Vous êtes sur la page 1sur 47

DATOS

ELEMENTO BASE PERALTE ESPESOR


COLUMNAS C.Ex. Diametro= 0.45
COLUMNAS C. In. Diametro= 0.65
COLUMNAS 0.5 0.5
VIGAS EN X 0.45 0.7
VIGAS EN Y 0.45 0.7
VIGA DE ECENARIO 0.65 0.9
LOSA MAC 0.175
HI 3.8
H2 3
H3 3
H4 2.6
H5 2.6
UBICACIÓN "Nazca" 15
USO TEATRO, OFICINAS

CARGA MUERTA: 1° NIVEL


PESO ESPEC.
ELEMENTO LONGITUD (M) ANCHO(M) ALTURA(M) (TN/M3) P.TOTAL (TN) X(M)

C-1 0.5 0.5 3.4 2.4 2.040 0


C-2 0.5 0.5 3.4 2.4 2.040 4.5
C-3 0.5 0.5 3.4 2.4 2.040 9
C-4 AREA= 0.16 3.4 2.4 1.298 19
C-5 0.5 0.5 3.4 2.4 2.040 0
C-6 0.5 0.5 3.4 2.4 2.040 4.5
C-7 0.5 0.5 3.4 2.4 2.040 9
C-8 0.5 0.5 3.4 2.4 2.040 14
C-9 0.5 0.5 3.4 2.4 2.040 19
C-10 AREA= 0.16 3.4 2.4 1.298 22.5
C-11 0.5 0.5 3.4 2.4 2.040 0
C-12 0.5 0.5 3.4 2.4 2.040 4.5
C-13 0.5 0.5 3.4 2.4 2.040 9
C-14 0.5 0.5 3.4 2.4 2.040 14
C-15 0.5 0.5 3.4 2.4 2.040 19
C-16 AREA= 0.16 3.4 2.4 1.298 26
C-17 AREA= 0.16 3.4 2.4 1.298 0
C-18 0.5 0.5 3.4 2.4 2.040 4.5
C-19 0.5 0.5 3.4 2.4 2.040 9
C-20 AREA= 0.33 3.4 2.4 2.708 14
C-21 0.5 0.5 3.4 2.4 2.040 19
C-22 AREA= 0.16 3.4 2.4 1.298 26
C-23 AREA= 0.16 3.4 2.4 1.298 4.5
C-24 AREA= 0.33 3.4 2.4 2.708 9
C-25 AREA= 0.33 3.4 2.4 2.708 19
C-26 AREA= 0.16 3.4 2.4 1.298 26
C-27 AREA= 0.16 3.4 2.4 1.298 26
C-28 AREA= 0.16 3.4 2.4 1.298 9
C-29 AREA= 0.33 3.4 2.4 2.708 14
C-30 AREA= 0.16 3.4 2.4 1.298 19
56.449
VIGAS
V-1 4.5 0.45 0.70 2.4 3.402 2.25
V-2 4.5 0.45 0.70 2.4 3.402 6.75
V-3 4.5 0.45 0.70 2.4 3.402 2.25
V-4 4.5 0.45 0.70 2.4 3.402 6.75
V-5 5 0.45 0.70 2.4 3.780 11.5
V-6 5 0.45 0.70 2.4 3.780 16.5
V-7 3.5 0.45 0.70 2.4 2.646 20.75
V-8 4.5 0.45 0.70 2.4 3.402 2.25
V-9 4.5 0.45 0.70 2.4 3.402 6.75
V-10 5 0.45 0.70 2.4 3.780 11.5
V-11 5 0.45 0.70 2.4 3.780 16.5
V-12 7 0.45 0.70 2.4 5.292 22.5
V-13 4.5 0.45 0.70 2.4 3.402 2.25
V-14 4.5 0.45 0.70 2.4 3.402 6.75
V-15 5 0.45 0.70 2.4 3.780 11.5
V-16 5 0.45 0.70 2.4 3.780 16.5
V-17 7 0.45 0.70 2.4 5.292 22.5
V-18 4.5 0.45 0.70 2.4 3.402 6.75
V-19 5 0.65 0.90 2.4 7.020 11.5
V-19´ 5 0.65 0.90 2.4 7.020 16.5
V-20 7 0.45 0.70 2.4 5.292 22.5
V-21 5 0.45 0.70 2.4 3.780 11.5
V-22 5 0.45 0.70 2.4 3.780 16.5
V-23 6 0.45 0.70 2.4 4.536 0
V-24 6 0.45 0.70 2.4 4.536 4.5
V-25 6 0.45 0.70 2.4 4.536 9
V-26 6 0.45 0.70 2.4 4.536 19
V-27 6 0.45 0.70 2.4 4.536 0
V-28 6 0.45 0.70 2.4 4.536 4.5
V-29 6 0.45 0.70 2.4 4.536 9
V-30 6 0.45 0.70 2.4 4.536 14
V-31 6 0.45 0.70 2.4 4.536 19
V-32 5 0.45 0.70 2.4 3.780 0
V-33 5 0.45 0.70 2.4 3.780 4.5
V-34 5 0.45 0.70 2.4 3.780 9
V-35 5 0.45 0.70 2.4 3.780 14
V-36 5 0.45 0.70 2.4 3.780 19
V-37 5 0.45 0.70 2.4 3.780 26
V-38 5 0.45 0.70 2.4 3.780 4.5
V-39 5 0.45 0.70 2.4 3.780 9
V-40 5 0.65 0.90 2.4 7.020 14
V-41 5 0.45 0.70 2.4 3.780 19
V-42 5 0.45 0.70 2.4 3.780 26
V-43 5 0.45 0.70 2.4 3.780 9
V-44 5 0.65 0.90 2.4 7.020 14
V-45 5 0.45 0.70 2.4 3.780 19
V-46 2 0.45 0.70 2.4 1.512 26
VI-1 6.9 0.45 0.70 2.4 5.216 28.8
VI-2 6.9 0.45 0.70 2.4 5.216 24.3
VI-3 6.7 0.45 0.70 2.4 5.065 2.3
VI-4 6.7 0.45 0.70 2.4 5.065 6.8
VI-5 7.6 0.45 0.70 2.4 5.746 22.5
215.719
LOZA MACISA
L1 AREA= 27 0.175 2.4 11.34 2.3
L2 AREA= 27 0.175 2.4 11.34 6.8
L3 AREA= 10.5 0.175 2.4 4.41 20.2
L4 AREA= 27 0.175 2.4 11.34 2.3
L5 AREA= 27 0.175 2.4 11.34 6.8
L6 AREA= 30 0.175 2.4 12.6 11.5
L7 AREA= 30 0.175 2.4 12.6 16.5
L8 AREA= 31.5 0.175 2.4 13.23 22
L9 AREA= 22.5 0.175 2.4 9.45 2.3
L10 AREA= 22.5 0.175 2.4 9.45 6.8
L11 AREA= 25 0.175 2.4 10.5 11.5
L12 AREA= 25 0.175 2.4 10.5 16.5
L13 AREA= 35 0.175 2.4 14.7 22.5
L14 AREA= 11.25 0.175 2.4 4.725 3
L15 AREA= 22.5 0.175 2.4 9.45 6.8
L16 AREA= 25 0.175 2.4 10.5 11.5
L17 AREA= 25 0.175 2.4 10.5 16.5
L18 AREA= 35 0.175 2.4 14.7 22.5
L19 AREA= 11.25 0.175 2.4 4.725 7.5
L20 AREA= 25 0.175 2.4 10.5 11.5
L21 AREA= 25 0.175 2.4 10.5 16.50
L22 AREA= 24.5 0.175 2.4 10.29 24.80
228.69

PISO TERMINADO S/C=0.14 ton/m2 ceramico

L1 AREA= 27 0.14 3.78 2.3


L2 AREA= 27 0.14 3.78 6.8
L3 AREA= 10.5 0.14 1.47 20.2
L4 AREA= 27 0.14 3.78 2.3
L5 AREA= 27 0.14 3.78 6.8
L6 AREA= 30 0.14 4.2 11.5
L7 AREA= 30 0.14 4.2 16.5
L8 AREA= 31.5 0.14 4.41 22
L9 AREA= 22.5 0.14 3.15 2.3
L10 AREA= 22.5 0.14 3.15 6.8
L11 AREA= 25 0.14 3.5 11.5
L12 AREA= 25 0.14 3.5 16.5
L13 AREA= 35 0.14 4.9 22.5
L14 AREA= 11.25 0.14 1.575 3
L15 AREA= 22.5 0.14 3.15 6.8
L16 AREA= 25 0.14 3.5 11.5
L17 AREA= 25 0.14 3.5 16.5
L18 AREA= 35 0.14 4.9 22.5
L19 AREA= 11.25 0.14 1.575 7.5
L20 AREA= 25 0.14 3.5 11.5
L21 AREA= 25 0.14 3.5 16.50
L22 AREA= 24.5 0.14 3.43 24.80
76.23

TOTAL 577.088

X= 12.84
Y= 14.50

CARGA VIVA 1° NIVEL


S/C
LOSA 1 TEATRO 0.3 Tn/m2

L1 AREA= 27 0.3 8.1


L2 AREA= 27 0.3 8.1
L3 AREA= 10.5 0.3 3.15
L4 AREA= 27 0.3 8.1
L5 AREA= 27 0.3 8.1
L6 AREA= 30 0.3 9
L7 AREA= 30 0.3 9
L8 AREA= 31.5 0.3 9.45
L9 AREA= 22.5 0.3 6.75
L10 AREA= 22.5 0.3 6.75
L11 AREA= 25 0.3 7.5
L12 AREA= 25 0.3 7.5
L13 AREA= 35 0.3 10.5
L14 AREA= 11.25 0.3 3.375
L15 AREA= 22.5 0.3 6.75
L16 AREA= 25 0.3 7.5
L17 AREA= 25 0.3 7.5
L18 AREA= 35 0.3 10.5
L19 AREA= 11.25 0.3 3.375
L20 AREA= 25 0.75 18.75
L21 AREA= 25 0.75 18.75
L22 AREA= 24.5 0.3 7.35
185.85

CUADRO RESUMEN

CUADRO RESUMEN
CM(TN) CV(TN)
1°NIVEL 577.09 185.85
2°NIVEL 570.45 163.35
3°NIVEL 567.127 148.3625
4°NIVEL 439.96 106.00
5°NIVEL 381.88 42.40

ESTIMACION DE PESO DE LA ESTRUCTURA

TEATRO CATEGORIA B CM CV DISEÑO %CV


OFICINAS CATEGORIA C P1 577.09 185.85 0.5
P2 570.45 163.35 0.5
147.8625 0.5
P3 567.127
P3 567.127
0.50 0.25
P4 439.96 106.00 0.25
P5 381.88 42.40 0.25
PTOTAL

CORTANTE BASAL V

MIRAR SIGUIENTE HOJA


Cvx= 0.273
Cvy= 0.273
V= 771.712

NIVEL PESO ALTURA K P *( h^K) ALFA V


PISO 1 670.013 3.800 1.000 2546.050 #REF! 771.712
PISO 2 #REF! 6.800 1.000 #REF! #REF! 771.712
PISO 3 641.183 9.800 1.000 6283.591 #REF! 771.712
PISO 4 466.463 12.400 1.000 5784.142 #REF! 771.712
PISO 5 392.481 15.000 1.000 5887.211 #REF! 771.712
#REF! *ALTURA ACUMULADA #REF!

MATRIZ DE FUERZAS

#REF! 1°PISO
#REF! 2°PISO
#REF! 3°PISO
#REF! 4°PISO
#REF! 5°PISO
#REF! 1°PISO
#REF! 2°PISO
#REF! 3°PISO
#REF! 4°PISO
#REF! 5°PISO
#REF! 1°PISO
#REF! 2°PISO
#REF! 3°PISO
#REF! 4°PISO
#REF! 5°PISO
CARGA MUERT
LONGITUD
Y(M) PX (TN-M) PY (TN-M) ELEMENTO (M) ANCHO(M) ALTURA(M)

0 0.000 0.000 C-1 0.5 0.5 3


0 9.180 0.000 C-2 0.5 0.5 3
0 18.360 0.000 C-3 0.5 0.5 3
0 24.658 0.000 C-4 AREA= 0.16 3
6 0.000 12.240 C-5 0.5 0.5 3
6 9.180 12.240 C-6 0.5 0.5 3
6 18.360 12.240 C-7 0.5 0.5 3
6 28.560 12.240 C-8 0.5 0.5 3
6 38.760 12.240 C-9 0.5 0.5 3
6 29.200 7.787 C-10 AREA= 0.16 3
12 0.000 24.480 C-11 0.5 0.5 3
12 9.180 24.480 C-12 0.5 0.5 3
12 18.360 24.480 C-13 0.5 0.5 3
12 28.560 24.480 C-14 0.5 0.5 3
12 38.760 24.480 C-15 0.5 0.5 3
12 33.743 15.574 C-16 AREA= 0.16 3
17 0.000 22.063 C-17 AREA= 0.16 3
17 9.180 34.680 C-18 0.5 0.5 3
17 18.360 34.680 C-19 0.5 0.5 3
17 37.908 46.032 C-20 AREA= 0.33 3
17 38.760 34.680 C-21 0.5 0.5 3
17 33.743 22.063 C-22 AREA= 0.16 3
22 5.840 28.551 C-23 AREA= 0.16 3
22 24.370 59.570 C-24 AREA= 0.33 3
22 51.447 59.570 C-25 AREA= 0.33 3
22 33.743 28.551 C-26 AREA= 0.16 3
24 33.743 31.147 C-27 AREA= 0.16 3
27 11.680 35.040 C-28 AREA= 0.16 3
27 37.908 73.109 C-29 AREA= 0.33 3
27 24.658 35.040 C-30 AREA= 0.16 3

VIGAS
0 7.655 0.000 V-1 4.5 0.45 0.70
0 22.964 0.000 V-2 4.5 0.45 0.70
6 7.655 20.412 V-3 4.5 0.45 0.70
6 22.964 20.412 V-4 4.5 0.45 0.70
6 43.470 22.680 V-5 5 0.45 0.70
6 62.370 22.680 V-6 5 0.45 0.70
6 54.905 15.876 V-7 3.5 0.45 0.70
12 7.655 40.824 V-8 4.5 0.45 0.70
12 22.964 40.824 V-9 4.5 0.45 0.70
12 43.470 45.360 V-10 5 0.45 0.70
12 62.370 45.360 V-11 5 0.45 0.70
12 119.070 63.504 V-12 7 0.45 0.70
17 7.655 57.834 V-13 4.5 0.45 0.70
17 22.964 57.834 V-14 4.5 0.45 0.70
17 43.470 64.260 V-15 5 0.45 0.70
17 62.370 64.260 V-16 5 0.45 0.70
17 119.070 89.964 V-17 7 0.45 0.70
22 22.964 74.844 V-18 4.5 0.45 0.70
22 80.730 154.440 V-19 5 0.65 0.90
22 115.830 154.440 V-19´ 5 0.65 0.90
22 119.070 116.424 V-20 7 0.45 0.70
27 43.470 102.060 V-21 5 0.45 0.70
27 62.370 102.060 V-22 5 0.45 0.70
3 0.000 13.608 V-23 6 0.45 0.70
3 20.412 13.608 V-24 6 0.45 0.70
3 40.824 13.608 V-25 6 0.45 0.70
3 86.184 13.608 V-26 6 0.45 0.70
9 0.000 40.824 V-27 6 0.45 0.70
9 20.412 40.824 V-28 6 0.45 0.70
9 40.824 40.824 V-29 6 0.45 0.70
9 63.504 40.824 V-30 6 0.45 0.70
9 86.184 40.824 V-31 6 0.45 0.70
14.5 0.000 54.810 V-32 5 0.45 0.70
14.5 17.010 54.810 V-33 5 0.45 0.70
14.5 34.020 54.810 V-34 5 0.45 0.70
14.5 52.920 54.810 V-35 5 0.45 0.70
14.5 71.820 54.810 V-36 5 0.45 0.70
14.5 98.280 54.810 V-37 5 0.45 0.70
19.5 17.010 73.710 V-38 5 0.45 0.70
19.5 34.020 73.710 V-39 5 0.45 0.70
19.5 98.280 136.890 V-40 5 0.65 0.90
19.5 71.820 73.710 V-41 5 0.45 0.70
19.5 98.280 73.710 V-42 5 0.45 0.70
24.5 34.020 92.610 V-43 5 0.45 0.70
24.5 98.280 171.990 V-44 5 0.65 0.90
24.5 71.820 92.610 V-45 5 0.45 0.70
23 39.312 34.776 V-46 2 0.45 0.70
3 150.232 15.649 VI-1 6.9 0.45 0.70
9 126.759 46.948 VI-2 6.9 0.45 0.70
19.5 11.650 98.771 VI-3 6.7 0.45 0.70
24.5 34.443 124.097 VI-4 6.7 0.45 0.70
25.5 129.276 146.513 VI-5 7.6 0.45 0.70

LOZA MACISA
3 26.082 34.02 L1 AREA= 27 0.175
3 77.112 34.02 L2 AREA= 27 0.175
4 89.082 17.64 L3 AREA= 10.5 0.175
9 26.082 102.06 L4 AREA= 27 0.175
9 77.112 102.06 L5 AREA= 27 0.175
9 144.9 113.4 L6 AREA= 30 0.175
9 207.9 113.4 L7 AREA= 30 0.175
11 291.06 145.53 L8 AREA= 31.5 0.175
14.5 21.735 137.025 L9 AREA= 22.5 0.175
14.5 64.26 137.025 L10 AREA= 22.5 0.175
14.5 120.75 152.25 L11 AREA= 25 0.175
14.5 173.25 152.25 L12 AREA= 25 0.175
14.5 330.75 213.15 L13 AREA= 35 0.175
18.7 14.175 88.3575 L14 AREA= 11.25 0.175
19.5 64.26 184.275 L15 AREA= 22.5 0.175
19.5 120.75 204.75 L16 AREA= 25 0.175
19.5 173.25 204.75 L17 AREA= 25 0.175
19.5 330.75 286.65 L18 AREA= 35 0.175
23.7 35.4375 111.9825 L19 AREA= 11.25 0.175
24.5 120.75 257.25 L20 AREA= 25 0.175
24.5 173.25 257.25 L21 AREA= 25 0.175
24 255.192 246.96 L22 AREA= 24.5 0.175

PISO TERMINADO S/C=0.14 ton/m2 ceramico

3 8.69 11.34 L1 AREA= 27


3 25.70 11.34 L2 AREA= 27
4 29.69 5.88 L3 AREA= 10.5
9 8.69 34.02 L4 AREA= 27
9 25.70 34.02 L5 AREA= 27
9 48.30 37.8 L6 AREA= 30
9 69.30 37.8 L7 AREA= 30
11 97.02 48.51 L8 AREA= 31.5
14.5 7.25 45.675 L9 AREA= 22.5
14.5 21.42 45.675 L10 AREA= 22.5
14.5 40.25 50.75 L11 AREA= 25
14.5 57.75 50.75 L12 AREA= 25
14.5 110.25 71.05 L13 AREA= 35
18.7 4.73 29.4525 L14 AREA= 11.25
19.5 21.42 61.425 L15 AREA= 22.5
19.5 40.25 68.25 L16 AREA= 25
19.5 57.75 68.25 L17 AREA= 25
19.5 110.25 95.55 L18 AREA= 35
23.7 11.81 37.3275 L19 AREA= 11.25
24.5 40.25 85.75 L20 AREA= 25
24.5 57.75 85.75 L21 AREA= 25
24 85.06 82.32 L22 AREA= 24.5
7408.45 8365.936

CARGA VIVA
S/C
LOSA 1 TEATRO

L1 AREA= 27
L2 AREA= 27
L3 AREA= 10.5
L4 AREA= 27
L5 AREA= 27
L6 AREA= 30
L7 AREA= 30
L8 AREA= 31.5
L9 AREA= 22.5
L10 AREA= 22.5
L11 AREA= 25
L12 AREA= 25
L13 AREA= 35
L14 AREA= 11.25
L15 AREA= 22.5
L16 AREA= 25
L17 AREA= 25
L18 AREA= 35
L19 AREA= 11.25
L20 AREA= 25
L21 AREA= 25
L22 AREA= 24.5

URA

CM+%CV
670.01
652.12

641.18
641.18

466.46
392.48
2822.26

*ojo como T es menor a 0.5, K=1

FI VA Lx Ly mtx mty
#REF! #REF! 19.000 20.000 #REF! #REF!
#REF! #REF! 19.000 20.000 #REF! #REF!
#REF! #REF! 19.000 20.000 #REF! #REF!
#REF! #REF! 19.000 20.000 #REF! #REF!
#REF! #REF! 19.000 20.000 #REF! #REF!
#REF!

DE FUERZAS

MTY
CARGA MUERTA: 2° NIVEL
PESO ESPEC. P.TOTAL
(TN/M3) (TN) X(M) Y(M) PX (TN-M) PY (TN-M) ELEMENTO

2.4 1.800 0 0 0.000 0.000 C-1


2.4 1.800 4.5 0 8.100 0.000 C-2
2.4 1.800 9 0 16.200 0.000 C-3
2.4 1.145 19 0 21.757 0.000 C-4
2.4 1.800 0 6 0.000 10.800 C-5
2.4 1.800 4.5 6 8.100 10.800 C-6
2.4 1.800 9 6 16.200 10.800 C-7
2.4 1.800 14 6 25.200 10.800 C-8
2.4 1.800 19 6 34.200 10.800 C-9
2.4 1.145 22.5 6 25.765 6.871 C-10
2.4 1.800 0 12 0.000 21.600 C-11
2.4 1.800 4.5 12 8.100 21.600 C-12
2.4 1.800 9 12 16.200 21.600 C-13
2.4 1.800 14 12 25.200 21.600 C-14
2.4 1.800 19 12 34.200 21.600 C-15
2.4 1.145 26 12 29.773 13.741 C-16
2.4 1.145 0 17 0.000 19.467 C-17
2.4 1.800 4.5 17 8.100 30.600 C-18
2.4 1.800 9 17 16.200 30.600 C-19
2.4 2.389 14 17 33.449 40.616 C-20
2.4 1.800 19 17 34.200 30.600 C-21
2.4 1.145 26 17 29.773 19.467 C-22
2.4 1.145 4.5 22 5.153 25.192 C-23
2.4 2.389 9 22 21.503 52.562 C-24
2.4 2.389 19 22 45.395 52.562 C-25
2.4 1.145 26 22 29.773 25.192 C-26
2.4 1.145 26 24 29.773 27.483 C-27
2.4 1.145 9 27 10.306 30.918 C-28
2.4 2.389 14 27 33.449 64.508 C-29
2.4 1.145 19 27 21.757 30.918 C-30
49.808
VIGAS
2.4 3.402 2.25 0 7.655 0.000 V-1
2.4 3.402 6.75 0 22.964 0.000 V-2
2.4 3.402 2.25 6 7.655 20.412 V-3
2.4 3.402 6.75 6 22.964 20.412 V-4
2.4 3.780 11.5 6 43.470 22.680 V-5
2.4 3.780 16.5 6 62.370 22.680 V-6
2.4 2.646 20.75 6 54.905 15.876 V-7
2.4 3.402 2.25 12 7.655 40.824 V-8
2.4 3.402 6.75 12 22.964 40.824 V-9
2.4 3.780 11.5 12 43.470 45.360 V-10
2.4 3.780 16.5 12 62.370 45.360 V-11
2.4 5.292 22.5 12 119.070 63.504 V-12
2.4 3.402 2.25 17 7.655 57.834 V-13
2.4 3.402 6.75 17 22.964 57.834 V-14
2.4 3.780 11.5 17 43.470 64.260 V-15
2.4 3.780 16.5 17 62.370 64.260 V-16
2.4 5.292 22.5 17 119.070 89.964 V-17
2.4 3.402 6.75 22 22.964 74.844 V-18
2.4 7.020 11.5 22 80.730 154.440 V-19
2.4 7.020 16.5 22 115.830 154.440 V-19´
2.4 5.292 22.5 22 119.070 116.424 V-20
2.4 3.780 11.5 27 43.470 102.060 V-21
2.4 3.780 16.5 27 62.370 102.060 V-22
2.4 4.536 0 3 0.000 13.608 V-23
2.4 4.536 4.5 3 20.412 13.608 V-24
2.4 4.536 9 3 40.824 13.608 V-25
2.4 4.536 19 3 86.184 13.608 V-26
2.4 4.536 0 9 0.000 40.824 V-27
2.4 4.536 4.5 9 20.412 40.824 V-28
2.4 4.536 9 9 40.824 40.824 V-29
2.4 4.536 14 9 63.504 40.824 V-30
2.4 4.536 19 9 86.184 40.824 V-31
2.4 3.780 0 14.5 0.000 54.810 V-32
2.4 3.780 4.5 14.5 17.010 54.810 V-33
2.4 3.780 9 14.5 34.020 54.810 V-34
2.4 3.780 14 14.5 52.920 54.810 V-35
2.4 3.780 19 14.5 71.820 54.810 V-36
2.4 3.780 26 14.5 98.280 54.810 V-37
2.4 3.780 4.5 19.5 17.010 73.710 V-38
2.4 3.780 9 19.5 34.020 73.710 V-39
2.4 7.020 14 19.5 98.280 136.890 V-40
2.4 3.780 19 19.5 71.820 73.710 V-41
2.4 3.780 26 19.5 98.280 73.710 V-42
2.4 3.780 9 24.5 34.020 92.610 V-43
2.4 7.020 14 24.5 98.280 171.990 V-44
2.4 3.780 19 24.5 71.820 92.610 V-45
2.4 1.512 26 23 39.312 34.776 V-46
2.4 5.216 28.8 3 150.232 15.649 VI-1
2.4 5.216 24.3 9 126.759 46.948 VI-2
2.4 5.065 2.3 19.5 11.650 98.771 VI-3
2.4 5.065 6.8 24.5 34.443 124.097 VI-4
2.4 5.746 22.5 25.5 129.276 146.513 VI-5
215.719
LOZA MACISA
2.4 11.34 2.3 3 26.082 34.02 L1
2.4 11.34 6.8 3 77.112 34.02 L2
2.4 4.41 20.2 4 89.082 17.64 L3
2.4 11.34 2.3 9 26.082 102.06 L4
2.4 11.34 6.8 9 77.112 102.06 L5
2.4 12.6 11.5 9 144.9 113.4 L6
2.4 12.6 16.5 9 207.9 113.4 L7
2.4 13.23 22 11 291.06 145.53 L8
2.4 9.45 2.3 14.5 21.735 137.025 L9
2.4 9.45 6.8 14.5 64.26 137.025 L10
2.4 10.5 11.5 14.5 120.75 152.25 L11
2.4 10.5 16.5 14.5 173.25 152.25 L12
2.4 14.7 22.5 14.5 330.75 213.15 L13
2.4 4.725 3 18.7 14.175 88.3575 L14
2.4 9.45 6.8 19.5 64.26 184.275 L15
2.4 10.5 11.5 19.5 120.75 204.75 L16
2.4 10.5 16.5 19.5 173.25 204.75 L17
2.4 14.7 22.5 19.5 330.75 286.65 L18
2.4 4.725 7.5 23.7 35.4375 111.9825 L19
2.4 10.5 11.5 24.5 120.75 257.25 L20
2.4 10.5 16.50 24.5 173.25 257.25 L21
2.4 10.29 24.80 24 255.192 246.96 L22
228.69

PISO TERMINADO

0.14 3.78 2.3 3 8.69 11.34 L1


0.14 3.78 6.8 3 25.70 11.34 L2
0.14 1.47 20.2 4 29.69 5.88 L3
0.14 3.78 2.3 9 8.69 34.02 L4
0.14 3.78 6.8 9 25.70 34.02 L5
0.14 4.2 11.5 9 48.30 37.8 L6
0.14 4.2 16.5 9 69.30 37.8 L7
0.14 4.41 22 11 97.02 48.51 L8
0.14 3.15 2.3 14.5 7.25 45.675 L9
0.14 3.15 6.8 14.5 21.42 45.675 L10
0.14 3.5 11.5 14.5 40.25 50.75 L11
0.14 3.5 16.5 14.5 57.75 50.75 L12
0.14 4.9 22.5 14.5 110.25 71.05 L13
0.14 1.575 3 18.7 4.73 29.4525 L14
0.14 3.15 6.8 19.5 21.42 61.425 L15
0.14 3.5 11.5 19.5 40.25 68.25 L16
0.14 3.5 16.5 19.5 57.75 68.25 L17
0.14 4.9 22.5 19.5 110.25 95.55 L18
0.14 1.575 7.5 23.7 11.81 37.3275 L19
0.14 3.5 11.5 24.5 40.25 85.75 L20
0.14 3.5 16.50 24.5 57.75 85.75 L21
0.14 3.43 24.80 24 85.06 82.32 L22
76.23 7330.08 8277.50

TOTAL 570.447

X= 12.85
Y= 14.51

CARGA VIVA 2° NIVEL


S/C
0.3 Tn/m2 LOSA 1

0.3 8.1 L1
0.3 8.1 L2
0.3 3.15 L3
0.3 8.1 L4
0.3 8.1 L5
0.3 9 L6
0.3 9 L7
0.3 9.45 L8
0.3 6.75 L9
0.3 6.75 L10
0.3 7.5 L11
0.3 7.5 L12
0.3 10.5 L13
0.3 3.375 L14
0.3 6.75 L15
0.3 7.5 L16
0.3 7.5 L17
0.3 10.5 L18
0.3 3.375 L19
0.3 7.5 L20
0.3 7.5 L21
0.3 7.35 L22
163.35
METRADO DE CARGAS
CARGA MUERTA: 3° NIVEL
LONGITUD
(M) ANCHO(M) ALTURA(M) PESO ESPEC.
(TN/M3) P.TOTAL (TN) X(M) Y(M) PX (TN-M)

0.5 0.5 2.8 2.4 1.68 0 0 0.00


0.5 0.5 2.8 2.4 1.68 4.5 0 7.56
0.5 0.5 2.8 2.4 1.68 9 0 15.12
AREA= 0.16 2.8 2.4 1.07 19 0 20.31
0.5 0.5 2.8 2.4 1.68 0 6 0.00
0.5 0.5 2.8 2.4 1.68 4.5 6 7.56
0.5 0.5 2.8 2.4 1.68 9 6 15.12
0.5 0.5 2.8 2.4 1.68 14 6 23.52
0.5 0.5 2.8 2.4 1.68 19 6 31.92
AREA= 0.16 2.8 2.4 1.07 22.5 6 24.05
0.5 0.5 2.8 2.4 1.68 0 12 0.00
0.5 0.5 2.8 2.4 1.68 4.5 12 7.56
0.5 0.5 2.8 2.4 1.68 9 12 15.12
0.5 0.5 2.8 2.4 1.68 14 12 23.52
0.5 0.5 2.8 2.4 1.68 19 12 31.92
AREA= 0.16 2.8 2.4 1.07 26 12 27.79
AREA= 0.16 2.8 2.4 1.07 0 17 0.00
0.5 0.5 2.8 2.4 1.68 4.5 17 7.56
0.5 0.5 2.8 2.4 1.68 9 17 15.12
AREA= 0.33 2.8 2.4 2.23 14 17 31.22
0.5 0.5 2.8 2.4 1.68 19 17 31.92
AREA= 0.16 2.8 2.4 1.07 26 17 27.79
AREA= 0.16 2.8 2.4 1.07 4.5 22 4.81
AREA= 0.33 2.8 2.4 2.23 9 22 20.07
AREA= 0.33 2.8 2.4 2.23 19 22 42.37
AREA= 0.16 2.8 2.4 1.07 26 22 27.79
AREA= 0.16 2.8 2.4 1.07 26 24 27.79
AREA= 0.16 2.8 2.4 1.07 9 27 9.62
AREA= 0.33 2.8 2.4 2.23 14 27 31.22
AREA= 0.16 2.8 2.4 1.07 19 27 20.31
46.487

4.5 0.45 0.70 2.4 3.402 2.25 0 7.655


4.5 0.45 0.70 2.4 3.402 6.75 0 22.964
4.5 0.45 0.70 2.4 3.402 2.25 6 7.655
4.5 0.45 0.70 2.4 3.402 6.75 6 22.964
5 0.45 0.70 2.4 3.780 11.5 6 43.470
5 0.45 0.70 2.4 3.780 16.5 6 62.370
3.5 0.45 0.70 2.4 2.646 20.75 6 54.905
4.5 0.45 0.70 2.4 3.402 2.25 12 7.655
4.5 0.45 0.70 2.4 3.402 6.75 12 22.964
5 0.45 0.70 2.4 3.780 11.5 12 43.470
5 0.45 0.70 2.4 3.780 16.5 12 62.370
7 0.45 0.70 2.4 5.292 22.5 12 119.070
4.5 0.45 0.70 2.4 3.402 2.25 17 7.655
4.5 0.45 0.70 2.4 3.402 6.75 17 22.964
5 0.45 0.70 2.4 3.780 11.5 17 43.470
5 0.45 0.70 2.4 3.780 16.5 17 62.370
7 0.45 0.70 2.4 5.292 22.5 17 119.070
4.5 0.45 0.70 2.4 3.402 6.75 22 22.964
5 0.65 0.90 2.4 7.020 11.5 22 80.730
5 0.65 0.90 2.4 7.020 16.5 22 115.830
7 0.45 0.70 2.4 5.292 22.5 22 119.070
5 0.45 0.70 2.4 3.780 11.5 27 43.470
5 0.45 0.70 2.4 3.780 16.5 27 62.370
6 0.45 0.70 2.4 4.536 0 3 0.000
6 0.45 0.70 2.4 4.536 4.5 3 20.412
6 0.45 0.70 2.4 4.536 9 3 40.824
6 0.45 0.70 2.4 4.536 19 3 86.184
6 0.45 0.70 2.4 4.536 0 9 0.000
6 0.45 0.70 2.4 4.536 4.5 9 20.412
6 0.45 0.70 2.4 4.536 9 9 40.824
6 0.45 0.70 2.4 4.536 14 9 63.504
6 0.45 0.70 2.4 4.536 19 9 86.184
5 0.45 0.70 2.4 3.780 0 14.5 0.000
5 0.45 0.70 2.4 3.780 4.5 14.5 17.010
5 0.45 0.70 2.4 3.780 9 14.5 34.020
5 0.45 0.70 2.4 3.780 14 14.5 52.920
5 0.45 0.70 2.4 3.780 19 14.5 71.820
5 0.45 0.70 2.4 3.780 26 14.5 98.280
5 0.45 0.70 2.4 3.780 4.5 19.5 17.010
5 0.45 0.70 2.4 3.780 9 19.5 34.020
5 0.65 0.90 2.4 7.020 14 19.5 98.280
5 0.45 0.70 2.4 3.780 19 19.5 71.820
5 0.45 0.70 2.4 3.780 26 19.5 98.280
5 0.45 0.70 2.4 3.780 9 24.5 34.020
5 0.65 0.90 2.4 7.020 14 24.5 98.280
5 0.45 0.70 2.4 3.780 19 24.5 71.820
2 0.45 0.70 2.4 1.512 26 23 39.312
6.9 0.45 0.70 2.4 5.216 28.8 3 150.232
6.9 0.45 0.70 2.4 5.216 24.3 9 126.759
6.7 0.45 0.70 2.4 5.065 2.3 19.5 11.650
6.7 0.45 0.70 2.4 5.065 6.8 24.5 34.443
7.6 0.45 0.70 2.4 5.746 22.5 25.5 129.276
215.719
OZA MACISA
AREA= 27 0.175 2.4 11.34 2.3 3 26.082
AREA= 27 0.175 2.4 11.34 6.8 3 77.112
AREA= 10.5 0.175 2.4 4.41 20.2 4 89.082
AREA= 27 0.175 2.4 11.34 2.3 9 26.082
AREA= 27 0.175 2.4 11.34 6.8 9 77.112
AREA= 30 0.175 2.4 12.6 11.5 9 144.9
AREA= 30 0.175 2.4 12.6 16.5 9 207.9
AREA= 31.5 0.175 2.4 13.23 22 11 291.06
AREA= 22.5 0.175 2.4 9.45 2.3 14.5 21.735
AREA= 22.5 0.175 2.4 9.45 6.8 14.5 64.26
AREA= 25 0.175 2.4 10.5 11.5 14.5 120.75
AREA= 25 0.175 2.4 10.5 16.5 14.5 173.25
AREA= 35 0.175 2.4 14.7 22.5 14.5 330.75
AREA= 11.25 0.175 2.4 4.725 3 18.7 14.175
AREA= 22.5 0.175 2.4 9.45 6.8 19.5 64.26
AREA= 25 0.175 2.4 10.5 11.5 19.5 120.75
AREA= 25 0.175 2.4 10.5 16.5 19.5 173.25
AREA= 35 0.175 2.4 14.7 22.5 19.5 330.75
AREA= 11.25 0.175 2.4 4.725 7.5 23.7 35.4375
AREA= 25 0.175 2.4 10.5 11.5 24.5 120.75
AREA= 25 0.175 2.4 10.5 16.50 24.5 173.25
AREA= 24.5 0.175 2.4 10.29 24.80 24 255.192
228.69

ISO TERMINADO

AREA= 27 0.14 3.78 2.3 3 8.69


AREA= 27 0.14 3.78 6.8 3 25.70
AREA= 10.5 0.14 1.47 20.2 4 29.69
AREA= 27 0.14 3.78 2.3 9 8.69
AREA= 27 0.14 3.78 6.8 9 25.70
AREA= 30 0.14 4.2 11.5 9 48.30
AREA= 30 0.14 4.2 16.5 9 69.30
AREA= 31.5 0.14 4.41 22 11 97.02
AREA= 22.5 0.14 3.15 2.3 14.5 7.25
AREA= 22.5 0.14 3.15 6.8 14.5 21.42
AREA= 25 0.14 3.5 11.5 14.5 40.25
AREA= 25 0.14 3.5 16.5 14.5 57.75
AREA= 35 0.14 4.9 22.5 14.5 110.25
AREA= 11.25 0.14 1.575 3 18.7 4.73
AREA= 22.5 0.14 3.15 6.8 19.5 21.42
AREA= 25 0.14 3.5 11.5 19.5 40.25
AREA= 25 0.14 3.5 16.5 19.5 57.75
AREA= 35 0.14 4.9 22.5 19.5 110.25
AREA= 11.25 0.14 1.575 7.5 23.7 11.81
AREA= 25 0.14 3.5 11.5 24.5 40.25
AREA= 25 0.14 3.5 16.50 24.5 57.75
AREA= 24.5 0.14 3.43 24.80 24 85.06
76.23 7290.89

TOTAL 567.127

X= 12.86
Y= 14.52

CARGA VIVA 3° NIVEL


OFICIANS 0.5 Tn/m2

AREA= 27 0.1 2.7


AREA= 27 0.1 2.7
AREA= 10.5 0.1 1.05
AREA= 27 0.25 6.75
AREA= 27 0.25 6.75
AREA= 30 0.25 7.5
AREA= 30 0.25 7.5 0.5
AREA= 31.5 0.1 3.15
AREA= 22.5 0.25 5.625
AREA= 22.5 0.25 5.625
AREA= 25 0.25 6.25
AREA= 25 0.25 6.25
AREA= 35 0.25 8.75
AREA= 11.25 0.25 2.8125
AREA= 22.5 0.25 5.625
AREA= 25 0.25 6.25
AREA= 25 0.5 12.5
AREA= 35 0.5 17.5
AREA= 11.25 0.5 5.625
AREA= 25 0.5 12.5
AREA= 25 0.5 12.5
AREA= 24.5 0.1 2.45
148.3625
CARGA MUERTA: 4° NIVEL
LONGITUD P.TOTAL
PY (TN-M) ELEMENTO (M) ANCHO(M) ALTURA(M) PESO ESPEC.
(TN/M3) (TN)

0.00 C-1
0.00 C-2
0.00 C-3
0.00 C-4
10.08 C-5 0.5 0.5 2.6 2.4 1.56
10.08 C-6 0.5 0.5 2.6 2.4 1.56
10.08 C-7 0.5 0.5 2.6 2.4 1.56
10.08 C-8 0.5 0.5 2.6 2.4 1.56
10.08 C-9 0.5 0.5 2.6 2.4 1.56
6.41 C-10
20.16 C-11 0.5 0.5 2.6 2.4 1.56
20.16 C-12 0.5 0.5 2.6 2.4 1.56
20.16 C-13 0.5 0.5 2.6 2.4 1.56
20.16 C-14 0.5 0.5 2.6 2.4 1.56
20.16 C-15 0.5 0.5 2.6 2.4 1.56
12.83 C-16 0 0.16 2.6 2.4 0.00
18.17 C-17 0 0.16 2.6 2.4 0.00
28.56 C-18 0.5 0.5 2.6 2.4 1.56
28.56 C-19 0.5 0.5 2.6 2.4 1.56
37.91 C-20 AREA= 0.33 2.6 2.4 2.07
28.56 C-21 0.5 0.5 2.6 2.4 1.56
18.17 C-22 AREA= 0.16 2.6 2.4 0.99
23.51 C-23 AREA= 0.16 2.6 2.4 0.99
49.06 C-24 AREA= 0.33 2.6 2.4 2.07
49.06 C-25 AREA= 0.33 2.6 2.4 2.07
23.51 C-26 AREA= 0.16 2.6 2.4 0.99
25.65 C-27
28.86 C-28 AREA= 0.16 2.6 2.4 0.99
60.21 C-29 AREA= 0.33 2.6 2.4 2.07
28.86 C-30 AREA= 0.16 2.6 2.4 0.99
33.525
VIGAS
0.000 V-1
0.000 V-2
20.412 V-3
20.412 V-4 4.5 0.45 0.70 2.4 3.402
22.680 V-5 5 0.45 0.70 2.4 3.780
22.680 V-6 5 0.45 0.70 2.4 3.780
15.876 V-7
40.824 V-8 4.5 0.45 0.70 2.4 3.402
40.824 V-9 4.5 0.45 0.70 2.4 3.402
45.360 V-10 5 0.45 0.70 2.4 3.780
45.360 V-11 5 0.45 0.70 2.4 3.780
63.504 V-12 7 0.45 0.70 2.4 5.292
57.834 V-13 4.5 0.45 0.70 2.4 3.402
57.834 V-14 4.5 0.45 0.70 2.4 3.402
64.260 V-15 5 0.45 0.70 2.4 3.780
64.260 V-16 5 0.45 0.70 2.4 3.780
89.964 V-17 7 0.45 0.70 2.4 5.292
74.844 V-18 4.5 0.45 0.70 2.4 3.402
154.440 V-19 5 0.65 0.90 2.4 7.020
154.440 V-19´ 5 0.65 0.90 2.4 7.020
116.424 V-20 7 0.45 0.70 2.4 5.292
102.060 V-21 5 0.45 0.70 2.4 3.780
102.060 V-22 5 0.45 0.70 2.4 3.780
13.608 V-23
13.608 V-24
13.608 V-25
13.608 V-26
40.824 V-27 6 0.45 0.70 2.4 4.536
40.824 V-28 6 0.45 0.70 2.4 4.536
40.824 V-29 6 0.45 0.70 2.4 4.536
40.824 V-30 6 0.45 0.70 2.4 4.536
40.824 V-31 6 0.45 0.70 2.4 4.536
54.810 V-32 5 0.45 0.70 2.4 3.780
54.810 V-33 5 0.45 0.70 2.4 3.780
54.810 V-34 5 0.45 0.70 2.4 3.780
54.810 V-35 5 0.45 0.70 2.4 3.780
54.810 V-36 5 0.45 0.70 2.4 3.780
54.810 V-37 5 0.45 0.70 2.4 3.780
73.710 V-38 5 0.45 0.70 2.4 3.780
73.710 V-39 5 0.45 0.70 2.4 3.780
136.890 V-40 5 0.65 0.90 2.4 7.020
73.710 V-41 5 0.45 0.70 2.4 3.780
73.710 V-42 5 0.45 0.70 2.4 3.780
92.610 V-43 5 0.45 0.70 2.4 3.780
171.990 V-44 5 0.65 0.90 2.4 7.020
92.610 V-45 5 0.45 0.70 2.4 3.780
34.776 V-46
15.649 VI-1
46.948 VI-2
98.771 VI-3 6.7 0.45 0.70 2.4 5.065
124.097 VI-4 6.7 0.45 0.70 2.4 5.065
146.513 VI-5
172.778
LOZA MACISA
34.02 L1
34.02 L2
17.64 L3
102.06 L4 AREA= 27 0.175 2.4 11.34
102.06 L5 AREA= 27 0.175 2.4 11.34
113.4 L6 AREA= 30 0.175 2.4 12.6
113.4 L7 AREA= 30 0.175 2.4 12.6
145.53 L8
137.025 L9 AREA= 22.5 0.175 2.4 9.45
137.025 L10 AREA= 22.5 0.175 2.4 9.45
152.25 L11 AREA= 25 0.175 2.4 10.5
152.25 L12 AREA= 25 0.175 2.4 10.5
213.15 L13 AREA= 35 0.175 2.4 14.7
88.3575 L14 AREA= 11.25 0.175 2.4 4.725
184.275 L15 AREA= 22.5 0.175 2.4 9.45
204.75 L16 AREA= 25 0.175 2.4 10.5
204.75 L17 AREA= 25 0.175 2.4 10.5
286.65 L18 AREA= 35 0.175 2.4 14.7
111.9825 L19 AREA= 11.25 0.175 2.4 4.725
257.25 L20 AREA= 25 0.175 2.4 10.5
257.25 L21 AREA= 25 0.175 2.4 10.5
246.96 L22
178.08

PISO TERMINADO

11.34 L1
11.34 L2
5.88 L3
34.02 L4 AREA= 27 0.14 3.78
34.02 L5 AREA= 27 0.14 3.78
37.8 L6 AREA= 30 0.14 4.2
37.8 L7 AREA= 30 0.14 4.2
48.51 L8 0.14
45.675 L9 AREA= 22.5 0.14 3.15
45.675 L10 AREA= 22.5 0.14 3.15
50.75 L11 AREA= 25 0.14 3.5
50.75 L12 AREA= 25 0.14 3.5
71.05 L13 AREA= 35 0.14 4.9
29.4525 L14 AREA= 11.25 0.14 1.575
61.425 L15 AREA= 22.5 0.14 3.15
68.25 L16 AREA= 25 0.14 3.5
68.25 L17 AREA= 25 0.14 3.5
95.55 L18 AREA= 35 0.14 4.9
37.3275 L19 AREA= 11.25 0.14 1.575
85.75 L20 AREA= 25 0.14 3.5
85.75 L21 AREA= 25 0.14 3.5
82.32 L22
8233.28 55.58

TOTAL 439.963

X= 12.43
Y= 16.27

CARGA VIVA 4° NIVEL


S/C
LOSA 1 OFICINAS 0.25 Tn/m2

L1
L2
L3
L4 AREA= 27 0.25 6.75
L5 AREA= 27 0.25 6.75
L6 AREA= 30 0.25 7.5
L7 AREA= 30 0.25 7.5
L8
L9 AREA= 22.5 0.25 5.625
L10 AREA= 22.5 0.25 5.625
L11 AREA= 25 0.25 6.25
L12 AREA= 25 0.25 6.25
L13 AREA= 35 0.25 8.75
L14 AREA= 11.25 0.25 2.8125
L15 AREA= 22.5 0.25 5.625
L16 AREA= 25 0.25 6.25
L17 AREA= 25 0.25 6.25
L18 AREA= 35 0.25 8.75
L19 AREA= 11.25 0.25 2.8125
L20 AREA= 25 0.25 6.25
L21 AREA= 25 0.25 6.25
L22
106
TA: 4° NIVEL CARGA
LONGITUD
X(M) Y(M) PX (TN-M) PY (TN-M) ELEMENTO (M) ANCHO(M)

C-1
C-2
C-3
C-4
0 6 0.00 9.36 C-5 0.5 0.5
4.5 6 7.02 9.36 C-6 0.5 0.5
9 6 14.04 9.36 C-7 0.5 0.5
14 6 21.84 9.36 C-8 0.5 0.5
19 6 29.64 9.36 C-9 0.5 0.5
C-10
0 12 0.00 18.72 C-11 0.5 0.5
4.5 12 7.02 18.72 C-12 0.5 0.5
9 12 14.04 18.72 C-13 0.5 0.5
14 12 21.84 18.72 C-14 0.5 0.5
19 12 29.64 18.72 C-15 0.5 0.5
26 12 0.00 0.00 C-16 0 0.16
0 17 0.00 0.00 C-17 0 0.16
4.5 17 7.02 26.52 C-18 0.5 0.5
9 17 14.04 26.52 C-19 0.5 0.5
14 17 28.99 35.20 C-20 AREA= 0.33
19 17 29.64 26.52 C-21 0.5 0.5
26 17 25.80 16.87 C-22 AREA= 0.16
4.5 22 4.47 21.83 C-23 AREA= 0.16
9 22 18.64 45.55 C-24 AREA= 0.33
19 22 39.34 45.55 C-25 AREA= 0.33
26 22 25.80 21.83 C-26 AREA= 0.16
C-27
9 27 8.93 26.80 C-28 AREA= 0.16
14 27 28.99 55.91 C-29 AREA= 0.33
19 27 18.86 26.80 C-30 AREA= 0.16

VIGAS
V-1
V-2
V-3
6.75 6 22.964 20.412 V-4 4.5 0.45
11.5 6 43.470 22.680 V-5 5 0.45
16.5 6 62.370 22.680 V-6 5 0.45
V-7
2.25 12 7.655 40.824 V-8 4.5 0.45
6.75 12 22.964 40.824 V-9 4.5 0.45
11.5 12 43.470 45.360 V-10 5 0.45
16.5 12 62.370 45.360 V-11 5 0.45
22.5 12 119.070 63.504 V-12 7 0.45
2.25 17 7.655 57.834 V-13 4.5 0.45
6.75 17 22.964 57.834 V-14 4.5 0.45
11.5 17 43.470 64.260 V-15 5 0.45
16.5 17 62.370 64.260 V-16 5 0.45
22.5 17 119.070 89.964 V-17 7 0.45
6.75 22 22.964 74.844 V-18 4.5 0.45
11.5 22 80.730 154.440 V-19 5 0.65
16.5 22 115.830 154.440 V-19´ 5 0.65
22.5 22 119.070 116.424 V-20 7 0.45
11.5 27 43.470 102.060 V-21 5 0.45
16.5 27 62.370 102.060 V-22 5 0.45
V-23
V-24
V-25
V-26
0 9 0.000 40.824 V-27 6 0.45
4.5 9 20.412 40.824 V-28 6 0.45
9 9 40.824 40.824 V-29 6 0.45
14 9 63.504 40.824 V-30 6 0.45
19 9 86.184 40.824 V-31 6 0.45
0 14.5 0.000 54.810 V-32 5 0.45
4.5 14.5 17.010 54.810 V-33 5 0.45
9 14.5 34.020 54.810 V-34 5 0.45
14 14.5 52.920 54.810 V-35 5 0.45
19 14.5 71.820 54.810 V-36 5 0.45
26 14.5 98.280 54.810 V-37 5 0.45
4.5 19.5 17.010 73.710 V-38 5 0.45
9 19.5 34.020 73.710 V-39 5 0.45
14 19.5 98.280 136.890 V-40 5 0.65
19 19.5 71.820 73.710 V-41 5 0.45
26 19.5 98.280 73.710 V-42 5 0.45
9 24.5 34.020 92.610 V-43 5 0.45
14 24.5 98.280 171.990 V-44 5 0.65
19 24.5 71.820 92.610 V-45 5 0.45
V-46
VI-1
VI-2
2.3 19.5 11.650 98.771 VI-3 6.7 0.45
6.8 24.5 34.443 124.097 VI-4 6.7 0.45
VI-5

LOZA MACISA TS=0.15 ULTIMO PISO


L1
L2
L3
2.3 9 26.082 102.06 L4 AREA= 27
6.8 9 77.112 102.06 L5 AREA= 27
11.5 9 144.9 113.4 L6 AREA= 30
16.5 9 207.9 113.4 L7 AREA= 30
L8
2.3 14.5 21.735 137.025 L9 AREA= 22.5
6.8 14.5 64.26 137.025 L10 AREA= 22.5
11.5 14.5 120.75 152.25 L11 AREA= 25
16.5 14.5 173.25 152.25 L12 AREA= 25
22.5 14.5 330.75 213.15 L13 AREA= 35
3 18.7 14.175 88.3575 L14 AREA= 11.25
6.8 19.5 64.26 184.275 L15 AREA= 22.5
11.5 19.5 120.75 204.75 L16 AREA= 25
16.5 19.5 173.25 204.75 L17 AREA= 25
22.5 19.5 330.75 286.65 L18 AREA= 35
7.5 23.7 35.4375 111.9825 L19 AREA= 11.25
11.5 24.5 120.75 257.25 L20 AREA= 25
16.50 24.5 173.25 257.25 L21 AREA= 25
L22

PISO TERMINADO

L1
L2
L3
2.3 9 8.694 34.02 L4 AREA= 27
6.8 9 25.704 34.02 L5 AREA= 27
11.5 9 48.3 37.8 L6 AREA= 30
16.5 9 69.3 37.8 L7 AREA= 30
L8
2.3 14.5 7.245 45.675 L9 AREA= 22.5
6.8 14.5 21.42 45.675 L10 AREA= 22.5
11.5 14.5 40.25 50.75 L11 AREA= 25
16.5 14.5 57.75 50.75 L12 AREA= 25
22.5 14.5 110.25 71.05 L13 AREA= 35
3 18.7 4.725 29.4525 L14 AREA= 11.25
6.8 19.5 21.42 61.425 L15 AREA= 22.5
11.5 19.5 40.25 68.25 L16 AREA= 25
16.5 19.5 57.75 68.25 L17 AREA= 25
22.5 19.5 110.25 95.55 L18 AREA= 35
7.5 23.7 11.8125 37.3275 L19 AREA= 11.25
11.5 24.5 40.25 85.75 L20 AREA= 25
16.50 24.5 57.75 85.75 L21 AREA= 25
L22
5466.97 7158.34

4° NIVEL CAR
S/C
LOSA 1 AZOTEA

L1
L2
L3
L4 AREA= 27
L5 AREA= 27
L6 AREA= 30
L7 AREA= 30
L8
L9 AREA= 22.5
L10 AREA= 22.5
L11 AREA= 25
L12 AREA= 25
L13 AREA= 35
L14 AREA= 11.25
L15 AREA= 22.5
L16 AREA= 25
L17 AREA= 25
L18 AREA= 35
L19 AREA= 11.25
L20 AREA= 25
L21 AREA= 25
L22
CARGA MUERTA: 5° NIVEL
P.TOTAL
ALTURA(M) PESO ESPEC.
(TN/M3) (TN) X(M) Y(M) PX (TN-M) PY (TN-M)

1.3 2.4 0.78 0 6 0.00 4.68


1.3 2.4 0.78 4.5 6 3.51 4.68
1.3 2.4 0.78 9 6 7.02 4.68
1.3 2.4 0.78 14 6 10.92 4.68
1.3 2.4 0.78 19 6 14.82 4.68

1.3 2.4 0.78 0 12 0.00 9.36


1.3 2.4 0.78 4.5 12 3.51 9.36
1.3 2.4 0.78 9 12 7.02 9.36
1.3 2.4 0.78 14 12 10.92 9.36
1.3 2.4 0.78 19 12 14.82 9.36
1.3 2.4 0.00 26 12 0.00 0.00
1.3 2.4 0.00 0 17 0.00 0.00
1.3 2.4 0.78 4.5 17 3.51 13.26
1.3 2.4 0.78 9 17 7.02 13.26
1.3 2.4 1.04 14 17 14.49 17.60
1.3 2.4 0.78 19 17 14.82 13.26
1.3 2.4 0.50 26 17 12.90 8.44
1.3 2.4 0.50 4.5 22 2.23 10.92
1.3 2.4 1.04 9 22 9.32 22.78
1.3 2.4 1.04 19 22 19.67 22.78
1.3 2.4 0.50 26 22 12.90 10.92

1.3 2.4 0.50 9 27 4.47 13.40


1.3 2.4 1.04 14 27 14.49 27.95
1.3 2.4 0.50 19 27 9.43 13.40
16.762

0.70 2.4 3.402 6.75 6 22.964 20.412


0.70 2.4 3.780 11.5 6 43.470 22.680
0.70 2.4 3.780 16.5 6 62.370 22.680

0.70 2.4 3.402 2.25 12 7.655 40.824


0.70 2.4 3.402 6.75 12 22.964 40.824
0.70 2.4 3.780 11.5 12 43.470 45.360
0.70 2.4 3.780 16.5 12 62.370 45.360
0.70 2.4 5.292 22.5 12 119.070 63.504
0.70 2.4 3.402 2.25 17 7.655 57.834
0.70 2.4 3.402 6.75 17 22.964 57.834
0.70 2.4 3.780 11.5 17 43.470 64.260
0.70 2.4 3.780 16.5 17 62.370 64.260
0.70 2.4 5.292 22.5 17 119.070 89.964
0.70 2.4 3.402 6.75 22 22.964 74.844
0.90 2.4 7.020 11.5 22 80.730 154.440
0.90 2.4 7.020 16.5 22 115.830 154.440
0.70 2.4 5.292 22.5 22 119.070 116.424
0.70 2.4 3.780 11.5 27 43.470 102.060
0.70 2.4 3.780 16.5 27 62.370 102.060
0.70 2.4 4.536 0 9 0.000 40.824
0.70 2.4 4.536 4.5 9 20.412 40.824
0.70 2.4 4.536 9 9 40.824 40.824
0.70 2.4 4.536 14 9 63.504 40.824
0.70 2.4 4.536 19 9 86.184 40.824
0.70 2.4 3.780 0 14.5 0.000 54.810
0.70 2.4 3.780 4.5 14.5 17.010 54.810
0.70 2.4 3.780 9 14.5 34.020 54.810
0.70 2.4 3.780 14 14.5 52.920 54.810
0.70 2.4 3.780 19 14.5 71.820 54.810
0.70 2.4 3.780 26 14.5 98.280 54.810
0.70 2.4 3.780 4.5 19.5 17.010 73.710
0.70 2.4 3.780 9 19.5 34.020 73.710
0.90 2.4 7.020 14 19.5 98.280 136.890
0.70 2.4 3.780 19 19.5 71.820 73.710
0.70 2.4 3.780 26 19.5 98.280 73.710
0.70 2.4 3.780 9 24.5 34.020 92.610
0.90 2.4 7.020 14 24.5 98.280 171.990
0.70 2.4 3.780 19 24.5 71.820 92.610

0.70 2.4 5.065 2.3 19.5 11.650 98.771


0.70 2.4 5.065 6.8 24.5 34.443 124.097

172.778
S=0.15 ULTIMO PISO

0.15 2.4 9.72 2.3 9 22.356 87.48


0.15 2.4 9.72 6.8 9 66.096 87.48
0.15 2.4 10.8 11.5 9 124.2 97.2
0.15 2.4 10.8 16.5 9 178.2 97.2

0.15 2.4 8.1 2.3 14.5 18.63 117.45


0.15 2.4 8.1 6.8 14.5 55.08 117.45
0.15 2.4 9 11.5 14.5 103.5 130.5
0.15 2.4 9 16.5 14.5 148.5 130.5
0.15 2.4 12.6 22.5 14.5 283.5 182.7
0.15 2.4 4.05 3 18.7 12.15 75.735
0.15 2.4 8.1 6.8 19.5 55.08 157.95
0.15 2.4 9 11.5 19.5 103.5 175.5
0.15 2.4 9 16.5 19.5 148.5 175.5
0.15 2.4 12.6 22.5 19.5 283.5 245.7
0.15 2.4 4.05 7.5 23.7 30.375 95.985
0.15 2.4 9 11.5 24.5 103.5 220.5
0.15 2.4 9 16.50 24.5 148.5 220.5

152.64

0.1 2.7 2.3 9 6.21 24.3


0.1 2.7 6.8 9 18.36 24.3
0.1 3 11.5 9 34.5 27
0.1 3 16.5 9 49.5 27
0.1
0.1 2.25 2.3 14.5 5.175 32.625
0.1 2.25 6.8 14.5 15.3 32.625
0.1 2.5 11.5 14.5 28.75 36.25
0.1 2.5 16.5 14.5 41.25 36.25
0.1 3.5 22.5 14.5 78.75 50.75
0.1 1.125 3 18.7 3.375 21.0375
0.1 2.25 6.8 19.5 15.3 43.875
0.1 2.5 11.5 19.5 28.75 48.75
0.1 2.5 16.5 19.5 41.25 48.75
0.1 3.5 22.5 19.5 78.75 68.25
0.1 1.125 7.5 23.7 8.4375 26.6625
0.1 2.5 11.5 24.5 28.75 61.25
0.1 2.5 16.50 24.5 41.25 61.25

39.7 4745.51 6229.26

TOTAL 381.881

X= 12.43
Y= 16.31

CARGA VIVA 5° NIVEL


0.1 Tn/m2

0.1 2.7
0.1 2.7
0.1 3
0.1 3
0
0.1 2.25
0.1 2.25
0.1 2.5
0.1 2.5
0.1 3.5
0.1 1.125
0.1 2.25
0.1 2.5
0.1 2.5
0.1 3.5
0.1 1.125
0.1 2.5
0.1 2.5

42.4
Departamento de lambayeque-provincia de chiclayo -capital Nueva arica -zona 4
CORTANTE VASAL edificaciones escenciales-locales municipales-1.5

Z .U .C .S
V  *P
R
CATEGORIA A

donde .
Z= 0.45 FACTOR ZONA ( TABLA N° 01 )
U= 1.5 FACTOR USO (TABLA N° 05 )
Cx= 2.5 FACTOR DE AMPLIFICACION SISMICA
Cy= 2.5 FACTOR DE AMPLIFICACION SISMICA
S= 1.05 PARAMETROS DE SITIO ( TABLA N° 03 )
Rx= 6.48 COHEFICIENTES DE REDUCCION ( TABLA N° 07 )
Ry= 6.48 COHEFICIENTES DE REDUCCION ( TABLA N° 07 )

Verificando C/R>=0.125
C/RX= 0.386 OK!
C/Ry= 0.386 OK

Factor de amplificación Sismica Para el eje x PERIODO FUNDAMENTAL

 Tp  hm
C  2.5   2.5 T 
T  Ct

Tp = 0.6 TIPO S2 DE TABLA Nº2 CT =


hm =
Cond. 1 0.446 < 0.6
Cx = 2.5 Usar
T=

Factor de amplificación Sismica Para el eje y PERIODO FUNDAMENTAL

 Tp  hm
C  2.5
 T 
  2 .5 T 
Ct
Tp = 0.6 TIPO S2 DE TABLA Nº2 CT =
hm =
Cond. 1 0.446 < 0.6
Cx = 2.5 Usar
T=

REEMPLAZANDO EN LA ECUACION SE OBTIENE

Vx= 0.273 ton


Vy= 0.273 ton

Z .U .C.S
D *G
R
DISEÑO DE SISMO ESTATICO

ZONAS CON PROBLEMAS DE ASENTAMIENTO Y


AMPLIFICACIÓN DE ONDAS SÍSMICAS EN LA CIUDAD
DE LAMBAYEQUE En la Ciudad de Lambayeque, no
podría producirse este efecto sísmico, ya que no
hiclayo -capital Nueva arica -zona 4 cuenta con suelos de baja capacidad portante,
consistencia blanda a muy blanda y niveles freáticos
próximos a las cimentaciones, factores que
incrementarían la probabilidad de ocurrencia de
éste efecto sísmico.S2

R=Ro*Ip*Ie

Para X Para Y
Ro= 8 *APORTICADO Ro= 8 *APORTICADO
IP= 0.9 *ESCOGER EL MENOR VA IP= 0.9
Ie= 0.9 Ie= 0.9
verificacion esquinas entrantes verificacion esquinas entrantes
lt= 19 lt= 20
20% 3.8 4
esquina entrant 5 esquina entrant 4
Rx= 6.48 Ry= 6.48

NDAMENTAL

35 Periodo Fundamental
15.6 ALTURA TOTAL DEL EDIFICIO EN METROS

0.445714286 VER PARA K

NDAMENTAL

hm

Ct
35 Periodo Fundamental
15.6 ALTURA TOTAL DEL EDIFICIO EN METROS

0.445714286
ATICO