Académique Documents
Professionnel Documents
Culture Documents
The following is a sketch of one of the Imaginary Gold Mining Company Limited mines,
namely Simple Mine 1. You are asked to simulate the airflow and heat flow in this mine
and to specify the cooling, airflow regulation etc to comply with certain requirements for
this mine.
Requirements
1
Steps
2
a. Change the branches in a logical sequence – start with the
downcast shaft – then progress through the station areas,
through the stopes until you reach the upcast shaft.
7. Once you have changed all the branches to match the sketch and the
provided information – you need to add a fan on top of the return shaft
– in order to move air through the mine. However – to determine what
fan to use – you need to know (amongst other) what the system
resistance of the mine is. The easiest way to determine the requirements
of a fan is to first change the branch at the top to a Control manager
of type Fix Flow – and to adjust its fixed volume flow input until it
meets the ventilation requirements as per the design. Then – you can
check the pressure rise required to achieve the air flow quantity – and
replace it with a fan capable of matching the parameters. The solving
process will be described later – for now, set the input to 100 m³/s (Bear
in mind the effect of density changes).
8. Since the abovementioned fix flow / fan will discard the air into
9. You also need to tell the program where the main fresh air intake of
the mine is – and you do that by assigning the Startnode property to a
single, specific node. For this example, navigate to the node on top of
the main downcast shaft, and double click on the node (or press E
whilst hovering over the node). If the button (Set as start node) is
enabled – click on it to set the current node as the start node. If the
button is greyed out (disbled), it indicates that the current node is already
3
the start node – and that no further action is required -except to click
It is highly recommended to solve using the Aero only option in the early
stages of modelling – before attempting to solve a Full or Thermo solution
4
11. If the solution
completed
successfully,
you should
see a green
check mark at
the top of the
screen. If not – you can click on the Solve >> Dashboard button to
investigate the cause.
12. Once you have managed to complete the Aero solution – you need to
verify that you are meeting the airflow requirement at X (Requirement
A). You might need to adjust the specified quantity of the fix flow (Step
7) to achieve it.
5
representation by changing the color mode type to Node – and the color
paramter to Dust.
14. To control (regulate) air flow quantities (Requirement C) – you will need
to add control managers (regulators) to divert air by increasing the
resistance in airways with too much air.
manager.
• Edit the type to be a Tunnel reduced area regulator – and set the
Fraction of area open to be 10% (Initial guess value).
6
15. Click OK to close the form – and resolve the network using the Solve
>> Aero button.
18. Hovering the mouse cursor over the stope branches will indicate the
branch outlet (stope reject temperature). Without cooling, this value
should be in the region of 28 °C. As per the requirements - add a control
manager of type Cooler – Fixed duty in front of the start node at the
entrance of the main downcast shaft. Set the initial duty to 1000 kW.
19. Resolve the model – and adjust the cooler – until Requirement D is
fulfilled. Note that you need to move the start node in front of the
cooler – otherwise the effect of the cooler will be discarded.
7
20. To perform a blast solution –
explosive input details first must be
added to the working places. To
quickly add it – click on the Solve
>> Add to all stopes button. Set
the Explosive type to ANFO
(branded < 152 mm) and click on
OK. Click OK again to close the message informing you that blasts were
added.
21. You need to perform a Thermo solution once again to ensure all the
values are up to date. Subsequently, click on the Blast clearance button.
8
Global defaults
Tunnels
Shafts
• Use Atkinson method with a friction factor of 0,025 for downcast shafts, and
0,004 for unequipped shafts.
• Average age of shafts is 10 years.
9
• Wetness rating of downcast shaft is wet and for the upcast shaft is very wet.
• Other heat load is a dry linear heat in all intake shafts of 5 kW per 100 m.
• Make Layer 1 – Shaft and services
• Model the shaft station area using the default tunnel settings
• Wetness rating for the shaft station area is very wet.
• Shaft station tunnels are 7 years old on average.
• Use Atkinson method with a friction factor of 0.015 for shaft station tunnels.
• Make Layer 1 – Shaft and services
Production zones
• The mining method is Narrow Reef stoping (single sided breast mining)
• Vent option: Upcast
• Face length: 200 (closest to sub shafts), 180, 160, 140 m
[adjust per stope]
• Stope width: 1.2 m
• Strike length: 80, 70, 60, 50 m [adjust per stope]
• Strike gully perimeter: 8m
• Dip gully perimeter: 12 m
• In-stope vent control: Good
• Backfill Typical
• Vent control to face: 7.5 m
• Panels: 4
• Active face: 100%
• Pressure drop: 1 Pa per 10 kg/s
• Establishment period: 12 months
• Status: Active
• Face advance rate: Edit to achieve 15000 t/month per stope
• Fissure water ingress: 0.1 ton/ton of rock at VRT
• Service water use: 1.0 ton/ton of rock at 20 °C
• Outlet DB/WB difference: Typical
• Dust load per stope: 50 mg/s
• The total kW rating for winches in the production zone is 60 kW being used
moderately.
• Visual Layer 1 – Production Zone
10