Wanted: A serious investor with cash to join our currently medium scale mining company. The
company is working on one good mine with grades that average 36 grams per ton. We also own
rights to mine anywhere within the country. The optimum target production is expected to exceed
500 troy ounces a month at the current mine where the main ore body is an estimated 1.5million
tons.
An estimated US$2.5milion is sufficient initially. 49pc of the venture is on offer and funds shall
be directly used to equip and refurbish the equipment making up the infrastructure and working
capital of the project.
Existing Infrastructure:
The current infrastructure is made up of the following, among other things:
• A shaft down to the first level with cross cuts to the reef;

• A head gear on the shaft , complete with the hoist;

• Underground rail system in the cross cuts;

• The milling system has a conveyor has a conveyor system from the grizzly to the crusher
and from the crusher to the ore bin;

• A 10x21 Samuel Osborne jaw crusher;

• An 8x4 ball mill and a 4x3 ball mill;

• Beneficiation is through two Querl bowls and a James table housed in a secure building;

• Two war man slime pumps;

• There are seven tanks for cyanide extraction of gold;

• A borehole has been dug to satisfy water requirements;

• Electricity bas been brought to the mine with 500KVA transformer;

• There is also a developed pit for open cast mining;

• Sundry tanks, tools and equipment too numerous to mention.

Available Mineral Resources on site:


The mine consists of claims covering four reefs, one is shafted and another is open cast. The
shafted reef has a mine life of 157years at the extraction of about thirty tones per day (over
1.5million tons). The underground grades vary from 16grm per ton to 220grm per ton of fine gold
with many nuggets. It is our hope that production will begin at one hundred tons per day with
three levels.
Opencast is expected to contribute initially some fifteen ton of undiluted ore per day with grades
of approximately 18grm to 36grm per ton expected.
In the period it ran as a small scale opencast operation 420 tons of ore recovered 15Kgs of gold.

1 http://www.scribd.com/RufaroMiningLtd
Rufaro Mining & Geological Services (Private) Limited
RUFARO MINING Ltd
BUSINESS PLAN
INTRODUCTION

Commission for intermediary services:


Any charges arising from your work on this project will only be raised when funded. No funds,
no commission basis. If you cannot find an investor, no liability will be raised on ourselves. Any
charges on the funding raised must be agreed with us in advance.
Terms applying to partners:
New partners have the option of being silent partners. They may become actively involved in the
project. They are welcome to participate in management or employ to safeguard their interests.
New partners are also welcome to sit on the director/owners’ board and will receive periodic
reports. Partners in the project may also visit frequently. No restrictions are imposed in any
regard to the partners’ involvement.
Country tax 7.5pc production

About the current partners:


The current owners have experience in the mining sector, as well as business management,
accounting and financial management. One director is the holder of CIS, CIMA and an MBA as
well as working experience in several large public and private companies. The second partner has
two university degrees in accounting and finance and served five year articles with one of the
large international Charted Accounting firms.

Updates to all documents available at http://www.scribd.com/RufaroMiningLtd

2 http://www.scribd.com/RufaroMiningLtd
Rufaro Mining & Geological Services (Private) Limited

Vous aimerez peut-être aussi