Académique Documents
Professionnel Documents
Culture Documents
NATIONAL HIGHWAY AUTHORITY
MINISTRY OF COMMUNICATIONS
GOVERNMENT OF PAKISTAN
JAN 2017
Peshawar - Karachi Motorway
Section II Sukkur - Multan
August 2018
FRED ENGINEERING
Roma | Almerìa | Casablanca | www.fredeng.eu
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Table of Contents
1 Introduction ................................................................................................................... 2
2 Background information ................................................................................................ 3
3 Items resulting from this Stage 1 Audit .......................................................................... 5
3.1 General ................................................................................................................... 5
3.2 The junctions .......................................................................................................... 9
3.3 Signing and markings ........................................................................................... 11
4 Audit Team Statement ................................................................................................. 14
APPENDIX 1 - List of drawings examined........................................................................... 15
APPENDIX 2 – Road Safety Audit feedback form ............................................................... 16
FRED ENGINEERING 1
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
1 Introduction
This report describes a Stage 11 Road Safety Audit carried out on the Feasibility study and
preliminary design of the Section II Sukkur - Multan of the Karachi – Multan - Lahore
Motorway, in Pakistan. The audit was carried out during May - June 2018.
The Audit Team members were as follows:
¡ Edoardo Mazzia, certified Road Safety Auditor approved according to Dir.
2008/96/EC, Team Leader, FRED Engineering S.r.l.
¡ Dr Kamran Ahmed, Team Member, FRED Engineering S.r.l.
The following NHA engineers also participated in the audit as Observers:
¡ Muhammad Hasan Khalil, NHA
¡ Zaier Abbas Zaidi, NHA
The audit comprised of a review of the preliminary design drawings provided by the design
office.
No Road Safety Audits were carried out before.
This Stage 2 audit has been carried out in accordance with international recognized
practices, with particular reference to the CAREC RSA Manual2. The team has examined
only those issues within the preliminary design related to the road safety implications of the
scheme and has therefore not examined or verified the compliance of the design to any
other criteria.
Appendix 1 describes the drawings examined by the Audit Team.
All of the issues highlighted in this report are considered by the Audit Team to require
action during the detail design stage in order to improve the safety of the roadway section
and minimise collision occurrence.
A feedback form containing both the Designer/Contractor’s response to this Audit and the
Auditor’s feedback is reported in the Appendix 2.
1
In accordance with current international practice (e.g. UK HD 19/15), Stage 1 generally refers to the
Preliminary Design Stage. However, it should be noted that according to some practices (e.g.
CAREC RSA Manual 2018) the same audit can be referred to as Stage 2, Stage 1 being the one
referred to the feasibility study.
2
CAREC Road Safety Engineering Manual 1 – Road Safety Audit (March 2018)
FRED ENGINEERING 2
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
2 Background information
The scope of this audit covers the Section II Sukkur – Multan of the Karachi – Lahore
Motorway (KLM), from km 391+800 to km 739+200 (about 347 km).
The Karachi - Lahore motorway is a controlled-access dual carriageway that is part of the
trade corridor linking ports of Karachi and Gwadar with China and Asian States. The
general alignment runs parallel to the National Highway N-5, which carries about 65%
traffic of Pakistan. The KLM can be divided into three sections: Hyderabad – Sukkur
Section, Sukkur – Multan Section and Multan – Lahore Section.
The project is implemented according to a Design-build system. The Contractor and design
consultant is a Joint Venture leaded by China State Construction Engineering Cooperation
Ltd (CSCEC).
No departures from standards have been notified to the Audit Team.
A proposed alignment of Sukkur Multan Motorway is shown in Figure 1 below.
The project is located in the province of Punjab and Sindh. It starts at approximately 2.3 km
to the south of National Highway N-5 in the city of Rohri and ends near Multan in the area
of Shujaabad. The proposed alignment mostly moves parallel to the National Highway N-5.
FRED ENGINEERING 3
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
The alignment has been designed according to AASHTO standards with a design speed of
120 km/h. The typical cross-section consists of two-way divided carriageways, having three
lanes on each direction (lane width is 3.65 m). Hard shoulders are also provided on both
sides: the outer shoulder is 3.0 m wide, while the inner one is 1.0 m wide (see Figure 2
below).
FRED ENGINEERING 4
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Anchorage method, profile and size of the design barrier suggest that there may be
a real risk that they will be not coherent with the safety level required for the type of
road and traffic in subject. An errant vehicle could be thus not properly protected.
FRED ENGINEERING 5
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Recommendation
It is recommended to install pre-cast New-
Jersey barriers shown in Figure 5, having a
containment level appropriate to the design
speed and the expected traffic (volume and
mix). In particular, it is recommended to
install barriers tested according to
internationally recognized standards (e.g.
EN 1317, MASH, etc.)3.
3.1.2 Problem
Location: general
Summary: roadside barrier could not properly restrain errant vehicles
Risk: high
The design does not provide information about the containment classes of safety
barriers. Roadside guardrails could be inappropriate to contain an errant heavy
vehicle.
There is the risk that they will be not coherent with the safety level required for the
type of road and traffic in subject. An errant vehicle could be thus not properly
protected.
Recommendation
It is recommended to install safety barriers having a containment level appropriate to
the design speed and the expected traffic (volume and mix). In particular, it is
recommended to install barriers tested according to internationally recognized
standards (e.g. EN 1317, MASH, etc.)4.
3.1.3 Problem
Location: general
Summary: steep gradient of fill slopes
Risk: very high
Gradient of fill slopes is 1:1.5. These embankments result in a high risk of vehicle
rollover and significant consequential injury if a vehicle should veer off the
carriageway.
According to the design if slope height is less than 2 m, no guardrail shall be set.
3
As an indication, the containment class should be at least H2 according to EN 1317 standards (but
other comparable standards can be considered)
4
As an indication, the containment class should be at least H1 according to EN 1317 standards (but
other comparable standards can be considered)
FRED ENGINEERING 6
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Recommendation
It is recommended to provide 1:3 or less steep fill slopes. In alternative it is
recommended to protect with a guardrail slopes higher than 1 m.
3.1.4 Problem
Location: general
Summary: gaps in the median are hazardous for errant vehicles
Risk: very high
Barrier emergency openings are provided on the median along the motorway. The
scope is to permit closing of a carriageway and the utilization of the other as a two-
way carriageway while maintenance work is performed on the closed one, as well as
to permit service and assistance vehicles to effect “U” turns so as to intervene more
quickly in emergencies.
Although the design report suggests closing these openings with removable
barriers, in the drawings they appear closed with a fence.
Any interruption on the continuity of the median barrier is a hazard for errant
vehicles.
Recommendation
It is recommended to close down the opening with removable barriers (see an
example on Figure 7 below).
FRED ENGINEERING 7
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
3.1.5 Problem
Location: Rahim Yar Khan toll plaza (km 525+530)
Summary: toll islands are not sufficiently protected
Risk: high
All toll plazas are proposed on the entry and exit ramps at each interchange, except
Rahim Yar Khan Toll Plaza which is proposed on the mainline at km 525+5305.
This rarity may surprise the drivers which could have a not adequate speed. The
possible crash with the nose of the toll island may lead to very serious
consequences.
Recommendation
It is recommended to install impact attenuators (crash
cushion) at noses of toll islands.
The attenuators should comply with internationally
recognised standards (e.g. European standard EN
1317-3)6.
5
Other mainline toll plazas are envisaged in adjacent sections
6
As an indication, the containment class should be at least 50 according to EN 1317-3 standards
(but other comparable standards can be considered)
FRED ENGINEERING 8
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Junction of Local
roads with Slip road
Moreover, these local roads often pass through small settlements before joining the
national highway. Higher traffic flow (especially heavy vehicles) accessing motorway
is expected on these local roads. The current geometric and road environment at
these local roads may constitute a serious danger, especially for vulnerable road
users, i.e. pedestrians, two-wheelers, etc..
Recommendation
It is recommended to adopt a layout for the junctions which ensures safe and
smooth traffic flow. Figure below shows the suggested layout for junctions.
It is also suggested that local roads leading to the national highway be rehabilitated,
so as to allow the safe flow of expected traffic.
FRED ENGINEERING 9
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
3.2.2 Problem
Location: all interchanges, service and rest areas
Summary: layout of exit ramps may be not adequate to safely diverge the traffic
streams
Risk: low
Exit ramps at interchanges and service/rest areas diverge from the mainline (without
a parallel auxiliary lane). The diverging area is just limited to the taper (length is not
provided).
Vehicles are forced to slow down on the traffic lane, thus obstructing other vehicles.
This configuration increase probability of rear end crashes occurrence.
Insufficient Length of
Decelerating Land and Taper
Recommendation
It is recommended to design a manoeuvring section, which is at least a 150 m long
taper adjacent to the motorway with appropriate decelerating lane.
FRED ENGINEERING 10
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Recommendation
Edge lines at least 15 cm in width are recommended.
3.3.2 Problem
Location: general
Summary: length of solid lines of lane lines is too short
Risk: medium
Lane lines are broken lines where the gap is 12 m and the solid line is 4 m long. The
length of the solid line seems to be too short to be appreciated effectively at the
speed of the motorway
There is a risk that vehicles may lose their trajectory and conflict with other vehicles
on adjacent lanes.
Recommendation
It is recommended that the solid line is at least 6 m long7.
3.3.3 Problem
Location: all ramps at interchanges
Summary: vehicles may enter into the motorway in the wrong direction
Risk: high
The loops of the cloverleaves are undivided 2-way roads until the nose where the
slip roads (exit and entry ramps) diverge. The Figure below shows the Rohri and
Ghotki interchanges signage layout.
At the nose no sign is provided to inform the direction about right direction.
Inattentive drivers may take the exit ramp in the wrong direction thus posing a
serious risk of head on crashes along the motorway.
7
Usually the gap is twice that of the line segments
FRED ENGINEERING 11
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Rohri Interchange
Layout
Ghotki Interchange
Layout
Figure 13 – Rohri and Ghotki interchanges sign layout
Recommendation
It is recommended to install the following signs:
¡ ‘Keep left’ (arrow) sign, showing the right direction to take
¡ 2 ‘No entry’ signs (on both roadsides), preventing the wrong direction being
taken
In order to reinforce the separation of flows, it is also advisable to install plastic
marker posts along the centreline.
FRED ENGINEERING 12
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
FRED ENGINEERING 13
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
FRED ENGINEERING 14
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
FRED ENGINEERING 15
Peshawar – Karachi motorway | Section II Sukkur - Multan Stage 1 RSA
Alternative
Recommended measures or
Problem Describe alternative measures. Give
Items resulting from Recommendation by the measure reasons
Ref. accepted reasons for not accepting
Stage 1 Audit Auditor accepted accepted by
[yes/no] recommended measure.
[yes/no] the Auditor
[yes/no]
Median barrier could It is recommended to (i) The current profile of New Jersey
not properly restrain install barriers tested according barriers is provided for all motorway in
errant vehicles to the country.
internationally recognized (ii) If yes, vehicle wouldn’t hit the barriers
3.1.1 standards (e.g. NO NO at 90°but laterally. The currently YES
EN 1317, MASH, etc.) 4 . designed barriers profile can also move
the impacting wheel and send it back
towards roadway to meet the TL-4
containment class.
Roadside barrier could It is recommended to install (i) The current W-beam guardrails are
not properly restrain barriers tested according to provided for all motorway in the country
3.1.2 errant vehicles internationally recognized NO NO and work well in practices. NO
standards (e.g. EN 1317, (ii) The current design meets the Contract
MASH, etc.) documents.
FRED ENGINEERING 16
APPENDIX 2- Road Safety Audit Feedback Form
Scheme: Peshawar-Karachi motorway | Section II Sukkur - Multan
Audit stage: 1 initial design
Alternative
Recommende measures or
Problems
Items resulting from d measure Describe alternative measures. Give reasons for not accepting recommended reasons
Recommendation by the Auditor accepted
Stage 2 Audit accepted measure. Only complete if recommended measure is not accepted. accepted by
Yes/No
Yes/NO the Auditor
(Yes/no)
(i) The current profile of New Jersey barriers are provided for all motorway in the
it is recommended to
median barrier could not country.
install barriers tested according to
3.1.1 properly restrain errant NO NO (ii)If yes, vehicle wouldn't hit the barriers at 90°but laterally. The currently designed YES
internationally recognized standards (e.g.
vehicles barriers profile can also move the impacting wheel and send it back towards
EN 1317, MASH, etc.) 4 .
roadway to meet the TL-4 containment class.
roadside barrier could not It is recommended to install barriers tested i The current W-beam guardrails are provided for all motorway in the country
3.1.2 properly restrain errant according to internationally recognized NO NO and work well in practices. YES
vehicles standards (e.g. EN 1317, MASH, etc.) ii The current design meets the Contract documents.
August 2018
FRED ENGINEERING
Roma | Almerìa | Casablanca | www.fredeng.eu
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
Table of Contents
1 Introduction ................................................................................................................... 2
2 Background information ................................................................................................ 3
3 Items resulting from the Stage 1 Audit ........................................................................... 5
4 Items resulting from this Stage 2 Audit .......................................................................... 6
4.1 General ................................................................................................................... 6
4.2 The junctions ........................................................................................................ 11
4.3 Signing and markings ........................................................................................... 19
5 Audit Team Statement ................................................................................................. 21
APPENDIX 1 - List of drawings examined........................................................................... 22
APPENDIX 2 – Road Safety Audit feedback form ............................................................... 23
ANNEX 1 – Photos of the site visit ...................................................................................... 29
FRED ENGINEERING 1
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
1 Introduction
This report describes a Stage 21 Road Safety Audit carried out on the detailed design of
the Section II Sukkur - Multan of the Peshawar – Karachi Motorway (PKM), in Pakistan. The
audit was carried out during May - June 2018.
The Audit Team members were as follows:
¡ Edoardo Mazzia, certified Road Safety Auditor approved according to Dir. 2008/96/EC,
Team Leader, FRED Engineering S.r.l.
¡ Dr Kamran Ahmed, Team Member, FRED Engineering S.r.l.
The following NHA engineers also participated in the audit as Observers:
¡ Muhammad Hasan Khalil, NHA
¡ Zaier Abbas Zaidi, NHA
The audit comprised of a review of the drawings relating to the scheme supplied by the
design office and a visit to the site by the team on 12 - 14 May 2018. Weather conditions
during the site visit were sunny.
Also present during the site visit were:
¡ Li Xiang, Manager Design CSCEC
¡ Usman Riaz, CSCEC consultant
At the moment of visit, the construction works were already in an advanced stage. This
audit, even if it refers to the design stage, therefore contains references to items already in
place.
The Audit Team had previously done a Stage 1 RSA of this scheme in June 2018.
This Stage 2 audit has been carried out in accordance with international recognized
practices, with particular reference to the CAREC RSA Manual2. The team has examined
only those issues within the design related to the road safety implications of the scheme,
and has therefore not examined or verified the compliance of the design to any other
criteria.
Appendix 1 describes the drawings examined by the Audit Team.
All of the issues highlighted in this report are considered by the Audit Team to require
action in order to improve the safety of the roadway section and minimise collision
occurrence.
A feedback form containing both the Designer/Contractor’s response to this Audit and the
Auditor’s feedback is reported in the Appendix 2.
1
In accordance with current international practice (e.g. UK HD 19/15), Stage 2 generally refers to the
Detailed Design Stage. However, it should be noted that according to some practices (e.g. CAREC
RSA Manual 2018) the same audit can be referred to as Stage 3, Stage 1 being the one referred to
the feasibility study.
2
CAREC Road Safety Engineering Manual 1 – Road Safety Audit (March 2018)
FRED ENGINEERING 2
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
2 Background information
The scope of this audit covers the Section II Sukkur – Multan of the Peshawar – Karachi
Motorway (PKM), from km 380+000 to km 772+018 (about 392 km).
PKM is a north-south skeleton motorway of Pakistan. Starting from Peshawar in the north,
it connects Islamabad, Multan, Sukkur and Hyderabad and ends at Karachi. Sukkur -
Multan Section, which is the longest section of PKM, is located in Sindh and Punjab
province which are the most affluent and densely populated regions of Pakistan.
According to the designer the construction of PKM will improve the road network of
Pakistan significantly, enhance the communication and provide connection between the
major cities of Pakistan. Moreover PKM will drive the economic development of the small
and medium-sized cities along the motorway, ease the traffic burden on the national
highways (N-55 and N-5) and improve overall traffic capacity of the north-south roads.
The project is implemented according to a Design-build system. The Contractor and design
consultant is a Joint Venture leaded by China State Construction Engineering Cooperation
Ltd (CSCEC).
The project is divided in seven sub-sections. No departures from standards have been
notified to the Audit Team.
The proposed alignment and sub-sections are shown in Figure 1 below.
The alignment has been designed according to AASHTO standards with a design speed of
120 km/h. The technical criteria adopted are as follows:
¡ Design speed: 120 km/h
¡ Width of standard cross section: 31.5 m
¡ Number of lanes: 6
¡ Width of lanes: 3.65 m
FRED ENGINEERING 3
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
FRED ENGINEERING 4
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
3.1.1 4.1.1
3.1.2 4.1.2
3.1.4 4.1.4
3.2.2 4.2.1
3.3.3 4.3.1
All other issues raised in the Stage 1 Road Safety Audit have been resolved, namely:
¡ Gradient of fill slopes is 1:3 (1:4 in the triangle zone adjacent to interchange ramps)
¡ Edge lines are 15 cm wide
¡ Solid lines of broken lines are 6 m long
FRED ENGINEERING 5
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
FRED ENGINEERING 6
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
Recommendation
It is recommended to install pre-cast New-
Jersey barriers shown in Figure 5, having a
containment level appropriate to the design
speed and the expected traffic (volume and
mix). In particular, it is recommended to Figure 5 – Example of a pre-cast New-Jersey
install barriers tested according to barrier tested with the standard EN 1317,
approved in class H2
internationally recognized standards (e.g.
EN 1317, MASH, etc.)3.
4.1.2 Problem
Location: general
Summary: roadside barrier could not properly restrain errant vehicles
Risk: high
The design does not provide information about the containment classes of safety
barriers. Roadside guardrails appear to be inappropriate to contain an errant heavy
vehicle.
There is the risk that they will not be coherent with the safety level required for the
type of road and traffic in subject. An errant vehicle could be thus not properly
protected.
Recommendation
It is recommended to install safety barriers having a containment level appropriate to
the design speed and the expected traffic (volume and mix). In particular, it is
recommended to install barriers tested according to internationally recognized
standards (e.g. EN 1317, MASH, etc.)4.
3
As an indication, the containment class should be at least H2 according to EN 1317 standards (but
other comparable standards can be considered)
4
As an indication, the containment class should be at least H1 according to EN 1317 standards (but
other comparable standards can be considered)
FRED ENGINEERING 7
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
4.1.3 Problem
Location: general
Summary: distance between safety barriers and lighting poles may be not sufficient
to protect errant vehicles
Risk: high
According to the design, at interchanges, lighting poles are installed right at the
edge of the carriageway, in a position where it is likely that they will be very close to
the guardrails.
This kind of barriers, in case of crash, bends absorbing part of the energy. There
must be adequate space for this dynamic deflection behind the safety barrier. If an
obstacle is present in this space, it is a hazard for errant vehicles and there is the
risk that they are not properly protected.
Recommendation
It is recommended to install the lighting poles outside the working width of the
guardrail (see Figure 7 below).
FRED ENGINEERING 8
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
4.1.4 Problem
Location: general
Summary: gaps in the median are hazardous for errant vehicles
Risk: very high
Barrier emergency openings are provided on the median along the motorway. The
scope is to permit closing of a carriageway and the utilization of the other as a two-
way carriageway while maintenance work is performed on the closed one, as well as
to permit service and assistance vehicles to effect “U” turns so as to intervene more
quickly in emergencies.
Although the design report suggests closing these openings with removable
barriers, in the drawings they appear closed with posts connected by a simple
chain.
Any interruption on the continuity of the median barrier is a hazard for errant
vehicles.
Recommendation
It is recommended to close down the opening with removable barriers (see an
example on Figure 9 below).
FRED ENGINEERING 9
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
4.1.5 Problem
Location: general
Summary: pillars in the median barrier are hazardous for errant vehicles
Risk: high
The width of the base of the central pillars of the gantries is 600 mm which is exactly
the width at the base of the median barrier. The pillar is 356 mm wide, which means
that it protrudes 103 mm on either side of the top of the barrier. Figure below shows
the base of under construction pillar.
These types of pillars are therefore dangerous unprotected hazards for errant
vehicles due to its size.
Figure 10 – Front view of the pillar base (left) and base under construction (right)
FRED ENGINEERING 10
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
Recommendation
It is recommended (i) to install gantries without central pillar, (ii) to widen the median
in order to host it without dangerous protrusion or (iii) to design a different pillar
consistent with the dimension of the barrier.
4.1.6 Problem
Location: general
Summary: diverging points are not adequately protected
Risk: high
Diverging points can represent serious dangers if not
adequately equipped. The drawings show an anti-
collision barrel that is supposed to be used to protect
these points. Their effectiveness is, however, limited
and do not protect properly vehicle occupants in the
event of an impact with an obstacle (e.g. in the
presence of a guardrail).
Recommendation
It is recommended to install impact attenuators (crash
cushion) at diverging points (interchanges, rest/service
areas) when there are dangerous obstacles to protect
(in this case, the barrier itself is a dangerous obstacle).
The attenuators should comply with internationally
recognised standards (e.g. European standard EN Figure 11 – Impact attenuator
1317-3)5.
5
As an indication, the containment class should be at least 80 according to EN 1317-3 standards
(but other comparable standards can be considered)
FRED ENGINEERING 11
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
Recommendation
It is recommended to design a manoeuvring section, which is at least a 150 m long
taper adjacent to the motorway.
4.2.2 Problem
Location: all interchanges; all service and rest areas
Summary: layout of entry ramps may be not adequate to safely merge the traffic
streams
Risk: medium
Merging of vehicles entering into the motorway with those travelling on the main
roadway is regulated by a taper approximately 175 m long. No parallel auxiliary
lanes are provided.
This configuration increase probability of lateral crashes occurrence, especially in
the presence of heavy traffic, because vehicles may not have enough space and
time to merge safely into the main traffic stream.
Recommendation
It is recommended to design a manoeuvring section, parallel to the main
carriageway, which is at least a 300 m long including the taper. This section shall
allow entering vehicles to attain the operating speed of the outer motorway traffic
lane and to merge into the flow in safety.
FRED ENGINEERING 12
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
4.2.3 Problem
Location: Rorhi interchange (km 386+127)
Summary: the junction where the motorway is connected does not have the
characteristics to ensure safe traffic flow
Risk: very high
This interchange will be the access point to the motorway for several years until the
route is completed southwards. During this period, the volume of traffic at the
intersection of the access road at the interchange and the N-5 road will be very high
and the current layout does not appear to guarantee adequate levels of safety.
Numerous conflicts will be present, and crashes will therefore be possible.
Recommendation
It is recommended to redesign the intersection with the N-5 road, giving priority to
turns to and from the motorway.
FRED ENGINEERING 13
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
4.2.4 Problem
Location: Pano Aqil interchange (km 413+978)
Summary: the road where the motorway is connected does not have the
characteristics to ensure safe traffic flow
Risk: high
The interchange connects to the N-5 highway via a small road with a very narrow
section. The project involves the rehabilitation of only the initial section, up to a small
bridge over a canal (here the width is only 4 m) that is not clear whether it is subject
to an intervention of rehabilitation or not.
The road section does not allow the simultaneous passage of two trucks and there
is a risk that crashes, including head-on collisions, may occur.
In addition, the right turns on the N-5 road are currently indirect, adjusted with U-
turns. The current configuration does not seem adequate for the expected traffic
volumes. Numerous dangerous conflicts will be possible, which may lead to
crashes.
Recommendation
Rehabilitation of the entire stretch of road between the interchange and the N-5
road, including the canal bridge, is recommended. The road section should be such
as to allow the safe transit of two trucks at the same time.
It is also recommended to improve the layout of the intersection with the N-5 road. It
is suggested to investigate the use of a traffic signals at the intersection of N-5 and
link road.
4.2.5 Problem
Location: Rahim Yar Khan interchange (km 560+043)
Summary: the junction where the motorway is connected does not have the
characteristics to ensure safe traffic flow
Risk: medium
The west ramp connects to a small local road which then crosses a more important
road where the east ramp is linked. The project does not foresee a rehabilitation of
this intersection.
FRED ENGINEERING 14
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
This intersection currently has four legs, but the project plans to rehabilitate it by
excluding one (it becomes a T-junction) without, however, providing for traffic
channelling (there is no traffic island).
The future traffic flow generated by the motorway (especially heavy goods vehicles)
is not consistent with this simple layout and may create dangerous conflicts at the
intersection.
FRED ENGINEERING 15
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
Recommendation
It is recommended that the 4-leg junction be rehabilitated in such a way as to have
geometric characteristics consistent with the type and expected traffic flow. In
particular it is suggested to provide a roundabout which has the double advantage
of reducing the points of conflict and moderating the speed.
4.2.6 Problem
Location: Bhawalpur interchange (km 687+642)
Summary: the interchange includes a small village
Risk: very high
The two ramps of the interchange connect on a small local road which then leads to
the N-115 road. Between the two intersections, along the local road, there is a small
village that will inevitably be damaged by new highway traffic (composed of
significant proportion of heavy vehicles).
In the village there are schools, mosques and a market, activities that generate an
intense movement of vulnerable users.
The project does not give any indication on how the impact of the new road will be
controlled.
In this situation, it is clear that there is a very high risk of pedestrians and other
vulnerable users involvement in road crashes due to the expected high traffic
demand on this road.
In addition, at the T-junction between the local road and the N-115 road, no
rehabilitation is envisaged. The current layout can lead to dangerous conflicts
between different traffic flows: rear-end and lateral collisions may occur.
FRED ENGINEERING 16
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
Figure 20 – Current layout of the junction between N-115 and local road
Recommendation
If the village cannot be bypassed or avoided, it is recommended to implement traffic
calming measures at the level of the crossing of the agglomeration in order to
safeguard vulnerable users.
Moreover, it is recommended to adopt a different layout for the T junction between
N-115 and local road, with storage/acceleration lanes for vehicles turning right and
traffic islands to drive vehicles on the correct trajectories (see Figure below).
4.2.7 Problem
Location: Jalal Pur interchange (km 701+446)
Summary: the junction where the motorway is connected does not have the
characteristics to ensure safe traffic flow
Risk: high
The slip roads are connected to the road N-115. The western ramp connects directly
to the national highway, while the eastern ramp connects to a local road that then
intersects the road N-115 at a 4-leg non-signalised junction. The project does not
foresee a rehabilitation of this intersection.
FRED ENGINEERING 17
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
The future traffic flow generated by the motorway (especially heavy goods vehicles)
is not consistent with this layout and may create dangerous conflicts at the
intersection.
In addition, at the T-junction between the western ramp and the road N-115 no
storage lane is envisaged for right turning vehicles. This layout can lead to
dangerous conflicts between the different traffic flows: rear-end and lateral collisions
may occur.
Figure 22 – 4-leg junction between N-115 and the local road (left) and T-junction on N-115 road (right)
Recommendation
It is recommended to rehabilitate the 4-leg junction, in such a way as to have
geometric characteristics consistent with the type and expected traffic flow. In
particular it is suggested to provide a roundabout which has the double advantage
of reducing the points of conflict and moderating the speed.
Moreover, it is recommended to adopt a different layout for the T junction with
storage/acceleration lanes for vehicles turning right and traffic islands to drive
vehicles on the correct trajectories (see Figure 23 below).
FRED ENGINEERING 18
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
Recommendation
It is recommended to install the following signs (see an example in the Figure
below):
¡ ‘Keep left’ (arrow) sign, showing the right direction to take
¡ 2 ‘No entry’ signs (on both roadsides), preventing the wrong direction being
taken
In order to reinforce the separation of flows, it is also advisable to install plastic
marker posts along the centreline.
FRED ENGINEERING 19
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
FRED ENGINEERING 20
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
FRED ENGINEERING 21
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
FRED ENGINEERING 22
APPENDIX 2- Road Safety Audit Feedback Form
Scheme: Peshawar-Karachi motorway | Section II Sukkur - Multan
Audit Stage:2 Detailed Design
Recommen Alternative
Problem
ded measures or
Items resulting from Stage 2 Recommendation accepted Describe alternative measures. Give reasons for not accepting recommended
measure reasons accepted
Audit by the Auditor Yes/No measure. Only complete if recommended measure is not accepted.
accepted by the Auditor
Yes/NO (Yes/no)
(i) The current profile of New Jersey barriers are provided for all motorway in the
It is recommended to install barriers tested country.
Median barrier could not
4.1.1 according to internationally recognized NO NO (ii)If yes, vehicle wouldn't hit the barriers at 90°but laterally. The currently designed YES
properly restrain errant vehicles
standards (e.g.EN1317,MASH, etc) barriers profile can also move the impacting wheel and send it back towards
roadway to meet the TL-4 containment class.
Roadside barriers could not It is recommended to install barriers tested i The current W-beam guardrails are provided for all motorway in the country
4.1.2 properly restrain errant according to internationally recognized NO NO and work well in practices. YES
vehicles. standards (e.g.EN1317,MASH, etc). ii The current design meets the Contract documents.
i The intersection between the crossed local road at Pano Aqil interchange and
N5, as well as the bridge over the canal, is not in the contract scope of the Project.
They are part of the local road network.
ii Based on the Highway Safety Audit Expert’s comments, CSCEC hereby
propose a future renovation plan for the intersection between the crossed local road
i Rehabilitation of the entire stretch of and N5 , in which the crossed road (including the bridge over the canal) is widened
road between the interchange and the N-5 into two-way 2-lane, the intersection is renovated into a signalized one, and special
The road where the motorway
road, including the canal bridge, is left-turn and right-turn lanes are added. The plan is provided for the Employer’s
is connected Pano Aqil
recommended. reference and implementation.
interchange (km 413+978)
4.2.4 ii It is also recommended to improve the YES NO YES
does not have the
layout of the intersection with the N-5 road.
characteristics to ensure safe
It is suggested to investigate the use of a
traffic flow.
traffic signals at the intersection of N-5 and
link road.
i The intersection between the local road and N115 is not in the contract scope
of the Project. It is part of the local road network.
ii Based on the Highway Safety Audit Expert’s comments, CSCEC hereby
propose a future renovation plan for the intersection between the local road and
N115, in which the intersection is renovated into a signalized one and special left-
turn and right-turn lanes are added. The plan is provided for the Employer’s
reference and implementation.
The junctionJalal Pur i It is recommended to rehabilitate the 4- iii Based on the Highway Safety Audit Expert’s comments, CSCEC proposes the
interchange (km 701+446) leg junction. following: adjust the position of the median; combine the left-turn traffic and the
where the motorway is ii it is recommended to adopt a straight traffic into one lane; separate the right-turn traffic and the straight traffic
4.2.7 YES NO YES
connected does not have the different layout for the T junction with and adopt two lanes; set up a marking-type traffic island 50ms after the right-turn
characteristics to ensure safe acceleration lanes for vehicles turning right lane of the intersection to protect right-turn vehicles.
traffic flow. and traffic islands.
FRED ENGINEERING 29
Peshawar – Karachi motorway – Section II Sukkur - Multan Stage 2 RSA
FRED ENGINEERING 30