Académique Documents
Professionnel Documents
Culture Documents
By
October 2020
Abstract
Delay has been one of the most prevalent challenges within church construction projects,
especially in the orthodox churches. Despite construction challenges and project delays within
most orthodox churches, there is still a lack of empirical evidence on unearthing the factors that
lead to church construction delays. This quantitative study is aimed at exploring church
construction delays within the Presbyterian Church of Ghana. After extensive literature and
theoretical review, a proposed construct was generated with a structured questionnaire and
distributed using the online survey tool, MikeCRM. Out of the 480 questionnaires distributed, 402
were completed and returned, representing a response rate of 84.8%. The questionnaires were
completed by 39.3% Other Positions, 21.9% Resident Pastors/Agents, 18.9% Managers, 9.95%
Project Managers, 5.90% Consultants, 1.99% Site superintendents (foreman), and 1.99%
Electricians. The sample data were analysed statistically using Exploratory Factor Analysis,
Confirmatory Factor Analysis, Cronbach’s Alpha, Pearson correlations, and AMOS for reliability
and validity and for measuring the suitability of the proposed constructs. The study confirmed six
factors as being responsible for the church construction delay with Material-related being the
highest influential factor and Client/Owner-related as the least. The other four factors include
findings will help academicians, building contractors and church stakeholders with awareness of
church construction delays. Theoretically, the findings will contribute to the existing body of
knowledge in the research area of church construction delay from the perspective of developing
countries.
1
Declaration: Signature
“I declare that this doctoral dissertation is entirely written by me and no resources other than those
stated in this study were used for the accomplishment of the research. I also declare that all the
quotations which were used in this study were either direct or indirect; each one of them is
properly referenced. I declare that this project has not been submitted elsewhere for any form of
examination or publication.”
2
Dissertation Committee – Signature
I certify that I have read this dissertation and that, in my opinion, it is fully adequate in
______________________________
I certify that I have read this dissertation and that, in my opinion, it is fully adequate in
______________________________
I certify that I have read this dissertation and that, in my opinion, it is fully adequate in
______________________________
3
Acknowledgement
The completion of this academic work has been accomplished by the grace of God and
with the great support of some scholars, colleagues, and friends. The SMC University professors:
Dr. Thomas Grisham, Prof. Ted Sun, and Prof. Francis Pol Lim, have been incredibly helpful in
the entire dissertation process. I am grateful to the UCN professors and faculty; the Presbyterian
Church of Ghana congregations I have pastored; Ascension Koforidua, Trinity Royals, Adweso-
Koforidua, and Australia. It is very significant to mention the following scholars and mentors of
PCG for their overwhelming support in my ministry; Rt. Rev. Prof. J.O.Y Mante (Moderator),
Very Rev. Prof. Cephas N. Omenyo (Ex-Moderator), Very Rev. Prof. Emmanuel Martey (Ex-
Moderator), Rev. Dr. Nii Noi Odonkor (G.A Clerk), Rev. Dr Samuel Ayete Nyampong (Ex-G.A
Clerk), Rev. Dr Charles Gyang Duah (Ex-G.AClerk), Rev. Dr. William Ofosu Addo (B/A
Chairperson), Rev. Dr. G.O. Kwapong (Ex-Akuapem Chairperson), Rev. Herbert Anim Opong
Ex-NAAP Chairperson), Rev. J.J. Kumi Duodu (NAAP Chairperson) Rev. Dr. Nana Opare
Kwakye (University of Ghana) and Rev. Godfried Asante Bamfo (1st Resident PCG minister of the
Australian Mission),
I am equally grateful to the following intellectuals for their encouragement and assistance
Prof. Smile Dzisi (immediate past vice-chancellor, KTU) for motivation, Rev. Dr Nicholas Apreh
Siaw for his continual guidance right from the start of the study, Dr Edwin Okoampa Boadu for his
interventions, Dr Richard Ohene Asiedu for his useful suggestions, and Dr. Andy Ohene Asare for
his timely analytical suggestions and Rev. E. O. Otu (Ex clerk of the Akuapem Presbytery) for
always making documents available when needed. Also, to Dr. and Mrs. Mintah for their unending
As well, I am thankful that this journey commenced with my dedicated lecturers, teachers,
and classmates particularly, the Kwame Nkrumah University of Science and Technology
(MBA/EMPA class of 2013), University of Cape Coast (MSc. class of 2014), Trinity Theological
4
Seminary (2009–year group); Presbyterian Training College, Akropong (‘Adikanfo’ class of
2003), Nsawam Senior High (class of 1999), Prince Boateng International class of 1996 and Sakyi
Agyakwa LA Primary (1987–1990). My family cannot be forgotten for their love and
encouragement. My lovely sisters, Patricia, Faustina, Agnes, Evelyn and Helina for continually
encouraging me, my wife, and my daughter; I love you. Finally, thank you to my research
assistants Abigail, Bevelyn, Collins, Daniel, David, Evelyn, Gloria, Hannah, Kate, Mary, Phyllis,
5
Table of Contents
Abstract .................................................................................................................................. 1
Dedication ............................................................................................................................ 17
Summary .......................................................................................................................... 32
6
Chapter 2: Literature Review............................................................................................... 33
Planning Theory....................................................................................................... 38
Execution Theory..................................................................................................... 40
Managerial dispute....................................................................................................... 55
Budgets. ................................................................................................................... 62
Disputes ................................................................................................................... 73
Litigation...................................................................................................................... 75
Abandonment ........................................................................................................... 76
8
Improve project plans with massive data..................................................................... 86
Summary .......................................................................................................................... 91
Conceptual framework................................................................................................. 97
9
Data Analyses ................................................................................................................ 112
Age............................................................................................................................. 116
RQ1: Relationship between Client /owner-related factors and Church ConD .......... 137
RQ2: Relationship between Church organization structure and Church ConD……. 138
RQ4: The association between Project-related factors and Church ConD ……...…..140
RQ5: The relationship between Material-related factors and Church ConD ... …….141
10
RQ6: The relationship between External-related factors and Church ConD ........ …142
H1: The relationship between Client /owner-related factors and Church ConD. ...... 149
H2: The relationship between ChuOS and Church ConD ......................................... 150
H3: The association between Quality-related factors and Church ConD .................. 151
H4: The relationship between Project-related factors and Church ConD ................. 151
H5: The relationship between Material-related factors and Church ConD ............... 152
H6: The relationship between External-related factors and Church ConD ............... 153
Conclusions.................................................................................................................... 154
The relationship between Client /owner-related factors and Church ConD. ............. 155
The relationship between Church organization structure and Church ConD………. 156
The relationship between Project-related factors and Church ConD ........................ 157
The relationship between Material-related factors and Church ConD ...................... 157
References.......................................................................................................................... 164
12
List of Tables
Table 4 Plan for Data Analysis for the research question. ........................................................... 113
13
List of Figures
Figure 11. Model fit of the independent variables tested amongst themselves............................. 126
14
List of Abbreviations
CR Composite Reliability
H Hypothesis
SD Standard Deviation
15
List of Appendices
16
Dedication
With joy in my heart, I dedicate this Doctor of Philosophy work to my lovely partners-in-
ministry. You are always there for me and the ministry. I cannot mention your names, but you
know you are a part of me. I pray for you to live long enough to see me use this knowledge to
17
Chapter 1: Overview
The delay in construction projects is regarded as a critical concern for contractors as well
as managers as it involves high cost overruns because of the extended deadline of the project
(Monghasemi, Nikoo, Fasaee, & Adamowski, 2015; Marzouk, & El-Rasas, 2014). The research is
framed to identify the core delay factors which are hindering the Church construction projects in
the Presbyterian Church of Ghana (PCG). This chapter delivers a brief overview of the research,
along with discussing the raised issues of delay in construction projects related to the church. The
identified information in the overview is used to frame questions to examine the influence of the
delay factors on the church construction projects. This research was conducted based on a
quantitative study where the independent variables (control variables) interconnected to the
hindrance in church construction were examined. Later in this study, the association between the
dependent and independent variables are established. The importance of the study is that it has the
potential to improve the project efficiency by reducing the influence of delay factors and this
knowledge is beneficial as well as vital for the policymakers, stakeholders, and managers involved
in project construction.
Research Problem
One of the things which remain of more significant concern in every country is the
economy, and how to boost it. Ghana, over the years, has shown several economic signs of
progress through the construction industry. However, lately, delays have been a worry and raised
national debate and concerns at various forums. The extreme level of prolonging completion dates
amidst the enormous cost incurred in these delays leaves a burden on the project managers,
contractors, and client/owners of the construction projects (Addo, 2016; Boys 2015; Marzouk, &
El-Rasas, 2014). Studies have revealed that Ghana had several occasions where the client/owner
18
incurs an extra cost to the tune of paying three times the initial contract amount. As a result, the
work suffers long schedules and raises concerns on the quality of the construction projects (Addo,
In the PCG, some church projects that commenced with a five-year completion plan have
been ongoing for over 10 years and still not completed (Adukrom District Report, 2014). Asiedu
and Alfen (2016); Aziz and Abdel-Hakam (2016); and Durdyev, Omarov, and Ismail (2017)
established that there are several project delays triggered by the project going over and above the
requisite budget and the required time frame. Construction projects that started with high hopes of
completion on schedule are being abandoned or suspended, resulting in economic loss. The
church, the society, and the government all give the impression of having experienced these stalled
projects with huge financial loss (Kog, 2017; Rachid, Toufik, & Mohammed, 2018). Kim and
Kang (2018), Mohammed (2016), and Rugenyi (2015) found an association with the failure of
project and low standard project performance as being influences of cost overruns.
According to Larsen, Shen, Lindhard, and Brunoe (2015) as well as Marzouk and El-Rasas
(2014), a delay triggered by construction project results in the loss of financial resources and time,
which negatively impact the parties concerned in carrying out the project. In some cases, an extra
one-third of the initial cost of the project is incurred because of delays caused during the execution
of the project. This form of procrastination is seen to create litigation and abandonment of projects
along with rising disputes (Alpkokin & Capar, 2019; Arcades Design & Construction (ADC),
The Church construction projects in the Presbyterian Church of Ghana (PCG) involve the
construction of a decent place within the church for worship purposes, building of church halls for
additional church functions, creation of church offices to execute administrative duties, building of
a residential place for the aged to receive care, and reconstruction and building of mission schools
for the Presbyterian educational unit (PCG–Constitution, 2016). These are the primary places that
19
are to be focused on during the building of the church to ensure its good standing. Few of the
congregations in the Presbytery were found to have worked efficiently to complete the project
related to the construction of the chapel, even though the completion dates were extended far
beyond the anticipated deadline. On the construction site it has been seen that other congregations
are still involved in the process of constructing chapels. In contrast, few have suspended their work
or have abandoned the chapel project due to lack of definitive knowledge regarding the time
The buildings of the residential facility for office projects and agents in the church
construction site are still at the worst stages. This is evident because most of the facilities have yet
to be seen in the planning stage or at the initial phase of implementation, even long after the
session (governing council) of the different congregations involved in the project had approved the
plan (Akuapem Presbytery Report, 2014). As a result of the delay caused in this project, it has
been seen that the agents of the Church (client/owners) are living in rented places, which are
located far away from the construction site, making it difficult for the agents to access the site and
execute their work effectively. In investigating the reasons behind the delay, the research is
going to explore the factors that contribute to this delay with the intention of improving the
Background of the study. The problems relating to the delay of construction projects have
been raised as a global phenomenon in the industry (Nyoni & Bonga, 2017; Prasad, Vasugi,
Venkatesan, & Bhat, 2019; Wang & Tam, 2014; Zack-Williams, 2017). The primary objective of
each client/owner, be it a church construction project or other, is to effectively attain the successful
completion of the project (Sohu, Memon, Abbasi, Pahore, & Ullah, 2016). As asserted by
Schwing and Urtasun (2015), the success of construction projects depends on their effective
planning as well as design. This is because an unplanned and unstructured project planning of
20
construction leads the workers as well as the contractors to get confused in executing the
construction effectively. Moreover, effective planning leads to lower cost and results in the
completion of the project within the given deadline, thus reducing the influence of delay factors
During the execution of the construction, the project is influenced by success factors that
play a crucial role in assisting the parties involved in the project to reach their determined goals as
previously planned. Moreover, the delay factors also influence the project negatively as the dates
for completion of the project are missed or postponed (Wang & Tam, 2014). To reduce delay in
construction projects, the project managers need to become concerned with the understanding of
the client/owner’s objectives concerning quality, utility, cost, and time along with project
establishment (Marzouk, & El-Rasas, 2014; Schwing & Urtasun, 2015). The fundamental aspects
related to project management include monitoring, integration, and control of the contributors in
the project along with evaluating effective relationships involved in the selection of resources and
alternatives in the project to achieve the sufficient satisfaction of the client / owner.
Various studies related to the delays in construction projects happening in Africa have
revealed that time overrun was the vital issue faced (Marzouk & El-Rasas, 2014; Wang & Tam,
2014). Moreover, in many cases, it was seen that the project cost had surpassed the estimated
budget, leading clients/owners to express dissatisfaction with the project, thereby causing a delay
in construction (Nyoni & Bonga, 2017; Prasad, et al., 2017). Further, failure of the contractors to
adequately understand the client’s requirements in the construction regarding the design and
quality to be maintained, also caused project delay as it raised conflicts and disputes between the
contractors and clients/owners. In cases where the contractors could not execute work
management within the allocated deadline, a delay occurred in the construction project (Durdyev,
Omarov, & Ismail, 2017; Wang & Tam, 2014). The concept related to delays in construction
projects can be evaluated if the definition regarding the evaluation dimensions is effectively
21
available. In construction projects, the appraisal proportions are seen to correspond to the usual
project limitations such as rate, time, and value parameters (Sha, Shahi, Pandit, & Pandey, 2017).
Historical Background. The PCG was established on 18th December 1828 and has 21
presbyteries, 5,000 congregations and preaching posts (PCG 188th Report, 2018). The Akuapem
Presbytery is one of the oldest Presbyteries in the PCG. The name Akuapem in Ghana is seen to
be synonymous in spelling with the PCG. This is because the place is surrounded by lofty
mountain ranges on which the first stop was made by Basel Missionaries who came to the Gold
Coast on December 18, 1828, to spread the gospel PCG Constitution (PCG–Constitution 2016;
Kwakye, 2018). As a result of the long-standing and immense evangelical success from 1843,
many indigenous people converted to Christianity, and more specifically, to the PCG. Moreover,
missionaries and African converts have taken on the task of the clergy to spread the gospel at
Akuapem as well as to the places where the traditional churches are already established. Further,
many schools have been developed and established by thePCG to offer formal education to the
The PCG established many educational and health facilities, which made it the third-largest
organization, surpassed only by the government services and healthcare services of the Catholic
Church, to deliver such facilities within the country (Kwakye, 2016). To effectively administer the
operation of the facilities in these areas, the PCG decided to set up Presbyteries, of which the
Akuapem Presbytery is one of the current 22 Presbyteries, each headed by a chairperson and
entrusted with overseeing the area’s spiritual development and physical factors. The Akuapem
Presbytery, being one of the largest and oldest presbyteries of the PCG, was established on July
21, 1922, with the synod held at Kyebi to deliver pastoral care in and around Anum and the
Akuapem area (PCG-Constitution, 2016). The Akuapem Presbytery presently covers the entire
traditional areas of Akuapem, some parts of Akyem Abuakwa, and New Juaben. The Presbytery,
including Akropong as its headquarters, consists of 25 districts, Abiriw, Aburi, Adawso, Adeiso,
22
Adoagyiri, Adukrom, Adweso, Amonokrom, Asuboi, Coaltar, Djankrom, Effiduase, Koforidua,
Larteh, Mamfe, Mampong, Mile 50, Nankese, Nsawam, Nsukwao, Suhum, Suhum New-Town,
Suhum Oforikrom, and Tutu. Almost all the 25 districts are currently undertaking construction
projects, and this confirms the vision perceived by the Church to cater to and fulfil the temporal
and spiritual requirement of its members (Akuapem Presbytery Report, 2013; 2014; PCG-
Constitution, 2016).
The rationale to execute the quantitative study was to seek an understanding of the
essential delay determinants related to the Presbyterian Church construction projects in Ghana.
Rachid et al. (2018) assert that construction delays have legal, economic, and social consequences.
There are substantial losses of financial resources as a result of delays in the construction projects
(Larsen, et al., 2015). The study further focused on the critical success or failure components
involved in the church construction projects so that the extent of the influence of each factor could
be assessed correctly when understanding their effect on project efficiency (Naoum, Herrero,
Egbu, & Fong, 2018). Despite the numerous contributions of work in the construction field, not
much has been done on the religious institutions. For instance, construction projects like road
construction and other governmental projects have attracted constant attention by industry and the
academic world (Chen, Shan, Chan, Liu, & Zhao, 2019b). Though the delays in church
constructions keep increasing in the PCG (Akuapem Presbytery Report, 2014), the available
conceptual and empirical studies executed on construction delays largely focused on roads and
other public institutions (Famiyeh, et al., 2017; Murwira, & Bekker, 2017). There were few
examples of literature identified on church construction projects, and these were also outdated.
23
material-related factors, Church organization structure (ChuOS), and external-related factors
(ExtRFs) was developed to investigate their relationships with Church construction delay.
Construction of any form of shelter is required for fulfilling cultural requirements of life, as
each group of individuals is looking for a decent place for their habitation (Alzraiee, Zayed, &
Moselhi, 2015). Over 1,500 building projects are undertaken each year in Ghana, with
approximately 320,000 workers employed on construction jobs (Ghana Construction, 2017). The
World Bank recently projected that the construction industry has a shortage of 60,000 handicraft
workers and construction workers and that by the year 2020, the construction firm expects over
250,000 skilled artisans to fill the gap (Darko & Löwe, 2016). The building of any shelter needs
expert, semi-expert, and non-expert persons for completion. That is, in building one standard
shelter in Ghana, at least fifteen to twenty labourers are required in addition to all the technical
experts, and it takes many tedious steps to get a building permit, which may delay the projects
along with the added cost involved (Addo, 2016; Alzraiee, et al., 2015).
of the delays in the church construction to accomplish effective project management. This study
has afforded a verifiable base of thoughts that offer knowledge about the delays in construction
projects and their impact on the PCG. In this respect, the outcomes of the study contributed to the
business and the educational domain in three main categories, which include theoretical, empirical,
and methodological.
Empirically, the study impacted the body of knowledge, since it investigated the impact of
church organizational structure on church construction delays. This provided a useful approach to
the church, resident minister/agent, session, Project, and Investments Committee (PIC), and church
group leaders with a more unobstructed view of the influence of church organizational structure on
24
delay; mainly, the need to strengthen communication and make it active within the church
structure (Mulugeta, 2019). Project Managers’ reputation will be maintained if they avoid delays.
Theoretically, the aim was to contribute to the current knowledge base in the business
especially in the study of project management, church management, engineering, and technology,
according to the perspective of strategic management and a developing country (Ilhan & Yobas,
2019; Zidane & Andersen, 2018). In the PCG construction projects give access to a convenient
place of worship, and aid in housing the agent-in-charge (PCG-Constitution 2016). Therefore, this
study has also helped in ensuring that proper measures are put in place to avoid any undue delay
and make judicious use of the available resources (Li, et al., 2019). The outcome aided scholars,
church leaders, managers, and those in the construction industry to improve on their human
resource management (HRM) for sustainability in Church construction projects and other related
structure projects (Kim, et al., 2018; Sutar & Mehendale, 2017). Finally, this research was in
fulfillment of the Central University of Nicaragua’s requirement for the award of Doctor of
Philosophy.
Research Design
This study aims at investigating the extent to which delays affect construction projects in
the PCG. Premised on the predictor variables, the unit of the analysis was the 25 Districts of the
Akuapem Presbytery, which undertook a construction project like a chapel building, building of
church halls, building of church offices and building of a church manse as a minister’s residence
(PCG-Constitution, 2016). According to the nature of the research question and study objectives,
the study utilized the quantitative technique. The data collection was gathered from 402
respondents through a cross-sectional survey using questionnaires. The methodology of this study
was established as a result of the extensive literature reviews on delays in construction projects. A
25
cross-sectional survey was employed based on the aim of the study: to explore the delays in
construction projects in the PCG. Hence, the need for a sufficient sample of the population from
persons involved in the construction industry like the Resident Pastors/Agents (clients/owners),
Electricians, and others (committee/session) using the online survey tool, MikeCRM. As indicated
by Babbie (2016), the cross-sectional survey was the best means of gaining enough data in order to
attempt generalization about the larger population from which the participants were chosen as
samples. Since the study attempted to examine the relationship between the independent and
questions designed for comprehensive interviews to measure or tally the answers and evaluate the
data statistically (Mayer, 2015; Nardi, 2018). The quantitative technique was used in this study to
assess various variables comprising areas relating to correlations between variables and employing
efficient statistics, such as correlations, testing theory, and variations between the means. The
hypotheses were developed to assist in having a sequential data analysis. The survey approach
helped in executing the study within a minimized time-frame and had a lower tolerance for errors
as well as maintained ambiguity in the study, resulting in the development of meaningful data
As mentioned by Creswell and Clark (2017), the survey approach is used in research as it
provides a broader view and information about the social phenomenon occurring in the
environment without any form of subjectivism. The positivist paradigm was used as a principle
for implementing this design. The quantitative technique was used to measure and verify the
outcome (Mayer, 2015); to contrast and compare the results (Nardi, 2018); to establish the validity
of the instrument and the conclusion (Creswell & Clark, 2017) and to appreciate and critique the
precision of the study outcome (Vance, Talley, Azuero, Pearce, & Christian, 2013).
26
This quantitative study gathered knowledge regarding the critical failure and delay factors
along with their level of association with the project. Moreover, the method was also used to
evaluate the impact of each of the factors on the construction project. In this study, the assessment
procedures employed in the quantitative technique, like statistics figures, charts, and tables, aided
the researcher in investigating, presenting, explaining, and analysing data for correlations and
trends.
Objectives of the study. The main objective of the research was to explore the delays in
construction projects in the PCG. The following sub-objectives aimed at leading the research to
construction delays.
construction delay.
construction delay.
construction delay.
delay.
construction delay.
Structure of the Thesis. This thesis is divided into five chapters, with the critical
Chapter One: Chapter One emphasizes the introduction, the background of the study,
historical background, research problem, purpose of the study, the significance of the study,
27
research design, objectives, research questions derived from the existing literature, hypotheses to
correspond the research questions, the structure of the thesis, and limitations.
Chapter Two: Chapter Two emphasizes the literature review, comprising intellectual
works and reviewed articles on construction projects, delay components, classification of delays,
and their impacts. This review will serve as the foundation of the study.
Chapter Three: Chapter Three sets out the methodology, the purpose of the study,
research design based on a quantitative study, reaffirming the research questions, hypotheses
corresponding with the research questions, population and sampling techniques, research
instrument, instrument validation to ensure the reliability and validity of data, data collection
procedures, and the conceptual framework to access the impact of the construction project in the
church.
Chapter Four: Chapter Four delivers the demographics (age, profession, level of
education) along with the data analysis of all the data obtained from the persons involved in the
construction project as in the stated hypothesis. This data analysis is in line with confirmatory
factor analysis, descriptive statistics, and exploratory factor analysis, and for each of the
hypotheses in the study constructs. Additionally, the validity and reliability analyses and the
correlation were performed, and the results are presented in chapter four.
Chapter Five: The last chapter offers conclusions and recommendations of the research
that links Chapters Two and Four. It also looks at the summary of the results from chapter four,
discussions of the results, and conclusions, both theoretically and empirically. Practical
recommendations to overcome Church construction delays are provided in this chapter. Finally,
recommendations for future research are presented. Figure 1 shows the structure of this study.
28
Figure 1
Note. This figure establishes the main structure of the thesis, indicating the beginning of the
introduction stages; chapter 2 deals with the theoretical review. Chapters 3 and 4 discuss the
29
Research Questions and Hypotheses
This study was primarily focused on six sets of questions based on the literature review:
construction Delay?
construction delay?
construction delay.
construction delay?
construction delay?
30
H4a: There is a substantial relationship between project-related factors and Church
construction delay.
delay?
construction delay.
construction delay.
construction delay?
construction delay.
The present study was hindered geographically concerning the chosen terrestrial size. It
was centralized in the Akuapem Presbytery, which is just a part of the eastern region of Ghana.
This brings a concern to any bid to take the study in a broader view. Although, it can be posited
that the findings of this study are like Church construction delay in other PCG Presbyteries, to
generalise them to the churches in other developing countries would be problematic. This suggests
that in other churches or developing countries, this model could be employed for further research.
This will assist in discovering the strength and usage of the model from the perspective of other
churches in Ghana or developing countries. Furthermore, many existing studies with adequate
information regarding church delay could not be used for executing this research as they were
31
Finally, since the study was quantitative, the researcher was limited in listening to other
opinions outside the questionnaire, though some of the respondents requested additional space in
the questionnaire to have their opinions aired. Nevertheless, this was not feasible owing to the
Summary
The delays in projects related to Church construction were a critical aspect to be focused on
as the delays end in missing the timeline for accomplishment, which results in boosting the
expenditure of the project (Famiyeh, et al., 2017; Larsen, et al., 2015). In this chapter, the problem
statement regarding the study topic was highlighted, which demonstrated that, owing to the
absence of sufficient aptitude in planning, ConD is encountered (Schwing & Urtasun, 2015). An
overview of the background of the study was adequately covered, which indicated that delays in a
construction project had raised global concerns (Fummey, 2017; Nyoni & Bonga, 2017; Wang &
Tam, 2014). A brief historical background of the PCG was given, which showed that PCG has 21
Presbyteries out of which Akuapem Presbytery recorded several construction projects in almost all
the 25 districts (Akuapem Presbytery Report 2013; 2014). The significance of the study was
addressed, which provided that a decent place is needed to facilitate the Church’s activities. This
study would also help in ensuring that proper measures are put in place to avoid any undue delays
and make judicious use of the available resources during church construction (Li, Li, Li & Wu,
2019). The chapter discussed the limitations of the study encountered during its execution, which
included hindrance geographically concerning the chosen terrestrial size, and outdated books and
32
Chapter 2: Literature Review
Chapter One of the research presented the introduction, the background, research problem,
the purpose of the study, research design, significance, research questions, hypotheses, and
limitation of the research. Chapter Two discusses the main problem under study with specific
aspects of construction project delays using the approach by Awuku-Gyampoh and Dzisi (2018),
which seeks to select current relevant literature materials with the year of publication from 2013
onwards. The core resources for the study include articles, books, theses, and dissertations from
Contextuality of the Problem. In the PCG, Church construction projects are key to
the safety and proper management of the church, as in all other presbyteries (PCG-Constitution
2016). However, in response to providing these infrastructures, there were church buildings and
minister’s residences (manses) which had been left unattended for several years, and there were no
signs of continuing the project. Some of these church projects had been abandoned, and the
building materials were disappearing while others had been destroyed (Shehu, Endut, and
Akintoye, 2014a). The increasing concern of congregants had emanated from several uncompleted
church projects within the local congregations and the districts (Akuapem Presbytery Report,
2014). Each year, budgets are approved at congregational, districts, and presbytery sessions which
specify church projects and questions are asked about what happens to the budget when the year
ends and the construction projects are still not complete (Flyvbjerg, 2014; PCG-Constitution
2016). Several strategies are used by the local congregations to raise funds annually to support,
among other top priorities, the construction projects of the church. Aside from this, projects and
investment committees are formed by each congregation to coordinate all church projects,
including construction (Akuapem Presbytery Report, 2014-2018). The question that remains
unanswered is why are church projects struggling for completion? Are there some elements which
trigger these rapid Church construction delays? What could be the ideal solution for the benefit of
33
the church, the community, and the country? Are there economic benefits to be derived when these
delays are controlled? The author seeks answers to these and many other questions, and will start
Review Direction for the Study. Delay is a critical concern for contractors and project
managers. It leads to high cost overruns when the deadline of a project is extended
(Monghasemi, et al., 2015; Marzouk, & El-Rasas, 2014). Several studies have been done on
construction delays, but hitherto the available works on construction delays have generally focused
on roads and other public institutions (Famiyeh, et al., 2017; Murwira, & Bekker, 2017). The few
scholarly works on Church construction projects are outdated, out of print or inaccessible on the
internet. The subsequent discussion here presents helpful resources for insight into the research
problem. It includes project management theories, with six construction delay-related components.
To be more specific, the areas are: delay components of the construction project (El-Gohary, Aziz,
& Abdel-Khalek, 2017; Kog, 2017; Smith, Beale, & Bowers, 2017), the classification of delay
(Chen, Shan, Chan, Liu, & Zhao, 2017) and delay factors in construction projects (Arditi, Nayak
& Damci, 2017; Senouci, Ismail, & Eldin, 2016). The rest are effects of project delay in
construction (Lu, Zhang, & Pan, 2015; Ojoko, Tanko, Jibrin, Ojoko, & Enegbuma 2016),
challenges faced in construction projects, and strategies available to improve the performance of
Review of Literature
The review of literature follows under six different headings. A critical examination of the existing
literature in the study is done by interacting with the materials through comparing, contracting and
synthesis. A summary is drawn at the end of the chapter detailing the key ideas.
34
Project Management Theories. In every organization or enterprise, there exist laid-down
rules, which serve as useful procedures to be followed in the execution of duties. In project
management, steps need to be followed to provide for the successful completion of tasks
(Heldman, 2018). The PMBOK Guide splits the methods of project management into five:
"initiating, planning, execution, controlling and closing processes." In a study, Tereso, Ribeiro,
Fernandes, Loureiro, & Ferreira (2019) discovered that there is a link between planning and four
of the known practices of project management and grouped them into toolsets. That includes
be the critical element in project management and runs through all the levels of the management
processes. Liu, Xue, Meng, Chen, & Sun (2020) found that the success of the project has to do
In a related development, Sofberi, & Zainal (2020) maintain that construction projects turn
into failures whenever there are lapses in the planning. In project management, making sound
decisions stems from proper preparation at the planning stages. The success or failure of the
project will reflect the amount of time invested in the early stages of the proposed work.
Improvement of work output cannot be made on any other level than the planning phase. Liu, Xue,
Meng, Chen, & Sun (2020) argue that the failure of project managers to achieve their set targets
can be linked to the type of project management procedure employed. Adopting the right process
with thorough preparation yields positively in project success. Tereso et al. (2019), emphasizing
adequate planning in projects at every level of the project management, further discovered five
modern lenses to be the most popular methods employed in project management. They include
baseline plans, Gantt charts, progress meetings, activity lists and kick-off meetings. These findings
are worth studying, and therefore, this study will consider the procedures used by Tereso et al.
35
Figure 2
Note. This figure displays the main features of project management. The focal areas are Initiating,
Planning, Executing, Controlling, Closing. Four toolsets make up the initiating/planning; the
Executing also has four toolsets while the Controlling comprises eight levels. It closures toolset is
also four. The planning runs through all the stages except the closure. Adopted from "Project
management practices in private organizations:" by Tereso, A., Ribeiro, P., Fernandes, G.,
Loureiro, I., & Ferreira, M. (2019). Project Management Journal, 50(1), p. 17. (DOI:
10.1177/8756972818810966). Copyright 2019 by Project Management Institute, Inc.
36
From Figure 2, the five philosophies of project management have been outlined as
study of the list provided in Figure 2, by Tereso et al. (2019) is like what was adopted from
PMBOK® Guide (2002), (as cited by Koskela, & Howell, 2002) as planning processes, controlling
Initiation Theory. The first stage of the project sequence in every project management is
the initiation theory. The initiating approach asks the question, "why" a task ought to be
accomplished and starts with defined objectives to guide the ideas. The project charter (scope and
goals) is then developed with the identified stakeholders. The need for the project, who the sponsors
are, and who to manage the project is extremely critical in this phase (Колеснікова, Бондар,
Москалюк, & Яковенко 2017). This is done through kick-off meeting to involve all the parties,
beneficiaries, and project managers to explain the intended project and begin the preliminary work.
The study of Tereso et al. (2019) ranked kick-off meeting, and project charter under the initiating
theory group and the latter placed in the first position as the overall most-used tool in project
management practices. Project charter was the sixteenth position in the ranking. In similar research,
Besner, & Hobbs (2006) found a kick-off meeting to be the second most used tool employed by
project management practitioners in the industry while placing project charter at the eighteenth
position. This is an indication that to a large extent, project managers use the kick-off meeting
approach for their opening planning, but not so frequently with the use of project charter.
Additionally, Колеснікова et al. (2017) maintain that there are four essential entities at the
initial level of project management, which are linked together for a collective goal. The list includes
the team for the project, the project location, the type of project and the client/owner. The project
37
team at the early stages decide together on the right site to host the intended project and involve the
stakeholders in the preliminary stages. According to Matu, Kyalo, Mbugua, and Mulwa (2020), the
stakeholders need to play an active role in the initial planning phases of the project to bring harmony
and united fronts. When stakeholders are involved from the preliminary stages of the project, they
understand and get motivated to keep track of the entire project process up to the closing phase of
Planning Theory. Planning has to do with the step-by-step outline of all the elements in
an anticipated project before its commencement. The advance groundwork puts in place what one
has decided to achieve within a given time frame. It is the arrangement of the pre-arranged ideas
and building on the pieces of information gathered at the initiation phase. Planning solves several
complicated issues and makes the execution of the proposed project smooth and less burdensome
(Schönbeck, Löfsjögård and Ansell, 2020; Sofberi and Zainal, 2020). A comprehensive analysis by
Tereso et al. (2019) reveals that the planning stage ought to be widely appreciated by a higher
percentage of the populace in project management. The preliminary phase is an obligation that
the forecasting phase of any project. Planning involves forecasting the activities of the project,
making room for a progress report, and provision for collating of the project outcome for
evaluation. Therefore, the failure and success of the project are connected to the initial plans put in
place. Whatever goes into the early planning surfaces in the output of the project. Taniguchi and
Onosato (2018), argue that effective planning advances reporting skills and aids the successful
completion of any required task. For the interest of this study, it will be beneficial to go deeper
38
Heldman (2018) explains that:
"…Schedule Development cannot be performed until all of the following core processes of
project Planning are completed: Scope Planning, Scope Definition, Resource Planning,
Planning, and Cost Estimating. Schedule Development must be completed prior to the Cost
Budgeting process, … Both processes then feed the final Planning process, Project Plan
In the view of Heldman (2018) the evidence of project success is likened to a detailed schedule
which is reliant on other relevant components ranging from scope planning to risk management
and budgeting. The progress of project planning cannot be made in isolation. All necessary steps
Mardiani (2018) maintains that whenever project managers plan a construction project,
they can evaluate the scheduled project to help in identifying potential risks that serve as threats to
the work. In this case, planners can make amends for both the existing projects as well as the
upcoming projects. Heldman (2018) stresses the worth of planning that the project's success is the
evidence of the volume of time devoted to the preparatory stages of the project. Taniguchi and
Onosato (2018) hold that there is a trio proportion of project management success. They include
being on schedule for the project execution, working within the projected budget and providing
details of the required work to help achieve the set goals of the set for the project. The planning
stage is all about "what and how?" Effective planning boosts time management cost control and
quality of the entire project. Project planning is directly proportional to the success of the project
39
Execution Theory. Execution is the “doing” of what was pre-arranged at the forecasting
stages. Thus, in the implementation of the required project, there must be coordination between the
design and the actual project. In a construction project, the architectural design is considered of
high importance at the planning stages and used by project managers to bring the plan into
operation at the execution processing stage (Leicht, Castro-Fresno, Dìaz, & Baier, 2020). In the
project execution, it is working on the schedule with the necessary stakeholders with the available
resources to bring the project charter to achieve the chosen project objectives. In brief, project
execution is the process of using the resources necessary to materialise the proposed project. Wen,
Qiang, & An (2017) discovered that clients/owners teaming up with the appropriate construction
management consultants would make project execution remarkably successful. There should be a
coordinated effort in pulling all the necessary specifications in the project charter to complete the
desired project. Tereso et al. (2019) detailed that the planning and the execution of any project are
simultaneous. This means that the execution stage is attained by observing schedule details for the
information to be managed, the people to be maintained, and compliance with the processes.
Nonetheless, Koskela and Howell (2002), argue that project managers often fail to deliver
projects as scheduled because of the lack of standard policies for project management. Fashina,
Abdilahi, and Fakunle (2020) think that poor communication amongst the shareholders and project
managers in project execution is, instead, the major challenge in the industry. In closing this gap,
Liu et al. (2020) point out that effective communication amongst the stakeholders and following of
the plan will promote a smooth execution of the project. In Figure 2, Tereso et al. (2019)
identification, Work Breakdown Structure (WBS), issue logged, and lessons learned. Yet, none of
those mentioned above met the most used procedure category. Project issue log ranked fifteenth,
and lesson learned ranked eighteenth among the seventy-nine tools, and procedures ranking used
as a yardstick. This implies that though the risk identification, WBS, issue log, and lessons learned
40
are familiar in the industry, they are not commonly used by project managers. One would agree
with Koskela, and Howell (2002) that the project execution process has not featured prominently
in the views of the stakeholders since the execution concept does not follow the required details.
The execution process must flow through delegation of responsibilities amongst all the parties
involved and with regular information flow to ensure strong working team (Wen, Qiang, & An,
2017).
Monitoring and Controlling Theory. Monitoring and Controlling are the checks and
regulatory measures applied to the executed project. Project monitoring and control runs through
the description of the project at the planning stage to the implementation and completion of the
project (Steinegger, 2020). In construction projects, paying attention to the project plan and
comparing it with what is being undertaken is monitoring. Supervising and Directing a project for
project performance are collectively done using the plan with the executed project as benchmarks
through regular meetings, recording and writing of the report (Tom& Paul, 2013).
In Figure 2, Tereso et al. (2019) revealed that the most used toolset under monitoring and
controlling are progress meeting, which ranked third in the analysis, with Gantt chart as the fourth
position and progress report in the sixth position out of the seventy-nine groupings assessed in that
study. This means that project managers regularly hold meetings on the ongoing projects with the
stakeholders to discuss up-to-date reports. Through the Gantt chart, the percentage of work done is
evaluated to give a clue to the outstanding work (Williamson & Scholefield, 2020). In another
development, Tereso et al. placed baseline plan (schedule, cost, and scope) in the fifth position, to
indicate that most project managers are familiar with examining the extent to which performance
deviates from the project plan. Customer satisfaction survey placed fourteenth and did not fall within
the first ten lists. The implication is that the project managers do not frequently find out the views
of their clients/owners on the executed project. Tom and Paul (2013) argue that the fact that project
41
management lacks adequate policies in the implementation of proper monitoring and control, means
On the other hand, Sofberi, and Zainal (2020) explain that in construction projects, the failure
or success of the work is determined at the planning phase and project managers must put in
maximum efforts to ensure a solid beginning that can be monitored and controlled for the project's
success. Every project that emphasises the monitoring of the approved plan with the ongoing work
can bring the entire project under control. In some cases, based on the project report, there can be
changes to the original request of the project plan (Tereso et. al., 2019; Tom & Paul, 2013).
Closure Theory. Project closure is the last stage that sums up all the events on the project
and the contract. The closing of the project is a sign of accomplishment. It can be the brief part of
the project management practices, or sometimes several demands need to be fulfilled for a mutual
settlement and future development (Sarfraz, 2009). In an article, Matu et al. (2020) argue that project
completion takes its direction from the active involvement in the project initiation. That is, both
project closure and the preliminary phrase have a healthy relationship. If project managers can
identify and involve the right stakeholders in the first phases of the project, there will not be much
chaos and stress at the closure stage. Zohrehvandi, Khalilzadeh, Hajizadeh and Cheraghi (2017)
found that many challenges like disagreements over entitlements, inadequate budgets and
insufficient resources occur at the closure phase of the project. What then is the right way to close a
project? Projects are closed mutually to ensure a smooth transition and to promote good after
contract relationship. It is significant to make an appraisal of experience learned and mistakes made
to serve as a guide to avoid repetition while being encouraged to build on the positive side.
Attaining approvals from all the parties involved in the project to validate acceptance of the
completed project is necessary. Sarfraz (2009) asserts that one of the challenges at the project
closure is the loss of interest before the completion of the project. Hence, getting the
clients/owners to sign the document endorses that the project is approved and serves as evidence to
42
indicate that no caveat can be raised on the closure of the work. Once the signature is appended, it
means that both parties agree on the completed project, and the contract must be closed positively
before picking up a new one. Ziddah, (2017) is of the view that delay and lack of documentation
interrupt the project closure process and that can hinder the final computation of cost for the final
payment to be made. Finalised reports are given on the whole project to specify recommendation
for future projects and not the limitations and the mistakes. Transition support is commended
before the implementation; the next parties to manage the project must understand the detailed
terminologies for a smooth hand over accordingly (Zohrehvandi, et al., 2017). The resources used
must be released, and all equipment, including unused materials, are to be returned to the right
office or persons. There must also be the need to archive all documents used in the project to serve
as references to give direction and to celebrate project success. Whether the project is cancelled or
completed, there is the need to end the project officially, and this involves a process called close
temporary venture, having a specified time and cost, and the intention is to create a unique and
attractive building that has a minimal edition. Effective teamwork for the entire project helps in
achieving the success of a construction project (Larsen, et al., 2015). These functions include a
high-level of coordination on the part of the workers, plant, and materials, and the permit for
construction and, as a result, delays have been quite prevalent in the construction industry. The
more complicated (Chen, Jin, Xia, Wu, & Skitmore, 2015). Along with these, various kinds of
delays occur during the construction of buildings, churches, and other related church projects. The
construction industry is an essential area that leads to the improvement of the economy of a
country. It is regarded as a tool that helps in the accomplishment of the public regarding the
time beyond the mentioned date for the positive finishing point of a construction assignment
(Chai, Yusof, & Habil, 2015). Some of the significant activities that are undertaken for the proper
construction of a church are the purchasing of construction materials, earthworks, levelling and
cleaning of the construction area, selection of a qualified contractor, and mobilization of the
church members to mitigate the delays considerably. The characteristics of the modern
construction projects are guided by innovative technologies, the participation of multiple parties,
frequent changes as desired by the owners, and new standards. Delay can be, and is, one of the
constant troubles in this industry. Certain factors describe contemporary construction projects,
such as propelled advances, constant changes as per the desires of the proprietor, and benchmarks.
It is an undertaking that slips over the scheduled timetable and is regarded as a significant issue in
construction projects (Belis, Pronk, Martens, Van Lanker, & Dispersyn, 2015).
Note. The label "a" through "i" (a-b-c-d-e-f-g-i) shows the original expected completion date. The 'j'
indicates that the work delayed, and the time of completion extended. Delays in the construction
project. Adapted from “Delay mitigation in the Malaysian housing industry”: A structural
equation modelling approach by Chai, et al. (2015). Journal of Construction in Developing
Countries, 20(1), 65. pg. 67. Copyright 2015 by Journal of Construction in Developing Countries.
44
Critical and non-critical delays. Critical as well as non-critical delays are widespread
within the construction industry and need to be treated as important. The critical delay is a
category that causes delays in the completion of the whole project. In contrast, non-critical delays
are the ones that do not have much effect on the completion time of a construction project. The
problems arising out of the critical delays have the primary source of forecasting of the Critical
Path Method (Akomah & Jackson, 2016). There are specific objectives via the critical path
• to identify the proceedings in the plan that provide the main risk of impacting the
• to identify the degree to which the vital activities might slip without any delays in the
There are two principal methods for the estimation of the date of a project using this
critical path method: The Backward Pass Calculation and the Forward Pass Calculation. The
Forward Pass helps to compute the QuickStart as well as quick termination dates for a project. On
the other hand, the Backward Pass estimates the dates of a late start and late finish (Zheng,
Jayasumana, Romera-Paredes, Vineet, Su, Du, & Torr, 2015). There are certain factors upon
• the physical constraints of a project that entail the way to build a job from a practical
point of view
• the necessities of a contract for phasing and sequence (Hammanda, et al., 2017)
45
There is a significant factor that, irrespective of whether one chooses to conduct an analysis
of the schedule of a construction project for the identification of the delays, is always present that
the contractor needs to give greater attention to this critical factor (Chen & Koltun, 2016). Each
project of the construction industry has a critical path, and the date of completion of the project is
impacted when there are delays in the critical activities. There are specific criteria for the
determination of the date of construction project completion (Schwing & Urtasun, 2015). These
include the project, the duration of a contractor in relation to the critical path activities, the
sequence of activities for the completion of the project and phasing, as well as a project’s physical
restraint (Jia, Shelhamer, Donahue, Karayev, Long, Girshick, & Darrell, 2014). The results of the
critical delays are extended field overhead, labour and material cost escalation, unabsorbed home
office overhead, idle labour and equipment cost, and liquidated damage.
type of delay that comprises more than one kind of delay component, irrespective of their types,
that either overlaps after a certain period or occurs at the same time (Chen, et al., 2017). It
becomes relevant to identify the type that is accountable for the delay in the entire project finishing
point. Thus, certain aspects, such as the duration of the delays, float ownership, the occurrence of
delays, and others, need to be taken into consideration. The concurrent delay is a type of delay that
is caused by the project owner or a general contractor that profoundly affects the project schedule
as well as the project completion date (El Gezery, 2018). Each of the project delays occurring
within the same period affects the completion time. It is the occurrence of multiple delays
simultaneously; one is the contractor risk incident and an additional one is the employer risk event,
and their effects. In many cases, business organizations remain entitled to cover the extra costs
because of delays. It is significant to identify the concurrent delays, as the owners increasingly use
this process as a tool for avoiding excess billing due to overhead and change of orders. Concurrent
delays result from the presence of multiple excusable delays that occur within the completion time.
46
Non-concurrent delays take place when the critical path of the schedule of construction is
affected by a single activity (Gardezi, Manarvi & Gardezi, 2014). Non-concurrent delays can be
excusable delays taking into consideration compensation that can give some relief to the contractor
by extending the time, remission of potential delays of damages concerning a given circumstance,
and liquidated damages. It can also be an inexcusable delay where the contractor may have an
enormous impact on the finishing date simultaneously with the owner (Gardezi, et al., 2014).
Compensable and non-compensable delays. Compensable delays are those that are
defined in the contract in most of the cases. There is an ability for the contractor to be
compensated for the cost of delay in any construction project based on circumstances. It is also
known as no damages for delay. The situation where the contractor is solely responsible for the
(Chen, et al., 2017). It is a type of delay that occurs due to unusual weather, fire, flood, or strikes.
It occurs when there is a lack of anticipation about the weather during that time of the year. The
contractor has the authority to extend the time of the project when there is severe weather. The
determination of the factors that constitute severe weather is based on the historical data of the
specific area (Baiden, Abdul-Razak, & Danku, 2015). A contractor should make a representation
about the weather conditions they have experienced so that they can request a time extension for
unusual weather. Non-compensable delays are ones where the contractor can only request a time
extension but not any other monetary compensation. Whether or not a delay is compensable
depends mainly on the terms of a contract. In most of the cases, a contract makes a note of the
types of delay that become non-compensable (Getahun, Macarubbo, & Mosisa 2016).
Excusable and non-excusable delays. Excusable delays are the ones that become
unforeseeable and are not within the control of a contractor in the construction industry. By
contrast, non-excusable delays are those within the control of a contractor. The main difference
47
between these two delays plays a significant part in the determination of the party that will be
liable for the delays. It also indicates whether a contractor can extend the project time and whether
he would be entitled to compensation for this date extension (Arditi, et al., 2017; Islami, Yang, &
The main reasons for excusable delays can be natural calamities, terrorist attacks, force
majeure clauses, political or social unrest, and delay by clients/owners. On the other hand, non-
excusable delays occur due to variety of reasons such as delayed procurement, delayed
mobilization, planning and scheduling, critical events that have not been made known to the
clients/owners at the time, and late submission of significant documents. Agyekum-Mensah and
Knight (2017); Amoatey, Ameyaw, Adaku, and Famiyeh (2015); Muhammed (2016); and Rao,
Shekar, Jaiswal, Jain, and Saxena (2016) found that certain events act as the source of excusable
• floods
• changes directed by owners (Agyekum-Mensah & Knight 2017; Amoatey, et al., 2015;
contractor to meet with the representatives of the workforce or through unfair labour
Delay factors in construction projects. There are numerous dynamics responsible for
delays in the project management of the construction business. Some researchers have described a
categorization of the causes of delays (Chen, et al., 2017 Islami, et al., 2015; Khahro, & Memon,
2018). There are certain geographical limitations which prevent this research from being applied
(Muhwezi, Acai, & Otim, 2014). For this reason, there have been several types of research about
the causes of the various kinds of delays. Some factors are major while the others are minor. The
literature review has indicated the classification of various factors in groups of numerous
related (Sambasivan, Deepak, Salim, & Ponniah, 2017), engineer-related, managerial dispute
factors (Gebrehiwet & Luo 2017), project-related factors (Aziz, & Abdel-Hakam 2016) and
Church organizational structure. The sections below will outline the details.
Potential delay issues. The possible delay features of Construction Projects include design-
include those related to the architectural designing and planning of the project, through to its
successful initiation and completion (Aziz, & Abdel-Hakam, 2016; Ramanathan, Narayanan, &
Idrus, 2012). The issues in design-related factors cause hindrances in the execution of construction
as the appropriate way to execute each step in building the construction is not known by the
contractors or engineering related to the project. Equipment-related factors include those that
2016). The lack of sufficient availability of equipment slows down the construction process and
49
creates hindrances in its completion. Labour-related factors include the workforces which are
involved in carrying out the construction, according to the designed plan and structure
(Gebrehiwet, & Luo, 2017). The client/owner-related factors are same as client/owner related
factors (ClientRFs) where the clients are the owner of the building to be constructed (Osei-Kyei, &
Chan, 2015). Thus, inappropriate involvement by them causes hitches in the execution of the
project as legal issues and disputes arise during the project. Engineer-related factors include those
that involve the different forms of engineer related to the construction project (Senouci, et al.,
2016). The lack of coordination among the engineers creates hindrances in the execution of the
project as well as increasing time in its building. Below are further descriptions of four other
components of delay under broader headings, they include, contractor-related factors, consultant-
labour and proper availability of materials act as the critical factor of success for the effective
execution of the building of construction projects (El-Gohary, et al., 2017). Several studies
have been carried by El-Gohary et al. (2017); Senouci et al. (2016); and Sohu et al. (2016) on
specific critical dimensions for assessing their relative contributions for scheduling delays in the
construction sector. There can be financial difficulties, problems of forecasting and preparation,
tool breakdowns and maintenance problems, shortages of material and equipment, shortage of
workforce, and slow mobilization, which have been identified as the key contributors for
contractor-related delay factors (Arditi, et al., 2017). Some of the primary considerations for
contractor-related factors are the challenges of cash flow and financing, inadequate human
resources, and poor project management (Mohammed 2016). Inadequate skills of the contractor’s
technical team, insufficient supervision, and site management, as well as difficulties in financing a
project, are also factors that have been identified as critical (Xiong, Skitmore, Xia, Masrom, Ye, &
Bridge, 2014).
50
The insufficient supply of resources and financial intricacies of the contractors are the focal
aspects of the occurrence of the delay. Some of the other delay factors related to contractors are
project, difficulties of the contractors in financing a project, conflicts involving the contractor with
other parties, and the reworking of activities (Gbahabo & Ajuwon 2017; Xiong, et al., 2014).
These conflicts are caused by errors made at the time of construction, ineffective planning,
project by the contractor, delays in the work of the subcontractors, high frequency of change of
subcontractors, and inadequacy of work (Vasilyeva-Lyulina, Onishi, & Kobayashi 2015). These
are the result of inefficient work, delays in the mobilization of the construction site, and inadequate
qualifications of the technical staff of the contractors. Other factors may include a shortage of
human resources and the commitment of errors during the construction activities being affected by
delays in the delivery of materials for a construction project and inadequate finance (Pall, Bridge,
brings about delays in contruction assignments. Lessing, Thurnell, and Durdyev (2017) asserted
that the late issuing of instruction by the owners or contractors, rough drawings of the designs, and
inadequate supervision by the different parties lead to consultant-related delays (Soomro, Memon,
Chandio, Sohu, & Soomro, 2019). Inadequate supervision by the consultants is a major cause of
this type of delay. Delays in the approval of changes within the scope of work, lack of proper skill
on the consultant’s part, and the late review of design documents are also responsible for delays in
the construction of a church or other building. Slow preparation of drawings, approval of the
drawings, incomplete specifications of the designs, rough drawings, and significant changes in the
designs may also create delays (Smith, et al., 2017). Commitment of errors by the designers and
inappropriate communication between the consultant and the client/owner are other factors to be
51
considered when discussing delays in construction processes (Dosumu, Idoro, & Onukwube,
2017).
Additionally, an inspection of all the functions takes much time, during which the progress
of the construction may be delayed for a substantial period until the plans can be be agreed (Smith,
et al., 2017). On the other hand, a lack of commitment from the consultant and architect affect the
construction system. Errors in the contract, as well as discrepancies and mistakes in the
documents, are also responsible for delays in the construction industry (Muhwezi, et al., 2014).
The significance of the various kinds of delays is that they have a ripple effect on the parties
associated with the activities of construction and even the citizens in the economy of the country.
The impacts of the delays are universal, irrespective of the delays that are restricted by
geographical factors. Wu, Ann, and Shen (2017) revealed that all the respondents selected cost
and time overruns as the most frequent reason for delay in construction projects. The excess cost
associated with the construction activities acts as a nuisance to the parties concerned in the
construction process (Aziz, & Abdel-Hakam, 2016). Taxpayers are not receiving a proper return
for their money due to cost overruns. The same is true for the contractors who are experiencing
abnormal losses and cash flow crises. The reputation of the consultants is also considerably
harmed, as the clients/owners lose confidence in the execution of their plan(Ngomi, 2017).
Another noticeable impact of the construction delay factor is the abandonment of entire
projects. Hence, this leads to the reduction of employment opportunities, loss of revenue for the
government, a slowing down of the economic activities, and the deterring of foreign investors
from the funding of construction projects in the economy of a country (Prasad, et al., 2019).
Testing of the activities also takes much time, and the consultants become responsible for this.
Contract management, quality assurance as well as control, and greater waiting time for the
authorization of tests and inspections are factors that are also responsible (Lessing, et al., 2017;
52
Client/Owner-related delay factors. Some studies have revealed ClientRFs to be
responsible for schedule delays (Asiedu & Alfen, 2016; Pall, et al., 2016). On the part of the
challenges in cash flow, delays are triggered in construction activities. (Sambasivan, Deepak,
Salim, & Ponniah, 2017). Another study showed that factors, such as deliberate decisions from
the clients/owners and inappropriate incentives for the contractors for finishing a construction
project before the estimated time, have an enormous impact on a construction project, leading to
delays (McCord, McCord, Davis, Haran, & Rodgers, 2015). Delay in payment of the workers,
including contractors, and regular changes may lead to delays in the construction project. Delay
factors in relation to the clients/owners include delay in equipping and handing over the site by the
contractor, late revision and approval of the design documents by the client, delays in the
endorsement of sample materials as well as shop drawings, poor communication, and coordination
by the title-holder and other parties involved in the whole process of construction in the
construction industry (Chen, et al., 2019b; Niazi & Painting, 2017). Other factors are
disagreement involving joint ownership in a construction project, lack of incentives and bonuses
forthe contractors and workers, suspension of work by the workers and owners, and slowness in
the decision-making process by the client/owners (Murwira & Bekker, 2017). Frequency and
sudden stoppages of construction work because of challenges of cash flow and delays in making
payments in due time to the construction workers are the main reasons behind this category of
delay (Nyoni & Bonga, 2017). Gbahabo and Ajuwon (2017) have acknowledged the factors of
payment and financing of the completion of works and changes in design by the clients/owners are
External-related factors. There have been peripheral, interrelated, delay factors in the
construction industry, known as external-related factors. They are one of the causes of schedule
delays. Some of the significant factors are price escalation and labour disputes as well as strikes,
53
slow granting of permits on the part of the government, civil disturbances, acts of God, and
inclement weather (Arditi, et al., 2017). Another study revealed that any kind of delay from the
authorities regarding work permits is very significant in this kind of delay (Muhwezi, Acai &
Otim, 2014). Unfavourable weather conditions are also responsible for the occurrence of
externally-related delays (Agyekum-Mensah &Knight, 2017; Arditi, et al., 2017; Muhwezi, et al.,
electricity (Dolage & Pathmarajah, 2015; Lines, et al., 2015; Najib, Soon, Zainal,
Other researchers, such as Lines, Sullivan, Smithwick, and Mischung (2015) and Najib et
• Delays in final inspection and certification by a third party; and delay in services
Furthermore, certain aspects, such as legal disputes, shortages in the supply of construction
materials in the market, delays in the manufacturing processes of specialized building materials,
and penalties for ineffective suspensions of the project, also trigger the external kind of delay.
54
There can be delays because of the unforeseen ground conditions as well as long waiting times for
distinct types of drawings that can act as significant factors for construction (Kagiri & Wainaina,
2017). In addition to these, another study revealed that unfavourable weather conditions and
subsurface soil conditions are vital contributors to the various kinds of delays in the construction
industry (Adam, Josephson, & Lindahl, 2017). Certain factors, such as harsh climate conditions at
the site of the construction projects, hostile social environment, as well as hostile economic and
political environments, act as key contributors to delays in construction (Sinesilassie, Tabish, &
Jha, 2017).
Managerial disputes. Conflicts that arise during the construction project and the
administrative dealings with such disagreements are known as managerial disputes. This is the
resolution or alternative dispute resolution in the construction work. According to Sutar and
Mehendale (2017), the construction industry is project-based, encompassing all contributors such
as the constructors, clients/owners, designers, consultants, and contractors with different cultural
backgrounds. These diversities usually lead to misunderstandings, conflicts, and disputes, which
impede the progress of work. Kim et al. (2018) argue that Human Resource Management (HRM)
is vital in the construction firm in managing the personnel in the field and offering guidance in
In construction, effective planning and efficient HRM plans ultimately affect quality,
budgets, and work schedules at the project level. However, these strategies are sometimes
interrupted by certain foreseen and unforeseen challenges that breed disputes and conflicts
(Arantes, Ferreira 2020). According to Madalina (2016) and Alpkokin and Capar (2019), conflicts
and disputes are pervasive in humanity. They are directly related to diversity, detachment of roles,
and obligations. The disputes that may arise from unresolved conflicts interrupt the flow of
planned activities. The PCG Constitution (2016) holds that the local church has enough room to
handle minor disputes before they get out of hand. It states, “the Senior Presbyter shall settle minor
55
disputes in the congregation referred to him/her by the Session or the Agent” (p. 25). Consonant
with this, Baker and Keiser (2019) and Merrills (2017) hold that a dispute becomes impossible to
The studies of Aziz and Abdel-Hakam (2016) and Gebrehiwet and Luo (2017) found that
the issues that trigger disputes and conflicts in Church construction delay include:
• Poor communication between owners and contractors (Chen, et al., 2019b; Madalina,
2016)
• Poor organization structure and frustrating procedure for dealing with society and
governmental regulations.
Financial mishandling. According to Gebrehiwet and Luo (2017) and Bowen et al.
(2015), the embezzlement of funds plays a critical role in project delays. Budgets compiled for
proposed projects are mismanaged and not adequately utilized for the intended purpose. Most
construction projects fail to materialize because they are either over-budgeted or under-budgeted.
Budgeted funds are mishandled, and shoddy work is presented in the end (Flyvbjerg, 2014).
Additionally, the study of Gebrehiwet and Luo (2017) ranked the causes of delay as
financial dishonesty, rises in the price of materials, lack of quality materials, late designing of
documents, late issuance of budgeted funds, ineffective planning, and scheduling of the project.
Nonetheless, Brunet (2019) argued that all the other activities revolve around the estimated budget
for the entire organization’s project. Any ongoing constructional project is forced to pause if there
56
Lack of supervision by the board. The absence of supervision by the contractor, the
site manager, or the congregational session is the lack of supervision (Arantes, & Ferreira 2020).
In a church construction project, the project committee, which is formed constitutionally by the
session, is mandated by the session to monitor work progress and update the session periodically
(Aziz, & Abdel-Hakam 2016; PCG-Constitution, 2016). In addressing the laborious nature of
project supervision, Sutar and Mehendale (2017) discovered ten tasks for site supervisors or
They include:
3. A guide to aid the junior engineer in interpreting scientific terms during the inspections.
corresponding parties.
10. Acknowledging and evaluating all resources in a comprehensive report (Sutar &
Mehendale, 2017).
Though Sutar and Mehendale (2017) outlined what site supervisors need to do, it is
significant to verify the circumstances that may lead to the negligence of duty by the site managers
neglecting their duty and whether that attitude hinders the workforce in the construction project
(Othman & Sokkar, 2019; Sutar & Mehendale, 2017). According to Chen et al. (2019b) and
57
Madalina (2016), poor communication is another issue affecting coordination. Absence of clear
and concise communication and the inability to use simple language to be understood by the
audience are significant issues that affect the smooth reporting and monitoring of an organization’s
activities. As a result, litigation and unresolved legal issues may arise to interrupt the progress of
construction change with political transitions. Until a building design is approved and permission
granted, no construction project can commence. In many instances, the registration process takes
two to five years to complete either a land title registration or a building permit issuance to begin a
construction project (Allen & Iano 2019). Some land documents get misplaced in the process of
registration, and the clients/owners must re-do and re-submit them. The tiresome nature of the
construction project (Lees, 2013; Mireku, Kuusaana, & Kidido, 2016). However, in the process of
working on some of these unregistered projects, the workers are stopped by the town and country
planning departments, and all tools and equipment are seized. The client is summoned to court,
and that starts another legal battle. Until the court case is decided and the ban on the land/project
is lifted, or the building permit is finalized, no work can be done. Mireku et al. (2016)
recommended that original landowners must endeavour to proceed with the final registration of
their lands at the land commission to have an official land title to curtail the stress in registration
after the land is sold. In a study exploring the primary sources of schedule delay, Rahman, Lee,
and Ha (2014) found political conditions to be a factor that can lead in the end to disturbances or
public strikes. Strikes will keep workers away from work for days or months, leading to the
58
Church organizational structure. Church organization structure has to do with all the
laid down hierarchies and procedures involved in the management of the church. In their study,
Sutar and Mehendale (2017) found that, in a construction project, active and well-organized HRM
strategies impact budgets, duration, and the value of the project outcome. The Church, PCG, like
any other organization, has a well-organized structure from the General Assembly to the
Presbytery, the District, and the congregational level. The congregational line of authority from
the top to the bottom is the structure of the church (see Figure 4).
59
Figure 4.
Notes: The order of church leadership from officers to session, administration, departments,
(2020)
60
Changes in Church Agents. Change is seen to be good and helps one to experience a new
culture and have different exposure. However, certain changes do more harm than good. The style
In the PCG, Agents-in-charge (Ministers or Catechists) are rotated and are given between one to
five years before being transferred. This rotation continues until a compulsory retirement in the
seventh year of the position (PCG-Constitution, 2016). In changing Church Agents, ongoing
projects commenced by the previous administration are expected to be continued, but this is often
not the case. Every leader seems to have an exceptional vision and style of administration at every
point in time. Some Church Agents ignore an existing construction project in the church and bring
a new project for execution (Akuapem Presbytery Report 2013, 2014; Vaccaro, Jansen, Van Den
Bosch, & Volberda, 2012). However, Doppelt (2017) found that change is gradual and significant
in sustaining an organization. The changes in administration, if not well managed, will lose their
main intention; managerial changes without guidance are futile, and non-leading changes break the
chain of sustainability. However, in another study, Doppelt and McDonough (2017) argue that
factual change in the direction of sustainability results in transformed principles and customs that
are geared towards choices impacting all spheres of the administration dissimilar from the status
quo. Directional leadership, aiming at long-term development, alters the usual norms of the
organization.
Institution; style of leadership impacts the progress of the organization’s activities, and decision-
makers’ innovation is subject to their background/ origin and perspective (Vaccaro, et al., 2017).
Leadership is significant in any local congregation of the PCG. Each congregation is “under the
jurisdiction and supervision of the District under which it was established or under which it was
placed in the presbytery” (PCG-Constitution, 2016, p. 18). The Agent-in-charge, comprising the
minister or the catechist; the senior presbyter; and the session clerk are the principal officers of the
61
congregation to ensure implementations of decisions. The session is made up of selected
presbyters elected by the congregation, with a total membership of up to 50, depending on the size
property within their jurisdiction such as the place of worship, Church institutional buildings and
congregational houses for Church Agents (Ministers and Catechists)” (PCG-Constitution, 2016, p.
19). This indicates how powerful the session is and, if the members are not innovative with
excellent leadership skills, it determines the outcome of any construction project they start.
According to the PCG-Constitution (2016), the session is the highest court at the
congregational level and is to make all the decisions of the congregation. The principal
congregational officers work together to implement the session’s decisions and update session
frequently. The Agent-in-charge is considered the general manager of the local congregation and
the moderator of the session. In their study, Sutar and Mehendale (2017) found that a general
manager:
• monitors and ensure that guidelines for the construction project are followed.
• Performs regular appraisal for improvement; and frequently briefs the board of
Additionally, Volberda, Van Den Bosch, and Heij (2013) asserted that leadership’s low
confidence level and lack of determination negatively affect decision-making while absence of
innovation impedes progress in all areas’ life. However, Durdyev and Mbachu, (2018) establish
that bridging excellent leadership and motivation will reduce setbacks in the construction projects.
Budgets. The estimated itemization of all costs of the entire project includes material,
labour, consultant, contractor, and administrative costs from the beginning of the construction
work till the end of the project. The PCG-Constitution (2016) allows all local congregational
sessions to draw up and approve a budget each year through the PIC. They present the budget for
62
approval by the session. If budgets are adopted by the session, it is important to understand why
construction project funds are diverted into another project. According to Brunet (2019), the
absence of strategic planning does not help to complete a project on time. Diversion of budget to
other unbudgeted projects leads to confusion and the inability to complete the desired project. In
the Akuapem presbytery report (2013) and Akuapem presbytery report (2014), most congregations
have been out of funds in their ongoing constructional projects. This eventually brought the entire
construction work to a halt. In response to this challenge, Asiedu, Frempong and Alfen (2017) and
Algwyad and Talib (2019) advocated that decision-makers, as well as project managers, must
make provision for contingencies in their budget and observe it to prevent cost overruns.
Moreover, Taniguchi and Onosato (2018) found that paying much respect to budgets and
work schedules results in the ultimate accomplishment of construction projects. If the approved
budget is not respected and worked with, other things, like time and work quality, will be
eventually affected. The work progress is interfered with if the estimated funds are not released on
time for materials and payment of other outstanding bills (Othman & Sokkar 2019). According to
the PCG-Constitution (2016), the session needs to prepare an annual budget and observe the
guidelines on funds mobilization, stating that “the funds of the congregation shall, a). Include
tithes, offerings, donations, and income from any other source approved by the session. b). Be
administered by the congregational session, and c). All sums of money received on account of the
congregation shall be paid into such bank as the congregational session may determine” (PCG-
Constitution, 2016, p. 22). Though the constitution of the PCG gives the sources of the funds for
the church, it is flexible on the types of bank accounts to be created. This begs the question of
whether this is the reason for not having specific bank accounts for the church construction
projects. Baker and Keiser (2019) asserted that a clearly stated constitutional clause helps the
parties involved to avoid conflicts. Long-term strategic planning, in most cases, is guided by the
organization’s constitution. The effectiveness of the forecast of activities needs to follow the aims
63
and objectives of the firm or the organization. Contractors need to monitor initial arrangements,
including funds for the project, to avoid project duration extension (Kim, et al., 2018).
by Mulugeta (2019) found that effective communication within an organization, such as the
church, strengthens the bond and creates a decent connection between the decision-makers
(session) and the congregants. It minimizes all forms of criticisms and launches an excellent
working spirit amongst the team and it builds reciprocated thoughtfulness between followers and
upper administration. In the management of the church, the session, which comprises the Agent-
in-charge and a selected group of Presbyters, is the principal decision-makers of the church (PCG-
Constitution, 2016). When the session makes any major decision that involves the attention of the
congregation, it is constitutional that the session Clerk must “communicate decisions authorized
25). The PIC is to be informed in writing or invited for a meeting on any decision the session
However, Mulugeta (2019) found that communication does not flow effectively in most
organizations. Top officials usually do not disseminate information to the members or employees.
Sometimes, employees may not be aware of an ongoing project and, in turn, give their own
interpretations. The activities of the organization are not made public, and the notice boards are not
updated. It must be established whether this assertion is accurate in the case of the church and if
there exists a communication gap between the decision-makers (session) and followers
(congregation). In connection with this, Madalina (2016) observed that traces of a break in
communication could be seen in situations such as a lack of feedback, not disclosing the realities,
According to Wyer (2019), when a piece of information is not presented correctly, the
64
Madalina (2016) found that, even though breaks in communication are probable and, at times,
inevitable in organizations, if they are not aptly addressed, they lead to conflict and unhealthy
disputes in many institutions. When communication does not have its place in Church construction
Project-related factors. Time is vital in any construction firm, just as cost and knowing
the use of time and cost helps in forecasting a proposed project. The initial arrangements prior to
commencing the drawings/ designs and engaging a consultant or a contractor are incredibly
significant to the project’s success. Abhishek et al. (2017) found that project-related factors
(ProjRF) influence construction negatively when there is inadequate infrastructure for workers or
logistics at the construction grounds; that is, workers’ inability to get to the construction site on
According to Aziz and Abdel-Hakam (2016), the top-ranked roots of Construction Delay
under Project-related factors are inappropriate project viability study, perverse project duration,
complicated project, unsuccessful delay penalties, and the nature of project bidding and award.
This was revealed in a study that found 293 triggering categories of delay which were further re-
Inappropriate project viability. Some of the proposed projects are very complex in
nature; they are not well planned or designed before their commencement. Such unsuitable
projects get shelved along the way. If the construction project does not seem to be realistic and
achievable, it becomes difficult to be executed, partly because the project will run out of time due
inadequate details and no risk appraisal in the designin/ drawings (Ramanathan, et al., 2012). In
another study, Famiyeh et al. (2017) discovered that impractical contract lengths demanded by
clients/owners and poorly-defined details of the project in the drawings impose a burden on the
execution of the project. The unrealistic nature of the scope of work makes it difficult to complete
65
the work on time. If the scope in the building design lacks enough details and specification,
coupled with insufficient risk assessment, the challenges are immense (Awuni, 2019). The effects
of subsurface conditions were also identified as potential delay factors for the project. For
instance, if the soil has a high water table, it is considered to have an impact on the environment
explicit terms and conditions attached for straightforward interpretations and implementation by
the contractor and subcontractors. Asiedu and Alfen (2014) disclosed that the failure to implement
all contract requirements by the parties involved affects project progress. If the contract clauses are
not spelt out, there are disparities and a whole lot of consequences happen as a result of changes in
site or working conditions. The study by Akogbe, Feng, and Zhou (2013) added that insufficient or
poor preparation before the commencement of the project is one of the significant factors of
project delay. Inadequate forecasting of the nature of bidding and award to be adopted in awarding
the contract may lead to giving the contract to an unqualified contractor. Sometimes the original
contract duration is limited in the contract, which is about double the estimated duration (Famiyeh,
Legal disputes between project participants. When agreement is not reached, or if the
parties involved in the projects are not in accord, it changes the comfortable atmosphere of the
the parties involved may lead to strikes and other unhealthy challenges (Wallensteen, 2018). It is
identified that the lack of long-term strategic planning to sustain the construction projects breeds
occasional disagreement, which can end in legal battles between the participants (Famiyeh, et al.,
2017).
Finally, Akogbe et al. (2013) and Zidane and Andersen (2018b) found ten significant delay
66
1. Financial ability of the contractor,
9. planning,
insufficient project designs (Akogbe, et al., 2013; Zidane & Andersen 2018b)
This discovery is supported by the work of Gebrehiwet and Luo (2017), who similarly
3. materials inflation,
10. unproductive project forecasting and planning (Gebrehiwet & Luo 2017).
67
Out of the ten factors identified by Gebrehiwet and Luo (2017), six other factors were
found by Famiyeh et al. (2017) as the main influences on time overruns in construction. These
inadequate scope definition for the project, variations originating from the client, lower-cost
valuation of the project by the consultants, and inadequate check-up of the consultants. However,
Asiedu and Alfen (2014) narrowed the study to contractors, consultants, and clients/owners and
found five significant factors responsible for overruns in public construction projects in Ghana,
which were tardiness and indecision in payment of workers, lack of implementation of contract
requirements by the parties involved, discrepancies and extra work as a result of deviations from
the contract, undue price variations of materials, and deviation from the contract.
construction work. Attakora-Amaniampong (2016) argues that a project’s success is related to the
quality of the construction project, whereas Algwyad and Talib (2019) hold the view that quality is
wholly related to the execution of the project. The conditions attached to the accomplishment of
the project determine its outcome. The desire for standard construction projects has faced a myriad
of challenges. According to Rahman et al. (2014), construction projects have adverse influences on
the project’s quality. Though several factors lead to project delay, the quest to seek quality in
construction work has adverse consequences on the project cost and materials involved. The lack
of quality planning affects the budget when there is a rise in the cost of materials (Dixit & Sharma,
2019). For instance, during an ongoing construction project, any rise in material cost affects the
initial project budget, and this has a direct influence on quality if contingency plans are not put in
place (Asiedu & Alfen 2016; Durdyev, et al., 2017). Correspondingly, Larsen et al. (2015) argued
that, owing to inadequate funds and logistics for construction projects, both the church and the
state are faced with the sub-standard quality in the construction industry. Concerning value, the
construction projects are affected by many challenges whenever a client/owner fails to honour part
68
of the initial agreement. This results in progress on the project being left until the settlement is
made. Algwyad and Talib (2019) suggest that to overcome cost and time overruns, there must be
Furthermore, Zidane and Andersen (2018) found that a sluggish check-up process on
completed work affects quality. Lack of quality assurance from the beginning of construction can
lead to delays in the construction project. Every work that demands thorough examination or
inspection must be done well. Therefore, if a contractor is made aware of the strict guidelines for
the inspection of the final work and the unfavourable effects of the contractor losing the licence for
subpar quality work in the final project, matters will be taken seriously bythe construction firm.
An excellent and quality construction project has been compromised for lack of planning and, in
some cases, the entire building has been pulled down for the right building guide not having been
followed (Buys, 2015; Marzouk & El-Rasas, 2014). In addressing the situation, Asiedu (2016)
proposed that, to ensure efficiency and quality work, the government needs a development board
to assist in restructuring the main activities of the construction industry. There is a need for the
department of feeder roads and public works department to be active in the discharge of their
duties. In addition, Algwyad and Talib (2019) suggested that the inclusion of adequate motivation
Furthermore, Adam et al. (2017) argued that low qualifications of the contractor’s workers
and technical staff have an implication for the quality of the work. Improper supervision and the
absence of appraisals or review of staff along with the background of the consultant or the
contractor as well as their previous work can lead to sub-standard work being done. If the staff
have little or no knowledge of the project, there is the likelihood of their not being able to
understand the drawings and details of the construction projects. Tang, Mason, and Wang (2015)
found that essential skills in management and a suitable ability to take charge are the necessary
competencies for development in the construction phase, and managers need them to function on
69
the project. Explicit theoretical and practical abilities and experiences are required in the
management of the project. Also, Gebrehiwet and Luo (2017) found that poor quality of material
affects the quality of the project. The lack of technical know-how of the client/owner of the
project makes it difficult to authenticate the quality of the materials in an ongoing project.
However, in cases where the client/owner or the consultants are determined to ensure quality,
On the other hand, ensuring that the right construction standards are maintained can slow
the entire project if the preferred materials are not readily available. A study by Larsen et al.
(2015) found that the lack of a quality policy leads to mistakes or oversights in construction
projects, which eventually causes construction delays, affecting project quality. Also, lack of
inspection by the client/owner, the consultant, or the qualified body affects the quality of the
projects. If there are no guides for the building, it becomes difficult to ensure the excellency of the
construction work. Zhang and Yangb (2019) suggested the need for construction workers to
safeguard the project’s quality by observing the laid down rules and systems to fulfil the set
Material-related factors. Materials are pivotal in the building industry and using
the prescribed material for the project is paramount in the success of the project (Allen, & Iano,
2019). Material-related factors include those that are related to the required building material for
framing the physical structure of the construction. The ineffective choice and selection of
material-related factors cause hindrances, such as the accidental collapse of the construction and
others (Senouci, et al., 2016). The variables linked to the quality of resources and the availability
or shortage of building materials used in the construction projects are the material-related factors.
The studies of Asiedu and Alfen (2016), Arthur (2016), Gebrehiwet and Luo (2017), and Pall
(2016) found that late delivery of material to the site, delay in endorsement of materials, wastage
70
of materials, substandard quality of materials, higher material cost, and financial restraint of the
According to Durdyev et al. (2017), late delivery of material is among the prominent
triggering factors in delays in Columbia’s construction projects. Failure to release the required
material needed at the constructional site is believed to have the tendency to slow the construction
project (Gebrehiwet, & Luo, 2017). In another development, wastage of materials occurs when
cheap materials are bought, and owing to the improper storage of the materials leading to exposure
to rain and sunshine, most of these materials are destroyed (Soomro, et al., 2019). The
mismanagement of the materials from the market to the building site and within the site causes
most of the materials’ waste. The failure to make design changes with client/owner’s frequent
changes and theft, lead to material waste (Bekr, 2014). Again, KV and Bhat (2019) were of the
view that the financial difficulties of the owner/client can also lead to an inability to supply the
needed resources for the project. Contractors will not be able to carry out the scheduled work until
In another development, Chen, You, Sharifi, Yao, and Gong, (2019) recommended the use
of environmentally-friendly materials for the construction project so that it can last longer.
However, sometimes these branded materials to be used for the project can be out of stock in the
market at the time when needed. The contractor might also want a particular brand of material for
the execution of the project, and the tendency to be disappointed by the suppliers may prolong the
project (Akogbe, et al., 2013; Zidane & Andersen 2018a). Besides, when there are increases in
material prices, it impacts the entire budget and, in some cases, the client/owners go for a cheaper
material to fit the budget without considering the quality. On the other hand, the contractor, or the
client/owner sometimes, in requesting materials from the suppliers, may opt for inferior quality to
save money (Gebrehiwet & Luo 2017; Ogunde, Olaolu, Afolabi, Owolabi & Ojelabi, 2017).
71
Moreover, Sutar and Mehendale (2017) recommended that there must be adequate monitoring and
Effects of project delay in church construction. Project delay damages construction flow
and hinders the working efficiency and completion of the project. The key effects of project delay
experienced in a construction project include time overrun, cost overruns, litigation, abandonment,
arbitration, and dispute. As mentioned by Ojoko et al. (2016), cost and time overruns are mainly
triggered due to the delay of correct project estimates executed by the contractor. The contractors
cause this delay effect because they do not possess effective management and organization skills.
Thus, the contractors, before the execution of the project, requires a reassessment their skills so
that any inefficiency can be resolved, and project delays can be avoided. Project delay not only
hinders the productivity and performance of the construction but also results in obstructing the
Time overrun. Time overrun refers to a situation where the contractor has not been able
to execute the construction project during the timeframe mentioned in the contract (Asiedu, 2015).
The time overrun experienced in a construction project can be categorized into two groups, which
include non-excusable and excusable delay. As mentioned by Amoatey et al. (2015), excusable
delay refers to those delays which are beyond the control of the contractor and are unforeseeable.
Excusable delays are caused mainly caused by the late delivery of instructions to the contractors in
executing further progress in the project, late approval in design and building materials, and late
access to the site enabling employees to do their work. As criticised by Marzouk and El-Rasas
(2014), the non-excusable delay is foreseen and triggered because of the lack of effective control
and organization by the contractor. Thus, once the project work faces a time overrun, it is evident
that it is not going to be completed within time, and it is required to extend the deadline for the
72
Time overrun requires that the party involved in unsound practices during the construction,
due to which the delay occurred, must pay a sufficient amount to the other party for compensation
of the damages done because of the project delays (Asiedu & Alfen, 2016). As mentioned by
Owolabi et al. (2014), construction projects often get delayed due to weather conditions which
render the contractor incapable of executing the project on time. Thus, in such cases, the
contractor can claim a time extension as the situation was not adequate in any way to complete the
However, Larsen et al. (2015) criticised the fact that contractors are unable to claim a time
extension in cases where a time overrun occurred due to their fault. This results in hindering the
execution of the project as materials, as well as money, are depleted, but no adequate return is
received from the construction project. The time overrun has a significant impact on church
construction, which adversely reduces the efficiency of its construction projects (Prasad, et al.,
2019). This is evident in the La Sagrada Familia Church in Barcelona, which was started in 1882
but due to ineffective time management, is still incomplete in 2017, and is not scheduled to be
completed until 2026. The time overrun impact on church construction was mainly due to trivial
reasons, such as complexity in the church design and interruption due to the Civil War, among
others. However, the impact of the time overrun has resulted in increasing the total construction
cost of the project along with the wastage of materials (Basilica De La Sagrada Familia, 2017).
project delay in construction because proper contractual agreements are not drawn up, which
occasions disputes and conflicts between contractual parties such as consultants, contractors,
clients/owners, and others (Dixit & Sharma, 2019). As mentioned by Lu et al. (2015), project
disputes occur because of a lack of effective communication between the contractors and the
owner of the construction. If the church or any institution fails to consider bridging the
communication gap in construction, disputes would be prolonged. Thus, the Project Manager has
73
to look after the situation and resolve the misunderstandings, disputes, and conflicts so that the
delay in construction can be resolved. As criticised by Vasilyeva-Lyulina et al. (2015), parties are
seen to be rigid in their attitudes and refrain from listening to the mediator while solving the
project disputes. This, in turn, creates project delays and damages the execution of the project, as
Disputes related to land acquisition, in many cases, are seen to affect project delays in
construction, especially in cases where the owner of the land bars the contractors from executing
construction work, resulting in conflict. In such cases, it is useful to appeal the decision to an
arbitrator to resolve the conflict (Chaphalkar, Iyer & Patil, 2015). The project disputes act as
threats affecting construction delay in a church. A notable example is the case of the land disputes
between the Roman Catholic Church in Weh and Indigenes of Weh Fondom. The report indicated
that the project dispute related to the surrounding land that is to be used by the church in the
expansion of their construction which has been going on for years, and that has resulted in
delaying their construction process for expansion. The arbitrator is also seen to have failed to
resolve the conflict, which has further added to the church construction delay (Lang, 2017).
officially appointed to resolve a dispute. However, many parties are often seen to show a refusal to
comply or accept the decision made by the arbitrator, resulting in hindered negotiation for the
execution of the construction project (Equbal, Banerjee, Khan, & Dixit, 2017). This, in turn, affects
delay in the construction project as disputable and inconsistent issues are raised. As mentioned by
Getahun et al. (2016), the choice of an active arbitrator is required; one who has a manageable
caseload so that the individual can concentrate on developing strategies and decision-making to
resolve the dispute for a specific construction project. The arbitrator with unmanageable caseloads
is often seen to execute decision-making in resolving disputes with great haste, which often
hinders the accomplishment of effective negotiation (Equbal, et al., 2017; Hughes, Champion, &
74
Murdoch, 2015). This negatively affects the project as delay in its execution is created because
collaborative and effective decision-making to execute the construction is not reached. The
arbitrators with practical legal and professional expertise are seen to have the experience to
develop well-reasoned and legally sound decision-making when resolving the raised dispute to
As mentioned by Komurlu and Arditi (2017), lack of practical legal knowledge by the
arbitrators causes them to make disputable legal decisions that adversely affect project delay. This
is because legal concerns create complications in the smooth execution of construction projects.
The arbitrators with improved practical knowledge are seen to act positively in resolving project
delay as they employ effective decision-making along with innovative strategies to resolve project
disputes with minimal time delay. As argued by San Cristóbal (2015), arbitrators require cost-
effectiveness in administering their services along with portraying strong management skills. This
parties, through collective decision-making, resolve their disputes in executing the smooth
Litigation. Many relevant parties concerned in a building project are seen to lack
acceptance of the collaborative decision-making executed by the arbitrator. This results in project
delays as conflict obstructs the proper progress of the construction process (Chaphalkar, et al.,
2015). Thus, litigation is used to resolve raised disputes. As mentioned by Amoatey et al. (2015),
litigation involves a legal proceeding which is undertaken with the help of the court to resolve
disputes between two opposing parties defending their respective rights. In the litigation process,
the judgement provided by the court regarding the disputed matter, if not accepted by either of the
parties, can be further appealed to the court for effective decision-making by delivering new proofs
and evidence. However, if either of the parties accepts the judgement provided during the
litigation process, then the guilty party must pay to the other party the value of the compensation
75
awarded. As criticised by Tarhini, Fakih, Arzoky, and Tarhini (2015), the litigation progress can
require extensive time in executing decision-making, which results in the construction project
missing the deadline for completion. This is because neither of the parties involved in the
accomplishment of the project wishes to work on it during the litigation process in order to execute
because the client cannot provide the required amount of finances needed for completion of the
project, among other reasons. As mentioned by Shehu et al. (2014a), a project may be abandoned
entirely due to the client's problems or dispute with the contractor. Moreover, bankruptcy, poor
quality marketing and sales, and deceit by the contractor, among other reasons, can also result in
(2014), project abandonment affects the contractor, supplier, consultant, and other parties involved
in the construction process. Moreover, project abandonment negatively influences the purchasers
Cost overruns. Cost overruns refer to the increased expenses incurred in a project due to
the contractor's lack of effective budgeting, evaluation, and analysis during the initiation of the
project (Larsen, et al., 2015). The cost overrun is directly related to time overrun because, when
an increased amount of time is required to complete the project due to delay, this in turn, raises
the overall cost. This is because the prices of building materials in the market rise with time,
which causes contractors to spend more finances when buying the materials (Niazi & Painting,
2017). Moreover, during the ConD, the labourers must be managed and, thus, contractors must pay
them to keep their numbers so that the effective workforce required to execute the construction
al. (2016), cost overruns occur due to ineffective financial planning made by the contractors for
76
which they must cover the loss and pay expenses to the owner. This further results in additional
delays in the construction, as a sufficient amount of finance may not available for the execution of
the project as required of the contractors by the owners (Buys, 2015). The cost overruns can be
adequately understood before their occurrence by the contractors if they can see the dynamics and
connections between the various sources involved with the construction project.
result in the loss of thousands and millions of valuable monies deposited by the public, which
culminates in causing serious financial issues. Moreover, challenges in construction related to the
Church not only cause financial hindrance but also lead to a lack of effective functioning of the
leadership and loss of confidence by the public in the pastor and church authorities. As
mentioned by Sears et al. (2015) challenges in church construction projects are faced because the
experience of planning and executing an effective building program that best meets the demands
and needs of the architecture and budget of the church is lacking among the members of the church
council. Initially, the most common challenge faced in construction related to the Church and
others includes failure to assume the accurate cost required for the execution and completion of the
project. As mentioned by Kerosuo, Miettinen, Paavola, Mäki and Korpela (2015), during the
initiation of the construction project, the owners are required for useful cost estimation to
determine the things they can afford in comparison to what they require. This estimation is needed
as it leads the owner to understand the limitations which they are being forced to impose on their
requirements to allow the budget needed to complete the construction project effectively.
and Arthur-Aidoo (2018), lack of adequate cost estimation is experienced when the owners do not
effectively link their budget planning with their requirements. This results in ineffective budget
estimation as the owners, due to overconfidence and enthusiasm to satisfy their requirement,
accept the construction plan blindly without investigating whether they would be able to pay for it
77
or not. However, due to lack of adequate finances, project delays occur which, in turn, raise the
overall cost of the construction to the point where the owner cannot afford to take the project on,
leading to abandonment (Addo, 2016; Asiedu & Alfen, 2015; Niazi & Painting, 2017). Failure to
access outside help for evaluation of the project is another challenge the owners face in
construction projects. Outside assistance is required because it helps the owner to get sufficient
knowledge regarding the resources to be appropriately used in the execution of the construction
project. As commented by Zhang, Sulankivi, Kiviniemi, Romo, Eastman, and Teizer (2015), an
experienced project planner helps to determine the best solution required for the building
Moreover, in many cases, it has been seen that the owner does not analyse the transparency
of information provided in a construction project. They do not feel the urge to know how much
finance is required or for which purpose during the construction, which acts as a big challenge for
them. As asserted by Sears et al. (2015), lack of transparency acts as a significant challenge in the
construction project as it paves the way to allowing contractors to indulge in deceptive activities.
This, in turn, causes the owners to spend extra finance for the completion of the project, thus
Last-minute changes create challenges, such as formula errors from pasting and cutting
along with forgotten line items in budget estimation. This results in the loss of the profitable
project, as a valid estimation of the cost is not correctly made due to the rise of errors. As
mentioned by Sears et al. (2015), during the development of the estimate for a construction
project, current focus is to be given to all aspects. However, in other cases, it has been realized
that proper focus has been given only to managing the strengths, whereas the weaknesses to be
encountered are ignored. This acts as a prime challenge that also delays and hinders the execution
of the project; errors in project planning are raised, which cannot be properly resolved, since
strategies have not been formed beforehand to resolve them (Larsen, et al., 2015). The allocation
78
of an incorrect amount of resources acts as a challenge that hinders the construction as a sufficient
amount of construction material needed to complete it is not available at the appropriate time.
Lack of attention to safety requirements and the lack of effective consideration of risk assessment
create challenges for construction projects. This is because they hinder the project execution as
well as createing time overrun issues for the contractors. As mentioned by Gurcanli, Bilir, and
Sevim (2015), existing safety consideration at construction sites makes the labourers working on
the site feel safe, which leads them to provide adequate services as demanded. However, a lack of
safety, makes the labourers feel neglected and fear for their lives, which results in providing a
lower concentration at work as well as an unwillingness to carry on with the project, leading to a
shortage of labour. The lack of a sufficient amount of labour due to safety issues delays the
project, as the staff required for the construction work are lacking (Zidane, & Andersen, 2018).
Thus, labour shortage issues create a delay in the construction project, acting as a challenge
because they create time overruns, which, in turn, increases costs. The rise in cost creates issues
that negatively affect the construction due to an adequate amount of finances not being available
from the owner as well as for the contractor to support the project, as the cost appears to the
management acts as a challenge in construction as it destroys productivity and slows the working
process. This is because labourers do not feel any enthusiasm to execute work and, thus, slow
The inefficiency that results from not acting against extravagant claims poses a challenge
for a construction project because it leads to the construction company or the contractor paying
extra costs. According to Hughes et al. (2015), lack of adequate information regarding all the
processes involved in framing the documentation of the project results in creating difficulties in
defending the claims made in the project. This is because the contractors cannot immediately
present proper evidence to justify the claims and this hinders the execution of the construction.
79
This, in turn, acts to increase the overall expenditure of the constructor in executing the project
resulting in his earning a lower profit. This is because the contractors must spend time and money
in reframing the project to meet the new claims that could not be justified by them due to a lack of
evidence. As criticised by Wimala, Akmalah, and Sururi (2016), multiple versions of the
documentation of the project create challenges, resulting in project delay and mistakes. This is
because such activity results in creating confusion among the staff, since many of them do not
have accurate knowledge about how the architectural plan was developed, based on which they are
The owners are often seen to demand unrealistic time frames from the contractors to
complete the project as they think that a lower time would result in theirspending a lesser amount
of money. This acts as a challenge in construction because it may creates lower strength of the
construction that is then liable to collapse or expire sooner than its usual lifeline. As mentioned by
Alotaibi, Sutrisna, and Chong (2016), the accomplishment of construction projects within
unrealistic deadlines makes the contractors hurry in framing resources and architectural planning
to execute the project. Thus, in a hurry, many valid points of risk are missed, and this results in
the development of faulty architectural planning, which does not provide a usual life expectancy to
the construction resulting in the negative image of the contractor in the market. As argued by
Agyekum-Mensah and Knight (2017), the negative image of the contractor in the marketresults in
their facing difficulties in acquiring further projects. This is because owners feel insecure, and
lack trust and confidence in recruiting the contractors to undertake their projects out of fear of the
destruction of the projects before their usual lifetime. Thus, this, in turn, creates challenges for the
contractors as they cannot effectively carry on their business within the market.
The lack of effective communication during the execution of the construction project acts
as a challenge. This is because many members miss useful information regarding the constant
evolution in the project planning. Thus, the non-collaborative working environment results in a
80
delay in the completion of the project. As mentioned by Gunduz and Yahya (2015), sudden and
constant changes in the construction project planning, as demanded by the owner, pose challenges
for the construction. This is because such activity slows the working progress of the labourers, as
they face difficulties in coping with the constant changes made to the architectural plan of the
project. As criticised by Durdyev and Ismail (2016), ineffective scheduling of the construction
acts as a challenge for the project, because it raises delay due to the inconsistent nature of the
service. A proper project schedule helps to prevent construction from being affected negatively.
Finally, the above presentation has a direct or indirect influence on projects in Ghana. The
delay-triggering factors that prolong projects in Ghana include financial issues, lack of evaluation,
last-minute challenges, lack of an initial risk assessment, lack of safety measures, lack of effective
communication, owners’ unrealistic time frames, and the ineffective scheduling of projects
(Soomro, et al., 2019). On any given project, lack of financial planning leads to cost overruns,
making it extremely difficult to complete a project on time (Larsen, et al., 2015; Lu, et al., 2015).
Ghana has seen communication gaps, especially between owners and contractors, leading to last-
minute changes by the owners, creating misunderstanding between the two parties. Lack of risk
assessment and lack of evaluation in most construction projects in Ghana has given rise to several
project delays. Safety measures not included in the execution plan affect project progress since
labourers feel it is not safe for them to commit themselves to the given work (Addo, 2016; Asiedu,
Strategies adopted. Below are the strategies that were adopted to improve performance in
construction projects.
level of the construction project, it is vital for the construction project management to adopt new
technology for taking the fastest path with the biggest payoff. In this context, it can be specified
that the PCG has faced a higher amount of mismanagement in conducting proper construction
81
projects due to using traditional construction methods . To enhance the productivity of
construction projects at the PCG, church leaders can focus on installing productivity software and
information modelling software that is effective for the leaders to eliminate the waiting time as
well as reduce costly reworking (Du, Tang, Liu, Wang, Wang, Shen, ... & Zhou, 2016). Different
technologies can be useful for the PCG to develop the efficacy of project managers, which further
Plan grid construction and productivity software. As stated by Kärnä and Junnonen
(2016), this software allows project managers as well as the team members to manage real-time
submissions, drawings, issues, mark-ups, and photos. In this milieu, it can be detailed that this
software can help the marketing leaders of the PCG to use the power grid to improve their project
performance as well as to elevate their productivity, thereby accelerating the construction work
and avoiding the chance of delays. As stated by Zheng, Le, Chan, Hu, and Li (2016),
implementation of this software makes the marketers able to reduce the trips as required as well as
reducing the time expenditure, thereby allowing the team to be involved in accurate as well as
useful take offs electronically, rather than using or surveying the other electronic means for
As Ghana is experiencing a proper economic boom due to due to the proper utilization of
agriculture and marketing, construction leaders associated with the PCG have enough financial
ability to install this software to speed up anydelayed work. Power grid productivity software is
essential at the construction site to process drawings, submittals and construction issues in the
shortest time, which makes the engineers and managers at the construction site sure to maintain
proper time management (Zailani, Ariffin, Iranmanesh, Moeinzadeh, & Iranmanesh, 2016).
Therefore, it can be stated that the PCG could install this software to improve their construction
work by reducing the allocated time required for individual construction work on the site.
82
Kahua collaboration and project management software. This software can be
implemented by the construction project manager to maintain proper collaboration among various
construction aspects of implementing proper legacy project management techniques and tools
(Olawale & Sun, 2015). A construction project is not a straightforward assignment; instead, it
needs optimum cooperation as well as collaboration among all the entities involved in the task. In
Ghana, the Presbyterian Church faces delays in construction work due to various technical,
demographic, and economic reasons (Prasad, et al., 2019). Therefore, Kahua can be a highly
effective software program that can be used by project managers to enhance and elevate their
Joshi and Khandekar (2015), it is essential for all the workers at the construction site to maintain
proper collaboration in their tasks, such as drawing, making submittals, maintaining the technical
database, and quantity surveying as well as quality controlling. By installing Kahua software the
PCG would be able to maintain proper coordination between all the disciplines associated with
construction work.
The Kahua software would allow marketers associated with construction at PCG to
develop a proper project management framework that can be followed by the marketers at the
construction site and can improve the productivity of the organization byensuring proper
cooperation among the work of different project stakeholders (Leong, Zakuan, Mat Saman, Ariff,
Md, & Tan, 2014). By promoting the rapid creation of all the constriction databases and
workflows, Kahua software can make the manager at the construction site efficient in accelerating
the development of the project and improving the project management process.
The Red Team and cloud construction project. According to Memon, Rahman, and Jamil
(2014), by using this software project managers have a proper cloud solution for maintaining the
account and financial databases. In this context, project managers at the construction site of the
PCG could send different construction drawings and databases to the power grid application. They
83
could pull the necessary requests for information (RFI) from the power grid application software
via the Red Team software. This software also makes the project manager engaged in the
construction project of the PCG proficient at making accurate commercial estimations, which
enhances the relevancy as well as the accuracy of the project. The Red Team is one of the fastest
accounting solutions that can enable the project manager to make the proper optimization of all the
accounting and financial databases. As stated by Bamfo-Agyei, Hackman, and Nani (2015), for
commercial project construction Red Team is highly recommended software that maintains proper
coordination between accounts as well as financial databases with the other aspects that allow a
project manager to be highly involved in maintaining the reliability and relevancy of the
construction project. Pharne and Kande (2016) found that Red Team cloud software is essential in
the case of construction work as it can be implemented by the project manager to manage different
management, and accounting. Therefore, in this context, the construction project of the PCG can
be improved and triggered towards its objectives by installing the software, which allows the
construction team to use this software to maintain proper technical communication as well as
collaboration online through sharing and creating the posting, contracting documents, posting
eSub construction project. eSub software assists project managers in developing efficient
coordination between the office and the construction site in real-time (Mir & Pinnington, 2014).
Along with the power grid, this software allows the project team and the project manager to send a
screenshot of technical drawings, annotations, and project databases that can be used by the team
members to make possible coordination among all the construction workers. In this context, team
members, as well as project managers appointed to the construction site at the PCG, could install
this sub-project software which would enable them to facilitate connectedness with the
stakeholders and reduce the time needed to complete the entire work (Hwang, Zhao, & To, 2014).
84
This software prevents the staff and construction managers from having to chase down the RFIs,
insurance documents, contract, and orders by keeping the proper uniform structure to move the
project towards its destination, to finish the project in a well-organized manner. It is vital for all
the staff to understand the weaknesses and strengths of the projects and construction planning,
which are essential to make possible any reformation in the entire project planning.
According to Mok, Shen, and Yang (2015), as the construction projects of the PCG are
experiencing considerable delays in finishing the construction work, there is a need to install eSub
software, which gives all the project team members the ability to store, create, and access all the
projects from their mobile devices. Team members can make and send notes from their
construction field and capture photos, which can then be sent to the project manager instantly to
ensure effective collaboration among the team members. According to Ngacho and Das (2014),
the eSub software would also help the team members to work by downloading the online mobile
application, thus enabling the PSG construction project team to update as well as document the
entire project database. According to Serpella, Ferrada, Howard, and Rubio (2014), by using this
software, team members can communicate with each other more quickly in a well-organized
manner, which not only increases the productivity of the organization but also impacts on the
overall performance of the construction workers at the construction site. By removing the need to
chase down multiple contracts, current project plans, RFIs, and insurance documents, the
employee can make the workers able to exercise effective coordination with the construction team
members, which is essential to enhance the quality of the project. According to Zohar and
Polachek (2014), by installing this software, team members can identify issues happening at the
site, helping them to develop arrangements to resolve the issues raised. By locating proper project
addresses and dealing with other key elements through the utilization of this software, the
construction workers can improve the performance level and effort of all the team members.
85
Improve project plans with massive data. As stated by Kärnä and Junnonen (2016), a
construction project can be easily handled by increasing its productivity and performance level
through reforming as well as restricting the project outline. In this context, the project manager at
a PCG construction site , can easily understand flaws and drawbacks of the project planning which
are responsible for the project delay. As per Gudienė, Banaitis, Podvezko, and Banaitienė (2014),
reformation of the project plan can make team members and the project manager of this
construction site evaluate the entire project decryption end-to-end to analyse the requirements and
expectations of the construction project. It is essential for all the team members to have explicit
knowledge about project progress and project requirements, which is possible only by doing good
project planning that allows the project managers as well as team members to maintain possible
involved in project planning. As per Prakash and Nandhini (2015), by developing, storing, and
accessing possible project construction databases, team members can input all the information
related to the projects in one relevant model that can be followed by all the project managers and
construction staff, thereby giving substantial benefits as well as improving the productivity of the
construction work. Contractors at the PCG construction site can easily make proper analysis and
evaluation of the previous database to identify as well as eliminate all the barriers and drawbacks
of the project planning. Serpella et al. (2014), state that by developing the useful matrices, project
managers and contractors can easily maintain the accuracy as well as the relevancy of the project
outcomes that would assist the project staff to enhance their performance level.
elevate the performance level of construction work, it is vital for the contractors to train the
work. As stated by Shen, Tuuli, Xia, Koh, and Rowlinson (2015), the construction supervisor can
86
fail or succeed at a job by their potentiality and experience. Contractors must ensure that all the
workers who are appointed to the field are well-experienced and able to deal with all kinds of
construction work. In this context, the contractors at a PCG construction site need to train their
supervisors and staff to make them able to understand the way to deal with various technical
aspects and equipment (Safo-Kantanka, et al., 2018). In most of the cases, contractors also train
their staff and supervisors on how to operate different technical types of equipment to run the
project consistently.
As stated by Obeidat and Aldulaim (2016), it is essential for the contractor to train the
supervisor, not only in handling different technical types of equipment, but also in applying their
best efforts to increase productivity and improve the project. Supervision at the construction site is
responsible not only for the day-to-day checking process, but also for maintaining a high level of
coordination among all the entities associated with the construction work. Completion of the
construction project in a well-organized manner has some milestones, which supervisors and
project developers need to recognize and implement. According to He, Tang, Wei, Duffield, and
Lei (2015), it is vital for all the supervisors to meet each project milestone on a proper schedule to
use all the organizational resources to finish the entire task within the allocated budget. In this
context, the contractors and supervisors in a PCG construction project must be well trained to
handle the whole construction task. This can be accomplished by incorporating new ideas and
thoughts, managing internal conflicts among the staff, maintaining and storing all the technical
database regarding the construction work, and reducing the changes of project delay by utilizing
prefabrication is the process used in the construction industry to assemble all the essential
components of the structure in a factory or other manufacturing site. It is one of the necessary and
conventional transition processes used by the project managers to transport different essential
87
materials to the construction sites. By using this method, contractors and project managers of a
PCG construction project can prefabricate all the indispensable technical elements and bring them
to the construction site without delay, rather than building each of them on the construction site.
According to Gudienė et al. (2014), prefabrication leads to reduction of the costs and improves
quality by giving the team members the ability to use highly efficient elements on the construction
sites, thus accelerating the completion of the project. It is essential for all the staff to be well-
trained in transporting the essential items from one construction site to another, providing a safe
and secure way of getting the best materials that can be used at the construction sites to gain better
productivity. For increasing the quality as well as the performance level of the project, it is
essential that cooperation among different entities is made possible (Serpella, et al., 2014).
Prefabrication makes the construction team able to improve the quality. In this context, PCG
construction work can be grouped into a different entity to accelerate the project completion.
Prefabrication would make it possible for the supervisor as well as the contractors to collect
different, essential components from other construction sites that would be relevant to the
completion of the construction work. As per Ngacho and Das (2014), prefabricated parts of the
equipment used on the construction site can be called subassemblies, which are essential to
incorporate all the possible equipment into the one model to enhance the efficiency as well as the
quality of the equipment. Prefabrication can reduce the schedule allocated for completing the
construction work, thereby giving the team members the ability to meet all the criteria for
Improve safety training. Accidents can be the primary causes of any category of project
delay as well as cost overruns. As stated by Hwang et al. (2014), contractors should be required to
conduct more safety training programs to train all their staff, project managers, and project team
members, in order to engage them in adopting proper safety methodologies, thereby maintaining
proper safety and security while working at the construction sites. It is vital for the staff to
88
maintain effective communication with each other to understand the efficacy and experience that
can be implemented to maintain reasonable safety within the organization (Chen, et al., 2019b).
Different or outdated safety measures are ineffective; therefore, contractors are required to
consistently implement innovative and new methodologies in the construction work to enhance
productivity and reduce all types of risks as well as liabilities (Mir & Pinnington, 2014; New
South Wales, 2016). Providing a strong awareness curriculum and raising more safety awareness
can ensure that the contractors on PCG construction projects know how they can maintain the
safety and security of the project while working in a well-organized manner. Therefore, it is vital
for the construction project that contractors not only provide training to the staff, but also that they
provide up-to-date knowledge to the staff by making them aware of the type of construction
equipment that can be used on the construction sites to accelerate the completion of the work.
(2015), it is evident that productivity is an essential aspect of the construction site that should be
maintained in a manner consistent with the project objectives. However, contractors need to shift
the project dynamic by making possible communication about the importance and usefulness of
productivity for the entire team. The contractor can better communicate with the construction
team and project managers to make them understand the actual aim of the project. In this context,
contractors at the Presbyterian Church can interact specifically with all the staff and supervisors to
enhance the involvement of all the staff in meeting the project goal (Sinesilassie, et al., 2017).
Communication would enable contractors to understand the strategies and weaknesses of the team
and allow them to take practical steps, such as training, self-assessment programs, and regular
conferences, to enhance the expertise and efficacy of the team members to deal with various
difficult tasks (Safo-Kantanka, et al., 2018). Demirkesen and Ozorhon (2017) affirm that by
maintaining possible interaction with the staff, project managers, and contractors, it is possible to
manage any conflict among the team members as well as project managers and supervisors
89
regarding job procedure and construction. In addition to this, effective communication is one of
the essential ways that help the construction staff share in the decisions and thoughts regarding the
construction project.
al.(2017), talent management is one of the sensitive as well as important issues on a construction
site, which enhances the productivity and the chances of the betterment of the construction project.
Contractors at PCG construction sites in Ghana need to find the best people with high skills and
proper experience in the construction field. It is imperative for the staff at the construction site to
have the necessary intelligence and the excellence to deal with the various complicated tasks that
would accelerate the growth and performance level of the task. Staff must have strong skills as
well as the proper mindset to put their best efforts into the tasks to deal with all the complicated
construction aspects. As per Memon et al. (2014), in this context it can be stated that project
managers and contractors at the PCG construction sites can utilize the autonomous system to
provide all the staff with enough power and freedom to use their expertise and experience to deal
with complicated tasks. However, contractors need to maintain proper supervision of each of the
staff to eliminate the chance of misuse of power and opportunity, thereby making the construction
framework free from all types of conflict and controversies. As per Leong et al. (2014) contractors
need to involve the staff in dealing with the new challenges at the construction site to examine
their efficacy and self-confidence, which are the cornerstone of getting better production and
meetings, the contractor would be able to recognize the ability as well as the efficacy of the
construction staff to deal with new challenges. By conducting transparent interview processes, the
contractor can find highly skilled and experienced candidates who can deal with challenging tasks.
Therefore, it is essential for the contractor at the construction site to recognize the strengths and
90
weaknesses of the staff to create potential workforces that can deal with any organizational
Summary
Chapter two considered the major project management theories needed for every project.
(Lui, 2020; Matu, 2020, Tereso, et al. 2019). Later in the review, delay factors influencing the
PCG construction projects were categorized under the following headings: material-related factors,
related factors and quality-related factors. The material-related factors were disscused in terms of
choice of material, wastage, money to purchase, and bad storage, which all trigger delay (Arthur,
2016; Asiedu, & Alfen, 2016; Pall, et al., 2016, 2018; PCG-Constitution, 2016; Wallensteen,
2018). The client /owner-related factors were highlighed to include disparities in orders,
design documents and their approval, delayed endorsement of sample materials, and poor
communication, leading to delays in construction projects (Addo, 2016; Alotaibi, et al., 2016;
Arditi, et al., 2017; McCord, et al., 2015; Sambasivan, et al., 2017). Also, Church organization
structure was outlined with respect to lack of budget, bad leadership skills, poor communication,
changes in leadership, and slow decision-making having an influence on delay (Doppelt &
McDonough 2017; Northouse, 2018; Sutar & Mehendale 2017; Volberda, et al., 2013). Project-
related factors were shown to have triggered delay in areas like disputes, unclear schedules,
unclear contract clauses, lack of planning, poor materials, and the low technical know-how of
subcontractors (Akogbe, et al., 2013; Kim, et al., 2018; Skaggs, & Chescheir 2003; Wallensteen,
2018). External-related factors covered areas that disturb construction projects like price increases,
price escalation, labour disputes, slow permits from government, civil disturbances, harsh climatic
conditions, hostile social, and economic, and political environments (Adam, et al., 2017;
91
Agyekum-Mensah & Knight, 2017; Lines, et al., 2015; Najib, et al., 2018; Sinesilassie, et al.,
2017). Finally, quality-related factors were discussed in terms of the low qualifications of workers
or technical staff, lack of technical know-how, lack of quality policy, improper supervision, and
absence of staff appraisal having an influence on Church construction delay (Asiedu & Alfen
2016; Algwyad & Talib, 2019; Attakora-Amaniampong, 2016; Buys, 2015; Durdyev, et al., 2017;
Gebrehiwet & Luo 2017; Larsen, et el., 2015; Rahman, et al., 2014; Zidane, & Andersen 2018).
The expanded forms of the delay components identified include: Managerial dispute
(Baker & Keiser, 2019; Kim, Lee, & Choi 2018; Merrills, 2017; Sutar, & Mehendale 2017),
Contractor-related (El-Gohary, et al., 2017; Kog, 2017), Design-related (Yousefi, et al., 2016), and
Consultant-related (Marzouk & El-Rasas, 2014; Smith, et al., 2017). The rest are Equipment-
related (Ngacho and Das 2014), and Labour-related (Arditi, et al., 2017; Olusanya 2018).
The four categories of delay that impact PCG construction projects were discussed,
revealing that delays that hinder the completion of the entire construction project were the critical
factor (Arditi, et al., 2017; El-Gohary, et al., 2017). The non-critical factors were those without
direct influence on the completion date of the Church construction project (Xiong, et al., 2014).
The non-concurrent delays occur whenever the critical path of the construction schedule is
influenced by a single action, but the concurrent delay has a number of activities contributing to its
occurrence (Chen, et al., 2017; Gardezi, et al., 2014). The delays that are mostly defined in the
contract are the compensable ones, and those that are triggered by unforeseen circumstances, like
The effects of project delay are also discussed and include: time overrun (Asiedu & Alfen,
2016; Ojoko, et al., 2016), abandonment, dispute, and litigation, (Hughes, et al., 2015; Lu, et al.,
2015; Shehu, et al., 2014a; Vasilyeva-Lyulina, et al., 2015). The rest of the effects consist of
negotiation and arbitration (Equbal, et al., 2017; Getahun, et al., 2016) and cost overruns (Larsen,
et al., 2015; Senouci, et al., 2016). The delay factors have some impact on Ghana’s construction
92
projects and will lead to the next chapter, which outlines the methodology adopted in this study
and examines the factors that impact the delay in construction projects (Asiedu & Alfen 2016;
al. (2018) and Sears et al. (2015) the challenges faced in construction projects and the strategies
93
Figure 5.
CONSTRUCTION
PROJECTS
CHART
CHALLENGES FACED
STRATEGIES FOR
IN CONSTRUCTION
IMPROVEMENT
PROJECT COMPONENTS
Note.: A constructional chart is showing the challenges encountered in the construction projects and
approaches to be adopted in improving Church construction project. Author’s Construct (2020)
94
Chapter 3: Methodology
This chapter explains the various research methods used for the study. The key elements
include purpose of the study, research design, hypotheses with research questions, sampling
strategy and population, research instrument, instrument validation, procedures for collecting data,
ethical consideration, data analysis and other approaches employed in the research.
The motivation for executing the quantitative study was to seek essential sympathetic delay
determinants that relate to Church construction projects in Ghana. Rachid et al. (2018) asserted
that construction delays have social economic, and legal consequences. There is a great loss of
financial resources in construction projects as a result of delays (Larsen, et al., 2015). The study
also aimed at the critical failure or success mechanisms implicated in the Church construction
projects so that the magnitude of impact of each factor was reviewed correctly in identifying its
validity for the efficacy of the project (Naoum, Herrero, Egbu, & Fong, 2018). Despite the
numerous contributions of work in the construction field, not much has been done with regard to
religious institutions. For instance, construction projects like road construction and other
governmental projects have attracted consistent attention from industry and academic world
(Chen, Shan, Chan, Liu, & Zhao, 2019b). Though the church constructions delays keep increasing
in the PCG (Akuapem Presbytery Report, 2014), the available conceptual and empirical studies
executed in ConD largely focused on roads and other public institutions (Famiyeh, et al., 2017;
Murwira, & Bekker, 2017). There was very little literature identified on Church construction
projects, and what was available was also out of date. Therefore, in order to bridge the theoretical
external-related factors was developed to investigate their relationship with Church construction
delay.
95
Research Design
This study aimed to explore the delays in PCG construction projects . Premised on the
predictor variables, the unit of the analysis was the 25 Districts of the Akuapem Presbytery, which
were undertaking construction projects such as chapel building, building of church halls, building
2016). Considering the nature of the research question and study objectives, the study utilized the
quantitative technique for this study. The data collection was taken from 402 respondents through
a cross-sectional survey using questionnaires. The methodology of the study was established as a
result of the overall literature reviews on delays in construction projects. A cross-sectional survey
was employed based on the aim of the study to explore the delays in PCG construction projects .
Hence, the need for a sufficient sample of the population from persons in construction projects like
project/construction managers, electricians and others (committee/session) using the online survey
tool, MikeCRM. According to Babbie (2016), a cross-sectional survey is the best means of
gaining enough data in order to attempt generalization about a larger population from which the
sample of participants has been drawn. Since the study attempted to examine the relationship
between the independent and dependent variables, a cross-sectional survey was considered as the
appropriate strategy.
questions designed for comprehensive interviews to measure or tally the answers and evaluate the
data statistically (Mayer, 2015; Nardi, 2018). The quantitative technique was used to assess
various variables comprising areas relating to correlations between variables and employing
efficient statistics, like correlations, testing theory, and variations between the means. The
hypotheses were developed to assist in producing a sequential data analysis. The survey approach
helped in the execution of the study in a minimized timeframe and had a lower acceptance for
96
errors as well as maintained vagueness in the study, stemming in the advancement of significant
collection of data (Creswell & Clark, 2017; Naoum & Egbu, 2016). As stated by Creswell and
Clark (2017), the survey approach is employed in research since it affords a wider viewpoint and
knowledge about the social phenomenon happening in the environment without any form of
subjectivism. The positivist paradigm was applied as a tenet for executing this design. The
quantitative technique was applied in this study for the rationales listed below:
• To establish the validity of the instrument and the conclusion (Creswell and Clark,
2017)
• To appreciate and critique the precision of the study outcome (Vance, et al., 2013).
This quantitative study gathered knowledge concerning the delay factors and critical failure, along
with their level of relationship with the project. Moreover, the method was also used to evaluate
the influence of each of the factors on the construction project. In this study, the assessment
procedures employed in the quantitative technique, such as statistical figures, charts, and tables,
aided the author in investigating, presenting, explaining, and analysing data for correlations and
trends.
Conceptual framework. The literature and theoretical review uncovered several influence
factors of construction delay. For instance, Amoatey et al. (2015) as well as Zidane and Andersen
However, Muhwezi (2014), regrouped those factors into four broader categories as consultant-
included financial and owner/owner-related factors, whereas Dixit and Sharma (2019) added
97
(2015), Muhwezi (2014), and Prasad et al. (2019), this study concentrated on six items to represent
1) Client/owner-related factors (Larsen, et al., 2015; Muhwezi 2014; Prasad, et al., 2019;
2) Church organization structure (Arditi, et al., 2017; Doppelt & McDonough 2017;
3) Quality-related factors (Akogbe, et al., 2013; Algwyad & Talib, 2019 Famiyeh, et al.,
2017; Kim, et al., 2018; Skaggs, & Chescheir 2003; Wallensteen, 2018).
4) Project-related factors (Akogbe, et al., 2013; Famiyeh, et al., 2017; Jackson, 2020; Kim,
5) Material-related factors (Arthur, 2016; Asiedu, & Alfen, 2016; Pall, et al., 2016;2018;
6) External-related factors (Adam, et al., 2017; Agyekum-Mensah & Knight 2017; Najib, et
al. 2018; Lines, et al., 2015; Najib, et al., 2018; Sinesilassie, et al., 2017).
The Church construction delay was the proposed dependent variable, as illustrated in
Figure 6. This proposed model was developed to help answer the six research questions. Hence,
98
Figure 6
(ProjRF) H
45 H
Material Related Factors
H6
5 H
(MatRF)
External Related Factors
6
(ExtRF)
Note. Church construction delay serve as the dependent variables being controlled by the six
independent variables. This means that the changes in the controlled variables trigger the
99
Table 1
variables
1. Client/Owner The extent the owner of the project Larsen et al. (2015); Muhwezi
Related Factors contributes to the church construction (2014); Nyoni and Bonga
2. Church The extent the chain of command in the Arditi et al. (2017)
3. Quality Related The degree to which interruptions in Algwyad and Talib (2019);
Factors construction impede the value of the Algwyad and Talib (2019);
4. Project Related The degree to which the issues associated Akogbe et al. (2013); Dixit
Factor with the planning, designing, starting, and and Sharma (2019); Famiyeh
completing the project are impeded in the et al. 2017; Jackson (2020);
Wallensteen, (2018)
100
5. Material Related The magnitude by which the Arthur 2016; Asiedu and
Factors mismanagement of resources hinders the Alfen 2016; Pall et al. (2016);
Wallensteen, (2018)
6. External Related The extent to which external issues in Adam et al. (2017);
2017).
Dependent Variable This is the variable regulated by the Rahman et al. (2014);
dependent variable.
Note. Definition of the proposed variables with responding references. Source: Author’s Construct
2020
101
Research Questions and Hypothese.
This study was primarily focused on six sets of questions based on the literature review.
RQ2: Is there a substantial relationship between Church organization structure and Church
construction delay?
construction delay.
construction delay?
construction delay?
102
H4a: There is a substantial relationship between project-related factors and Church
construction delay.
delay?
construction delay.
construction delay.
construction delay?
construction delay.
This section describes the population and the sampling size strategy. The relevant
justification for the selection of the target sample size for the study is outlined.
Population of the study. A target population is defined as the inclusive class of specific
components of the population that is significant to the study unit. In contrast, a sample is a
segment of the population that is selected to be examined in order to interpret the set population in
mind (Rubin & Babbie 2016). The population included those in the construction firms in Ghana.
These include builders, woodworkers, plumbers, and electrical workers. In the year 2012, an
approximate building contractors’ populace of 1,600 was given by the Chartered Institute of
Building-Ghana (Ahmed, Hatira, & Valva, 2014). The total membership of woodworkers in
103
Ghana was over 40,000 (GNA, April 2015) and the overall number of PCG Agents stood at 5,701
In the current study, the population is 2,400 covering stakeholders in Church construction
projects such as the building of chapels, ministers’ residences, church halls, offices, and other
church-related projects in Ghana. (Ahmed, et al., 2014; Akuapem Presbytery Report 2014; PCG
Report 2018; ) Nevertheless, the participants of the study were church stakeholders or decision-
makers in Church construction projects and building contractors who have worked on church
leaders on the project and investment committee/session. Those holding major positions in the
church construction projects were chosen as the study sample because they are responsible for
decision-making at church. Accordingly, the author performed a quantitative study into delays in
construction projects and their influence on the church. The idea for choosing the location and
various roles/professions in the construction projects was to explore the broader view of the delays
in Church construction projects. Though all the PCG congregations in Ghana are involved in
construction projects, PCG Akuapem Presbytery has several ongoing construction projects in
almost all the 25 districts (Akuapem Presbytery Report 2013; 2014). A second reason for the
study area selection was that the researcher had spent over six years as a Presbyterian minister in
the selected study area and is more familiar with the trends of Church construction projects and
delays, making data collection easier. In conclusion, during the data-gathering procedure the
researcher could not incorporate the entire population because of the financial commitment and the
duration needed. Nonetheless, since church construction projects share similar physical
characteristics, the nature of the study sample varies, and it is meant to represent subclasses of the
population of church construction projects in the PCG and other churches in Ghana.
104
Sampling procedure. In applying the purposive random sampling, self-administered
questionnaires were used to gather the data. Distribution was done by purposively selecting key
Church Construction Project leaders in PCG Akuapem Presbytery between September and
December of 2019. Nevertheless, for the intention of this study, a letter was written to the
Presbytery office to seek permission to engage the participants in the Presbytery and ensure they
were all working on a project or had recently worked on a construction project. Only
congregations or districts which were involved in construction projects were chosen for this study
and subsequently gave their consent to take part. This was used to enable the researcher to
carefully monitor the data-gathering process in order to regulate the number during the data
collection to reduce attrition and dropout. Out of the 700 project leaders who fell within the
Sample size selection. The deployment of the sample selection technique and how it
symbolized the population had a substantial consequence on the study outcomes. Thus, it was
imperative for the sample to have the projecting features of the study populace. In considering the
chosen sample from the population of the study, the sample must exhibit some estimated
The target population was assumed to have the characteristic of interests cited in Mugenda and
Mugenda (2008), which suggested that 50% was the suitable sample size. Thus, the study applied
the Cochran sample size formula to calculate the appropriate sample size of the study units as
follows:
𝒁𝟐 · 𝒑(𝟏 − 𝒑)
𝒆𝟐
𝒁𝟐 · 𝒑(𝟏 − 𝒑)
𝟏+( )
𝒆𝟐 𝑵
105
Confidence Level (1−α) 95%
As shown in Table 2 the procedure used to arrive at the sampled number of study units has
been simplified.
106
Table 2
Sample Size Determination
e2 = 0.0016
Alpha divided by 2 for Z α/2 0.025 i.e. if α = 0.05, => 0.05/2 = 0.025
𝒁𝟐 ·𝒑(𝟏−𝒑)
𝒆𝟐
=> 𝟐
𝒁 ·𝒑(𝟏−𝒑)
𝟏+( )
𝒆𝟐 𝑵
= 600.25
= 1.25
Numerator 𝟔𝟎𝟎.𝟐𝟓
Sample size (n)= = => 480
𝐷𝑒𝑛𝑜𝑚𝑖𝑛𝑎𝑡𝑜𝑟 𝟏.𝟐𝟓
Therefore, n = 480
Note. The Table demonstrates the steps used for the sample size calculation. The population
size (N=2400); Confidence level (1−α= 0.05); p-value, is 50% (0.5); Margin of error (e = 0.04);
and Z-score = (1.96). Based on the formula, the numerator was calculated and had 600.25
which was divided by the denominator with 1.25. The sample size for the study is n = 480.
107
Research Instrument
The 20th version of the Statistical Package for Social Sciences (SPSS) was used to
examine the descriptive statistics such as the standard deviation (SD), mean, frequency
distribution, Exploratory Factor Analysis (EFA), and regression. Similarly, the 24th version of the
Analysis of Moment Structure (AMOS) was applied in Confirmatory Factor Analysis (CFA) as
well as Structural Equation Modelling (SEM) (Babbie, Wagner, & Zaino, 2018). The EFA was
adopted to verify the existence of correlations in the intended model. To verify the overall
significance of all the correlations within the correlation matrix for the Kaiser-Meyer-Olkin Test
(KMO) and Bartlett’s Test and Chi-Square. The CFA was applied to verify decency in the model.
Cronbach’s Alpha was used to measure internal uniformity and to check validity and reliability for
further analysis of the research. The correlation was employed to test for the suitability of
Instrument Validation.
To identify the precision of the questionnaire and to ascertain the clearness of the
instrument from the respondents, internal reliability and validity became necessary, as indicated by
Fraser, Fahlman, Arscott, and Guillot, (2018). A pilot study was conducted by distributing a total
investment committee/session. In the end, 60 responses were returned, making 92.3% percent.
Pilot Study instrument reliability. In Table 3, a Cronbach's alpha was used to evaluate
the internal uniformity and to demonstrate the reliability assessment for each scale. The measures
obtained depicted suitable reliability. The range measured from .741 to .916 for the Church
construction delay. Thus, higher than the minimum requirement of 0.6, making the proposed
108
Pilot study validity of instrument. The confirmation needed to authenticate the expected
results called for validity, which was reliant on the assertions made (Kane, 2016). Validity implies
the capacity of instrument to evaluate its expected rationale for the underlying construct. The
a) Face validity was proven subjectively to be accurate for the study objectives (Burns &
b) Discriminant validity, which showed that some of the items had high values, suggesting
few items were redundant and indicating the need to restrain the unwanted pairs.
c) Convergent validity showing an evidence that all items of the proposed model were
Therefore, the study, employed three categories of validity (face, discriminant, and
convergent) to measure the respective model (Burns & Bush, 2005; Kane, 2016; Zohrabi, 2013).
109
Table 3
Note. Scale statistics showing the Mean, Variance, Standard Deviation (SD), and
with Cronbach’s Alpha between .740 and .846
One of the vigorous procedures of any research is the gathering of data, which has two
parts: primary and secondary data (Johnson, Reynolds, & Mycoff, 2019). The direct data that the
study gathers for a precise study are the primary data, whereas the secondary data are the accounts
made by witnesses and that accessible from other sources. Other factors that contribute to data
collection include the accessibility of the material or resources, cost involved, the study duration,
and the expected precision level (Creswell & Creswell, 2017; Khan, 2014).
In this study, the primary data was collected using two steps. In the first step, a semi-
structured questionnaire was used to gather data from persons directly involved in the Church
construction projects, like Church Agents (Ministers and Catechists), project managers,
contractors, and consultants. In the second stage of the data gathering, a questionnaire that gave a
110
detailed view of the study was developed and used in the data collection through an extensive
Without any variations, all the respondents received a similar questionnaire, since the
research was an empirical study aiming at exploring delays in construction projects of the
Akuapem Presbytery of the PCG. With regards to the time frame, the economic aspect, and the
large sample size for this study, an online survey was preferred for the collection of data and
respondents had the option to print it out or respond directly online (Bernard & Bernard, 2013;
Bowen, Edwards & Cattell, 2015). The study, without any manipulation of variables, contacted
participants, such as the agents (Minister and Catechists), managers, consultants, site
members, through text messages, e-mail, Facebook, LinkedIn, telephone, and WhatsApp with the
questionnaire link. Employing the online survey tool MikeCrm, the respondents filled in all the
A covering letter was attached to the questionnaire, spelling out the essence of finishing the
questionnaire and guaranteeing all the respondents that their information would be kept
confidential. Respondents had the choice to complete a printed or online questionnaire. The online
survey tool MikeCRM enabled the researcher to have access to all responses in real-time (Bowen,
et al., 2015). The online survey tool is “easy to analyse; they come on a spreadsheet” (Bernard &
Respondents either completed the online questionnaire or, for those who opted to fill it out
manually, were sent the questionnaire via email in order to print it. All questionnaires sent via
electronic mail were followed-up with calls after the expiration of the four weeks given. Sending a
constant reminder to respondents increases the rate of responses (Van Mol, 2017). In all, the
111
level). A standard 5 Likert Scale was adopted as a measurement for all the items, with the scale
range: 1-Strongly Disagree, 2-Disagree, 3-Neutral, 4-Agree, 5-Strongly Agree (Willis, 2015).
Ethical concerns. To guarantee the aptness of the study, the author employed the most
elegant approach by adopting all the procedural ethics concerning the persons involved (Quinlan,
Babin, Carr, & Griffin, 2019). The two vital ethical rules of Walliman (2017) were adopted. First,
the personal morals of the researcher concerning integrity and honesty were upheld. The
researcher ensured that integrity is kept in every facet of the study. All materials used were
adequately acknowledged, and the data collected were stored correctly and used for the purpose
Secondly, the researcher handled the people involved with politeness and honoured their
consent and privacy. There was no breach of the confidentiality of respondents. The information
obtained from the respondents was not disclosed to a third party. This means the privacy of the
respondents was kept with a high level of confidentiality. There was no dishonesty in the gathered
data. The researcher tried to avoid data duplication or influencing the persons involved in the data
collection. Regarding respondents’ consent, the researcher explained to the respondents their
freedom and the willingness to either participate or withdraw from taking part in the survey
The researcher also followed the ethical writing principles of UCN. The Central University
of Nicaragua is very particular that researchers provide a genuine work devoid of plagiarism.
Data Analyses
In analysing the gathered data, the EFA was adopted to verify the existence of correlations
in the intended model, as indicated in Figure 6. The KMO and Bartlett’s tests were used to verify
variance and the CFA to verify decency in the model. The correlation was used to test for the
suitability of variables and to identify if there are any issues of multicollinearity and regression, as
shown in Table 4.
112
Table 4
1 (RQ 1): The EFA - verify the existence of correlations in the intended model
2 (RQ 2): KMO, EFA, CFA, correlation, regression and Bartlett’s Test.
3 (RQ 3): KMO, EFA, CFA, correlation, regression and Bartlett’s Test.
4 (RQ 4): KMO, EFA, CFA, correlation, regression and Bartlett’s Test.
5 (RQ 5): KMO, EFA, CFA, correlation, regression and Bartlett’s Test.
6 (RQ 6): KMO, EFA, CFA, correlation, regression and Bartlett’s Test.
Note. This table illustrates the statistical tools used to address each of the six Research Question
(RQ). KMO is the Kaiser Olkin Test, EFA is the Exploratory Factor Analysis; and CFA refers to
Confirmatory Factor Analysis, Author’s construct 2020.
113
Summary
Chapter three carefully reviewed the methodology for the research and the related
elements. The key components included the purpose of the study, which disclosed that financial
resources are lost in construction projects as a result of delays, and the sparse available church
construction literature was also out of date, hence, the study was to bridge such theoretical gaps
(Larsen, et al., 2015). The rationale for choosing the quantitative technique was discussed, which
revealed that the technique helped to measure and verify the outcome (Mayer, 2015), to contrast
and compare the study results (Nardi, 2018), to establish the validity of the instrument and the
conclusion (Creswell and Clark, 2017), and to appreciate and critique the precision of the study
The chapter also underscored the six research questions and their corresponding hypotheses
in exploring church construction delay in the PCG. A conceptual framework was developed based
on the literature and theoretical review, to include six independent variables and a dependent
variable. The church construction delay is the proposed dependent variable to hypothesize a
et al., 2015), Church organization structure (Arditi, et al., 2017), Quality-related factors (Algwyad
& Talib, 2019), Project-related factors (Jackson, 2020), Material-related factors (Asiedu & Alfen
The population was identified to be those in the construction firms in Ghana. These
included blockwork, woodwork, plumbing, and electrical works. The sample population was the
key stakeholders in church construction projects such as chapel, minister’s residence, the building
of church halls or offices in the PCG. The research design was uncovered and indicated that a
sectional survey to obtain the primary data from 402 participants involved in the construction
114
The assessment of the internal accurateness of the questionnaire and consistency of the
instrument were tested in a pilot study. The Cronbach’s alpha was .741 to .916, showing an
internal uniformity and validity for each scale. Thus, higher than the minimum requirement of 0.6,
making the proposed constructs reliable. Ethical consideration in the data collection was
addressed, which indicated that the researcher observed academic integrity and honesty as well as
ensured the privacy of the respondents (Quinlan, et al., 2019; Walliman, 2017).
Finally, the plan for data analysis was outlined to show the various instruments to be used
in analysing the gathered data. KMO, EFA, CFA, correlation, regression and Bartlett’s Test were
115
Chapter 4: Data Analysis and Presentation of Results
The study had the central aim of investigating and identifying delays caused in the
construction project of PCG. The first part of this section dealt with an established theoretical
information concerning the study, the research questions, and the methodology. The chapter
further considered the collection of data using the online survey which were obtainable in three
distinct units. The first section of the survey covered the participants’ socio-demographic
variables. The second segment included discussions of the analysis in line with the research
question, R1 to R6. The final part is a summary and tabulation of the outcomes of the hypothesis,
Demographics Statistics
Demographics are the statistical features of the target group that distinguishes the group.
According to Asiedu (2015), “the demographic profile of the respondents and the verifiability and
consistency test conducted should enhance the credibility of the responses” (p.150). In this study,
the demographics used included age, profession or role, academic level, and job experience to
scrutinize and to disclose the possible impact of the delay factors in Church construction (Vance,
et al., 2013).
Age. In Table 5, the six-step ordinal scale was used, which revealed that 47.1% of
participants were between the age group of 31-40. Similarly, respondents between the ages of 21-
30 were 31.1%, and 12.9% of participants represented the age group 41-50. Moreover, 7.96%
represented the age group above 51; whereas, 0.99% were below the age of 20. This information
is demonstrated in Figure 7.
116
Figure 7
Age of Respondents
200
180 189
160
140
Number of Respondents
120
125
100
80
60
40 52
20 32
4 0.99% 31.09% 47.10% 12.90% 7.96%
0
Below 20 21-31 31-40 41-50 51 &Above
Age
Note. The vertical, 0-200, shows the number of respondents. The horizontal part displays the
positions of the participants and the rate obtained, ranging from 0.99% to 47.10%
Profession or Role. This portion of the study presents background information of the
respondents. In using the eight-step nominal scale, the participants were requested to specify the
role they played in the construction projects. Table 5 illustrates that the majority of the
respondents had various roles in the construction industry. Since the study sought to involve
people in the construction field and other persons in managerial positions of the Church, 39.3% of
the respondents were persons in other managerial positions in the Church, while 21.9% were
Church Pastor/Agent and 18.9% were managers. Additionally, 9.95% of the total respondents
117
were project/construction managers, whereas consultants, site superintendents (foreman), and
electricians out of the overall respondents represented 5.90%, 1.99%, and 1.99%, respectively as
described in Figure 8.
Figure 8
180
160
158
140
120
Number of Respondents
100
80 88
76
60
40
40
20
39.30% 21.90% 18.90% 24 5.90% 8 1.99% 9.95% 8 1.99%
0
Profession
Note. The vertical, 0-180, shows the number of respondents. The horizontal part displays the
positions of the participants and the rate obtained, ranging from 8.99% to 39.30%
seven-step nominal scale. Table 5 reveals the outcomes that the majority of the respondents, 322
constituting 80.1%, had a university education, and 40 respondents, denoting 9.95%, were college
graduates. Moreover, 24 respondents, representing 5.97% of the overall respondents, had other
118
qualifications, while 16 respondents, denoting 3.98%, were high school graduates. This
Figure 9.
Level of education
Notes: The vertical, 0-350, shows the number of respondents. horizontal part represents the
Years of Experience. As seen in Table 5, a five-step ordinal scale was used to define the
the number of participants’ years on the construction projects. The outcomes revealed that 134 of
the respondents, signifying that 33.3%, had between 1-5 years of experience in the church
construction firm, while 96 of the over-all respondents, representing 23.9%, correspondingly had
6-10 years’ experience in the construction firm. However, 64 of the total respondents,
representing 15.9%, had almost a year experience in the construction firm; while 60 of the overall
respondents, denoting 14.9%, had 11-15 years of experience in the construction firm.
119
Furthermore, 24 of the total respondents, representing 11.9% of the respondents, had 16 years and
above experience in the construction firm. This information is proven in Figure 10.
Figure 10.
Years of Experience
160
Number of Respondents
33.30%
140
120 134
23.90%
100
80 15.90% 96
14.90% 11.90%
60
64 60
40
48
20
0
Almost a year 1-5 years 6-10 years 11-15 years 16 years and
above
Years of Experience
Notes: The vertical, 0-350, shows the number of respondents. horizontal part represents the
specific qualifications of respondents, ranging from 3.98% to 33.30%.
120
Table 5.
Note. Demographic Statistics on the age, profession/role, educational level, and year of experience
on the job.
121
From the table, age range of respondents in the study showing that most of them were
between the ages of 31-40 years, whereas the least participants aged below 20 years. Participants
profession/ role in the construction project, indicating that those with other managerial positions
participated more with 39.3% rate whereas electricians and site superintendents (foreman) were
the least participants with 1.99% each. Respondent level of education shows 80.1% as the highest
for University graduates and the least being 3.98% for high school leavers. The respondents’ year
of experience in the construction firm showing 1-5 years experience being the highest and 16 years
Statistical tools analysis. This aspect presents the analysis of all the statistical tools
employed in the review of the data. The discussion includes the Statistical Package for Social
Sciences (SPSS), Exploratory Factor Analysis (EFA), the Moment Structure (AMOS),
Confirmatory Factor Analysis (CFA), and Structural Equation Modelling (SEM), The Kaiser-
Meyer-Olkin Test (KMO) and Bartlett’s Test and Chi-Square (Babbie, et al., 2018).
Exploratory Factor Analysis. EFA was completed with Maximum Likelihood Method of
extraction in defining relationship level amongst the constructs. The results indicated that the
research data generously showed the overall significance of all the correlations within the
correlation matrix for KMO and Bartlett’s Test of sampling adequacy of 0.846, significant with
approximate Chi-Square of 9.345E3 at 9630 df, p<0.000. Per psychometric properties, Table 6
indicates that all other assumptions relating to the observed values for the pattern of the rotated
This signified acceptance to proceed with the factor analysis on the set of data. Besides,
the observed communalities for all the items were satisfactorily high, ranging from 0.4 to 0.8,
indicating enough correlations among the construct’s items in the study model. The reproduced
correlation matrix also recorded 64, constituting 10.0% non-redundant residuals higher than 0.05,
122
with a total variance of 68.0% explained. All items had strong loadings except for Projection-
Table 6
Pattern Matrix
Components
1 2 3 4 5 6 7
ChuOS1 .879
ChuOS3 .872
ChuOS2 .863
ChuOS5 .851
ChuOS4 .849
ChuOS6 .803
ClientORF1 .895
ClientORF6 .890
ClientORF4 .889
ClientORF2 .809
ClientORF5 .798
ClientORF3 .741
ExtRF4 .847
ExtRF3 .844
ExtRF5 .828
ExtRF2 .813
ExtRF6 .794
ExtRF1 .645
QuaRF3 .849
QuaRF1 .839
QuaRF2 .837
QuaRF4 .818
QuaRF5 .798
MRF4 .874
MRF1 .855
MRF2 .833
MRF3 .785
ChConD3 .897
ChConD4 .861
ChConD2 .731
ChConD1 .694
ProjRF3 .788
ProjRF4 .781
ProjRF2 .745
ProjRF1 .655
ProjRF5 .485
Note. The Removal Procedure was carried out with the Main Factor Assessment. Rotation
Approach using the Promax with Kaiser Normalization for all the study independent variables.
123
Confirmatory Factor Analysis. Through a covariance-based method, a measurement
model was derived and validated using a rotated pattern matrix. The factor analysis examined
indicated a decent measurement model for the study. The modification indices generated
suggested covariance among most of the error terms to generate a decent and robust fit in the
measurement model. An affirmation of the results justified the links amongst the said indicators
with their corresponding latent variables. Chi-square/df (cmin/df), RMSEA, GFI, and CFI, TLI,
SRMR, and P-Close were all strongly compared to their critical thresholds in the quest of
Goodness of fit indices assessment for the model. Apart from GFI, which had a less than the
threshold of > 0.95 with an index value of 882, all other remaining index values met their
thresholds for measurement model to prove an established acceptable projecting ability with a Chi-
square of 999.505, and degrees of freedom at 544. To affirm the values derived for the fit indexes,
all paths of items estimations were found to be adequately higher than .50.
124
Table 7
Chi-Square
Chi-Square 999.505
Degree of Freedom 544
Probability Level .000
The Goodness of Fit Indices
Categories Name of Index Index Value Threshold
Absolute Fit RMSEA .046 <.05 good; .05-.10 moderate;>.10 bad
P-Close .945 >.05
GFI .882 >.95
RMR .080 <.09
.95 great;>.90 traditional;>.80 sometime
Incremental Fit CFI .950
permissible
TLI .942 >.90
Parsimonious Fit Chi-square/df (cmin/df) 1.837 <3 good; <5 sometimes permissible
Note. The Goodness of fit indexes of the measurement model showing in comparison, an accepted
predictive ability with a threshold of >0.95 and an index value of 882. A lesser threshold observed
125
Figure 11
Measure model.
Note. This is a Confirmatory Factor Analysis. Through a covariance-based method, a measurement model
was generated and validated using a rotated pattern matrix. The factor analysis examined indicated a decent
measurement model for the study. The modification indices generated suggested covariance among most
of the error terms to generate a decent and robust fit in the measurement model.
126
Convergent Validity and Reliability. Validity and reliability were conducted to meet the
requirement of proceeding to model the construct. As seen in Table 8, the items and constructs in
the study data were carefully examined to identify any validity concerns by examining convergent
validity with computed Average Variance Extracted (AVE) where the square roots of AVEs were
equated to inter-component relationships. The preferred range of 0.5 and above was achieved
except for Project-related facors, which had 0.405, which was below 0.5. However, this was
acceptable since Lam (2012) suggested that AVE less than 0.5 is acceptable if Composite
Reliability (CR) is more than the acceptable level of 0.6. In this case, CR for Project-related
Furthermore, MSVs were concurrently calculated and compared to construct AVEs, which
vindicated the uniqueness of the constructs in the research model, as well as generating and
comparing CR values of 0.70 threshold which designate any problematic issues of deficient
interior uniformity of the instruments for the survey. The results for CR values, showed that it
surpassed the 0.7 threshold, ranging from 0.769 to 0.935, as well as observed values for both
MSVs less than the AVEs values, indicating that there existed distinct factors in the research
model. Additionally, for all the constructs, the study revealed the estimates for the Cronbach’s
Alpha as 0.742 to 0.913 which were above the minimum requirement of 0.6.
127
Table 8
CR AVE MSV (H) ChConD ChuOS ORF ExtRF QuaRF MatRF ProjRF Alpha
ExtRF 0.888 0.575 0.067 0.913 0.259 0.058 0.172 0.758 .869
QuaRF 0.874 0.581 0.116 0.878 0.340 0.275 0.059 0.058 0.762 .886
MatRF 0.875 0.643 0.284 0.941 0.533 0.357 0.327 0.195 0.285 0.802 .869
ProjRF 0.769 0.405 0.038 0.796 -0.061 -0.036 0.019 0.196 0.082 0.028 0.637 .742
Note. Cronbach alpha was found to be .742 to 0.913. Thus, higher than 0.6, making the construct reliable
128-129
Common Method Bias. Common method bias (CMB) is characterised as a bias in a
dataset caused as a result of external issues to the instruments that might have affected the
response given or the instrument attempts to uncover. In other words, a study with most of the
variance explained by a single factor is deemed to be a significant CMB (Burns & Bush 2005).
Since the data collected was steered by the using the online survey tools, there are high chances of
methodical biases in the response which can escalate or deflate the response (Gaskin 2016;
Harman’s single factor test. The IBM SPSS was employed to conduct Harman's single
factor experiment to ascertain whether a single factor explained majority of the variation by
constraining some of the factors obtained from the EFA into a loaded in a common factor or a
single factor, instead of eigenvalues extraction. Because the total variance for a single factor
extracted was 19.0%, which was less than 50.0%, this suggested or implied that there were no
Descriptive Statistics. The descriptive statistics, which were the SD and mean of all the
measures, are illustrated in Table 8. The Church construction delay had a mean of 3.11 with an SD
of .889. The client /owner-related factor had a mean of 3.71 and an SD of 1.027. The mean of
quality-related factors was 3.24 while the SD was 1.034, while the project-related factors had a
mean of 3.44 and an SD of .797. The external-related factors had a mean of 2.86 and an SD of
.996, Church organization structure also had 2.98 as the mean and 1.092 as the SD. The mean for
130
Table 9
Descriptive Statistics
correlation was employed in the correlation analysis. In Table 10, the independent and dependent
variables were concurrently examined, and the independent variables showed a weak association
among one another. Moreover, the connection between the dependent and the independent
variables was extremely positive. Hence, there were no challenges with multicollinearity, and that
131
Table 10
Correction
ConD
Church ConD
ClientORF .220**
Note. The correlation among the independent and between the dependent variables. The
independent variables showed a weak association among one another. Whereas the correlation
among the dependent and the independent variables was extremely positive.
Structural Equation Model (SEM) and Hypothesis Test. The model obtained a good fit
given 1283.589 chi-square, 560 degrees of freedom (df) and Chance level of .000 while all other
criteria were met demonstrating obtained fitness values for the research model with the exception
of P-close (.004), GFI (.851), and RMR (.172), which did not meet the threshold. Table 11
132
Table 11
Chi-Square
Chi-Square 999.505
Chi-square/df
Parsimonious Fit 2.292 <3 good; <5 sometimes permissible
(cmin/df)
Note. The Goodness of Fit assessment for the model. Chi-square/df (cmin/df), RMSEA, GFI,
TLA, SRMR, and P-Close were all strongly compared to their critical thresholds.
133
Figure 12
Path Estimate.
Note. This figure is the path estimate desmostrating the link between the dependent and indepent variables. The
abbreviation for the controlled variables are expended as ChuOS for Church organization structure; ClientRF for
Client-ralated; ExRF for external-related factor; QuaRF as quality-related factor; MatRF as material-related factor;
ChConD for Church construction delay; and ProjRF for project-related factor.
134
Path Estimate. There were Path estimates for both the effect and outcome variable.
The estimated regression coefficients analysis shows positive effect between all predictor
Material- related factors, Church organizational structure, and Project-related factors), and the
outcome variable Church construction delay. For every single increase in Church organization
related factors, and Project-related factors on Church construction delay will increase by a
percentage of .155, .074, .112, .146, .212, and -.111, respectively, as the estimated regression
forecasted. Similarly, the probability estimates of attaining high critical ratios of 2.892 to 6.337
are less than 0.05, 0.01, and 0.1 for Church organization structure, client /owner-related factors,
factors. The analysis ascertained that there was a stable linear and definite relationship among all
construction delay.
H1a: There is a relationship between client /owner-related factors and Church construction
delay.
H2a: There is a substantial relationship between Church organization structure and Church
construction delay.
construction delay.
construction delay.
135
H40: There is no substantial relationship between project-related factors and Church
construction delay.
construction delay.
delay.
delay.
construction delay.
construction delay.
related factors was the most significant predictor of all the remaining variables on the factors,
positively affecting the Church construction delay. In contrast, client /owner-related factors had
the lowest significant correlation on Church construction delay, comparably. Furthermore, at .05
and 0.01 level of significance, there existed enough indication to decide that all the observed
slopes in the research model were not equivalent to zero to the extent that, Church organization
related factors, and Project-related factors, β 0) in that, all these predictor variables are suitable in
136
Table 12
Hypothesis Testing
Note. A tabulation of the research outcome showing the variables, statistical inference, on ChuOS,
The findings of this study answered the six research questions and the preceding
construction delay?
In answering the above research question, the current research analysis in Table 9
confirmed a positive association between client /owner-related factors and Church construction
delay with an SD and mean of 3.71 and 1.027, respectively. Further, analysis on validity and
reliability in Table 11 indicated that all the requirements were met for proceeding to model the
construct, with CR of 0.912, AVE of 0.637, and MSV of 0.107. The independent and dependent
variables in Table 10 were concurrently examined using the Pearson correlation, and the link
between the independent and the dependent variables was extremely positive, showing that all the
137
constructs were stable. Hence, there were no challenges with multicollinearity, which made it very
Furthermore, the path estimate was generated for the effect of the predictor variable of
client /owner-related factors, on the outcome variable of Church construction delay. As seen in
sTable 12 and Figure 12 the estimated regression coefficients analysis showed a positive effect
between the predictor variable of client /owner-related factors and the outcome variable Church
construction delay, such that, for every single increase in a client /owner-related factor, Church
construction delay will increase by a percentage of .074, as the estimated regression forecasted.
Correspondingly, the probability estimates of attaining high-level critical ratios of 2.892 to 6.337
were less than 0.05, 0.01, and 0.1 for client /owner-related factors. The analysis ascertained that
there was a stable linear and definite relationship among the predictor variable and the outcome
variable. Therefore, the above analysis conducted enabled the research question to be answered by
rejecting the null hypothesis and accepting the alternative hypothesis: H1a: There is a substantial
To answer this research question, the current research analysis in Table 9 indicated that
there existed a positive relationship between Church organization structure and Church
construction delay with an SD and mean of 2.98 and 1.092, respectively. Further analysis on
validity and reliability from Table 11 indicated that all the requirements were met for proceeding
to model the construct, with CR of 0.935, AVE of 0.705, and MSV of 0.176. The independent and
dependent variables in Table 10 were concurrently examined using the Pearson correlation, and
the link between the independent and the dependent variables was extremely positive, showing
that all the constructs were stable. Hence there were no challenges with multicollinearity, which
138
Additionally, the path estimate was generated for the effect of the predictor variable of
Church organization structure on the outcome variable of Church construction delay. From Table
12 and Figure 12 the estimated regression coefficients analysis revealed a positive effect between
the predictor variable of Church organization structure and the outcome variable Church
construction delay such that, for every single increase in a Church organization structure, Church
construction delay will increase by a percentage of .155, as the estimated regression forecasted.
Correspondingly, the probability estimates of attaining high-level critical ratios of 2.892 to 6.337
were less than 0.05, 0.01, and 0.1 for Church organization structure. The analysis established that
there is a strong linear and positive relationship among the predictor variable and the criterion
variable. Therefore, the above analysis conducted enabled the research question to be answered by
rejecting the null hypothesis and accepting the alternative hypothesis: H2a: There is a momentous
construction delay?
The above research question was answered through the current research analysis in Table
9, which revealed a positive relationship between quality-related factor and Church construction
delay, with an SD and mean of 3.24 and 1.034, respectively. Further analysis from Table 11 on
validity and reliability indicated that all the requirements were met for proceeding to model the
construct, with CR of 0.874, AVE of 0.581, and MSV of 0.116. The independent and dependent
variables in Table 10 were concurrently examined using the Pearson correlation, and the link
between the independent and the dependent variables was extremely positive, showing that all the
constructs were stable. Hence there were no challenges with multicollinearity, which made it very
Also, the path estimate for the effect of the predictor variable of quality-related factor on
the outcome variable of Church construction delay was examined. From Table 12 and Figure 12,
139
the estimated regression coefficients analysis indicated a positive effect between the predictor
variable of quality-related factors and the outcome variable Church construction delay such that,
for every single increase in a quality-related factor, Church construction delay will increase by a
estimates of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05, 0.01, and 0.1
for quality-related factor. The analysis established that there was a stable linear and definite
relationship among the predictor variable and the outcome variable. Therefore, the above analysis
conducted answered the research question by rejecting the null hypothesis and accepting the
alternative hypothesis: H3a: There is a substantial relationship between quality-related factors and
construction delay?
The above research question was answered through the current research analysis. Table 9
revealed a positive relationship between project-related factors and Church construction delay with
an SD and mean of 3.44 and .797, respectively. Further analysis in Table 11 on validity and
reliability indicated that all the requirements were met for proceeding to model the construct, with
CR of 0.769, AVE of 0.405, and MSV of 0.038. The independent and dependent variables in
Table 10 were concurrently examined using the Pearson correlation, and the link between the
independent and the dependent variables was extremely positive, showing that all the constructs
were stable. Hence there were no challenges with multicollinearity, which made it very appropriate
Moreover, the path estimates for the effect of the predictor variable of Project-related
factors on the outcome variable of Church construction delay was examined. From Table 12 and
Figure 12, the estimated regression coefficients analysis indicated a positive effect between the
predictor variable of Project-related factors and the outcome variable Church construction delay
140
such that, for every single increase in a Project-related factor, Church construction delay will
probability estimates of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05,
0.01, and 0.1 for Project-related factors. The analysis established that there was a stable linear and
definite relationship among the predictor variable and the outcome variable. Therefore, the above
analysis conducted answered the research question by rejecting the null hypothesis and accepting
the alternative hypothesis: H4a: There is a substantial relationship between project-related factors
construction delay?
The above research question was answered through the current research analysis, which
construction delay with an SD and means of 3.38 and 1.035, respectively. Further analysis from
Table 11 on validity and reliability indicated that all the requirements were met for proceeding to
model the construct, with CR of 0.875, AVE of 0.643, and MSV of 0.284. The independent and
dependent variables in Table 10 were concurrently examined using the Pearson correlation, and
the link between the independent and the dependent variables was extremely positive, showing
that all the constructs were stable. Hence there were no challenges with multicollinearity, which
Again, the path estimate for the effect of the predictor variable of material-related factors
on the outcome variable of Church construction delay was examined. From Table 12, and Figure
12, the estimated regression coefficients analysis indicated a positive effect between the predictor
variable of material-related factors and the outcome variable of Church construction delay such
that, for every single increase in material-related factors, Church construction delay will increase
141
estimates of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05, 0.01, and 0.1
for material-related factors. The analysis established that there was a stable linear and definite
relationship among the predictor variable and the outcome variable. Therefore, the above analysis
conducted answered the research question by rejecting the null hypothesis and accepting the
construction delay?
In the quest to answer this research question, the current research analysis in Table 9
with an SD and mean of 2.86 and .996, respectively. Further, analysis on validity and reliability in
Table 11 indicated that all requirements were met for proceeding to model the construct, with CR
of 0.888, AVE of 0.575, and MSV of 0.067. The independent and dependent variables in Table 10
were concurrently examined using the Pearson correlation, and the link between the independent
and the dependent variables was extremely positive, showing that all the constructs were stable.
Hence there were no challenges with multicollinearity, which made it very appropriate to proceed
Furthermore, the path estimate was generated for the effect of the predictor variable of
external-related factors on the outcome variable of Church construction delay. From Table 12 and
Figure 12, the estimated regression coefficients analysis showed a positive effect between the
predictor variable of external-related factors and the outcome variable of Church construction
delay such that, for every single increase in external-related factors, Church construction delay
Correspondingly, the probability estimates of attaining high-level critical ratios of 2.892 to 6.337
were less than 0.05, 0.01, and 0.1 for external-related factors. The analysis established that there
142
was a stable linear and definite relationship among the predictor variable and the outcome variable.
Therefore, the above analysis conducted answered the research question by rejecting the null
hypothesis and accepting the alternative hypothesis: H6a: There is a substantial relationship
Summary of Results
Chapter Four discussed the socio-demographic variables of participants and data analysis.
In Table 5, the age ranges of respondents in the study showed that the ages of 31 to 40 years were
the highest respondents’, whereas the least number of participants were aged below 20 years.
Participants' profession/role in the construction project revealed that those with other managerial
positions participated more, with a 39.3% rate. In contrast, electricians, and site superintendents
(foreman) were the least participants, with 1.99% each. Respondents’ level of education showed
80.1% as the highest for University graduates and the least being 3.98% for high school leavers.
Respondents' years of experience in the construction firm showing 1-5 years’ experience
being the highest and 16 years and above as the least of the participants. On the other hand, in
Table 6, the reduction of the data was obtained using the principal component analysis and rotated
matrix and Promax with Kaiser Normalization. The observed communalities for all the items were
satisfactorily high, ranging from 0.4 to 0.8, demonstrating enough correlations among the items for
the constructs in the study model. In Figure 12, the path estimate showed the relationship between
the independent and dependent variables to be positive. The independent and dependent variables
in Table 10 were concurrently examined using the Pearson correlation, and the link between the
independent and the dependent variables was extremely positive, showing that all the constructs
were stable. Hence, there were no challenges with multicollinearity, which made it very
appropriate to proceed with the analysis. In Table 9, the descriptive statistics of all the
measurements had a mean of 2.86 to 3.71 and an SD of .88 to 1.092. In Table 11, the reliability
and validity conducted met all the requirements to proceed to model the construct. All the AVEs
143
had above the preferred 0.5 range except project-related factors with 0.405 but was accepted since
the CR for project-related factors was 0.769 and beyond the acceptable 0.6 level, as argued by
Lam (2012). The CR values for all the constructs exceeded the threshold of 0.7, ranging from
0.769 to 0.935. All the observed values for both MSVs were less than the AVEs values, indicating
that there existed distinct factors in the study model. Also, estimates from Cronbach's Alpha
values were 0.742 to 0.913, which were above the minimum requirement of 0.6 for all the
Table 13
Hypothesis
Estimate p
Constructs Remarks
Note. The table illustrates all the hypotheses with the corresponding estimated regression statistics
and P values to determine the acceptance or rejection status.
144
Chapter 5: Conclusions and Recommendations
This chapter summarizes the quantitative technique findings, discussion of the results,
conclusion strategic recommendations for all the findings, and future recommendations. These
findings are within the 402 respondents who participated in the survey in the Akuapem Presbytery
of PCG. This section scrutinized six research questions with the corresponding hypotheses for
related factors, Material-related factors, and Project-related factors on Church construction delay,
which was in line with the initial plan to use a questionnaire for data collection (Todorović, et al.,
2015). The outcomes are presented in Tables, charts, and figures to give quantifiable data for
analysis.
The study revealed six research questions and their respective hypothesis. This part of the
research summarizes the findings of each of the outlined hypothesis in the study for Church
H10: client /owner-related factors have no relationship with Church construction delay.
H1a: client /owner-related factors have a relationship with Church construction delay.
The study revealed in Figure 12 that there was a stable linear and definite relationship
among the predictor variable and the outcome variable. The null hypothesis for H1 was rejected,
and the alternative hypothesis was accepted: H1a: client /owner-related factors have a relationship
with Church construction delay. There was a positive connection between client /owner-related
factors and Church construction delay, with an SD and mean of 3.71 and 1.027, respectively. The
validity and reliability showed that all necessities criteria were met with CR of 0.912, AVE of
0.637, and MSV of 0.107. In Table 10, the independent and dependent variables were
concurrently examined using the Pearson correlation, and the link between the independent and the
145
dependent variables was extremely positive, showing that all the constructs were stable. The
probability approximations of attaining high-level critical ratios of 2.892 to 6.337 were less than
construction delay.
H2a: Church organization structure has a substantial relationship with Church construction
delay.
The analysis in Table 9 shows that the independent and dependent variables were
concurrently examined using the Pearson correlation, and the link between the independent and the
dependent variables was extremely positive. Figure 12 shows that the probability approximations
of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05, 0.01, and 0.1 for
Church organization structure. Also, there was a stable linear and definite relationship among the
predictor variable and the criterion variable. This, therefore, led to the null hypothesis’ rejection
and approval of the alternate hypothesis: H2a: Church organization structure has substantial t
relationship with Church construction delay. Again, there was a positive relationship between
Church organization structure and Church construction delay with an SD and a mean of 2.98 and
1.092, respectively. The validity and reliability showed that all the requirements were met for
proceeding to model the construct, with CR of 0.935, AVE of 0.705, and MSV of 0.176.
H30: quality-related factors have no significant association with Church construction delay.
H3a: quality-related factors have a significant association with Church construction delay.
There was a positive relationship between quality-related factors and Church construction
delay, with an SD and a mean of 3.24 and 1.034, respectively. The validity and reliability showed
that all the requirements were met for proceeding to model the construct, with CR of 0.874, AVE
of 0.581, and MSV of 0.116. As seen in Table 10, the independent and dependent variables were
concurrently examined using the Pearson correlation, and the link between the independent and the
146
dependent variables was extremely positive. Figure 12 indicates that the probability
approximations of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05, 0.01,
and 0.1 for quality-related factors. Also, there was a stable linear and definite relationship among
the predictor variable and the outcome variable. This, therefore, resulted in the null hypothesis’
rejection and approval of the alternate hypothesis: H3a: Quality-related factors have a considerable
delay.
H4a: Project-related factors have a substantial relationship with Church construction delay.
The study revealed a positive relationship between project-related factors, and Church
construction delay, with an SD and a mean of 3.44 and .797, respectively. The validity and
reliability showed that all the requirements were met for proceeding to model the construct, with
CR of 0.769, and AVE of 0.405, MSV of 0.038. Table 10 shows that the independent and
dependent variables were concurrently examined using the Pearson correlation, and the link
between the independent and the dependent variables was extremely positive. The probability
approximations of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05, 0.01,
and 0.1 for project-related factors. Also, there was a stable linear and definite relationship among
the predictor variable and the outcome variable. Therefore, this led to the null hypothesis’ rejection
and approval of the alternate hypothesis: H4a: There is a substantial relationship between external-
delay.
delay.
147
The findings showed that the validity and reliability of all the requirements were met for
proceeding to model the construct, with CR of 0.875, AVE of 0.643, and MSV of 0.284. Also,
there was a positive relationship between material-related factors and Church construction delay,
with an SD and a mean of 3.38 and 1.035, respectively. In Table 10, the independent and
dependent variables were concurrently examined using the Pearson correlation, and the
independent variables showed a weak association among one another, whereas the link between
the independent and the dependent variables was extremely positive. The probability
approximations of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05, 0.01,
and 0.1 for material-related factors. Also, there was a stable linear and definite relationship among
the predictor variable and the outcome variable. Therefore, this led to the null hypothesis’ rejection
and approval of the alternate hypothesis: H5a: There is a relationship between material-
construction delay.
construction delay.
The results discovered that there was a positive association between External-related
factors and Church construction delay, with an SD and a mean of 2.86 and .996,
respectively. The validity and reliability showed that all the requirements were met for
proceeding to model the construct, with CR of 0.888, AVE of 0.575, and MSV of 0.067.
In Table 10, the independent and dependent variables were concurrently examined using
the Pearson correlation, and the link between the independent and the dependent variables
was extremely positive, showing that all the constructs were strong. The probability
approximations of attaining high-level critical ratios of 2.892 to 6.337 were less than 0.05,
0.01, and 0.1 for External-related factors. Also, there was a stable linear and definite
148
relationship among the predictor variable and the outcome variable. Therefore, leading to
the null hypothesis’ rejection and approval of the alternate hypothesis: H6a: There is a
This aspect deals with the discussions of the outcomes attained from the data analysis in
Chapter Four. The main components of the discussion are compr sed of the influences of Church
factors, Material-related factors, and Project-related factors on Church construction delay. The
construction delay.
The findings revealed that the client /owner-related factors have a substantial relationship
with Church construction delay (β = 0.740; p<0.04). This result demonstrated a low proof counter
to the null hypothesis and an endorsement of the alternate hypothesis. This finding corresponds to
those of Gbahabo and Ajuwon (2017) and Nyoni and Bonga (2017), which revealed that client
/owner-related factors have a significant influence on project delays. In the literature, Sambasivan,
et al. (2017) explained that, whenever there are discrepancies in instructions or interruption in
decision-making, and challenges in the cashflow, construction activities delay. In line with the
study results, Alpkokin and Capar (2019) and Kim and Kang (2018) argued that the client/owner’s
inability provided a clarified perception of the total cost of the construction project and whether
they can afford the proposed construction projects. The study of McCord et al. (2015) added that
the deliberate attempt of the client/owners and the lack of remuneration for early completion of
In conformity with these findings, the studies of Purnus and Bodea (2014) have indicated
that, just as working during the night time as preferred by most of the Clients/owners, the cost gets
149
higher concerning providing inputs for arrangements of lights at night and other allowances to
compensate the workers’ efforts for extra hours. Moreover, Mohammad, Ani and Rakmat (2017)
and Purnus and Bodea (2014) agreed with the study findings that client /owner-related factors
have a significant component in construction delay and attributes the absence of better equipment
and lack of planning by client/owners as significant components. Also, the study of KV and Bhat
(2019) affirmed the findings that client /owner-related factors trigger construction delay if there is
findings with the previous work concluded in support of the alternate hypothesis that client
The results indicated that Church organization structure has a significant influence on
Church construction delay (β = 0.155; p<0.000). The outcome portrayed low evidence support to
the null hypothesis and an agreement of the alternate hypothesis. These findings are signs of
noncompliance to the PCG-Constitution (2016) that spells out the church structure to be followed
for effective administration. The church mandates the local session to oversee all Church projects.
A study by Northouse (2018) mentioned that leadership plays an essential part in the management,
not well regulated, defeat its core intention, and non-leading change breaks sustainability. The
findings again reflect the Akuapem Presbytery report (2014) in the literature review that improper
Similarly, the results parallel the work of Asiedu et al. (2017), who found that the lack of
administrative contingencies in the budget contributes to project delay. Besides, the findings
confirm those of Brunet (2019) that lack of proper decision-making by the organization and the
absence of strategic planning in organizations breed delay. Also, Mulugeta (2019) and Madalina
150
(2016), in their studies, assented that organizational structure is a hindrance to administrative
progress when there is a communication barrier. In conclusion, the evidence presented in the study
and the discussions show that Church organization structure has a considerable connection with
construction delay.
The outcome showed that quality-related factors have a positive influence on Church
construction delay (β = 0.146; p<0.000). This result was a low indication on the null hypothesis
and an endorsement of the alternate hypothesis. The findings affirmed the study of Rahman et al.
(2014) that delay in construction work has opposing influences on the quality of the project, with
lack of planning being the key element. Similarly, Durdyev et al. (2017) and Asiedu and Alfen
(2016) attributed inferior project quality to inadequate budget allocation for the construction
project. Besides, Larsen et al. (2015) emphasized that as a result of poor financial planning, the
government, politicians, industries, and church suffer the consequences of inferior quality
construction projects. In agreement with the findings, Buys (2015) and Marzouk and El-Rasas
(2014) argued that the absence of effective monitoring of the construction project from the
commencement of the construction leads to low standard work. On the contrary, Bowen et al.
(2015) and Niazi and Painting (2017) deplored the bribery and corruption attributes of both the
government and the contractors, which deter the quality of construction projects. The results and
the discussions showed that there exists a meaningful relationship between quality-related factors
construction delay.
The study disclosed that there was a positive relationship between project-related factors
and Church construction delay (β = -0.111; p<0.000). This outcome rejected the null hypothesis
151
and accepted the alternative hypothesis. The findings confirmed with that of Aziz and Abdel-
Hakam (2016), who found project-related factors as a component of construction delay and linked
them to uncertain project duration and complicated project design as vital elements of project-
related factors. Moreover, the work of Wallensteen (2018) emphasized the study outcome that
project-related factors, such as legal disputes between project parties, are a construction delay
component.
Nevertheless, the work of Ramanathan et al. (2012) substantiated the study results that
becomes challenging in its implementation. In a comparable view of the findings, Famiyeh et al.
(2017) revealed that project-related factors are a significant component of construction delay due
(2013) realized that improper preparation ahead of commencing the construction project is one of
the critical elements of project delay. In support of the project-related factors in construction
delay, Asiedu and Alfen (2014) concluded that tardiness and indecision in payment of workers
trigger the project-related delay. Based on the findings and previous results, the study concluded
delay.
The study revealed a positive relationship between material-related factors and Church
construction delay (β = 0.212; p<0.000). This conclusion showed acceptance of the alternate
hypothesis while rejecting the null hypothesis. The survey endorsed the findings of Arthur (2016),
Gebrehiwet and Luo (2017), and Pall (2016) who identified material-related factors as a crucial
factor of construction delay. In addition, the study findings were like those of KV and Bhat
(2019), who argued that material-related factors trigger construction delay and attributed them to
152
timely basis for the project. Similarly, in another study, Durdyev et al. (2017) confirmed that
material-related factors are prominent sources of construction delay and ascribed them to late
delivery of the essential materials for the construction. Agreeing with the findings, Gebrehiwet
and Luo (2017) concluded that material-related factors lead to construction delay when there is an
increase in material prices and when the clients/owners prefer cheaper material to suit their budget.
From the analysis of the study and the literature support, it was evident that material-related
construction delay.
delay, the study found that external-related factors have a positive relationship with Church
construction delay (β = 0.112; p<0.001). This outcome was proportional to the earlier argument of
Arditi et al. (2017) that external-related factors influence construction delay in that some
uncontrollable external-related factors are over and above the control of the contractor, the
client/owner, and the project manager. Also, the study finding was like that of Addo (2016),
Alzraiee et al. (2015) and Baiden et al. (2015) who resolved that external-related factors increase
the construction delay to the extent that price appreciation, labour disputes, acts of God, and harsh
Moreover, Najib et al. (2018); and Sinesilassie et al. (2017) discovered in support of the
findings that external-related factors are hypothetical generating factors of construction delay but
linked them to components such as late access to the site, unsuitable site conditions, and
unfriendly economic and political environments. In support of the results, Agyekum-Mensah and
Knight (2017) and Adam et al. (2017) maintained that external-related factors have a massive
impact on construction delay due to the late issuance of building permits and the late approval of
drawings as well as unfavourable weather conditions. As a result of the findings, and the
153
discussions, the study confirmed a considerable relationship between external-related factors and
Conclusions
This research was an empirical study of the Akuapem Presbytery of the PCG that sought to
explore the delays in construction projects. An extensive literature review was done to uncover
aspects of delay, including its components, classification, factors, and effects. Challenges in the
construction project and ways of improving construction projects were also discussed.
Furthermore, questionnaires were generated and distributed to 480 persons in the construction
(those on the project and investment committee/session), using the online survey tool, MikeCRM.
Out of the 480 questionnaires distributed, 402 were completed and returned, representing a
response rate of 83.8%. Also, employing the sample data, the intended study model was then
examined statistically using EFA, CFA, the Pearson correlation, and AMOS.
In the first place, the EFA was adopted to verify the existence of correlations in the
proposed model. The results indicated that the research data generously showed the overall
significance of all the correlations within the correlation matrix for KMO and Bartlett’s test of
sampling adequacy of 0.846, significant with approximate Chi-Square of 9.345E3 at 9630 df,
p<0.000. The CFA was used to verify decency in the model, and the results justified the
relationships among the observed indicators and their parallel latent variables. Again, the validity
and reliability conducted met the criteria for this study, which suggested a further analysis of the
research. Also, the Pearson correlation was employed to test for the suitability of variables and
identify any issues of multicollinearity. The analysis established no issues with the
multicollinearity. Though, the relationship among the independent variables demonstrated weak
association among one another, the correlation amongst the dependent variable, Church
154
construction delay and independent variables, client /owner-related factors, external-related-
organization structure was stable. In another development, the data analysis was conducted for six
hypotheses with the corresponding objectives to investigate the relationships that exist between
Church construction delay and client /owner-related factors, Church organization structure,
In all, the findings confirmed the module created fit for the study (see Figure 6). Therefore, the
delay.
delay. In answering the above research question, the present research analysis in Table 9 showed
a positive association between client /owner-related factors and Church construction delay. The
outcomes implied that clients/owners trigger delays in church construction delay. Practically, it
means that when the resident minister/pastor or the agent in charge of the congregation (the
client/owner) fails to provide the basic things like money or materials needed to continue the work,
there is a delay in the Church construction, as presented by Nyoni and Bonga (2017). The analysis
further indicated that comparing all the six constructs, client /owner-related factors had the lowest
connection on Church construction delay (β = 0.074, p<0.004). This discovery, to some extent, did
not agree with all the earlier literature. The finding is totally opposite to the work of Mohammad et
al. (2017), who confirmed client/owner related factors as a major influence of project delay,
whereas Sambasivan et al. (2017) promoted client/owner satisfaction as priority. Out of sixty
proposed delay causes identified by McCord et al. (2015) the client/owner related factor was
ranked among the first three causes of construction delay. This is an indication that in the Church’s
setting, though client/owners trigger delay, it is not as high as in the public sector. The church has
155
structures that must be followed by the resident minister/pastor who serves as the client/owner in
charge of the construction project, and he cannot be 100% blamed for all the delays.
delay
construction delay. The results indicated that Church organization structure has a considerable
relationship with Church construction delay (β = 0.155, p<0.000). This finding implied that the
laid down chain of command and church management systems have a substantial relationship with
Church construction delay. The PCG has a procedure for executing construction projects, which
includes the use of the PIC through the session (PCG-Constitution, 2016). Therefore, whenever
there is a leadership challenge or when the laid down principles of the church are not followed in
executing the Church construction projects, it automatically hinders the flow of work in proposed
construction projects. The discovery was equivalent to Chen et al. (2019b), which indicated that
breaks in administrative command among the parties involved trigger delays. It was proved that
there are adequate correlations among all the six proposed components for Church organization
structure in the construct, ranging from 0.485 to 0.788. The degree to which Church organization
structure influences construction delay was found in components like Church Agents (0.879), no
long-term strategic planning (0.872), the style of leadership by church decision-makers (0.863),
diversion of church funds into other things (0.851), no specific project budgets for the construction
work (0.849), and lack of communication among church decision-makers and church members
(0.803) (Asiedu, et al., 2017; Brunet, 2019; Doppelt, 2017; Madalina, 2016; Mulugeta, 2019;
Northouse, 2018).
delay. Considering the cost and resources put into the construction project, the quality-related
156
factors were analysed, and the outcome revealed a positive correlation with the Church
construction delay (β=0.146, p<0.000). This finding was equivalent to that of Algwyad and Talib,
(2019) and Attakora-Amaniampong (2016) who asserted that the project’s quality has a significant
influence on construction delay. Additionally, Table 6 indicates that there are adequate
correlations among all the six proposed components for quality-related factors in the constructs,
ranging from 0.798 to 0.849. They included lack of quality assurance in the project (0.849), the
quality planning (0.839), the understanding of the potential benefits of quality implementation
(0.837), and the appropriate quality supervision and appraisal of the quality plan (0.798) (Bowen,
et al., 2015; Durdyev, et al., 2017; Larsen et al., 2015; Niazi & Painting 2017; Rahman, et al.,
delay. In examining the relationship between project-related factors, and Church construction
delay, the study disclosed a positive association amongst the project-related factors, and Church
construction delay (β = -0.111, p<0.000). It was established that all the six anticipated
components of the project-related factors, had a satisfactory correlation range from 0.485 to 0.788.
They included original contract duration (0.788), unfavourable contract clauses (0.781), and legal
disputes between project participants (0.745). The rest was the complexity of projects such as the
size and kind of the project (0.655), and insufficient description of an ample date for completing
the project (0.485). The findings were similar to the works of Akogbe et al. (2013); Aziz and
Abdel-Hakam (2016); Famiyeh et al. (2017); Niazi and Painting (2017); and Wallensteen (2018).
construction delay. The study revealed a positive relationship between material-related factors
and Church construction delay (β = 0.212, p<0.000). It was further established that material-
157
related factors are the most influential delay component in the PCG. This finding was in
congruence with Rahman et al. (2014), who ranked material pricing as the highest delay factor.
Akogbe et al. (2013) also classed lack of funds to procure materials as a major factor of
delay. Furthermore, it was also demonstrated that there were adequate correlations among all the
four proposed components for material-related factors in the constructs, ranging from 0.785 to
0.874. The components included a delay in the approval of materials (0.874), lack of quality
resources (0.855), shortage of building materials (0.833), and late delivery of material to the site
(0.785). The results conformed to the earlier works of Arthur (2016); Asiedu and Alfen (2016);
Kagiri and Wainaina (2017); Pall et al. (2016); and Sambasivan et al. (2017).
construction delay, the study found that external-related factors have a positive relationship with
Church construction delay (β = 0.112, p<0.001). This finding implied that the external-related
factors have consequences for construction delays in the Presbyterian Church of Ghana. It was
confirmed that there were adequate correlations among all the six proposed components for
Church organization structure in the construct, ranging from 0.485 to 0.788. This included the
third party’s delay in completing final assessment and documentation (0.847), unfavourable
weather conditions (0.844), and thefts done on-site (0.828). Also, price fluctuations in building
materials (0.813), insufficient manufacturing of local raw material (0.794), and modifications in
government policies and by-laws (0.645) (Agyekum-Mensah & Knight, 2017; Lines, et al., 2015;
158
Practical Recommendations
There are several practical implications of the discoveries and contributions of this study,
which, when utilized, can help both the church and the nation. The study recommends these
The client/owner of the project or the church must be presented with improved awareness
about the budget of the construction project and whether or not the necessary money can be
provided for the efficient carrying out of the proposed projects. This can be done when the
client/owner seeks construction experts’ counsel on the intended project, and ensures the provision
of adequate funds to meet the prepared budget before commencing the work (Larsen, et al., 2015).
This can do away with the interruption of the church construction projects due to insufficiency of
the funds. Again, an eventuality plan needs to be prepared each time if there are ineffective funds
and this can be used to raise resources for the rapid purchasing of materials at any moment to
avoid delays (Arantes, & Ferreira, 2020; KV & Bhat, 2019). Furthermore, there is the need to
have a manual or a handbook that spells out the details of the project to be constructed, and
responsibilities are to be assigned to the right persons before the work starts. This aids in
strengthening the chain of command in terms of who does what at what time, and leads to
thorough discussions among all the key parties, like the contractor, the site engineer, and the
consultant, with the client/owner’s team (Nyoni & Bonga, 2017). There is a need to have an active
communication channel between the workers and the client/owner. This can best be done by
frequent weekly scheduling or fortnightly meetings between all the key parties involved in the
project (Gebrehiwet & Luo, 2017). Besides, the client/owner must approve of the intended
building design before starting the project and understand that regular unplanned changes in the
project are a breach of the contract rules and attract a penalty. Also, the client/owner must
endeavour to have all the design documents approved by the authorized or the certified board
159
ahead of starting the project. This would prevent later review and endorsement of the building
The church must give directives that, until one construction project is completed, a new
project cannot be undertaken. This can be achieved by implementing a sustainable strategic plan
for construction projects (Schwing & Urtasun, 2015). Church Agents (ministers and catechists),
on transfers to and from a station, must update themselves about the strategic plan and continue
from where a construction project was paused. To achieve this, the session (board) and the local
project committee must brief such agents. Strict adherence to this will not hinder construction
projects in the congregations, even if a minister (Resident Pastor) or an agent is transferred (PCG-
Constitution, 2016). Again, every decision to undertake a construction project must be made by
the session (board), and must empower the church’s PIC to present details of the project for
discussion and approval. The PIC must be made up of experts (architects, engineers, building
consultants, project managers, and financial planners). The CAB of the church must be tasked by
session (board) to prepare precise budgets for construction projects and propose possible ways of
opened to directly deposit project funds to avert the diversion of funds intended for construction
works into other activities (Zack-Williams, 2017). There must be frequent feedback from the
various committees, like the PIC and the CAB, to the session (board). This can, ideally, be done
by co-opting a session (board) member each to the CAB and the PIC to update session (board),
and then the session will keep the congregation abreast regularly.
160
Recommendations for quality-related factors. At the beginning of the construction
project, there must be a proper briefing for the workforce on quality assurance. The PIC, the
consultant, contractor, and all the parties involved must sign a declaration of providing quality
work. This can be attained by proper planning involving the supply of top-quality resources (Dixit
& Sharma, 2019; Tang, et al., 2015). The parties participating in the construction project need to
be educated to appreciate the implications of using accredited and standardized materials for the
projects and the need to supply them promptly (Gebrehiwet, & Luo, 2017). This is achievable
when the emphasis is placed on proper monitoring and evaluation of the construction work (Zhang
& Yangb, 2019). The church needs to outsource an accredited monitoring and evaluation board to
inspect the work at each of the stages and offer suggestions where necessary. To ease this process,
the PCG must implement a policy on quality construction projects for the church.
project must be detailed and justifiable. This means the timeline for the entire project
must be strategic enough, allowing for unforeseen circumstances (Akogbe, et al., 2013). This can
be carefully done by making room for building in stages; for instance, the first stage, from
foundation to flooring; second stage up to lintel; third stage up to roofing; a fourth stage for the
finishing phase. Also, there must be decent contract clauses, which can be done by making all the
clauses in the building contract very clear and easy to read and understand (Famiyeh, et al., 2017;
Kim, et al., 2018). Once this is done, it will prevent needless disputes between project
participants (Equbal, et al., 2017). In addition, there must be a manual for a church building and
church manse (mission house). The PCG must establish criteria for construction projects in the
church, especially for the congregations in the less-endowed communities. Such projects must be
modest and affordable to build and complete within the shortest period taking all risks into account
(Awuni, 2019).
161
Recommendations for Material-related factors. To avoid late endorsement of
construction materials, the client/owner, contractor, consultant, or the manager must start the
process far ahead of time and be sure that the proposed materials for the project are available in the
market. The approved sample materials for the project must be ordered ahead of time in the
required quantity (Soomro, et al., 2019). There must be adequate quality resources, which
includes experienced and qualified workforces as well as standard materials for the project
(Akogbe, et al., 2013). There is a need to make provision for the prompt delivery of materials to
the project site (Gebrehiwet & Luo, 2017). This can best be accomplished by appointing a works
superintendent to oversee the project materials and schedule delivery (Sutar & Mehendale 2017).
the completed construction work by the authorized examining board (Allen & Iano, 2019). There
should be a penalty for consultants or contractors who fail to adhere to the provisions of the
contract. The client/owner and the consultant must ensure that inspection of the completed work is
done swiftly and adequately with certification. Again, there must be provision of a proper storage
facility for the building materials and also enough shade for the workers to counter unfavourable
weather conditions that may disturb the flow of work (Durdyev, et al., 2017). Also, to avoid the
theft of materials and other useful resources, there must always be a security guard on site as well
as enough lights around the storage area at night (Zidane, & Andersen, 2018). Furthermore, to
avoid price fluctuations in building materials, there must be a proper and approved budget before
the commencement of the projects (Asiedu, et al., 2017). This means there must be a contingency
plan to cater for any shortage, where applicable. In addition, there is the need to purchase materials
in bulk and from the approved producer. This would prevent the purchasing of inferior materials
and material wastage (KV & Bhat, 2019). In cases where the required materials are out of stock,
the contractor, the consultant, the manager, or the client/owner must plan for an alternate product.
162
There is a need for all the project parties involved to be well informed of modifications made in
government policies and by-laws before commencing any construction project (Wyer, 2019).
In accordance with the study limitations in Chapter One and the several benefits derived
from the Church construction projects, this study presented the basis for future research. For
1. Concerning the geographical study size, it is suggested that upcoming researchers should
cover the entire PCG, so the results can uncover different patterns of factors that can lead
2. The model created for this study has been developed on the perception of construction
delays which some developing nations have been using (see Figure 6). Therefore, future
factors affecting the Pentecostal churches and the PCG and to determine the restraining
4. Future researchers must consider conducting both qualitative and quantitative studies to
5. Finally, future researchers should consider expanding the research model to help address
all the risks that might arise during such projects. This would help stakeholders in
mitigating risk. To further help eliminate construction delays, technology for risk
(clients/owners, contractors, consultants, and session) should have a risk management plan.
163
References
Acebes, F., Pajares, J., Galán, J. M., & López-Paredes, A. (2014). A new approach for project
control under uncertainty. Going back to the basics. International Journal of Project
Adam, A., Josephson, P. E., & Lindahl, G. (2015). Implications of cost overruns and time delays
Berlin, Heidelberg.
Adam, A., Josephson, P. E. B., & Lindahl, G. (2017). Aggregation of factors causing cost overruns
and time delays in large public construction projects: trends and implications. Engineering,
Adebowale, O. J., & Ayodeji, F. J. (2015). Analysis of construction-related factors affecting the
Addo, J. (2016). Delay and Its Effect on The Delivery of Construction Projects in Ghana. African
Adukrom District Report, (2014). Presbyterian Church of Ghana, Adukrom District Report.
Agyekum-Mensah, G., & Knight, A. D. (2017). The professional’s perspective on the causes of
Ahiaga-Dagbui, D. D., Love, P. E., Smith, S. D., & Ackermann, F. (2017). Toward a systemic
view to cost overrun causation in infrastructure projects: A review and implications for
Ahmed, K., Hatira, L., & Valva, P. (2014). How can the construction industry in Ghana become
sustainable?
164
Akogbe, R. K. T., Feng, X., & Zhou, J. (2013). Importance and ranking evaluation of delay
Akomah, B. B., & Jackson, E. N. (2016). Contractors’ perception of factors contributing to road
79-85.
Akuapem Presbytery Report, (2014). Projects and Investment Report. Accessed on 28th February
Akuapem Presbytery Report, (2013). Projects and Investment Report. Accessed on 3rd June 2015
from www.akuapempresbyteryadm.org
Alade, K. T., Lawal, A. F., Omonori, A. A., & Olowokere, E. N. (2016). Causes and effects of
Allen, E., & Iano, J. (2019). Fundamentals of building construction: materials and methods.
Alotaibi, N. O., Sutrisna, M., & Chong, H. Y. (2016). Guidelines of Using Project Management
Tools and Techniques to Mitigate Factors Causing Delays in Public Construction Projects
Alzraiee, H., Zayed, T., & Moselhi, O. (2015). Dynamic planning of construction activities using
Alpkokin, P., & Capar, M. S. (2019). Dispute boards in Turkey for infrastructure projects.
165
Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015). Analysing delay causes and
Arantes, A., & Ferreira, L. M. D. (2020). Underlying causes and mitigation measures of delays in
Arcades Design and Construction (2018): Global Construction Disputes Report 2018: Does the
https://www.arcadis.com/en/united-states/our-perspectives/global-construction-disputes-
report-2018-does-the-construction-industry-learn-from-its-mistakes/
Arditi, D., Nayak, S., & Damci, A. (2017). Effect of organizational culture on delay in
Arocho, I., Rasdorf, W., Hummer, J., & Lewis, P. (2017). Time and cost characterisation of
emissions from non-road diesel equipment for infrastructure projects. International Journal
nigeria/
Asiedu, R. O., (2015). Assessment of Cost and Time Overruns of Public Building Projects in
Asiedu, R. O., & Alfen, H. W. (2015). Assessing the frequency of factors engendering cost
overruns using frequency indices and factor analysis for public building projects in Ghana.
Journal of International Real Estate and Construction Studies ISSN, 2153, 6813.
Asiedu, R. O. &Alfen, H. W. (2016). Asiedu, R. O., & Alfen, H. W. (2016). Understanding the
underlying reasons behind time overruns of government building projects in Ghana. KSCE
166
Asiedu, R. O., Frempong, N. K., & Alfen, H. W. (2017). Predicting the likelihood of cost
24(1), 21-39.
Asiedu, R. O., (2015). Assessment of Cost and Time Overruns of Public Building Projects in
construction firms: A structural equation model approach. Architecture Research, 6(3), 68-
79.
Awuni, M. A. (2019). Risk Assessment at the Design Phase of Construction Projects in Ghana.
https://doi.org/10.5897/JPAPR2018.0425
Aziz, R., & Abdel-Hakam, A. (2016). Exploring the delay causes of road construction
Babbie E. (2008) The basics of social research [M]. Belmont, Wadsworth, CA, 2008
Babbie, E., Wagner III, W. E., & Zaino, J. (2018). Adventures in social research: Data
Baiden, B., Abdul-Razak, S., & Danku, J. (2015). The impact of project risk factors on national
Bamfo-Agyei, E., Hackman, J. K., & Nani, G. (2015). Assessment of The Public Procurement Act
167
Equbal, A., Banerjee, R., Khan, Z. R., & Dixit, R. B. (2017). Construction Disputes in
Construction Work Sites and Their Probable Solutions. International Journal of Civil
Baker, J. S., & Keiser, L. (2019). NAFTA/USMCA Dispute Settlement Mechanisms and the
Bekr, G. A. (2014). Study of the causes and magnitude of wastage of materials on construction
Basilica De La Sagrada Familia (2017). History and Architecture: Sagrada Familia, Retrieved on
Belis, J., Pronk, A., Martens, K., Van Lancker, B., & Dispersyn, J. (2015). Experimental
Bernard, H. R., & Bernard, H. R. (2013). Social research methods: Qualitative and quantitative
approaches. Sage.
Bilbo, D., Bigelow, B., Escamilla, E., & Lockwood, C. (2015). The comparison of the construction
Bowen, P., Edwards, P., & Cattell, K. (2015). Corruption in the South African construction
Brook, M. (2016). Estimating and tendering for construction work. England: Taylor & Francis.
297
168
Buys, F. (2015). Five Causes of Project Delay and Cost Overrun, and their Mitigation Measures.
Callwood, A., Cooke, D., Bolger, S., Lemanska, A., & Allan, H. (2018). The reliability and
Chai, C. S., Yusof, A. M., &Habil, H. (2015). Delay mitigation in the Malaysian housing industry:
Challender, J., & Whitaker, R. (2019). The Client Role in Successful Construction Projects.
Routledge.
Chaphalkar, N. B., Iyer, K. C., & Patil, S. K. (2015). Prediction of the outcome of construction
dispute claims using multilayer perceptron neural network model. International Journal of
Chen, G. X., Shan, M., Chan, A. P., Liu, X., & Zhao, Y. Q. (2017). Investigating the causes of
delay in grain bin construction projects: the case of China. International Journal of
Chen, Q., & Koltun, V. (2016). Full flow: Optical flow estimation by global optimisation over
regular grids. In Proceedings of the IEEE Conference on Computer Vision and Pattern
Chen, S., You, Z., Sharifi, N. P., Yao, H., & Gong, F. (2019a). Material selections in asphalt
pavement for wet-freeze climate zones: A review. Construction and Building Materials,
201, 510-525.
169
Chen, G. X., Shan, M., Chan, A. P., Liu, X., & Zhao, Y. Q. (2019b). Investigating the causes of
delay in grain bin construction projects: the case of China. International Journal of
Chen, Q., Jin, Z., Xia, B., Wu, P., & Skitmore, M. (2015). Time and cost performance of design-
Cherkaoui, K., Baptiste, P., Pellerin, R., Haït, A., & Perrier, N. (2017). Proactive tactical planning
approach for large-scale engineering and construction projects. The Journal of Modern
Chin, L. S., & Hamid, A. R. A. (2015). The practice of time management on a construction
Costantino, F., Di Gravio, G., & Nonino, F. (2015). Project selection in project portfolio
Cowlishaw, S., Cowlishaw, S., Merkouris, S., Chapman, A., & Radermacher, H. (2014).
Pathological and problem gambling in substance use treatment: A systematic review and
Creswell, J. W., & Clark, V. L. P. (2017). Designing and conducting mixed methods research.
Sage publications.
Creswell, J. W., & Creswell, J. D. (2017). Research design: Qualitative, quantitative, and mixed
Darko, E & Löwe, A (2016). Ghana’s construction sector and youth employment. Working Paper.
170
Demirkesen, S., & Ozorhon, B. (2017). Measuring Project Management Performance: Case of
Desai, N., Amin, A. A., & Zala, L. B. (2018). Mode choice analysis and its dependence of Time,
Cost, Distance and Purpose of Trip: A case study of wards in South zone of Ahmedabad
City. Building information modelling in combination with real-time location systems and
Dixit, S., & Sharma, K. (2019). Factors Influencing Construction Time Delay on High Rise
Projects in India.
Doppelt, B., & McDonough W., (2017). Sustainability, governance and organizational
Routledge.
Dosumu, O., Idoro, G., & Onukwube, H. (2017). Causes of Errors in Construction Contract
Dixit, S., & Sharma, K. (2019). Factors Influencing Construction Time Delay on High Rise
Projects in India.
Du, L., Tang, W., Liu, C., Wang, S., Wang, T., Shen, W., ... & Zhou, Y. (2016). Enhancing
171
Durdyev, S., & Ismail, S. (2016). On-site construction productivity in Malaysian infrastructure
Durdyev, S., & Mbachu, J. (2018). Key constraints to labour productivity in residential building
18(5), 385-393.
Durdyev, S., Omarov, M., & Ismail, S. (2017). Causes of delay in residential construction
El Gezery, A. S. (2018). Construction Delays and Concurrent Delays (Doctoral dissertation, The
El-Gohary, K. M., Aziz, R. F., & Abdel-Khalek, H. A. (2017). Engineering approach using ANN
to improve and predict construction labour productivity under different influences. Journal
Famiyeh, S., Amoatey, C., Adaku, E. and Agbenohevi, C. (2017). Major causes of construction
time and cost overruns. Journal of Engineering, Design and Technology, 15(2), 181-198.
https://doi.org/10.1108/JEDT-11-2015-0075
Fincham, J. E & Draugalis, J. R. (2013) The Importance of Survey Research Standards. The
from https://ncbi.nlm.nih.gov/pmc/articles/pmc3578336/
Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview.
Fraser, J., Fahlman, D. W., Arscott, J., & Guillot, I. (2018). Pilot testing for feasibility in a study
172
Gardezi, S. S. S., Manarvi, I. A., & Gardezi, S. J. S. (2014). Time extension factors in the
Gebrehiwet, T., & Luo, H. (2017). Analysis of delay impact on construction project based on
RII and correlation coefficient: Empirical study. Procedia engineering, 196, 366-374.
Gbahabo, P. T., & Ajuwon, O. S. (2017). Effects of Project Cost Overruns and Schedule Delays in
Getahun, A., Macarubbo, Y. C., & Mosisa, A. (2016). Assessment of Construction Dispute
Resolution in Ethiopian Somali Regional State Road Projects: A Case Study on Road
https://oxfordbusinessgroup.com/overview/forward-momentum-construction-sector-
continues-be-major-engine-growth
Gilbert, A., Sovacool, B. K., Johnstone, P., & Stirling, A. (2017). Cost overruns and financial risk
in the construction of nuclear power reactors: A critical appraisal. Energy Policy, 102, 644-
649.
GNA (16th April 2015). Petition from Association of Furniture and wood workers Association.
furniture-industry-stakeholders-88403-amp.html
Goulding, J. S., Pour Rahimian, F., Arif, M., & Sharp, M. D. (2015). New offsite production and
business models in construction: priorities for the future research agenda. Architectural
Gudienė, N., Banaitis, A., Podvezko, V., & Banaitienė, N. (2014). Identification and evaluation of
the critical success factors for construction projects in Lithuania: AHP approach. Journal
173
Gunduz, M., & Yahya, A. M. A. (2015). Analysis of project success factors in the construction
Gunduz, M., Nielsen, Y., & Ozdemir, M. (2013). Fuzzy assessment model to estimate the
Gurcanli, G. E., Bilir, S., & Sevim, M. (2015). Activity-based risk assessment and safety cost
estimation for residential building construction projects. Safety science, 80, 1-12.
Haddadi, A., Johansen, A., & Andersen, B. (2016). A Conceptual Framework to Enhance Value
He, W., Tang, W., Wei, Y., Duffield, C. F., & Lei, Z. (2015). Evaluation of cooperation during
project delivery: Empirical study on the hydropower industry in southwest China. Journal
Hughes, W., Champion, R., & Murdoch, J. (2015). Construction contracts: law and management.
London: Routledge.
Hwang, B. G., Zhao, X., & Toh, L. P. (2014). Risk management in small construction projects in
32(1), 116-124.
Ilhan, B., & Yobas, B. (2019). Measuring construction for social, economic and environmental
Ikediashi, D. I., Ogunlana, S. O., & Alotaibi, A. (2014). Analysis of project failure factors for
İlhan, M, Güler, N. (2017). The Number of Response Categories and the Reverse Directional Item
Problem in Likert-Type Scales: A Study with the Rasch Model, 8(3), 321-343. DOI:
10.21031/epod.321057
174
Islami, R. C., Yang, J. B., & Wibowo, A. (2015). Identifying Non-Excusable Delay Causes
for Developing Countries: An Empirical Study from Indonesia. In The 19th Symposium on
Jackson, B. J. (2020). Construction management jumpstart: the best first step toward a career in
Jia, Y., Shelhamer, E., Donahue, J., Karayev, S., Long, J., Girshick, R., ... & Darrell, T. (2014,
Johnson, J. B., Reynolds, H. T., & Mycoff, J. D. (2019). Political science research methods. Cq
Press.
Joshi, A. D., & Khandekar, S. D. (2015). Project Management for Construction Projects:
Kagiri, D., & Wainaina, G. (2017). Time and Cost Overruns in Power Projects in Kenya: A Case
Study of Kenya Electricity Generating Company Limited. ORSEA Journal, 3(2), 89-112.
Kärnä, S., & Junnonen, J. M. (2016). Benchmarking construction industry, company and project
2092-2108.Kerosuo, H., Miettinen, R., Paavola, S., Mäki, T., & Korpela, J. (2015).
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach planning
Causal Study. Engineering, Technology & Applied Science Research, 8(6), 3561-3564
175
Khan, S. N. (2014). Qualitative research method: Grounded theory. International Journal of
Khattri, T., Agarwal, S., & Gupta, V. (2016). Causes and Effects of Delay in Construction Project.
Kim, K. P., & Kang, C. W. (2018). Exploring Project Management Research Trends for Project
Kim, M. H., Lee, E. B., & Choi, H. S. (2018). Detail engineering completion rating index
schedule-cost performance for offshore oil and gas EPC projects. Sustainability, 10(7),
2469.
Kog, Y.C., (2017). Project Management and Delay Factors of Public Housing
04017028.
appropriate sample size in survey research appropriate sample size in survey research.
Komurlu, R., & Arditi, D. (2017). The Role of General Conditions relative to Claims and Disputes
Kwakye. A.N.O. (2016). Christianity in Postcolonial Ghana. The Presbyterian Church of Ghana: A
Kwakye. A.N.O. (2018). Studies in World Christianity. Returning Africa Christian in Mission to
KV, P., & Bhat, N. (2019). Analysis of causes of delay in Indian construction projects and
176
mitigation measures. Journal of Financial Management of Property and Construction,
24(1), 58-78.
Lang, M.K., (2017). Land Disputes Between the Catholic Church and Indigenes of Weh
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2015). Factors affecting schedule
delay cost overrun, and quality level in public construction projects. Journal of
Latiffi, A. A., Mohd, S., & Brahim, J. (2015). Application of Building Information Modeling
(BIM) in the Malaysian Construction Industry: A Story of the First Government Project.
InA. Editor, B. Editor (Eds.), Applied Mechanics and Materials: Vol. 773. International
Integrated Engineering Summit 2014 (pp. 943-948). Switzerland: Trans Tech Publications.
Lee, C. K., Yiu, T. W., & Cheung, S. O. (2016). Selection and use of alternative dispute resolution
Leong, T. K., Zakuan, N., Mat Saman, M. Z., Ariff, M., Md, S., & Tan, C. S. (2014). Using project
practices in the construction industry. The scientific world journal, 2014, 56-89.
Lessing, B., Thurnell, D., & Durdyev, S. (2017). Main factors causing delays in large construction
projects: Evidence from New Zealand. Journal of Management, Economics and Industrial
Lines, B. C., Sullivan, K. T., Smithwick, J. B., & Mischung, J. (2015). Overcoming resistance to
177
Li, L., Li, Z., Li, X., & Wu, G. (2019). A review of global lean construction during the past two
Management.
Lu, W., Zhang, L., & Pan, J. (2015). Identification and analyses of hidden transaction costs in
Manley, K., & Chen, L. (2016). The impact of client characteristics on the time and cost
Marzouk, M. M., & El-Rasas, T. I. (2014). Analysing delay causes in Egyptian construction
Mayer, I. (2015). Qualitative research with a focus on qualitative data analysis. International
McCord, J., McCord, M., Davis, P. T., Haran, M., & Rodgers, W. J. (2015). Understanding delays
Memon, A. H., Rahman, I. A., & Jamil, M. H. A. (2014). The severity of Variation Order Factors
Mireku, K. O., Kuusaana, E. D., & Kidido, J. K. (2016). Legal implications of allocation
papers in land transactions in Ghana—A case study of the Kumasi traditional area. Land
178
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
Mittal, Y. K., & Paul, V. K. (2018). Identification of critical factors for delay in metro rail projects
30-39.
Mohammad, N., Ani, A. I. C., & Rakmat, R. A. O. (2017). Causes and effects of variation orders
in the construction of terrace housing projects: A case study in the State of Selangor,
Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega
Monghasemi, S., Nikoo, M. R., Fasaee, M. A. K., & Adamowski, J. (2015). A novel multi-criteria
Mugenda, O. M., & Mugenda, A. G. AG (2008) Research Methods: Quantitative and Qualitative
Muhwezi, L., Acai, J., & Otim, G. (2014). An assessment of the factors causing delays in building
Work: Case of Oromia Technical, Vocational, Education, and Training Bureau (Doctoral
179
Murwira, D., & Bekker, M. (2017). Building an infrastructure project performance in the North-
West Province Department of Public Works and Roads. Acta Structilia, 24(2), 128-145.
Najib, A. F., Soon, N. K., Zainal, R., Ahmad, A. R., & Hasaballah, A. H. A. (2018). Influential
Springer, Singapore.
Naoum, S. G., & Egbu, C. (2016). Modern selection criteria for procurement methods in
Naoum, S. G., Herrero, C., Egbu, C., & Fong, D. (2018). An integrated model for the stressors,
Ngacho, C., & Das, D. (2014). A performance evaluation framework of development projects: An
Niazi, G. A., & Painting, N. (2017). Significant factors causing cost overruns in the construction
NSW, Training Services (2016). Vocational Education and Training - NSW Apprenticeships and
Traineeships. http://training.nsw.gov.au/vet
Nyoni, T., & Bonga, W. G. (2017). Towards factors affecting delays in construction projects: A
case of Zimbabwe. Dynamic Research Journals' Journal of Economics and Finance (DRJ-
180
Obeidat, M. A. Q., & Aldulaimi, S. H. (2016). The role of project management information
systems towards the project performance the case of construction projects in the United
Ogunde, A., Olaolu, O., Afolabi, A. O., Owolabi, J., & Ojelabi, R. A. (2017). Challenges
Ojoko, E. O., Tanko, B. L., Jibrin, M., Ojoko, O., & Enegbuma, W. L. (2016). Project Delay
Causes and Effects in the Construction Industry. In IGCESH. Proceedings of the 6th
223.
Olawale, Y., & Sun, M. (2015). Construction project control in the UK: Current practice, existing
Olusanya, O. A. (2018). Subcontracting Systems and Social Protection in the Informal Building
Osei-Kyei, R., & Chan, A. P. (2015). Review of studies on the Critical Success Factors for Public-
Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project
design firms through addressing gap of the workforce skills in developing countries: a
181
Owolabi, J. D., Amusan, L. M., Oloke, C. O., Olusanya, O., Tunji-Olayeni, P. F., Dele, O., ... &
Owusu-Manu, D., Edwards, D. J., Pärn, E. A., Asiedu, R. O., & Aboagye, A. (2018).
Pall, G. K., Bridge, A. J., Skitmore, M., & Gray, J. (2016). A comprehensive review of delays in
power transmission projects. IET Generation, Transmission & Distribution, 10(14), 3393-
3404.
Panda, S. (2017). A case on Integrated Time and Cost Monitoring of Construction Projects. PCG
Report (2018). 188th Anniversary Report. Official website of the Presbyterian Church of
Pharne, M. P., & Kande, G. N. (2016). Application of Benchmarking Method in the Construction
Prakash, K., & Nandhini, N. (2015). Evaluation of Factors Affecting Construction Project
Prasad, K. V., Vasugi, V., Venkatesan, R., & Bhat, N. S. (2019). Critical causes of time overrun in
Presbyterian Church of Ghana. (2016). Constitution. Waterville publishing house, Accra, Ghana
(pp. 161-166).
Purnus, A., & Bodea, C. N. (2014). Correlation between time and cost in a quantitative risk
Quinlan, C., Babin, B., Carr, J., & Griffin, M. (2019). Business research methods. South
182
Western Cengage.
Rachid, Z., Toufik, B., & Mohammed, B. (2018). Causes of schedule delays in construction
Rahman, M. D., Lee, Y. D., & Ha, D. K. (2014). Investigating main causes for schedule delay in
Ramanathan, C., Narayanan, S. P., & Idrus, A. B. (2012). Construction delays causing risks
on time and cost-a critical review. Construction Economics and Building, 12(1), 37-57.
Rao, B. P., Shekar, S. C., Jaiswal, N., Jain, A., & Saxena, A. D. (2016). Delay Analysis of
Reh, F.J. (2018). Basic Project Management 101: What Is Project Management? Project
101-2275338
Rubin, A., & Babbie, E. R. (2016). Empowerment series: Research methods for social work.
Cengage Learning.
Rugenyi, F. (2015). Assessment of the Triple Constraints in Projects in Nairobi: The Project
Samarghandi, H., Tabatabaei, S. M. M., Taabayan, P., Mirhashemi, A., & Willoughby, K. (2016).
Studying the reasons for delay and cost overrun in construction projects: The case of Iran.
Sambasivan, M., Deepak, T. J., Salim, A. N., & Ponniah, V. (2017). Analysis of delays in the
183
equation modelling (SEM) approach. Engineering, Construction and Architectural
San Cristóbal, J. R. (2015). The use of Game Theory to solve conflicts in the project management
Management, 3, 43-58.
Safo-Kantanka, O. Y., Aigbavboa, C. O., & Arthur-Aidoo, B. M. (2018, July). Constraints to the
Springer, Cham.
Schwing, A. G., & Urtasun, R. (2015). Fully connected deep structured networks. arXiv preprint
arXiv:1503.02351.
Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., & Segner, R. O. (2015). Construction
Senouci, A., Ismail, A. A., & Eldin, N. (2016). Time and Cost Overrun in Public Construction
Senouci, A., Ismail, A., & Eldin, N. (2016). Time delay and cost overrun in Qatari public
Serpella, A. F., Ferrada, X., Howard, R., & Rubio, L. (2014). Risk management in construction
653-662.
Sha, M. K., Shahi, P. B., Pandit, R., & Pandey, A. (2017). Causes and Effects of Delays in
Sha'ar, K. Z., Assaf, S. A., Bambang, T., Babsail, M., & Fattah, A. A. E. (2017). Design–
184
Shehu, Z., Endut, I. R., & Akintoye, A. (2014a). Factors contributing to project time and hence
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014b). Cost overrun in the Malaysian
Shen, Y., Tuuli, M. M., Xia, B., Koh, T. Y., & Rowlinson, S. (2015). Toward a model for forming
Sinesilassie, E. G., Tabish, S. Z. S., & Jha, K. N. (2017). Critical factors affecting schedule
Skaggs, R. W., & Chescheir III, G. M. (2003). Effects of subsurface drain depth on nitrogen
Skarlicki, D. P., O’Reilly, J., & Kulik, C. T. (2015). The third-party perspective of (In)justice. In
Editors (Eds.), The Oxford handbook of justice in the workplace (pp. 235-239). London:
Oxford Publishers.
Smith, P., Beale, R., & Bowers, P. (2017). The Planning Guide to Piping Design. Texas: Gulf
Professional Publishing.
Sohu, S., Memon, N. A., Abbasi, S. A., Pahore, M. A., & Ullah, K. (2016, December). Causes of
Soomro, F. A., Memon, M. J., Chandio, A. F., Sohu, S., & Soomro, R. (2019). Causes of time
185
Sutar, A. A., & Mehendale, A. P. (2017). Overview Of Human Resource Management
Tang, Y., Mason, R. J., & Wang, Y. (2015). Governments’ functions in the process of integrated
Taniguchi, A., & Onosato, M. (2018). Effect of Continuous Improvement on the Reporting
15.
Tarhini, A., Fakih, M., Arzoky, M., & Tarhini, T. (2015). Designing guidelines to discover the
Tedla, Y., & Patel, D. (2018). Improving Effective Material Management by Identifying common
Thirty, M. (2013). The future of project management in a digital economy. Paper presented at PMI
Global Congress 2013 - North America, New Orleans, LA. Newtown Square, PA: Project
Management Institute.
Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D. (2015).
Tong, A., Tong, A., Palmer, S. C. Craig, J. C., Craig, J. C.; Strippoli, G. F.M. (2016). A guide to
186
Vance, D. E., Talley, M., Azuero, A., Pearce, P. F., & Christian, B. J. (2013). Conducting an
article critique for a quantitative research study: Perspectives for doctoral students and
Van Mol, C. (2017). Improving web survey efficiency: the impact of an extra reminder and
Vaccaro, I. G., Jansen, J. J., Van Den Bosch, F. A., & Volberda, H. W. (2012). Management
Vasilyeva-Lyulina, A., Onishi, M., & Kobayashi, K. (2015). Delay analysis methods for
Volberda, H. W., Van Den Bosch, F. A., & Heij, C. V. (2013). Management innovation:
Management as fertile ground for innovation. European Management Review, 10(1), 1-15.
Walker, A. (2015). Project management in construction. New York: John Wiley & Sons.
Wang, J., Li, Z. & Tam, V.W., (2014). Critical factors in effective construction waste
minimisation at the design stage: a Shenzhen case study, China. Resources, Conservation
Watkins, M. W. (2018). Exploratory factor analysis: A guide to best practice. Journal of Black
University Press.
187
Wimala, M., Akmalah, E., & Sururi, M. R. (2016). Breaking through the Barriers to Green
Wu, Z., Ann, T. W., & Shen, L. (2017). Investigating the determinants of contractor’s construction
and demolition waste management behaviour in Mainland China. Waste Management, 60,
290-300.
Xiong, B., Skitmore, M., Xia, B., Masrom, M. A., Ye, K., & Bridge, A. (2014). Examining the
Yousefi, V., Yakhchali, S. H., Khanzadi, M., Mehrabanfar, E., & Šaparauskas, J. (2016).
Proposing a neural network model to predict time and cost claims in construction projects.
Zailani, S., Ariffin, H. A. M., Iranmanesh, M., Moeinzadeh, S., & Iranmanesh, M. (2016). The
moderating effect of project risk mitigation strategies on the relationship between delay
factors and construction project performance. Journal of Science and Technology Policy
Zhang, S., Sulankivi, K., Kiviniemi, M., Romo, I., Eastman, C. M., & Teizer, J. (2015). BIM-
based fall hazard identification and prevention in construction safety planning. Safety
Zhang, Q., & Yangb, S. (2019). Research on Problems and Strategies in Quality Management of
188
Zheng, S., Jayasumana, S., Romera-Paredes, B., Vineet, V., Su, Z., Du, D., ... & Torr, P. H.
Zheng, X., Le, Y., Chan, A. P., Hu, Y., & Li, Y. (2016). Review of the application of social
Zidane, Y. J., & Andersen, B. (2018a). Causes of Delay and their Cures in Major Norwegian
Zidane, Y. J. T., & Andersen, B. (2018b). The top 10 universal delay factors in construction
Zohrabi, M. (2013). Mixed Method Research: Instruments, Validity, Reliability and Reporting
Zohar, D., & Polachek, T. (2014). Discourse-based intervention for modifying supervisory
Žujo, V., Car-Pušić, D., Žileska-Pancovska, V., & Ćećez, M. (2015). Time and cost
189
Appendices
Appendix A
Questionnaire
Ethical Consideration
Please be informed that the individual responses to this study are strictly protected and
confidential. This study will not disclose the identity of the respondents. The survey questionnaire
should take about 5 to 10 minutes to complete. Please note that you are not under any compulsion
to participate in this research, and you are unrestricted to pull out at any stage without prejudice.
The research guarantees confidentiality and will ensure there is no access to your data, and the
questionnaire does not reveal who is filling out. Information will be stored only aggregate data on
a computer, and all surveys notes, and data will be kept with high security.
190
What is your age? *
▪ Below 20
▪ 21-30
▪ 31-40
▪ 41-50
▪ 51 and Above
What is your profession or role? *
▪ Church Pastor/Agent
▪ Manager
▪ Consultant
▪ Site superintendent (Foreman)
▪ Project/Construction Manager
▪ Electrician
▪ Carpenter
▪ Mason
▪ Supplier
▪ Other
What is your highest level of education? *
▪ High School
▪ College
▪ University
▪ Other
How many years of experience do you have in your profession or role? *
▪ Almost a year
▪ 5 years
▪ 6- 10 years
▪ 11-15 years
▪ 16 Years and Above
191
Client-Owner Related Factors
Contractor-Related Factors *
192
Consultant-Related Factors *
Managerial Dispute *
Financial mishandling
Litigation
193
Material-Related Factors *
Wastage of materials
Project-Related Factors *
194
Church Organizational Structure *
External-Related Factors *
Rating range: Strongly Disagree-1 Disagree-2 Neutral-3 Agree-4 Strongly Agree-5
195
Base on your experience in construction projects, to what extent do you agree or disagree
delays
196
Appendix B
List of Agents-in-charge
Table C1
Mampong 3 7 10
Mile 50 5 11 16
Nankese 2 25 27
Nsawam 4 11 15
Nsukwao 6 8 14
Suhum 4 15 19
Suhum New Town 3 20 23
Suhum Oforikrom 4 14 18
Tutu 2 6 8
Note. The list includes Minsters and Catechists who are leading church construction projects in the
197
Appendix C
Table D1
198
199
200