Académique Documents
Professionnel Documents
Culture Documents
W
MC Limited began as a gold exploration, mining new ore stockpile, a new autogenous mill, and additional
and management company in Western Australia flotation cells in the copper concentrator section. The
in 1933. Since the 1950s the company has diver- hydrometallurgical plant expansion includes the tailings
sified and expanded to become a significant pro- leach area and the copper-uranium solvent extraction area.
ducer and exporter of processed minerals and metals. A new smelter complex has a nominal capacity of 180,000
WMC began exploring southern Australia for copper in tpa copper, while an associated acid plant has a capacity of
1961. In 1977 drilling revealed a large prospective ore 1,640 tpd sulfuric acid. The copper refinery has been
deposit located in the Stuart Shelf geological province at expanded to a nominal capacity of 179,000 tpa electro
Olympic Dam (Figure 1). Mineral reserves are now known refined copper and 23,750 tpa electrowon copper. In addi-
to be 11.4 Mt of copper, 0.34 Mt of uranium (as uranium tion, a new gold and silver refinery has been constructed.
oxide), 400 tons of gold and 2,790 tons of silver.
Between 1988 and 1995 production rates increased signifi- OEP Establishes Requirements
cantly and continue to increase. With increased production, To manage the expansion, WMC appointed an Olympic
came a need for further expansion which will be executed in Expansion Project (OEP) team made up of WMC consult-
two phases. The first increases the production rate from 85,000 ants and contractors.
tpa copper to 150,000 tpa with capacity for 200,000 tpa, and The OEP team sought an open solution to their control
the second increasing overall production to 350,000 tpa. system needs. The original facilities were controlled by an
A copper production rate of 200,000 tpa will yield average ABB Mod300 DCS system using proprietary hardware and
production of approximately 4,630 tpa of uranium oxide, software. The new facilities will have more than 400,000
real-time PLC variables, 40,000 physical I/O points and
FIGURE 1.
20,000 serial I/O points. The new controls will use an open,
OLYMPIC DAM MINE non-proprietary system that can be easily maintained and
expanded in the future.
In addition to the technical requirements, OEP wanted a
partnership approach to the management and development
of the system. Citect and Allen-Bradley offered OEP a com-
bined solution using Allen-Bradley plant floor controllers
(PLCs), the Citect SCADA package and a Microsoft SQL ser-
ver. Ethernet was selected as the best communication method
as the open, non-proprietary platform allowed a multitude of
vendor hardware to be supported across the site. This new
control system was chosen following a comprehensive analy-
sis based on the technical solution offered, cost effectiveness
WMC’s Olympic Dam facility has been through several expansion and Citect and Allen-Bradley’s partnering abilities.
phases, the latest of which employs Citect’s SCADA software to Citect engineered the project over 18 months, with a
replacing an aging DCS. manning level of 42 engineers at its peak. Project teams cor-
responded to designated process areas including: smelter,
2,050 kgpa gold and 23,000 kgpa silver. Future expansion hydromet, concentrator, refinery, mine, auxiliaries, infra-
may generate production rates of 350,000 tpa copper, 7,730 structure and existing plant upgrade. A separate team
tpa uranium oxide, 3,630 kgpa gold and 49,600 kgpa silver. addressed the development of project standards and docu-
mentation pertaining to the control system.
Expanded Mining Operations Development tools provided by Citect allowed a single
While underground mining operations remain mostly unal- development database for SCADA configuration, PLC pro-
tered, an extensive new plant maximizes the mine’s ore gramming, and much of the documentation, which greatly
extraction capabilities. The metallurgical plant features a minimizing the engineering effort.
60 APRIL/2005 www.controlglobal.com
CT0504_60_62_CanThey.qxp 3/21/05 4:37 PM Page 61
www.controlglobal.com
CT0504_60_62_CanThey.qxp 3/21/05 4:38 PM Page 62
• Fully redundant 100-Mbps Ethernet trol room (communications center) location and inside the control room
switched network running TCP/IP and distributed remote locations. itself, with 100-Mpbs switched links
over single- and multi-mode fiber • Fully redundant 10-Mpbs unshield- direct to all SCADA Servers.
optic cable is used between the con- ed twisted pair is used at each remote • All remote computers and other
selected computers have redundant
network interfaces in each PC with
one on each LAN, forming a com-
pletely redundant communication
path to each of them.
• Most of the plant floor controllers are
also Ethernet-based with dual
Ethernet connections. The SCADA
I/O servers automatically switch to the
standby Ethernet connection on the
PLC if the primary connection fails.
• The SCADA system provides for
fully redundant hot fail-over server
facilities for data acquisition and dis-
tribution (I/O server) functionality.
• The SCADA software provides for
fully redundant hot fail-over server
facilities for Trend, Alarm and
Report servers. Each of these tasks is
allocated to a specific pair of primary
and standby servers.
Inherent Performance
The SCADA system’s built-in data
optimization for communications to
the plant floor controllers allows the
large-scale application to be manufac-
tured similarly to a small-scale applica-
tion. Multiple I/O servers were used to
localize the process areas.
The SCADA system automatically
caches the data for each plant floor
controller, thereby minimizing the
communications required to distribute
the data to multiple SCADA clients.
This built-in functionality results in
minimal performance impact on the
entire system when large numbers of
SCADA clients are added.
The SCADA software’s scalability
and data management allows it to pro-
vide extremely high performance on
large-scale systems without increasing
engineering complexity. C
62 APRIL/2005 www.controlglobal.com