127
14.3.13 Sampling device Q201.1 and Q201.2 (3 pages)
(Optional in scope of supply) 128
14.3.14 Lamp drive cabinet (LDC) 131
14.3.15 Control cabinet 132
14.3.16 Remote control panel (Optional) 133
14.3.17 Transformer (Optional) 134
14.3.18 Air filter / Filter regulator (Optional) 135
14.3.19 Additional pumps (Optional) 136
14.3.20 UV reactor and LDC / Lamp power cable 139
6
1 Ship specific information
Enter vessel specific information in the table below. This will facilitate reading information and
drawings in this document, since some drawings include information for all system sizes /
dimensions, and the document contains information for options only used by on some vessels. In
PDF, either edit the document or add a text box.
Data Value
Number or UV reactors 1
This document contains general guidelines for the on board design and installation planning. Alfa
Laval deliver PureBallast as a semi assembled system, with the main components, UV reactor
and control system, pre assembled and tested ready to be connected to the vessels associated
systems according to the specifications within this document. The installing party (shipyard,
installation company etc) must design the ship specific installation and supply materials for piping,
power feed etc.
The purpose of this document is to facilitate the design and installation phase. The information given
should be sufficient to produce necessary documentation to update the ship specific information for
installation and approval by designated classification society.
The guide gives information that is relevant for planning the installation and how to furnish the
vessel with the equipment on board. It contains information about basic requirements and
which calculations that must be performed to secure performance of the system. It also contain
information about how to integrate the system regarding piping, feedback signals and optional
remote control solutions.
Components mentioned in this document can be found in the Flow chart drawing and the dimension
drawings included the Drawings section in this document. Components are identified by their ID,
for example control valve (V201-8).
Note that the function and performance of PureBallast are dependent of the installation. Therefore,
it is important that the design and installation is done according to the information given in this
document.
NG
WARNI
!
• Read chapter 1. Safety.
• Before installing a component, always read the Ex certificate delivered with the component.
This is especially important if the certificate number contains an “X”. Consult the overview in
section Ex protection.
• The installation must be done according to rules regarding installations in potentially explosive
environments, for example IEC 60079 series.
• Installation must be done by a fully trained professional installer.
• Damages related to transport and installation should be recorded.
The table below is a list of all PureBallast components and consumables delivered by Alfa Laval.
The list is compiled on the top level so that integrated components are not described, because they
are already mounted at delivery. For example, the valves on the UV reactor are not described
individually in the list, since they are already mounted as a part of the component.
Component ID Function
Main components
UV reactor, 1 UVR 1 The main water treatment component in the system, including
pieces. reactor, valves, UV sensor, temperature sensor, temperature
switch and level switches.
Lamp drive LDC 1 Electrical cabinet feeding the UV lamps in the UV reactor with
cabinet, 1 power via lamp power supplies (LPS).
piece
Lamp power W211 Power cables between UV reactor and lamp drive cabinet. Length
cable, specified in order.
Control Control Contains the main control panel, from which PureBallast is
cabinet, 1 cabinet controlled. It also contains breaker and communication components
piece such as PLC, switches for communication with remote interface,
remote control panels etc, and terminals to connect signal cables
to components and external systems.
CIP module, CIP Cleaning-in-place module for automatic cleaning of the UV reactor
1 piece after treatment, mainly clean the UV lamps quartz sleeves. The
CIP module is also used to drain and fill the UV reactor during CIP
process and to fill the filter with fresh water after for preservation
reasons.
Remote Extra control panels to control and monitor the PureBallast system.
control panel Number according to order.
(optional)
Valves
Component ID Function
Control V201-8 • Main outlet valve from the PureBallast system to the vessel’s
valve, ballast system after treatment.
1 piece
• Automatic pressure regulation to maintain needed pressure
including
during back flush.
positioner
• Automatic flow regulation during operation to secure needed
minimum flow to cool the UV lamps and secure that max flow
is not exceeded.
The positioner function as connection point for signal and power
cables to the component.
Filter outlet V201-32 • The valve directs the water flow from the PureBallast filter to
valve the UV reactor. (Closed during deballast)
including
• The switch box function as connection point for signal and
switch box,
power cables to the component.
1 piece
Valve V201-9 • Filter bypass valve open during deballast, when the filter is not
including used. (Closed during ballast)
switch box,
• The switch box function as connection point for signal and
1 piece
power cables to the component.
Valve, V212-31 • Bypass valve to bypass the complete PureBallast system. The
1 piece valve is solely operated from the ISCS.
including
• The switch box function as connection point for signal and
switch box
control cables to the component.
(Optional as
part of scope
of supply)
Cooling V403–35 • Supplies cooling water to the UV reactor(s) to protect the lamps
water inlet from overheating during start-up. The valve is common for all
valve, installed UV reactor(s).
1 piece
• The switch box function as connection point for signal and
including
control cables to the component.
switch box
Check valve, CV201 Check valve before the UV reactor to secure water in the UV
1 piece reactor.
Ancillary equipment
Component ID Function
Sampling Q201-1 Sampling points to tap water for test of water before and after
device, 2 Q201-2 treatment.
pieces
(Optional as
part of scope
of supply)
Consumables
CIP liquid, 12 The liquid is used for the first filling of CIP liquid.
liters
Additional equipment is needed to install the PureBallast system, apart from components included
in Alfa Laval’s scope of supply (according to order). These needs to be designed, supplied and
installed by the party responsible for the installation.
• Support for mounting heavy components, for example extra support for the UV reactor.
• Electrical and signal cables.
• Pipes for ballast water, cooling water and CIP.
• Tubings for instrument air and deareation pipe.
• Ancillary equipment, for example sieve for stripping.
• Flange for sampling devices, if the device is included in scope of supply. If not, the complete
sampling device.
• Bypass valve, if not included in scope of supply.
• Booster pumps for backflus water (P309–1) and cooling water (P401 and P403), if used and not
included in scope of supply. See under heading External component signals.
• Power supply cabinet (not part of Alfa Laval’s scope of supply). Must be installed in safe zone.
• Two main breakers: To be installed in the main switch board. See section Electrical subsystem
on page .
The installing party is responsible for selecting and purchasing the equipment according to
specifications in the documents below:
• Connection list
• Quality specification for water
• Quality specification for instrument air
• Drawings Control cabinet / Cable list and Lamp drive cabinet (LDC) / Cable list state
requirements for cables.
This section contains information relevant for planning the installation of mechanical components
and connections to water and instrument air.
The relation between the components is important. Example: Cooling water inlet valve V403-35
must be installed between valve V201-9 and V201-19. The flow chart also defines where
components are to be placed in relation to pipe intersections.
Installation prerequisites:
• The PureBallast must be installed in a machinery space on the vessel (engine room, pump
room etc defined as zone 1 or 2) with
5.2 Ex zones
PureBallast Ex is classed for use in hazardous areas in accordance to the IEC 60079 series of
standards: Zone 1 , explosion group IIC and temperature class T4 (135°).
5.3 UV reactor
Requirements and recommendations for UV reactor installation differs depending on if one or more
UV reactors are installed.
• The UV reactor must be oriented so that the UV lamps are perpendicular (90°) to pipe 201
with flow to the UV reactor. This will result in an even distribution of the water within the UV
reactor, so that all water is treated equally. See relation between pipe 201 and position of the
UV lamps in the illustrations below.
AOT manifold2
• The UV reactor must be secured so it withstands the forces of load applied by a full UV reactor
(520 kg) at the vessel’s maximum heeling degree.
• The UV reactor must be fixated at the bottom and supported at the top to carry the weight of
the component. Use the upper and lower fixing holes (1) in the support structure to fixate the
component to the steel construction of the hull. If this is not enough, completing stays has to
be made. There are four fixing holes on each side at the bottom and four at the top, after
the lifting beam has been removed.
6 AOT installation
• Prepare the inlet piping first. Then mount the UV reactor onto the inlet flange and secure it.
Finally install the outlet piping onto the top of the UV reactor.
• We recommend that the installation of the reactor is planned to be supported by its lifting point
until the units lower part is completely secured to the foundation and inlet flange.
• No fixtures should be attached to the reactor housing by welding, since this will damage or
distort the reactor, and potentially affect the biological performance of the component.
5.4 Filter
Installation prerequisites:
• The filter is recommended to placed close to the ballast water pump for best back flush
performance.
• When planning the location of the filter, consider the installation height and the need for a lifting
device to be used to lift the heavy cover and insert during installation and maintenance. See
basic size drawing for required installation height and access area. Filter cover and element
weight (kg): 285.
• The filter can be bolted or welded in place.
• A draining valve (not part of Alfa Laval’s scope of supply) can be installed to facilitate draining of
the filter during maintenance. See connection 460 in the filter dimension drawing.
• See section Pipe design on page for details for pipe 309.
5.5 CIP module
Installation prerequisites:
• The CIP shall be placed close to the UV reactor to secure that the CIP fluid (250 liter) can
circulate.
• It is recommended that the CIP module is installed below the UV reactor, or on the same level
and that the pipes to and from the UV reactor is installed according to the illustration below.
There must be no risk for additional water or air pockets in the piping. This will minimize dilution
or loss of CIP liquid and secure good pump efficiency.
- Pipe 321: Downward gradient towards both the CIP module and the UV reactor. There
must be no risk for water or air pockets inf the pipe.
- Pipe 320: Downward gradient from the UV reactor towards the CIP module. A water
lock can be created close to the CIP module, before a vertical pipe to the CIP module, as
illustrated to the left below. This is not needed if the liquid can flow by gravity to the CIP
module, as illustrated to the right below. There must be no risk for water or air pockets in
the pipe, which can affect efficiency in a negative way.
Left: CIP in level with UV reactor. Right: CIP on lower level than the UV reactor.
6 CIP_AOTrelation
• The deaeration pipe after deaeration valve V571-1 must reach approximately 2 meters
higher than valve V321-2 at the UV reactor to avoid water spillage during CIP process. It is
recommended that the deaeration pipe is led to a scupper to collect eventual (minor) water
spillage.The deaeration pipe must end in safe zone, to avoid hazardous gas to enter the UV
reactor during when valve V571–1 is opened.
• Pipe connections to the CIP must be made so that the connection is not exposed to any moment
or load. This is particularly important when connecting the plastic flanges.
• Pipe 460.2 (drain of used CIP liquid) should not be lead to bilge tank due to the low pH value.
Drain to one of the following: drain, waste or sludge tank.
• It is recommended that pipe 460.2 is connected so that used CIP liquid (250 liters) is drained to
one of the following: waist oil tank, drain tank or sludge tank. CIP liquid should be handled
according to local regulations. Note that the CIP liquid have a low pH value (approximately
3.0 when changed) and that it also contain residues from the cleaning process. See Quality
specification / CIP liquid on page .
• Max tightening torque for bolts on flanges: 20 Nm.
• The flow meter should be installed after inlet valves (V403–35, V201–9 and V201–32) and
before V201–8.
• We recommend that a straight pipe is installed before and after the flow meter, with length
(L) proportional to the pipe diameter (⌀) according to the illustration below. This will secure
accurate measure.
• Do not install the flow meter at the highest point in the pipe: This result in partially filled pipes.
Do not install in a pipe with a downward flow direction: The water shall not stream by gravity.
If there is a a risk of pour measuring conditions (e.g. partially filled pipes), install a siphon
(1) downstream of the flowmeter.
DI Down pipes
DI Horizontal orientation
• Note that the flow transmitter housing and the display can be turned. This makes the placing
of the flow meter flexible.
• Pressure monitoring device must be installed vertically on a horizontal pipe. If not it will not
function.
• A solution (not part of Alfa Laval’s scope of supply) must be attached to safety valve RV201.
The valve shall be drained to a scupper, with a solution which always allows water to be drained
from the valve. See Pressure monitoring device / Dimension drawing.
5.8 Valves
The valves in PureBallast are operated by instrument air from the vessel’s instrument air system
and they are connected to the control cabinet by signal cables to give feedback.
Installation prerequisites:
Component Guidelines
Component Guidelines
signal is not integrated, the position must also be entered in
this log book.
Extra bypass valves (not part If PureBallast can be bypassed using other valves (apart from
of Alfa Laval’s scope of supply) V212-31), these valves (or combination of valves) must be
integrated to PureBallast control system, since all bypass
cases must be logged, according to the IMO convention.
Control valve (V201-8) Must be placed as the last component on pipe 201.
Cooling water valve (V403-35) The valve must be installed between filter bypass valve
V201-9 and UV reactor inlet valve V201-19.
Check valve (CV403) (not part Optional to use. If used, it must be placed before the cooling
of Alfa Laval’s scope of supply) water valve V403–35.
Check valve (CV201) The valve must be installed before the UV reactor inlet valve
V201-19. It is recommended to be installed as close as
possible to the UV reactor.
Check valve (CV310) The valve is installed on the flange for pipe 310.1 on the CIP.
Non-return valves (not part of It is recommended to installed non-return valves at the end of
Alfa Laval’s scope of supply) the following pipes: 309, 402 and 404, as a safety precaution.
For piping dimension JIS/EN 300 and JIS 350 the valve can
NOT be mounted directly on the filter due to the adaptor plate.
For other dimensions the valve can be mounted directly on
the filter flange.
Filter outlet valve (V201–32) According to flow chart. See V201–3 regarding mounting.
Component Guidelines
Vacuum breaker vavle If the height difference between the PureBallast system and
the ballast water tank is over 10 meters, a vacuum breaker
valve should be considered. A vacuum breaker valve (not part
of Alfa Laval’s scope of supply) eliminates the risk of cavitation
in the downward going part of pipe 201 after treatment.
VacuumBreaker
General requirements
• Cabinets must be firmly attached and must not amplify vibrations to or from the hull.
• Cabinets must be installed so that there is free space available to open the door.
• Maximum distance (lamp power cable length) to the UV reactor: 150 meters.
• Maximum distance (cable length) to the control cabinet: 100 meters.
• The cabinet must be placed on a firm level surface and fixated. The legs of the component can
be bolted or welded in place on a steady foundation. It is possible to detach the cabinet from
the bottom frame to facilitate installation. The cabinet shall also be attached to the bulkhead
using the attachment bolts on the top of the cabinet. The cabinet is fixed to the ships structure
via vibration dampers to minimize the effect of vibrations from the hull affecting components
inside the cabinet.
• The cooling water supply must be connected to meet the requirements in the Connection list on
page under item 401. Correct temperature and flow are crucial to secure that the LDC is cooled
in a sufficient way. The cooling water installation must be verified after a couple of hours, to
make sure that there is no leakage in the cabinet.
Installation prerequisites:
• One sampling device shall be installed before filter inlet valve V201-3 and the second one
as close to the overboard valve as possible. If there are several discharge lines, it might be
necessary with a sampling device on each.
• The placement of the sampling points is subject to approval by class society.
• Sampling device should be installed in a straight pipe without elbows, tees or other fittings. It is
not allowed to install a connecting pipe between the control valve V201–8 and the sampling
device. No water from other sources than from PureBallast may mix with the ballast water.
Ideally, the pipe where the component is installed should be vertical and as long as possible.
The sampling device should be installed where the flow in the pipe is fully mixed and fully
developed. For full details, see standard ISO 11711-1:2013(E).
• The sampling device must be accessible for maintenance and taking samples, including the
possibility to close valve before and after, to avoid leakage during maintenance.
• Flanges for connecting the sampling devices must be installed before the pipe is coated.
• If Alfa Laval’s sampling device is used, the device must be mounted with the sampling pipe
opening pointing in the flow direction. See drawing on page 128 .
• LDC cooling water pump (P401-1): Booster pump so that cooling water flow to LDC (during
operation) shall give minimum flow according to Connection list, for Item/Connection 401.
• UV reactor cooling water pump (P403-1): Booster pump so that cooling water flow to UV
reactor (during startup and pause) shall give minimum flow according to Connection list, for
Item/Connection Item/Connection 403.
• Filter backflush pump (P309-1): Booster pump to secure enough flow in pipe 309 for sufficient
filter backflush according to Connection list, for Item/Connection 309.
Start and stop of the booster pumps are handled by signals sent from the control system. See
External component signals on page 62 via hardwire or remote interface.
The stripping process is basically the same as a ballast process with the following difference: A
stripping eductor (or a stripping pump) should be used to secure minimum flow in the system.
Stripping eductor
The use of stripping eductor is approved by the Norwegian Maritime Authority, and is included in the
PureBallast type approval certificate.
According to MEPC 67 “there is no need to develop guidance on stripping operations using eductors
as it is not recommended that ballast water sampling be performed during stripping operations”
(ref MEPC 67/WP.1 - 2.32).
• The eductor (not part of Alfa Laval’s scope of supply) must be installed before the PureBallast
system.
• If an eductor is used, driving water is used to get enough flow. We recommend that the driving
water alone (without the ballast water flow from the tank) fulfils the minimum flow requirement
for deballast operation. This will minimize the risk of shut down due to low flow when flow
of ballast water is uneven.
• The driving water used in the stripping process, must be filtered from particles larger than
approximately 5 mm. Filter should be placed before eductor and/or pump.
• Procedures to dispose of sediments from the sieve must be included in the vessel’s ballast
water management plan.
Stripping pump
As an alternative to an eductor, the ballast water pump or a dedicated stripping pump can be used.
If the pump used for stripping is different from the normal ballast water pump, it is possible to
connect specific signal cables to be used when PureBallast request the start of the stripping pump.
This section gives information about pressure drop during ballast/deballast operations, and
requirements to secure efficient backflushing. The information must be considered when the
ballast water system is dimensioned.
This section also contains information about calculations that must be done to secure sufficient
performance.
• Sea water: Used for cooling UV lamps in the UV reactor during start-up. Pipe 403 is
recommended to be connected to the vessel’s sea water cooling system or dedicated UV
cooling water pump (P403-1) for UV reactor cooling. Booster pump is not part of Alfa Laval’s
scope of supply.
• Low temperature (LT) fresh water: Used for cooling the lamp drive cabinet (LDC) during
operation. Pipe 401 and 402 can be connected as a loop to the fresh water cooling system.
The water must be taken from safe zone.
• Fresh water: Used for flushing and filling up of UV reactors after treatment.
6.2 Valves outside PureBallast
During process, the PureBallast requires that a number of valves outside of PureBallast’s control
are opened to lead the flow in a correct way.
A request to open the valves can either be given to the operator in a popup message in the control
system or automatically, if feedback signals are integrated via the remote interface or via hardwire.
PureBallast requires feedback that the valves are opened. The feedback can either be done by
confirming the popup or automatically in feedback signals are integrated. Without feedback, the
process is canceled. Valves are to be closed when requested by popup or when the request
signal is redrawn (goes low).
Ballast process
• Pipes shall be designed to carry the weight of the component and media.
• Pipes must be pressure approved by a classification society or equivalent, or be tested under
supervision of a classification society and/or at the ship yards pipe shop etc.
• Pipe 403 and valve V403-35 (cooling water valve, reactor): 50, 65 or 80
Dimension decided at order, smalles recommended.
• Pipe 309 (backflush): Pipe dimension MUST be increased to 150 after V309–1. Cone is not
part of Alfa Laval’s scope of supply. This is required to secure reliable backflush operation.
• Pipe 309 (backflush): It is recommended to use as few bends as possible in pipe 309, to
get as low pressure resistance as possible.
• CIP pipes: Non-corroding material is recommended for pipes used for CIP liquid, due to low pH
value: 320, 321 and 460.2.
• Penetration Ex zone dividing bulk heads is not recommended. If done, special precaution must
be taken with regards to applicable rules and classification society.
• It is not recommended to use plastic pipes for pipe 201 closer than approximately two meters
from the UV reactor. It UV light will affect the material and shorten its life time.
• Also see information in section Material selection on page 15.
UV reactor ≤ 0.20 bar pUVR: 0.20 bar (0.02 MPa) including PureBallast valves.
Piping is not included, since it is installation specific.
Note that 0.50 bar is the default limit value for triggering an
automatic back flush (parameter p305). This parameter is
set by Alfa Laval during commissioning.
Total ≤ 0.70 bar ≤ 0.70 bar (0.07 MPa) not including piping.
BFpressure
A pressure calculation must be done to secure sufficient backflush flow in pipe 309 and to secure
that the ballast water pump can overcome pressure drop according to the table below:
This value will be entered in parameter p304 (Required pressure to start backflush) during
commissioning. The parameter defines pressure needed to perform an efficient backflush operation
and is the setpoint for the pressure that the control valve (V201-8) will maintain during backflush.
This section contains information relevant for planning the electrical installation and routing.
Control cabinet
LDC – Heat Heat transfer from/to the LDC is depending on ambient temperature. The need
dissipation for cooling the area where the LDC is placed, is therefore dependent on ambient
temperature.
At an ambient temperature of
Cables – General
• Dimension of cables must be within the cable gland range stated in the dimension drawings
for respective component.
• Major compoentnts (UVR, filter, CIP and cabinets) must be earthed. The earth nut is indicated
as “791” or “PE bolt” in the dimension drawings.
• Cabinets must be earthed. The earth nut is indicated as “791” in the dimension drawing.
• Earth cables must have a cross-section large enough in relation to the supply cables from the
vessel. Otherwise the equipment might be damaged during welding.
• Electrical cables must be properly suspended and supported according to applicable regulations.
• Cable entries to cabinets must be sealed, using the built in cable glands. See instruction Cable
glands in system manual, chapter 7. Service manual.
• Cabling shall be done according to specification in Electrical system layout on page 89, and
the electrical drawings. Cabling must also be done according to rules regarding installations in
potentially explosive environments, for example IEC 60079 series. This includes cable routing,
cable types and cable marking to simplify identification and fault finding.
• Power cables shall be separated from signal and bus cables. Distance between them reduces
electrical noise transfer.
- If placed on a cable rack, place power and signal cables on opposite sides.
- If cables are routed in tubes due to narrow space, the power and signal cables shall be
routed in separate tubes.
• EMC: Cables shall be peeled down to the cable shield. The shield must be connected to earth.
W210.xx – Multi core cable for UVR components. Connection to lamp drive cabinet.
• Lamp power cable W211A-D (included in scope of supply) shall be connected from X3 in LDC to
X20:B in junction box on the UV reactor. Cables from junction box to lamps are pre-assembled.
Note: Lamp power cable dellivered from Alfa Laval must be used.
• The lamp power cable should not be winded. If it is to long, cut it before it is connected.
• Power cable W201.1 to be connected to main switch board: Max Icu 50 KA.
• Signal cables W210A and B to be connected from X1 in LDC to X20:A in junction box on the UV
reactor. Cables from junction box to components are pre-assembled.
Control cabinet
This section describes the Ex protection of PureBallast. It covers the components that are part of
the Ex protection and a description of the electrical system, including the safety control system.
This information is necessary to get a full understanding of the Ex protection and how it is installed.
The illustration and tables below includes all components that are part of the Ex protection, sorted
on UV reactor, filter, CIP module and pipe net.
• Design and installation must follow a Ex standard for eliminating the risk of explosion, for
example IEC 60079 series.
• The person installing PureBallast must have knowledge about the specific Ex standard used to
eliminate the risk of explosion, for example IEC 60079 series.
• The party responsible for the installation shall carry out an inspection to verify that the
installation is correct regarding the Ex protection.
Summary
PureBallast Ex is classed for use in zone 1 hazardous areas in accordance to the IEC 60079 series
of standards, explosion group IIC and temperature class T4 (135°). It fulfills the European Directive
ATEX 2014/34/EU recommended by the IMO for use in marine applications and the IECEx certified
equipment scheme. All components in the zone are certified.
To secure that the UV lamp quartz sleeves are cooled, there must always be water in the UV
reactor when the lamps are lit. This is secured by the use of a check valve and monitored by double
sensors for fluid level and temperature. If any value deviates, or if signal is missing, the control
system (or safety control system) will shut down the UV reactor immediately. The UV reactor (Exd)
is hermetic sealed from outer atmosphere and is made flameproof (Exd). The LDC is separated
from the UV reactor and placed in safe zone.
During normal operation, the control system monitors PureBallast automatically, based on input
from sensors, to secure safe function. In addition to the control system, a safety control system
(Exi) is used. It is separate from the control system, and therefore redundant to strengthen the
protection allowing one fault tolerance. If the normal control system fails, the safety control system
will shut down the system. The safe control system is based on safety relays and is hardwired.
8.1 Ex components
All components in zone 1 have been chosen to be compliant with the Ex requirements. The
illustration and tables below list all electrical components that are part of the Ex protection, sorted
on UV reactor, filter, CIP module and pipe net.
For detailed information, see the EC certificates in the Ex binder delivered with the system.
6 EX components
8.1.1 UV reactor
All components on the UV reactor are connected to the lamp drive cabinet (LDC). The LDC is
then connected to the control cabinet.
1 UV reactor UV reactor
– 2 Junction boxes
– Cable gland
5 QT201-50 UV sensor
– Barrier (smart repeater) installed in LDC
6 V320-4 Valves
V321-2
V404-36 – Actuator (air driven)
– Solenoid coil
– Sensor, inductive
– Barrier (isolating amplifier) installed in LDC
– Tank
– Junction box
– Cable gland
– Fuse
8.1.3 Filter
All components on the filter are connected to the control cabinet via the junction box.
– Flow sensors
– Cable gland
– Barrier for transmitter
– Junction box
– Cable gland
– Actuator
– Solenoid coil
– Switch box
– Cable gland
– Positioner
– Cable gland
– Barrier for sensor
17 V201-3 Valves
18 V201-9 – Actuator
– Solenoid coil
19 V201-32 – Switch box
– Cable gland
20 V212-31
21 V403-35
6 EX description 2
This system is based on safety relays and is hardwired to avoid the need of a separate validation of
the software. All function in the safety system is using redundancy to ensure one fault tolerance.
6 EX description 3
6 EX description 0
Normal operation includes thermal protection through a PT1000 element connected to the PLC via
distributed I/O. This circuit will shut down the LPSs by breaking the 24V DC control voltage feeding
them via K1 if the UV reactor reach a temperature of 60°C.
Below, the circuit for temperature control under normal operation is shown in red.
6 EX description 4
The safe control circuit for the UV reactor will only affect the UV reactor and not the other parts of
the system (e.g. filter and CIP unit) since their safety are not depending on it.
This circuit works as a separate system outside the normal control system deploying two different
functions to control the overheating. It is based on a certified safety controller.
• Temperature limiting circuit – controls that the UV reactor does not overheat.
• Level control circuit – controls that the UV reactor does not run dry.
A redundant temperature limiting circuit consisting of one temperature limit switch (TS) and one
PT1000 element (TT) connected to KS01 via intrinsically safe barriers (IS). This interlocks the LPSs
and if the temperature rises above either of the sensors limits (TT level 1 = 60°C, TT level 2 = 62.5
°C and TS = 65°C) the UV reactor is shut down.
The output is redundant by breaking contactor group Q1, Q2 and Q3 together with interrupting the
24V DC feed to the LPSs.
6 EX description 5
If the circuit is tripped, the Reset button S01 on the LDC door starts blinking. When the temperature
falls below 60 (the lowest value of the temperature transmitter and switch) the circuit is reinstalled
and the cabinet can be reset by pushing and releasing (negative edge) the Reset button S01.
6 EX description 6
A redundant level control circuit consisting of two level switches (LS201-29 and LS201-30)
connected to KS01 via intrinsically safe barriers (IS). These will shut down the LPS if the UV reactor
is empty for more than 9 seconds. The time of 9 seconds is long enough to allow air pockets in the
water, but not so long that any heat is produced.
If the circuit is tripped, an automatic reset will be performed when both level switches are activated
again and the input circuit is closed.
The output uses the same redundant structure as the temperature limit circuit. Below, the circuit is
highlighted red.
6 EX description 7
The global emergency stop circuit is designed to handle unexpected situations. It will shut down the
UV reactor the same way as the safety control circuit without any delays.
6 EX description 8
If global emergency stop is triggered, the PLC gets a high signal. This will in return execute
appropriate measures with all other actuators (e.g. filter and valves) in the system which does not
need to be safely disconnected by the emergency stop since their safety are not depending on it.
When triggered, the emergency stop is reset by pushing and releasing (negative edge) the Reset
button S11 on the control cabinet door.
Since the power contactors in each LDC (Q1, Q2 and Q3) are not monitored by the safety controller,
the feedback from them is connected to an input of the distributed I/O. This will indicate if one or
more contactors are erroneous, and the PLC will prohibit use of the system.
6 EX description 9
6 EX description 00
The safety control system of the UV reactor secures that there is water in the UV reactor before
power on.
This section contains information relevant for planning the installation and routing of instrument air
to the components that are pneumatically operated.
Instrument air shall be connected to the vessel’s instrument air system according to the following:
• Air distribution drawing: Layout and components requiring instrument air, including connection
dimensions.
• Connection list:
- Required pressure.
- Air consumption during operation and peak load (including time for peak load).
• Quality specification / Instrument air on page 95: The instrument air must be dry and clean
according to the quality specification. I not, components will be damaged and the system will
not work properly. If instrument air is not available, a solution must be implemented to achieve
air according to specification.
• Dimension drawings: Details and connection points.
Note:
This section contains information relevant for planning integration for controlling PureBallast and
signals for communication between PureBallast and external components, which are not part of
Alfa Laval’s scope of supply.
External bypass valves (if used) must be integrated to be logged by PureBallast event log. All other
interfaces are optional. Note that implemented options are tested during commissioning, wherefore
they shall be ready by that time.
Installation prerequisites:
• Remote control panel is mounted according to according to drawing Remote control panel /
Dimension drawing on page . Note the clearance area.
• Mounted at an optional location in safe zone.
• Cable requirement for communication cable (W501) depends on lengt between remote control
panel and control cabinet. See below:
Programming and integration shall be done according to the document Remote interface
implementation guide, which can be required from your local Alfa Laval sales office and Control
cabinet / Circuit diagram.
1. As a base for the integration, the Remote interface implementation guide (this document) should
be used. It contains all necessary information for the programming. Also chapter 2 and 3 from
the system manual contains valuable supplementary information.
2. Contact the automation firm in time to plan and realize the programming.
As a standard, we recommend that the customer integrate according to the list under heading
Required implementation. But consider if more functions should be implemented to get a more
user friendly system. Remember that later additions are always more expensive.
3. The integration should be tested by the automation firm according to the instruction under
heading Preliminary communication and signal test. This should be done before commissioning.
4. The implementation must be done at the time of the commissioning. This is necessary for
Alfa Laval to be able to test run the system from the ship’s control system as a part of the
commissioning.
The communication is either handled by the remote interface (if the option is integrated) or via
hardwires between the vessel’s ISCS and PureBallast’s control cabinet. It is also possible to use
hardwire, even if remote interface is integrated.
Signals are defined to handle all combinations of power step (amount of power) and function
(request, grant and run). More than one signal can be sent (or received) at the same time to
achieve, for example step 1 and 2 to request power for 3 UV reactors.
As an alternative, it is possible to use power step 4 (common) that always will be used, regardless
of the number of UV reactors used for a specific process. The common power is defined as the
number of installed UV reactor times the defined power consumption for one UV reactor.
After installation, the signals need to be tested. This is done by simulating signals from the control
system, page 1.4 Power request. See ststem manual, chapter 3. Operating instructions and control
system description, instruction Simulate power request.
The purpouse of external feed is to avoid cavitation by reducing the flow before it reaches
PureBallast so that flow does not have to be reduced by PureBallast’s control valve V201-8.
Normally when the flow is high, the flow is only reduced by V201-8. If V201-8 is closed to a high
degree, there is a risk for cavitation in the system with noise, vibration and wear of V201-8 as
consequences.
When external feed is used, PureBallast controll system will request increased/decreased flow. The
signal is intended to regulate the pump speed of a frequency controlled ballast water pump, but can
also be used to regulate opening and closing of a valve installed before PureBallast. The signal can
either be sent via remote interface (optional) or by a hardwired 4-20 mA external feed signal.
Valve V201-8 operates (open/closes) in a range between a parameter set value (p157) and 100 %,
where default is 70 %. Within this range, flow is regulated by V201-8 without cavitation.
Area 1 V201-8 (blue line) increases slowly until it is completely open. External feed signal
(black line) increases to let the valve end in a position where it can start controlling
the flow again.
Area 2 V201-8 closes to build up pressure (yellow) for a backflush. When a backflush
is triggered, the external feed control signal remain unchanged to secure flow
for the backflush.
pump, so that V201-8 can open. Less flow is needed after the backflush, since the
the filter is clean.
3 CalibExampleExtFeed
Many of these component signals must be activated in the control system page 5.2 – Main
parameters 2, except from External feed control. Output indicates signal from PureBallast and Input
indicates signal from ISCS.
Consider which signals that shall be used, to be able to plan cable routing and integration.
Installation requirements:
Note: A list of integrated signals shall be available at commissioning, to facilitate parameter settings
for Alfa Laval commissioning engineer.
Signal Explanation
Common alarm What: Output signal from PureBallast that there is an (any) active
(mandatory to be alarm. An alarm shuts down ongoing process.
integrated)
Why: Common alarm must be integrated to indicate alarm in
stations where PureBallast is monitored and controlled. Used
if remote control panels (optional) are used. If remote interface
(optional) is used, this is an alternative to alarm indication via remote
interface address 07:7.
External bypass 1, 2, 3 What: Input signal to PureBallast that an external bypass valve (not
is open part of Alfa Laval’s scope of supply).
All bypass cases must be logged in the event log. The event log
state the position of the bypass valve (open/close) and time for
status change, not the reason for opening the valve. The reason,
for example internal transfer, must be entered in the vessel’s ballast
water log book. If GPS signal is not integrated, the position must
also be entered in this log book.
Signal Explanation
Request ”Open What: Output signal from PureBallast to request opening of relevant
overboard valves” valves (not operated by PureBallast). After process is stopped, the
signal goes low to request that the valve are closed.
Feedback ”Overboard What: Input signal to PureBallast to confirm that relevant valves
valves are open” are open.
Request ”Start BW What: Output signal from PureBallast to request start of the ballast
pump” water pump. After process is stopped, the signal goes low to request
pump to be stopped.
Feedback ”Ballast water What: Input signal to PureBallast to confirm that the ballast pump
pump is running” is started.
Signal Explanation
Request ’’Start stripping What: Output signal from PureBallast to request start of stripping
pump’’ pump (not operated by PureBallast). After process is stopped, the
signal goes low to request that the pump is stopped.
Feed back “Stripping What: Input signal to PureBallast to confirm that the stripping pump
pump is running’’ is started.
LDC cooling water pump What: Output signal from PureBallast to request start of the LDC
(P401-1) cooling pump for line 401. Pump P401-1 is used during ballast,
deballast, pause and heeling mode.
UV reactor cooling water What: Output signal from PureBallast to request start of the UV
pump (P403-1) reactor cooling pump for line 403. Pump P403-1 is used during
start-up, ballast, deballast, pause and heeling mode.
Signal Explanation
Backflush pump What: Output signal from PureBallast to request start of the
(P309-1) backflush pump for line 309. Pump P309-1 is used during backflush
to established required flow in the pipe.
Heeling mode (internal What: Input signal to PureBallast to enter heeling mode. Equal to
transfer) pushing the Pause button in control system.
External system stop What: Input signal to PureBallast to shut down the system.
PureBallast running What: Output signal from PureBallast that a process is running.
10.6 GPS
It is possible to integrate signals from the vessel’s GPS to PureBallast. It is optional, but strongly
recommended to connect GPS. The information is used to stamp events in the Event log with GPS
position. Note that the IMO convention requires that it must be possible to verify position for ballast
water treatment activities.
The GPS is integrated according to drawing Control cabinet / Interconnection diagram and Control
cabinet / Circuit diagram.
Requirements: The GPS communication must use protocol NMEA-0183, version 4.00 and should
be connected to module X20IF1030 in the control cabinet.
• Serial: RS422
• Baud rate: 4800 bps
• Parity: None
• Bits/characters: 8
• Stop bits: 1
The position data shall be sent as messages according to RMC, GLL or GGA.
Note: If RMC is used, time and date in the control system is retrieved from vessel’s GPS.
Before a system is approved for usage and installation, a number of approvals are needed.
Alfa Laval will also obtain class type approval for PureBallast from the major classification societies.
These class type approvals shows that the system scope of supply meet respective class rule
requirements.
For retrofit installations, it is recommended that contact is established as soon as possible to get
the design documentation approved so that the approval process does not delay the progress of
installation, and to schedule an on board visit.
The design documents are to be submitted by the installing party or the ship owner, and should be
approved before the installation is begun. The classification society will reply in an Approval letter.
Each classification society has their own requirements regarding documents and information to
be submitted. Always check with the classification society in question to verify their specific
requirements.
It is recommended that the vessel specific documentation refers to the main drawings for PureBallast
(flowchart, electrical system layout etc, to clarify connections etc), or that they are attached.
The list below contains the documents normally required for approval:
An on board survey is also normally required by both the classification society and the flag
administration. Normally, the classification societies are recognized organizations by the flag
administration, wherefore the classification society cover both roles. Completed survey results
in an installation approval.
Note: The customer is responsible for final detailed inspection to ensure that the system is installed
according to IEC 60079 series.
The commissioning can also be coordinated and used as a part of the installation survey.
This section contains information relevant for planning the on board installation. Instructions on how
to mechanically install and adjust the components are included in the system manual, delivered
with the system.
• Before installing the system, read the system manual and follow the instructions in Design and
installation guide and system manual 7. Service manual.
• Always read and follow the documentation included in shipment of components and spare
parts regarding handling, safety and disposal.
• Handle the delivery with care in order not to damage the equipment or cause personal injuries.
NG
WARNI
!
• Components must be lifted using correct lifting tools (such as a forklift truck, a crane) and tackle
with a load capacity greater than the weight of the component.
• Any complementary lifting instructions must be followed.
• Components must be empty when lifted.
• The UV reactor, filter, CIP and control cabinet must be lifted according to the instructions in
the following sections.
12.2.1 UV reactor
Weight of UV reactor (empty): 560 kg. L=750 mm.
6 AOT Lift
12.2.2 Filter
Protect external components or remove from filter, under lifting.
A=950 mm.
6 FilterLift
12.2.4 Cabinets
Use intended lifting attachment at the top of the cabinet.
Control cabinet
Weight: 50 kg.
Center of gravity: A=500 mm. B=300 mm.
Protect the control panel screen when lifting the control cabinet.
6 CabinetLift
The actions below must be performed after installation, before system is put into operation. This is
important to avoid that the filter and the UV reactor is damaged by material from the ballast tanks
or remainders from the installation. These actions shall be performed both for new builds and
retrofit installations.
Before the system is operated the first time the actions below must be done.
NOTE
• All pipes leading to PureBallast must be well flushed to avoid that debris harm the filter and
UV reactor quartz sleeves.
• All ballast water tanks must be well cleaned before PureBallast is tested or put into operation.
This is valid both for new builds and retrofit installations.
First operation
• During the first operation, the filter shall be bypassed, to avoid that debris harms the filter
elements.
• We recommend that a strainer is used during the first operations, to avoid that debris harms
the system.
• The first time a tank is stripped, PureBallast must be bypassed, to avoid that debris harms
the system.
This section contains drawings for the PureBallast system. It is divided into three main parts:
• General drawings – overall and principle information for system layout (pipes, components,
electricity, air and water).
• Dimension drawing – detailed component information (dimensions, sizes etc).
• Electrical drawings – detailed electric information (circuit diagrams, cable lists etc).
See the Contents section at the beginning of this document to get an overview of included drawings.
573644
(15A)
(150A)
(32A)
(350A)
(32A)
(32A)
(32A)
(32A)
(32A)
(350A)
(350A)
(32A)
(50A)
9025605
9008504
9015785_Page_2
9015785_Page_3
9015785_Page_4
9015785_Page_5
9015785_Page_6
6+,36<67(0
9HVVHOFRQWUROV\VWHP (OHFWULFDOSRZHU
:
1RWH:$'$OID/DYDOFDEOHPXVWEHXVHG
GLVWULEXWLRQFHQWUDO
:
$ : 9$&+]SKDVH /'&Q:$'DUHV\VWHPVL]HGHSHQGHQW 3RZHUSHU/'&FDELQHWDQGUHFRPHQGHG:QFDEOHVL]H
: 895VL]H :$[ N:[PPð
: 895VL]H :$:%[ N:[PPð
: 895VL]H :$:%:&:'[ N:[PPð
5HPRWHFRQWUROSDQHOV : :
14.2
5HDFWRU
5HDFWRU
:$ :$
:% :%
& :& :&
:' :'
14.2.4 Electrical system layout (3 pages)
(6 ,1 287 (6 (6 ,1 287 (6
*1' *1'
9026486_1
:)
:
: :
:
'
: 1RWH,I/'&FRQQHFW
:WR/'&287
6DIH]RQH : :QRWQHHGHG
=RQH
(
:
:$ :%
: : :
: : : : : : : :$ :% : :
)
3XPSVRSWLRQDO
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
SDJH SDJH
(G 6(78)(1 3XUH%DOODVW([
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
(OHFWULFDOV\VWHPOD\RXW &XUUHQWSDJH
14
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
&DEOHRYHUYLHZ $OID:DOOB)B
$ 0LQFURVVVHFWLRQ
&DEOHQDPH 6RXUFHIURP 7DUJHWWR FDEOHW\SH DOOFRQGXFWRUV IXQFWLRQWH[W
>PP@
14
9026486_2
:& /'& 895 $/)$/$9$/ 0D[0
/'& 895
:' /'& 895 $/)$/$9$/ 0D[0
/'& 895
'
: && ),/7(5 3RZHUFDEOHDUPRXUHG TPYCY-1.5 ([G
: && ),/7(5 6LJQDOFDEOHVKLHOGHG TTYCYS-4 [ ([H
: && &,3 6LJQDOFDEOHVKLHOGHG
: && 5&3 /$1&$7H6KLHOGHGRUEHWWHU 0D[P
:) && 5&3 0XOWLPRGHILEHUXP ,IPRUHWKDQPXVHILEHUFDEOH
: && 6+,36<67(0 6LJQDOFDEOHVKLHOGHG [ 6DIH]RQH
: 6LJQDOFDEOHVKLHOGHG [
: && /'&(6 6LJQDOFDEOHVKLHOGHG
: /'&(6 /'&(6 6LJQDOFDEOHVKLHOGHG
( :$ && ),7 6LJQDOFDEOHVKLHOGHG TTYCS-1 [ ([G
:% 6LJQDOFDEOHVKLHOGHG MPYCS-2 2
[
: && 9 6LJQDOFDEOHVKLHOGHG ([H
General drawings
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
SDJH SDJH
(G 6(78)(1 3XUH%DOODVW([
14.2 $SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&XUUHQWSDJH
90
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
91
General drawings
&DEOHRYHUYLHZ $OID:DOOB)B
$ 0LQFURVVVHFWLRQ
&DEOHQDPH 6RXUFHIURP 7DUJHWWR FDEOHW\SH DOOFRQGXFWRUV IXQFWLRQWH[W
>PP@
: && 9 6LJQDOFDEOH ([H
14.2
%
&
9026486_3
'
(
)
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
SDJH SDJH
(G 6(78)(1 3XUH%DOODVW([
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&XUUHQWSDJH
14
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14.2 General drawings 14 Drawings
9010001
553407
590773
594956
14.2 General drawings 14 Drawings
14.3.2 Filter
Adaptor plate
9014866_01
14 Drawings 14.3 Dimension drawings including
technical data
9014866_02
9007179
V201-32
V403-35
9007181
9007177
9008462
9007183
9025960
9004842#3
128 590066 1
Book No.Rev 2017–09–01
14 Drawings 14.3 Dimension drawings including
technical data
590066 2
590066 3
9012102#3
9012094
9029115
9018092
9025768
9029122
9025772
9007280
'
&
$
%
(
)
'DWH
(;7 &&
6833/<9$&
/5 /5
[
/
0D[IXVH$
/6 /6
: 4
/
1DPH
/7 /7
/
&&
3( 3(
3(
3(
3(
2ULJLQDO
$SSU
(G
'DWH
6(78021$
6(78)(1
/'& &&
2*:+ 2*:+
2* 2*
*1:+ *1:+
&$7H6)873
5HSODFHPHQWRI
3XUH%DOODVW([
&211(&7,21
,17(5)$&(
%8 %8
),567/'&
:/$1
%8:+ %8:+
; ;
*1 *1
%1:+ %1:+
%1 %1
6+ 6+
6+
6+
5HSODFHGE\
/'& &&
2*:+ 2*:+
2* 2*
&XUUHQWSDJH
*1:+ *1:+
&$7H6)873
&211(&7,21
,17(5)$&(
%8 %8
:/$1
/$67/'&
%8:+ %8:+
; ;
*1 *1
,QWHUFRQQHFWLRQGLDJUDP
%1:+ %1:+
%1 %1
&&
6+ 6+
6+
6+
'RFXPHQW1R
&XVWRPHUGHVFULSWLRQ
&XUUHQWSDJH
&&
3%
SDJH
1H[W
141
Electrical drawings
&&
&&
&&
&&
&&
&&
$
;
;
;
3(
3(
3(
6RXUFHIURP
3( 3(
14.4
6+
6+
6+
%
:
[
[
[
:
:
&
[
[
[
6+
6+
6+
7DUJHWWR
3(
6+,36<67(0
6+,36<67(0
'
(;7
9
8
8
(
)
9 9 306,17(5)$&(
)(('%$&.)520 )(('%$&.72
&21752/&$%,1(7 &21752/&$%,1(7
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_23
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14.4 Electrical drawings 14 Drawings
SDJH
3UHY
'
&
$
%
(
)
'DWH
6+,36<67(0 &&
%%
;.
$
1DPH
&&
%%
;.
$
[
2ULJLQDO
$SSU
(G
'DWH
306,17(5)$&(
8 &&
:
%%
6(78021$
6(78)(1
[ ;.
$
&&
%%
;.
$
6+,36<67(0 &&
5HSODFHPHQWRI
3XUH%DOODVW([
8 ;
5HSODFHGE\
&&
6+ 6+
3(
3(
&XUUHQWSDJH
6+,36<67(0 &&
,QWHUFRQQHFWLRQGLDJUDP
&&
[
(;7(51$/
:
6,*1$/6
8 [ ;
'RFXPHQW1R
&XVWRPHUGHVFULSWLRQ
&&
6+ 6+
3(
3(
&XUUHQWSDJH
&&
3%
SDJH
1H[W
9028841_24
SDJH
3UHY
'
&
$
%
(
)
7DUJHWWR 6RXUFHIURP
0RGLILFDWLRQ
'DWH
6+,36<67(0 &&
%%
;.
$
1DPH
&&
%%
;.
$
2ULJLQDO
$SSU
(G
'DWH
&&
%%
6(78021$
6(78)(1
;.
$
&&
[
%%
;.
(;7(51$/
:
$
6,*1$/6
8 [ &&
5HSODFHPHQWRI
3XUH%DOODVW([
%%
;.
$
&&
%%
;.
$
&&
%%
;.
5HSODFHGE\
$
&&
%%
;.
$
&&
&XUUHQWSDJH
6+ 6+
3(
3(
,QWHUFRQQHFWLRQGLDJUDP
0 &&
[
),/7(502725
&&
/
:
0
/
0 [ ;
/
*1<( *1<(
3(
3(
'RFXPHQW1R
&XVWRPHUGHVFULSWLRQ
&XUUHQWSDJH
&&
3%
SDJH
1H[W
9028841_25
&&
&&
&&
&&
&&
&&
$
6:
;
14
;
;
3(
3(
6RXUFHIURP
3( 3( 3( 3( 6+ ,1 287
2*:+
*1:+
%1:+
%8:+
5;
7;
2*
*1
%1
%8
6+
6+
6+
$
$
$
$
%
%
%
%
&$7H6)873
[
:)
[[
:
[
:
:
&
[
2*:+
*1:+
%1:+
%8:+
5;
7;
2*
*1
%1
%8
6+
6+
6+
$
$
$
$
%
%
%
%
7DUJHWWR
'
&,3
&,3
5&3
5&3
&&
6:
6:
3(
3(
( ;
Electrical drawings
)
),/7(56,*1$/6 &,3&211(&7,21 5(027(&21752/3$1(/ 5(027(3$1(/
/$1&211(&7,21 237,&$/),%(5
&XUUHQWSDJH
&211(&7,21
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_26
&&
14.4
SDJH SDJH
144
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
145
Electrical drawings
&&
&&
&&
&&
&&
&&
&&
&&
$
;
;
;
3(
3(
;
;
;
6RXUFHIURP
6+
6+
6+
6+
6+
$
$
$
$
$
$
%
%
%
%
%
%
:$
:%
[[
[[
[[
[[
[
:
:
:
&
[
[
6+
6+
6+
6+
6+
$
$
$
$
$
$
%
%
%
%
%
%
7DUJHWWR
/'&
'
(;7
(;7
5,
5,
5,
),7
),7
;
;
;
;
(
)
*36,17(5)$&( 5(027(,17(5)$&( (0(5*(1&<6723/'& ),7 ),7
&211(&7,21 &211(&7,21 ([G ([G
237,21$/ 27,21$/
56
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_27
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14.4 Electrical drawings 14 Drawings
SDJH
3UHY
'
&
$
%
(
)
'DWH
(;7 &&
;
1DPH
&/26(23(1
&&
[
%%
: ;.
9
$
9
2ULJLQDO
$SSU
(G
'DWH
[
&&
%%
6(78021$
6(78)(1
;.
$
&&
6+ 6+
3(
3(
3(
5HSODFHPHQWRI
3XUH%DOODVW([
(;7 &&
$ [[ $
% :$ % 7
9
([L
9 [
&&
6+ 6+
3(
3(
5HSODFHGE\
(;7 &&
$ [[ $
%%
% :% % ;.
9
&/26(
$
&XUUHQWSDJH
9
[
&&
6+ 6+
3(
3(
3(
,QWHUFRQQHFWLRQGLDJUDP
&&
(;7 &&
;
&/26(23(1
&&
[
%%
: ;.
9
$
9 [
&&
'RFXPHQW1R
%%
;.
$
&&
6+ 6+
3(
3(
3(
&XVWRPHUGHVFULSWLRQ
&XUUHQWSDJH
&&
3%
SDJH
1H[W
9028841_28
&&
&&
&&
&&
&&
&&
&&
&&
&&
;.
;.
;
;
;
;
;
3(
3(
6RXUFHIURP
3( 3( 3( 3( %% $ %% $ 3(
14.4
*1<(
*1<(
*1<(
6+
6+
$
%
%
[[
:
:
:
:
:
[
[
[
[
&
[
[
*1<(
*1<(
*1<(
6+
6+
$
%
7DUJHWWR
/ / / 3( / / / 3( / / / 3( 3( 3(
3UHVV-%
0
0
0
'
(;7
9
;
0
0
0
(
)
0 0 0 37 9
6<67(035(6685( &/26(23(1
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_29
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
&&
&&
&&
&&
&&
&&
&&
$
;.
;.
;.
;.
14
;
3(
3(
6RXUFHIURP
%% $ %% $ 3( %% $ %% $ 3(
6+
6+
%
:
:
[
[
&
[
[
6+
6+
7DUJHWWR
3(
'
(;7
(;7
9
9
(
Electrical drawings
)
9 9
&/26(23(1 &/26(23(1
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_30
&&
14.4
SDJH SDJH
148
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
149
Electrical drawings
3RZHUFRQGXFWRUVVKDOOEHEODFN
,QVXODWHGHQGIHUUXOHVVKDOOEHXVHGXSWRPPð
PPðDQGXSXVHSLQRUULQJFDEOHOXJ
6WDQGDUG,3&:+0$$$&ODVV
$
6LJQDOFRQGXFWRUVVKDOOEHEOXHPPð
4 4 4
$ $ $
,! ,! ,! ,! ,! ,! ,! ,! ,!
&
&
'
14.4
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
%.
%.
%.
PPð
PPð
PPð
%.
%.
%.
%.
%.
%.
%.
%.
%.
%
PPð
PPð
PPð
%.
%.
%.
.
'
&
4
.
.
.
14.4.2 Control cabinet / Circuit diagram
)
.
.
.
7
7
7
$
&
&
PPð
PPð
PPð
PPð
*1<(
%.
%.
%.
'
:
(;732:(56833/< ;
3(
[
6833/<9$&
0D[IXVH$ /5 /6 /7 3(
3(
: *1<(
( [
0
)
),/7(502725 6833/< 6833/<
6833/< 0
0.6kW, 4P, 1.6A
&XUUHQWSDJH
%2267(53803
0
9'&32:(5
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
SDJH
&& SDJH
9028841_1
(G 6(78)(1 3XUH%DOODVW([ &&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&RQWUROFDELQHW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
4
$
$
$
.
.
.
$
4
$
4
14
PPð
PPð
PPð
%.
%.
%.
PPð
PPð
PPð
PPð
PPð
PPð
%.
%.
%.
%.
%.
%.
.6
%
%
. . .
' ' '
) ) ) ) ) ) )
$ $ $ & & & &
&
&
&
&
&
&
&
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
%.
%.
%.
%.
%.
%.
%.
%.
%.
$ $ $ $
. . . .
0 $ 0 $ 0 $ 0 $
;
'
3( 3( 3(
;
: *1<( : *1<( : *1<(
[ [ [
(
0 0 0
Electrical drawings
0
0
0
/ / / 3( / / / 3( / / / 3(
0
0 0
0 0
0
& % % %
& % % %
& % % %
' & & %
,1&/8'(',)%2267(53803237,21 ,1&/8'(',)%2267(53803237,21 ,1&/8'(',)%2267(53803237,21
)
%2267(53803 %2267(53803 %2267(53803 &21752/&,5& &21752/&,5& &21752/&,5& &21752/&,5&
0 0
&XUUHQWSDJH
9028841_2
150
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&RQWUROFDELQHW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14 Drawings 14.4 Electrical drawings
SDJH
3UHY
'
&
$
%
(
)
0RGLILFDWLRQ
3RZHUVXSSO\
4
4
4
XQLW
$
7
)
'DWH
3/&+0,6:,7&+
(OHFWURQLFIXVH
PPð PPð
/2$'
$&
6833/<
%8 %8
/
,&
6(75(6(7
67$786
$&
PPð
1DPH
*1'
/
1&
%8
$&
/
PPð
;
%8
%XVEDU
%XVEDU
PPð PPð
2ULJLQDO
$SSU
(G
'DWH
3(
*1<( *1<(
3(
$
3(
6(78021$
6(78)(1
23
'&2.
,,1
6:
5HSODFHPHQWRI
3XUH%DOODVW([
)
',*,7$/,2
(OHFWURQLFIXVH
6833/<
/2$'
,&
6(75(6(7
67$786
*1'
1&
;
%XVEDU
5HSODFHGE\
;
;
4 $
$ 23
; 7
&XUUHQWSDJH
9'&SRZHU
(OHFWURQLFIXVH
',*,7$/,2
/2$'
6833/<
6(75(6(7
&&
67$786
*1' $
1&
.6
;
)
&XVWRPHUGHVFULSWLRQ
(OHFWURQLFIXVH
([%$55,(5$1$/2*
/2$'
,&
6(75(6(7
6833/<
67$786
*1'
1&
;
;
;
7
(;7(51$/
6833/<
&XUUHQWSDJH
&&
;
3%
$
SDJH
1H[W
9028841_3
'
&
$
%
(
)
$
0RGLILFDWLRQ
% 5;&3
(
&38
'DWH
$
,)
,)
% 5;,)
(
3RZHUOLQN/'&
1DPH
$
% 5;,)
(
*36
2ULJLQDO
$SSU
(G
'DWH
$
6(78021$
6(78)(1
% 5;,)
)
,QVWDOOHGLIUHPRWHLQWHUIDFHRSWLRQ
$
% 5;',
)
5HSODFHPHQWRI
3XUH%DOODVW([
$
% 5;',
)
$
% 5;',
)
5HSODFHGE\
$
% 5;$,
)
$
&XUUHQWSDJH
% 5;$2
$
$
% 5;36
3/&OD\RXW
$
&&
$
% 5;'2
$
$
% 5;'2
$
'RFXPHQW1R
$
% 5;'2
$
$
&XVWRPHUGHVFULSWLRQ
% 5;'2
$
$
% 5;'2
$
$
% 5;'2
$
&XUUHQWSDJH
&&
3%
SDJH
1H[W
9028841_4
,1&/8'(',)5(027(&21752/3$1(/237,21
;
;
;
;
;
;
;
$
23
&RQWUROSDQHO 6: &20 9$ 9%
/DQ$ /DQ%
86% 86% ; ; ; ;
,1 287
14.4
7' 5'
86%
%
:)
:/$1 2SWLFILEHUFDEOHPXOWLPRGH
86%
&$7H6)873 FDEOH [P 5; 7;
'RRU
5; 7;
5&3
:)
&
&&
'
:/$1 &RQQHFWWR23/DQ$LIQRWUHPRWHSDQHORSWLRQ :/$1
&$7H6)873 &$7H6)873 FDEOH
;
$ ; ; ; ; ; ; ,) ,)
5-
& 9'& 9'& *1' 9'& 9'& *1' ,) ,)
6+
( (WKHUQHW (3/
,) ,)
:
;&3 ; &$7H6)873
86% 5(027(&21752/3$1(/
,),)
/$1&211(&7,21 2*:+ 2* *1:+ %8 %8:+ *1 %1:+ %1 6+
86%
5&3
:
)
86%
&&
'RRU
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
SDJH
&& SDJH
9028841_5
(G 6(78)(1 3XUH%DOODVW([ &&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&&38 &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
;
;
([:
([:
$
([/'&
([/'&
14
6+ 6+
%
2*:+
2*:+
*1:+
*1:+
%1:+
%1:+
%8:+
%8:+
:/$1 :/$1
2*
2*
*1
*1
%1
%1
%8
%8
&$7H6)873 &$7H6)873
&
; ;
6+ 6+
5- 5-
'
:/$1 :/$1
&$7H6)873 FDEOH &$7H6)873 FDEOH
(
Electrical drawings
$
&
(3/ (3/
,) ,)
) ;,)
),567/'&
,17(5)$&(
&211(&7,21
/$67/'&
,17(5)$&(
&211(&7,21
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
&&
14.4
SDJH SDJH
9028841_6
154
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&,QWHUIDFH &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
155
Electrical drawings
*36
,17(5)$&(
$
D E 6+
14.4
%
:
6LJQDO
FDEOH
VKLHOGHG
6+
$
%
[[
&
;
9,36&'68%0 6+'
6+'
'
:
&$%/('68%
(
$
& 6+/' 7;'5HV 5;''$7$ 5HV *1' 9P$ 7;'?5HV 5;'?'$7$ 5HV
) ;,)
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
SDJH
&& SDJH
9028841_7
(G 6(78)(1 3XUH%DOODVW([ &&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&*36LQWHUIDFH &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$
;
14
:
5,
%
6+
:
& 6LJQDO
FDEOH
VKLHOGHG
[[ $ $ % % 6+
; ,1&/8'(',)5(027(,17(5)$&(237,21
' 9,36&'68%0 6+'
6+
:
&$%/('68%
(
Electrical drawings
$
& 6+/' 7;' 5;' 5HV *1' 9P$ 7;'? 5;'? 5HV
5HV '$7$ 5HV '$7$
)
56
;,)
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
&&
14.4
SDJH SDJH
9028841_8
156
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&5,LQWHUIDFH &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
157
Electrical drawings
.6
)
;
;
$
14.4
%
4 ) ) ) )
$ & & & &
&
4
$
'
4
$
(
) ;',
6<67(06723)520
6$)(7<5(/$<.6
'&)86(
$/$50
06&2021
)86($/$50
0
$/$50
0
$/$50
0
$/$50
&XUUHQWSDJH
0
$/$50
(0(5*(1&<6723
5(/($6('
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
SDJH
&& SDJH
9028841_9
(G 6(78)(1 3XUH%DOODVW([ &&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDOLQSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
(;7
9
9
9
9
9 9 9 9 9
2SHQ 2SHQ 2SHQ 2SHQ
$
3(
3(
3(
3(
3(
2SHQ
&ORVH &ORVH &ORVH &ORVH &ORVH
%
: :% $ % : : : :
6LJQDO 6LJQDO 6LJQDO 6LJQDO 6LJQDO 6LJQDO
FDEOH FDEOH FDEOH FDEOH FDEOH FDEOH
VKLHOGHG VKLHOGHG VKLHOGHG VKLHOGHG VKLHOGHG VKLHOGHG
[ [[ [ [ [ [
;
;
;
;
;
;
;
;
&
; ;
&
; ;
%% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $
%% .
;
; .
%%
. . . . . . . . . . . .
'
%%
; .
%%
; ;
(
:
: (
Electrical drawings
9
&/26(23(1
9
&/26(
9
&/26(23(1
&XUUHQWSDJH
9
&/26(23(1
9
&/26(23(1
9
&/26(23(1
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_10
&&
14.4
SDJH SDJH
158
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDOLQSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
159
Electrical drawings
6+,36<67(0
(;$03/(&211(&7,21
$
14.4
%
: :
6LJQDO 6LJQDO
FDEOH FDEOH
VKLHOGHG VKLHOGHG
[ [
;
& ;
&
; ;
%% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $ %% $
%%
;.
.
. . . . . . . . . . . .
'
%%
.
;
;
(
: :
[PP <( *1 %8 97 [PP %. %1 5' 2* <( *1 %8 97
) ;',
(;7(51$/
6<67(06723
(;7(51$/
%<3$6623(1
(;7(51$/
%<3$6623(1
(;7(51$/
%<3$6623(1
(;7(51$/
)(('%$&.
%:3803581
(;7(51$/
)(('%$&.
29(5%2$5'
&XUUHQWSDJH
9$/9(23(1
+((/,1*02'( (;7(51$/
)(('%$&.
675,33,1*3803581
306
*5$17('
306
*5$17('
306,17(5)$&( 306
*5$17('
&20021
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_11
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDOLQSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
(;7 3UHVV-% (;7
),7 37 37 37
'&
$ *1' *1' *1'
'&
14
5'
6+
%.
FDEOHVFUHHQWR FDEOHVFUHHQWR
EHLQVXODWHG EHLQVXODWHG : :
; 3( 6LJQDO 6LJQDO
%
FDEOH FDEOH
5'
5'
6+
6+
%.
%.
[ [
),/7(5-%
;
3( 3(
&
'
:$ $ % :% $ % : % $ : $ % $ %
6LJQDO 6LJQDO 6LJQDO 6LJQDO
FDEOH FDEOH FDEOH FDEOH
VKLHOGHG VKLHOGHG VKLHOGHG VKLHOGHG
[[ [[ [[ [[
; ;
;
;
;
(
Electrical drawings
;
$
& $,, $,8 $,8, $,, $,8 $,8, $,, $,8 $,8, $,, $,8 $,8,
) ;$,
),7
6<67(0:$7(5)/2:
37
6<67(035(6685(
&XUUHQWSDJH
37
35(6685(6(1625
),/7(5
37
35(6685(6(1625
),/7(5
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_12
&&
14.4
SDJH SDJH
160
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&$QDORJLQSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
161
Electrical drawings
$ $ ;$2
&
$2, $28 $28, $2, $28 $28,
14.4
%
;
;
7
7 ,1 9 *1' 7
7 7
P$
7 7
7 287 7
&
:$ $ %
6LJQDO
FDEOH
VKLHOGHG
[[
'
(
(;7
) EHLQVXODWHG
9
&21752/9$/9(
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_13
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&$QDORJRXWSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$ $ ;36
&
14
.
% '
.6
6 6
&
&
%
&
.6 .6 .
% % '
;
&
[
;
6 .
' [ '
.
' (6
; 3(
$
;
'
:
6LJQDO
FDEOH 6
VKLHOGHG
&
[ 6+
;(6
2*
2*
6+
(
;
;
([/'&
Electrical drawings
([:
;
;
;
)
32:(5
6833/<
(0(5*(1&<6723
/'&&$%,1(7
6,*1$/
723/&
,1',&$7,21
(675,33('
&XUUHQWSDJH
(0(5*(1&<6723
5(6(7
32:(5
6833/<
(0(5*(1&<6723
&,5&8,7
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_14
&&
14.4
SDJH SDJH
162
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&3RZHUVXSSO\ &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
163
Electrical drawings
$ $ ;'2
&
'2 '2 '2 '2 '2 '2 '2 '2 '2 '2 '2 '2
PLQPPð
14.4
%
;
;
; 3( 3(
5'
0
0
)DQ
&
%/
+
;
[ [
[
'
:
6LJQDO
FDEOH
VKLHOGHG
[
PLQPPð
(
&,3
) ) ) ) ) ) ) ) )
3( 3(
.6
;
Drawings
)
9028841_15
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDORXWSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$ $ ;'2
&
14
12 &20 12 &20 12 &20 12 &20 12 &20 12 &20
%
;
&
3(
3(
'
:
6LJQDO
FDEOH
VKLHOGHG
[
(
Electrical drawings
6+,36<67(0
)
306
5(4
306
5(4
306
5(4
&XUUHQWSDJH
306
5(4
&20021
306
581
306
581
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_16
&&
14.4
SDJH SDJH
164
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDORXWSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
165
Electrical drawings
$ $ ;'2
&
12 &20 12 &20 12 &20 12 &20 12 &20 12 &20
14.4
%
;
;
&
'
:
6LJQDO
FDEOH
VKLHOGHG
[
(
9
9
9
9
9
9
9
9
6+,36<67(0
Drawings
)
306
581
306
581
&20021
9
&XUUHQWSDJH
9028841_17
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDORXWSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$ $ ;'2
&
14
12 &20 12 &20 12 &20 12 &20 12 &20 12 &20
$
%
;
; ;
&
3(
3(
:
6LJQDO
FDEOH
VKLHOGHG
[[ % $
'
:
),/7(5-%
;
6LJQDO
FDEOH
VKLHOGHG
[
(
Electrical drawings
(;79
)
6+,36<67(0
),/7(5
%$&.:$6+
9$/9(
&XUUHQWSDJH
&20021
:$51,1*
&20021
$/$50
5(48(67/'&
%2267(53
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_18
&&
14.4
SDJH SDJH
166
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDORXWSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
167
Electrical drawings
$ $ ;'2
&
12 &20 12 &20 12 &20 12 &20 12 &20 12 &20
14.4
%
;
&
'
: :
6LJQDO
FDEOH
VKLHOGHG
[
(
6+,36<67(0
Drawings
)
5(48(67895
%2267(53
5(48(6767$57
%:3803
5(48(67
23(129(5%2$5'
9$/9(
&XUUHQWSDJH
385(%$//$67
5811,1*
5(48(6767$57
675,33,1*3803
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_19
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDORXWSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$ $ ;'2
&
14
$ &20 $ &20 $ &20 $ &20 $ &20 $ &20
%
;
.6
%
&
:
6LJQDO
FDEOH
VKLHOGHG
'
[
;
)
)
)
(
Electrical drawings
6+,36<67(0
)
5(48(67),/7(5
%$&.)/3
&XUUHQWSDJH
9028841_20
&&
14.4
SDJH SDJH
168
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDORXWSXW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
169
Electrical drawings
$
14.4
%
;.
;.
;.
;.
&
;
'
: :
6LJQDO 6LJQDO
FDEOH FDEOH
VKLHOGHG VKLHOGHG
[ [
(;7 6+,36<67(0
9
3(
2SHQ
(
&ORVHG
3(
2SHQ
)
9 9 9
&/26(23(1 )(('%$&.72 )(('%$&.)520
&21752/&$%,1(7 &21752/&$%,1(7
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 3% 1H[W
9028841_21
SDJH
(G 6(78)(1 3XUH%DOODVW([ && &&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
%\SDVVFRQWURO%\SDVVYDOYHFRQQHFWLRQ &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$OID:DOOB)B
WRWKHH[WHQWH[SUHVVO\DJUHHGXSRQ
7KLVGRFXPHQWPD\FRQVWLWXWHD
FRQWUDFWXDOREOLJDWLRQRQWKH
&DEOHVXVHGVKRXOGEHVKLSERDUGFDEOHVGHVLJQHG
SDUWRI$OID/DYDO$%RQO\
$
14
%
: [ && ;. 6+,36<67(0 8 [ SURGXFHUV1H[DQV6ZHGHQ
7KLVGRFXPHQWDQGLWVFRQWHQWVLVRZQHGE\$OID/DYDO$%SXEODQGSURWHFWHGE\ODZVJRYHUQLQJLQWHOOHFWXDOSURSHUW\DQGWKHUHWRUHODWHGULJKWV:LWKRXWOLPLWLQJDQ\ULJKWV
9028841_31
14.4
SDJH
&& SDJH
170
(G 6(78)(1 3XUH%DOODVW([ &&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&DEOHOLVW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14 Drawings 14.4 Electrical drawings
'
&
$
%
(
)
'DWH
(;7 /'&
/5 /5
[
/
/
32:(56833/<
/6 /6
: 4
/
/
1DPH
/7 /7
/
/
/'&
3( 3(
3(
3(
3(
2ULJLQDO
$SSU
(G
'DWH
6(78021$
6(78021$
$27 /'&
5HSODFHPHQWRI
3XUH%DOODVWSURMHFW([
(3/$1
[
([L&$%/(
;([L :$ ;
5HSODFHGE\
3(
3(
3(
3(
$27 /'&
6+ 6+
3(
;([L 3(
&XUUHQWSDJH
$27 /'&
,QWHUFRQQHFWLRQGLDJUDP
/'&
[
([L&$%/(
;([L :% ;
([
'RFXPHQW1R
3(
3(
3(
3(
$27 /'&
6+ 6+
3(
;([L 3(
&XVWRPHUGHVFULSWLRQ
$27 /'&
[
([H&$%/(
:&
;([H ;
7RWDOQRRISDJHV
/'&
3%
SDJH
1H[W
9015565_18
/'&E
/'&D
14
/'&
/'&
/'&
$27
$27
$
-%%
-%%
;
;
;
;
3(
6RXUFHIURP
3( 3( 3(
6+
6+
6+
%
:&
:$
:&
:%
[
[
[
[
&
6+
6+
6+
7DUJHWWR
3( 3( 3(
'
/'&
/'&
$27
$27
$27
$27
$27
;([H
;%
;%
;%
-%$
3(
3(
(
Electrical drawings
)
([H&$%/( /$03&$%/( /$03&$%/( /$03&$%/(
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_19
14.4 /'& ([
SDJH SDJH
172
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
173
Electrical drawings
/'&E
/'&E
/'&
$27
$27
$
-%%
-%%
;
;
;
6RXUFHIURP
14.4
3( 3( 3(
6+
6+
6+
6+
%
:'
:&
:
[
[
[
&
6+
6+
6+
6+
7DUJHWWR
3( 3( 3(
/'&E
/'&D
/'&
'
$27
$27
;%
;%
3(
3(
;
;
(
)
/$03&$%/( /$03&$%/(
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_20
SDJH
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'& ([ /'&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
6LJQDOFRQGXFWRUVVKDOOEH
EOXHPPð
; / / / /
6XSSO\EORFN / / / /
$
/ / / /
14
/ /
PPð
PPð
PPð
/ /
%.
%.
%.
/ /
4 4 4
,!! ,!! ,!! ) ) ,!! ,!! ,!! ,!! ,!! ,!!
3(
%
14.4.6 Lamp Drive Cabinet (LDC) / Circuit diagram
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
=
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
%.
/
/
/
%.
%.
%.
(0&ILOWHU
*1<(
/2$'
/,1(
/ / /
&
7
7
7
; 8 9 : 3(
PPð
PPð
PPð
%.
%.
%.
*1<(
. . .
' . ( (
0 ./
3(
4 )DQ
;7 )
PPð
PPð
PPð
/ / / SKDVH
%.
%.
%.
/, 0 0
W V a
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
'
%.
%.
%.
%.
%.
%.
%.
%.
%.
6,
W V
$ $ $
,,
/2& . . .
& & &
$ $ $
PPð
PPð
PPð
%.
%.
%.
/ / /
./ ./
.
1& &20 *1' 9
( : )
%8
<(
(;732:(56833/<
[
Electrical drawings
32:(56833/< /5 /6 /7 3(
;
(;7
/ / / 3(
9$&
;
;
;
;
;
;
;
;
;
+]SKDVH
E
E
E
D
D
D
(OHFWULFDOSRZHU
GLVWULEXWLRQFHQWUDO
4
4
4
$
;
$
$
4
4
4
4
4
4
)
5&3
6833/<9$& 6833/<
44
&XUUHQWSDJH
)$1&,5&8,7 6833/<
44
6833/<
44
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
14.4
SDJH
/'& ([ SDJH
9015565_1
174
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3RZHUVXSSO\ODPSGULYHFDELQHW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
175
Electrical drawings
;
.
;
.
;
.
$
/ / /
/ / /
/ / /
4 4 4
$ $ $
14.4
,! ,! ,! ,! ,! ,! ,! ,! ,!
%
%
&
3( 3( 3(
%
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
*1<(
*1<(
*1<(
:+
:+
:+
%1
%1
%1
%.
%.
%.
: : :
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
*1<(
*1<(
*1<(
&
:+
:+
:+
%1
%1
%1
%.
%.
%.
/36 /36 /36 /36 /36 /36
$ / / / 3( $ / / / 3( $ / / / 3( $ / / / 3( $ / / / 3( $ / / / 3(
/DPS ,1387 /DPS ,1387 /DPS ,1387 /DPS ,1387 /DPS ,1387 /DPS ,1387
SRZHU SRZHU SRZHU SRZHU SRZHU SRZHU
VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387
3( 3( 3( 3( 3( 3(
'
: : : : : :
/36 /36 /36 /36 /36 /36
[ [ [ [ [ [
(
;
;
;
;
;
;
;
;
;
D
D
D
D
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
Drawings
)
$
$27 ;%
&XUUHQWSDJH
%
$27 ;%
D
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
SDJH
/'& ([ SDJH
9015565_2
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3RZHUVXSSO\ODPSGULYHFDELQHW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
;
.
;
.
;
.
$
14
4 4
$ $
,! ,! ,! ,! ,! ,!
&
3( 3( &
%
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
*1<(
*1<(
:+
:+
%1
%1
%.
%.
: :
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
*1<(
*1<(
&
:+
:+
%1
%1
%.
%.
/36 /36 /36 /36
$ / / / 3( $ / / / 3( $ / / / 3( $ / / / 3(
/DPS ,1387 /DPS ,1387 /DPS ,1387 /DPS ,1387
SRZHU SRZHU SRZHU SRZHU
VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387
3( 3( 3( 3(
'
: : : :
/36 /36 /36 /36
[ [ [ [
(
;
Electrical drawings
;
;
;
;
;
;
;
;
;
;
;
;
E
E
E
E
;%
;%
;%
;%
:&
/36FDEOH
[
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
)
D
&XUUHQWSDJH
&
$27 ;%
E
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
14.4
SDJH
/'& ([ SDJH
9015565_3
176
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3RZHUVXSSO\ODPSGULYHFDELQHW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
177
Electrical drawings
;
.
;
.
;
.
$
4 4 4
$ $ $
14.4
,! ,! ,! ,! ,! ,! ,! ,! ,!
'
'
'
3( 3( 3(
%
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
*1<(
*1<(
*1<(
:+
:+
:+
%1
%1
%1
%.
%.
%.
: : :
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
PPð
*1<(
*1<(
*1<(
&
:+
:+
:+
%1
%1
%1
%.
%.
%.
/36 /36 /36 /36 /36 /36
$ / / / 3( $ / / / 3( $ / / / 3( $ / / / 3( $ / / / 3( $ / / / 3(
/DPS ,1387 /DPS ,1387 /DPS ,1387 /DPS ,1387 /DPS ,1387 /DPS ,1387
SRZHU SRZHU SRZHU SRZHU SRZHU SRZHU
VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387 VXSSO\ 287387
3( 3( 3( 3( 3( 3(
'
: : : : : :
/36 /36 /36 /36 /36 /36
[ [ [ [ [ [
(
;
;
;
;
;
D
D
D
D
;%
;%
;%
:'
/36FDEOH
[
/$03
/$03
/$03
/$03
/$03
/$03
/$03
/$03
Drawings
)
D
E
&XUUHQWSDJH
'
$27 ;%
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
SDJH
/'& ([ SDJH
9015565_4
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3RZHUVXSSO\ODPSGULYHFDELQHW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14.4 Electrical drawings 14 Drawings
SDJH
3UHY
'
&
$
%
(
)
E
0RGLILFDWLRQ
)
)
)
$
7
:$
VKLHOGHG
[
)
6LJQDO
FDEOH
PPð
'DWH
(OHFWURQLFIXVH
;
$&
%8
/
77 /2$'
7
,&
6(75(6(7
$&
/
77 67$786
7 *1' PPð
$&
1&
%8
1DPH
/
77
7
77
%XVEDU
%XVEDU
7
;
3(
3(
76
7
2ULJLQDO
$SSU
(G
'DWH
3(
$
76
$27 ;([L
7
$
6(78021$
6(78021$
.6
47
7
XQLW
3RZHUVXSSO\
'&2.
47 .
7
,,1
/6
7
/6
7
;([L
5HSODFHPHQWRI
3XUH%DOODVWSURMHFW([
(3/$1
3( 3(
;([L
;
PPð
%8
$
[
[
'RRU
32:(521
:KLWH
+
[
.
6LJQDO
FDEOH
/6
7
/6
7
.
9*6
7
.
9*6
7
.6
9*6
7
&XUUHQWSDJH
/36
9*6
$27 ;([L
7
%
.
)
9*6
7
7
(OHFWURQLFIXVH
9*6
7
/2$'
9'&SRZHU
,&
67$786
*1'
9*6 1&
7
;([L
3( 3(
;([L
;
$
([
4
/6
:&
VKLHOGHG
'RFXPHQW1R
[
6LJQDO
.
FDEOH
;
9
$
$
9
$
$ ;
$ .
&
+
9
9
9
7RWDOQRRISDJHV
/'&
9
3%
9
SDJH
1H[W
9015565_5
$
14.4
% 5;'2
% 5;$2
% 5;%&
% 5;&6
% 5;$7
% 5;36
% 5;',
% 5;',
% 5;$,
$
$
)
)
$
(
)
)
)
$
$
$
$
$
$
$
$
$
&
,)
,)
'
(
)
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
SDJH
/'& ([ SDJH
9015565_6
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&OD\RXW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
&&
;
;
:
:
$
&&
&&
14
6+ 6+
%
2*:+
2*:+
*1:+
*1:+
%1:+
%1:+
%8:+
%8:+
:/$1 :/$1
2*
2*
*1
*1
%1
%1
%8
%8
&$7H6)873 &$7H6)873
&
; ;
6+ 6+
5- 5-
'
:/$1 :/$1
&$7H6)873 &$7H6)873
(
Electrical drawings
$
& 5- 5-
(3/ (3/
,) ,)
) ;%&
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
14.4
SDJH
/'& ([ SDJH
9015565_7
180
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&%XV 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
181
Electrical drawings
&
$
;36
$
9%&;;/ 9%&;;/ *1' 9,2 9,2 *1'
14.4
%
&
'
(
;
;
;
Drawings
)
3/&32:(5 3/&
6833/< &20021
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
SDJH
/'& ([ SDJH
9015565_8
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&3RZHUVXSSO\ 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
/36 /36 /36 /36 /36 /36 /36 /36 /36 /36 /36 /36 /36 /36 /36 /36
E& E& E& E& E& E& D& D& & & & & & & D& D&
:+
:+
$
*1' %1
*1' %1
14
*1
*1
/36
<(
<(
.
% '
.
(
&
.
)
'
;
;
(
: :+ *1' %1
Electrical drawings
$
& 7[' 5[' *1' 7[' 5[' *1'
) ;&6 56
02'%86
&211(&7,21
/36
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
14.4
SDJH
/'& ([ SDJH
9015565_9
182
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&,QWHUIDFH 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
183
Electrical drawings
;
;
;
$
14.4
4
%
:
% /6
,
4 ,,
% 0ƻ
& 4
D%
4
D%
4
E%
'
4
E%
4
E%
.6
.6
)
;
(
9015565_10
SDJH
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'& ([ /'&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDOLQSXW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
;
;
;
;
;
;
;
;
$
14
.6
7
& ;
.
' &
.
&
(
.
Electrical drawings
&
$ ;
& ( ( ( ( ( ( ( (
', ', ', ', ', ', ', ',
)
;', 0XOWLOLQH ;
923(1 9&/26( 923(1 9&/26(
)(('%$&.
&217$&7256 /6 76 )$8/7
&XUUHQWSDJH
%$55,(5
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_11
14.4
SDJH
/'& ([ SDJH
184
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDOLQSXW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
185
Electrical drawings
&
$
$
;'2
'2 '2 '2 '2 '2 '2 '2 '2 '2 '2 '2 '2
14.4
%
&
;
'
: %8 %.
0
.
$ [ +HDW
H[FKDQJH
. +
YDOYH
& $ *UHHQ [
/$0321
'RRU
(
Drawings
;
+
6
;
;
;
;
;
;
)
$&7,9$7(/36 89/$0321 62/(12,'9$/9( 9 9 9
&XUUHQWSDJH
9 9
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_12
SDJH
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'& ([ /'&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&'LJLWDORXWSXW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
;
;
$
14
7 7
)DXOWRXW 7
7 ,1 7
, 7
7 7
*1' 9 *1' 9 7
7 287 9 *1' 7
%
$
;
7
;
&
'
(
Electrical drawings
$
& $,, $,8 $,8, $,, $,8 $,8, $,, $,8 $,8, $,, $,8 $,8,
) ;$,
896(1625
,1387
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_13
14.4
SDJH
/'& ([ SDJH
186
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&$QDORJLQSXW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
187
Electrical drawings
$ $ ;$2
&
$2, $28 $28, $2, $28 $28, $2, $28 $28, $2, $28 $28,
14.4
%
&
'
(
;
Drawings
)
)$1&21752/
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_14
SDJH
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'& ([ /'&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&$QDORJRXWSXW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
;
;
;
;
$
14
9'&
7
9 /)
Nj&
%
/)
&
7
7
. 287
77 77
[ [ [ [ 3:5
9'&
'
; $ % 3(
:
[ :+ 5'
;
;
.6
.6
(
Electrical drawings
$
& 6HQVRU 6HQVH 6HQVRU 6HQVRU 6HQVH 6HQVRU 6HQVRU 6HQVH 6HQVRU 6HQVRU 6HQVH 6HQVRU
) ;$7
/'&$,5 /'&+($7(;&+$1*( $27
7(03(5$785( :$7(57(03
&XUUHQWSDJH
7(03(5$785(,1387
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_15
14.4
SDJH
/'& ([ SDJH
188
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3/&7HPSLQSXW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
189
Electrical drawings
;
;
;
;
;
;
$
7 7 7
7 ,1 9 *1' 7
7 ,1 9 *1' 7
7 ,1 9 *1' 7
7 1$085 7
7 1$085 7
7 1$085 7
7 287 287 , 7
7 287 287 , 7
7 287 287 , 7
7 ,, 7
7 ,, 7
7 ,, 7
14.4
7 287 287 7
7 287 287 7
7 287 287 7
%
.
.
;
;
&
.6 77 76 /6 /6
$ $ $ $ 9 9 2 2 7 7 7 7 , , , ,
$
.
'
% $
, , , , 0 0 0 0 2 2 2 2
76 76 /6 /6
; 3(
(
.
'
: 6+ : 6+
'RRU
6+
Drawings
)
&&
$
$
$
$
:
&& ; ; 3(
+
;
;
+
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
9015565_16
SDJH
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'& ([ /'&
SDJH
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
6DIHW\UHOD\FLUFXLW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$OID:DOOB)B
WRWKHH[WHQWH[SUHVVO\DJUHHGXSRQ
7KLVGRFXPHQWPD\FRQVWLWXWHD
FRQWUDFWXDOREOLJDWLRQRQWKH
&DEOHVXVHGVKRXOGEHVKLSERDUGFDEOHVGHVLJQHG
SDUWRI$OID/DYDO$%RQO\
$
14
%
: [ /'& ; 66& /'& ; [ SURGXFHUV1H[DQV6ZHGHQ
7KLVGRFXPHQWDQGLWVFRQWHQWVLVRZQHGE\$OID/DYDO$%SXEODQGSURWHFWHGE\ODZVJRYHUQLQJLQWHOOHFWXDOSURSHUW\DQGWKHUHWRUHODWHGULJKWV:LWKRXWOLPLWLQJDQ\ULJKWV
:KHUH66&LVLQGLFDWHGLWVKRXOGEHDVLJQDOVKLHOGHGFDEOH
UHODWHGWRWKLVGRFXPHQWQRSDUWRIWKLVPD\EHFRSLHGUHSURGXFHGRUWUDQVPLWWHGLQDQ\IRUPRUE\DQ\PHDQVHOHFWURQLFPHFKDQLFDOSKRWRFRS\LQJUHFRUGLQJRU
ZLWKWKHVKLHOGSURSHUO\FRQQHFWHGWRHDUWKDVVKRZQLQWKH
HOHFWULFDOGUDZLQJV
14.4.7 Lamp Drive Cabinet (LDC) / Cable list
&
[&DEOHQRWLQFOXGHGLQWKH$OID/DYDOGHOLYHU\
'
(
5(0$5.6
WKHVHHNLQJRIFULPLQDOSURVHFXWLRQ
Electrical drawings
9015565_21
14.4
SDJH
/'& ([ SDJH
190
(G 6(78021$ 3XUH%DOODVWSURMHFW([ /'&
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&DEOHOLVW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14 Drawings 14.4 Electrical drawings
'
&
$
%
(
)
'DWH
%U %O 3(
:
9$/9(
9
;([H
1DPH
*1<( *1<(
3(
6+ 6+
3(
2ULJLQDO
$SSU
(G
'DWH
6(78021$
6(78021$
$27 $27
%1 [ %1
23(1&/26(
)(('%$&.
:*6
9
:+ :+
9*6 %8 %8 ;([L
%. %.
5HSODFHPHQWRI
3XUH%DOODVWSURMHFW([
(3/$1
$27
6+ 6+
3(
;([L
$27 [ $27
%U %O 3(
:
5HSODFHGE\
9$/9(
9
*1<( *1<( ;([H
3(
6+ 6+
3(
&XUUHQWSDJH
$27 $27
%1 [ %1
23(1&/26(
)(('%$&.
:*6
9
:+ :+
,QWHUFRQQHFWLRQGLDJUDP
9*6 %8 %8 ;([L
$27
%. %.
$27
6+ 6+
3(
;([L
([
$27 $27
[
'RFXPHQW1R
/(9(/6:,7&+
%1 %1
:
/6
:+ :+
/6 %8 %8 ;([L
%. %.
&XVWRPHUGHVFULSWLRQ
$27
6+ 6+
3(
;([L
[
/(9(/6:,7&+
:
/6
$27 $27
%1 %1
/6 ;([L
:+ :+
%8 %8
7RWDOQRRISDJHV
$27
3%
SDJH
1H[W
'
&
$
%
(
)
[
/(9(/6:,7&+
'DWH
:
/6
$27 $27
%. %.
/6 ;([L
$27
1DPH
6+ 6+
3(
;([L
2ULJLQDO
$SSU
(G
'DWH
$27 $27
6(78021$
6(78021$
%1 [ %1
75$160,77(5
:
77
:+ :+
7(03
77 %8 %8 ;([L
%. %.
$27
5HSODFHPHQWRI
3XUH%DOODVWSURMHFW([
(3/$1
6+ 6+
3(
;([L
$27 $27
%1 [ %1
:
77
6(1625
:+ :+
5HSODFHGE\
89
47 %8 %8 ;([L
%. %.
$27
6+ 6+
3(
;([L
&XUUHQWSDJH
[
$27 $27
:
76
6:,7&+
%1 %1
7(03
,QWHUFRQQHFWLRQGLDJUDP
76 :+ :+ ;([L
$27
%8 %8
%. %.
$27
6+ 6+
3(
;([L
([
%U %O 3(
:
9$/9(
9
*1<( *1<( ;([H
3(
6+ 6+
3(
&XVWRPHUGHVFULSWLRQ
:
9$/9(
9
*1<( *1<( ;([H
3(
6+ 6+
3(
7RWDOQRRISDJHV
$27
3%
SDJH
1H[W
9015566_5
$27
$
;([H
6RXUFHIURP
14.4
3( 3(
*1<(
6+
%
:
[
&
*1<(
6+
7DUJHWWR
%U %O 3(
'
$27
9
)
9$/9(
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
SDJH
$27 ([ SDJH
9015566_6
(G 6(78021$ 3XUH%DOODVWSURMHFW([ $27
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
;
;
;
;
/'&$
/'&%
/'&&
/'&'
/'&
/'&
/'&D
/'&E
$
14
-%%
% ;%
:$
:$
:$
:$
:$
:$
:$
:$
:$
:$
:$
:$
:$
:$
:$
:$
:%
:%
:%
:%
:%
:%
:%
:%
:%
:%
:%
:%
:%
:%
:%
:%
&
14.4.9 UV reactor / Circuit diagram
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
'
% % % % % % % % % % % % % % % %
/$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03 /$03
(
Electrical drawings
)
/'&
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
14.4
SDJH
$27 ([ SDJH
9015566_1
194
(G 6(78021$ 3XUH%DOODVWSURMHFW([ $27
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
3RZHUVXSSO\$27 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
195
Electrical drawings
/'&
;
;
$
%
/'&
/'&
$
-%$
14.4
3( 3( 3( 3( 3( 3( 3(
% ;([L 3( 3( 3( 3(
FDEOHVFUHHQWR FDEOHVFUHHQWR
EHLQVXODWHG EHLQVXODWHG
6+ 6+ 6+ 6+ 6+ 6+ 6+
&
: %1 :+ %8 %. : %1 :+ : %1 :+ %8 %. : %1 %. : %1 %. :*6 %1 :+ %8 %. :*6 %1 :+ %8 %.
0)66+ 0)66+ 0)66+ 0)66+ 0)66+ 0)66+ 0)66+
[ [ [ [ [ [ [
'
(
77 76 47 /6 /6 9*6 9*6
%1 %. %1 %. / / 2XW 2XW / / 2XW 2XW
/ 2XW / 2XW
)
7(03(5$785( 7(03(5$785( 89 /(9(/6:,7&+ /(9(/6:,7&+ 23(1&/26( 23(1&/26(
75$160,77(5
77
6:,7&+
76
6(1625
47
/6
&XUUHQWSDJH
/6 )(('%$&.
9
)(('%$&.
9
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
SDJH
$27 ([ SDJH
9015566_2
(G 6(78021$ 3XUH%DOODVWSURMHFW([ $27
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&RQWUROFLUFXLW$27$ 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
;
/'&
&
/'&
$
14
-%$
;([H 3( 3( 3( 3( 3( 3( 3( 3( 3( 3(
%
[ + [ +
*UHHQ :KLWH
[ /$0321 [ 32:(521
&
' : *1<( 6+ : *1<( 6+ : *1<( 6+ : *1<( 6+ : *1<( 6+
[ [ [ [ [
(
9 9 9 9 9
Electrical drawings
%U %O 3( %U %O 3( %U %O 3( %U %O 3( %U %O 3(
)
9$/9( 9$/9( 9$/9( 9$/9( 9$/9(
9 9 9 9 9
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
14.4
SDJH
$27 ([ SDJH
9015566_3
196
(G 6(78021$ 3XUH%DOODVWSURMHFW([ $27
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&RQWUROFLUFXLW$27% 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
197
Electrical drawings
$OID:DOOB)B
WRWKHH[WHQWH[SUHVVO\DJUHHGXSRQ
7KLVGRFXPHQWPD\FRQVWLWXWHD
FRQWUDFWXDOREOLJDWLRQRQWKH
&DEOHVXVHGVKRXOGEHVKLSERDUGFDEOHVGHVLJQHG
SDUWRI$OID/DYDO$%RQO\
$
12 7<3( 6RXUFHIURP ,16758&7,21 7DUJHWWR 5(0$5.
DFFRUGLQJWR,(&
: [ $27 ;([H $27 9 )ODPHUHWDUGHQWDFFRUGLQJWR,(&
:*6 [ $27 ;([L $27 9*6 )LUHUHWDUGHQWDFFRUGLQJWR,(&
: [ $27 ;([H $27 9 +DORJHQIUHHDFFRUGLQJWR,(& ,(&
:*6 [ $27 ;([L $27 9*6
)OH[LEOHLQVXODWLQJVOHHYLQJDFFRUGLQJWR,(&
: [ $27 ;([L $27 /6
14.4
%
: [ $27 ;([L $27 76 SURGXFHUV1H[DQV6ZHGHQ
7KLVGRFXPHQWDQGLWVFRQWHQWVLVRZQHGE\$OID/DYDO$%SXEODQGSURWHFWHGE\ODZVJRYHUQLQJLQWHOOHFWXDOSURSHUW\DQGWKHUHWRUHODWHGULJKWV:LWKRXWOLPLWLQJDQ\ULJKWV
(
5(0$5.6
WKHVHHNLQJRIFULPLQDOSURVHFXWLRQ
)
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 3% 1H[W
SDJH
$27 ([ SDJH
9015566_7
(G 6(78021$ 3XUH%DOODVWSURMHFW([ $27
14
$SSU 6(78021$ &XVWRPHUGHVFULSWLRQ
&DEOHOLVW 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
6LJQDOFRQGXFWRUVFDQEHPPðLIQRWRWKHUZLVHVWDWHG
6LJQDOFRQGXFWRUVVKDOOEHEOXHLIQRWRWKHUZLVHVWDWHG
,QVXODWHGHQGIHUUXOHVVKDOOEHXVHG
$
14
23
7RXFKSDQHO
14.4.11 Remote control panel (optional) / Circuit diagram
5LQJIRU0
3(
/$1$ /$1%
*1'
86% &20
%
5
6
2Q2II
'RRU
:86%
&
+
'RRU 2SWLRQDO
6: &20 9$ 9%
86% [ [
'RRU
[ :/$1 ; ; ; ;
/&,1 /&287
&$7H6)873 7' 5'
'
*1<( PPð
*1<( PPð
:/$1 &RQQHFWWR23/$1$
&$7H6)873 LI6:LVQRWSUHVHQW
;
5-
(
; 3( 6+
PPð
9
Electrical drawings
*1<(
3( 3(
5LQJIRU0 5LQJIRU0
PPð
*1<(
P
)
5LQJIRU0
&XUUHQWSDJH
3UHY 'DWH 'RFXPHQW1R 5&3 1H[W
14.4
SDJH
5&3 SDJH
198
(G 6(78-$' 5&3
9015558
$SSU 6(78-$' &XVWRPHUGHVFULSWLRQ
5&3 7RWDOQRRISDJHV
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
199
Electrical drawings
$
7
6RXUFHIURP
14.4
8 9 : 3(
14.4.12 Transformer (optional) / Interconnection diagram
/5
/7
/6
%
:
[
&
;
/5
/7
/6
7DUJHWWR
/ / / 3(
'
([W
)
&URVVVHFWLRQGHSHQGVRQ
VKLSVYROWDJHDQGSRZHU
RI3XUH%DOODVWV\VWHP
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 7UDQVIRUPHU 1H[W
SDJH SDJH
9028912_2
(G 6(78-$' 7UDQIRUPHU
14
$SSU 6(78-$' &XVWRPHUGHVFULSWLRQ
,QWHUFRQQHFWLRQGLDJUDP &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
Book No.Rev 2017–09–01
Drawings
$
14
%
9WR3XUH%DOODVWV\VWHP
14.4.13 Transformer (optional) / Circuit diagram
8 9 :
7 %ROWVLQVLGHWUDQVIRUPHUFDVLQJ
&
3(
8 9 :
:
[
&URVVVHFWLRQGHSHQGVRQ /5 /6 /7
VKLSVYROWDJHDQGSRZHU
' RI3XUH%DOODVWV\VWHP
(;7
9$&+]3KDVH
6KLSVSRZHU
/ / / 3(
5 6 7
(
Electrical drawings
)
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 7UDQVIRUPHU 1H[W
14.4
SDJH SDJH
9028912_1
200
(G 6(78-$' 7UDQIRUPHU
$SSU 6(78-$' &XVWRPHUGHVFULSWLRQ
&RQQHFWLRQ &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
201
Electrical drawings
$OID:DOOB)B
WRWKHH[WHQWH[SUHVVO\DJUHHGXSRQ
7KLVGRFXPHQWPD\FRQVWLWXWHD
FRQWUDFWXDOREOLJDWLRQRQWKH
&DEOHVXVHGVKRXOGEHVKLSERDUGFDEOHVGHVLJQHG
SDUWRI$OID/DYDO$%RQO\
$
12 7<3( 6RXUFHIURP ,16758&7,21 7DUJHWWR 5(0$5.
DFFRUGLQJWR,(&
: [ 7 ([W ; )ODPHUHWDUGHQWDFFRUGLQJWR,(&
)LUHUHWDUGHQWDFFRUGLQJWR,(&
+DORJHQIUHHDFFRUGLQJWR,(& ,(&
)OH[LEOHLQVXODWLQJVOHHYLQJDFFRUGLQJWR,(&
14.4
2WKHUHTXLYDOHQWDQGDSSURYHGFDEOHVPD\EHXVHG
&DEOHDUHDVDUHFDOFXODWHGZLWKFRUUHFWLRQIDFWRU
&RGHGHVLJQDWLRQVIRUFDEOHVREWDLQDEOHWKURXJKFDEOH
RWKHUZLVHRUIRUDQ\SXUSRVHZLWKRXWWKHH[SUHVVHGSHUPLVVLRQRI$OID/DYDO$OID/DYDOZLOOHQIRUFHLWVULJKWVUHODWHGWRWKLVGRFXPHQWWRWKHIXOOHVWH[WHQWRIWKHODZLQFOXGLQJ
%
SURGXFHUV1H[DQV6ZHGHQ
7KLVGRFXPHQWDQGLWVFRQWHQWVLVRZQHGE\$OID/DYDO$%SXEODQGSURWHFWHGE\ODZVJRYHUQLQJLQWHOOHFWXDOSURSHUW\DQGWKHUHWRUHODWHGULJKWV:LWKRXWOLPLWLQJDQ\ULJKWV
:KHUH66&LVLQGLFDWHGLWVKRXOGEHDVLJQDOVKLHOGHGFDEOH
UHODWHGWRWKLVGRFXPHQWQRSDUWRIWKLVPD\EHFRSLHGUHSURGXFHGRUWUDQVPLWWHGLQDQ\IRUPRUE\DQ\PHDQVHOHFWURQLFPHFKDQLFDOSKRWRFRS\LQJUHFRUGLQJRU
ZLWKWKHVKLHOGSURSHUO\FRQQHFWHGWRHDUWKDVVKRZQLQWKH
HOHFWULFDOGUDZLQJV
5HFRPHQGDWLRQRIYROWDJHFODVV
5DWHGYROWDJHRISRZHUFDEOHVN9
& 5DWHGYROWDJHRILQVWUXPHQWDWLRQFDEOHVPLQ9
14.4.14 Transformer (optional) / Cable list
[&DEOHQRWLQFOXGHGLQ$OID/DYDOGHOLYHU\
'
(
5(0$5.6
WKHVHHNLQJRIFULPLQDOSURVHFXWLRQ
)
&XUUHQWSDJH
3UHY 'DWH (3/$1 'RFXPHQW1R 7UDQVIRUPHU 1H[W
SDJH SDJH
9028912_3
(G 6(78-$' 7UDQIRUPHU
14
$SSU 6(78-$' &XVWRPHUGHVFULSWLRQ
&DEOHOLVW &XUUHQWSDJH
0RGLILFDWLRQ 'DWH 1DPH 2ULJLQDO 5HSODFHPHQWRI 5HSODFHGE\
14.5 Intrinsically safe circuits 14 Drawings
Cable selection
The five IS circuit cables are not delivered by Alfa Laval, and must therefore be selected by the
party responsible for designing PureBallast. The cables must be correct for installation in the
hazardous zone, and they must match the requirements for the intrinsically safe circuits according
to the Exi max multicore cable length calulation.
Requirements for each cable (and underlying apparatuses) are described in the Exi max multicore
cable length calulation documents. The table below is an overview of the documents. After the
table, the documents are available. Each The documents are sorted in two levels:
• Example calculation: Example of standard cables and how to calculate cable specifics to
verify that the cable can be used.
• Verification fo selected/installed cable: Documents describing the basic data for the
underlaying apparatuses. This section shall be filled out according to the instruction. They can
also be used if a cable needs to be changed after installation.
Follow the instruction for each of the five verification documents for the IS circuit cables.
2. Verify that the intended cable complies with stated parameters in the document according to
section Verification of selected/installed cable.
3. Send the completed documents to ship yard / owner for storage on board the vessel.
9025366_Page_2
14 Drawings 14.5 Intrinsically safe circuits
9017961_Page_2
14 Drawings 14.5 Intrinsically safe circuits
9017961_Page_3
14.5 Intrinsically safe circuits 14 Drawings
9017961_Page_4
14 Drawings 14.5 Intrinsically safe circuits
9017961_Page_5
14.5 Intrinsically safe circuits 14 Drawings
9017961_Page_6