Académique Documents
Professionnel Documents
Culture Documents
CONSTRUCTION PRACTICE
SOIL CHARACTER
PILE
FOOTING
COLUMN / BEAM / SLAB
BRICK WALL
PLASTER
FINISHING WORK- TILES, MARBEL FITTING
SOIL CHARACTER IN FIELD
SOIL CHARACTER IN FIELD
SOIL CHARACTER IN FIELD
PILE
PILE
PILE
PILE
PILE
PILE
PILE TEST
PILE TEST
FOOTING
FOOTING
FOOTING
BRICK WORK
BRICK WORK
BRICK WORK
BRICK WORK
BRICK WORK
BRICK WORK
BRICK WORK
BRICK WORK
BEAM RE-
RE-BAR
BEAM RE-
RE-BAR
COLUMN RE-
RE-BAR
COLUMN TIES
COLUMN RE-
RE-BAR AND TIES
COLUMN RE-
RE-BAR
EXTERIOR COLUMN RE-
RE-BAR
SLAB RE-
RE-BAR
SLAB SAGING
CONSTRUCTION PRACTICE
Earthquake Resistance (IS:13920-
(IS:13920-1993)
Beams
(i) Minimum reinforcement - p > 0.24*sqrt (fck) / fy
(ii) Maximum reinforcement - p < 0.025 or less than 2.5 %
(iii) At least two bars should be provided continuously both at top and
bottom.
(iv) The positive moment of resistance at the face of a joint should not
be less than one-
one-half of the negative moment of resistance provided
at that face of the joint.
(v) Neither the negative nor the positive moment of resistance at any
section along the member length should be less than one- one-fourth of the
maximum moment of resistance provided at the face of either joint.
(vi) When a beam frames into a column, both the top and bottom bars
of the beam should be anchored into the column so as to develop
their full strength in bond beyond the section of the beam at the face
of the column, that is, the anchor length should be equal to Ld.
CONSTRUCTION PRACTICE
Earthquake Resistance (IS:13920-
(IS:13920-1993)
Shear Stirrups
(vii) The spacing of vertical shear stirrups should not exceed 0.25 d in a
length equal to 2d near each end of the beam and 0.5d in the remaining
length of the beam.
(viii) The hook in shear stirrup should be at 135o and the minimum length of
the hook should be 10 times the bar dia.
Columns
(i) Special confining steel must be provided above and below the beam
connections in a length which is largest of the following :
- 1/6 th of the clear height of the column
- larger lateral dimension of the column, and
- 450 mm.=18”
(ii) The pitch of the lateral ties should not exceed 1/4th of the minimum
member dimension nor 100 mm.
(iii) Helical ties are preferred over lateral ties in a column.
CONSTRUCTION PRACTICE
Earthquake Resistance (IS:13920-
(IS:13920-1993)
IN RESIDENTIAL BUILDINGS
In normal beams up to about 4 m span, 4 to 6 no.12 mm to 16 mm dia. high
strength deformed bars should normally be sufficient depending upon the
loads.
In normal beams up to about 4 m span, shear stirrups of 8 mm dia.-
dia.- 2 legged
@ 250 mm c/c should be sufficient.
In normal slabs up to about 4 m x 4 m span, 8 mm high strength deformed
bars @ 100 mm c/c should be sufficient in 100 mm thick slabs.
In lintels up to about 3 m span over doors or windows, 3-
3-10 mm bars should
be sufficient.
In sun shades up to about 45 cm cantilever span, 8 mm bars @ 150 mm c/c
should be sufficient. These bars must be anchored into the lintel by at least 60
cm length.
In normal columns,
columns, 12 mm bars should be sufficient. The exact number will
depend upon the load.
The following drawings illustrate some commonly encountered situations for
detailing of reinforcement.
CONSTRUCTION PRACTICE
DETAILING OF REINFORCEMENT
The quantity of reinforcement in various members varies as follows :
Singly reinforced beams - 0.20 % minimum and 1% maximum of
the area of cross-
cross-section of the beam
Doubly reinforced beams - 0.20% minimum and 4% maximum of
the area of cross-
cross-section of the beam
Slabs - 0.12% minimum of the area of cross-
cross-section of the slab
Columns - 0.8% minimum and 6% maximum of the area of cross- cross-
section of the column
ANCHORAGE
The anchorage length of a bar in tension = 60 times the dia of bar
The anchorage length of a bar in compression = 45 times the dia of
bar
Hooks - Sometimes it becomes necessary to provide hooks or bends
in high strength deformed bars whenever straight length of a bar is not
available. The hooks may be at 90 degrees or 180 degrees. The
minimum length of hooks in main reinforcing bars is 4 times the dia of
bar after bending the bar.
Hooks are also very important in shear stirrups.
stirrups. The minimum length
of hooks in shear stirrups is 6 times the dia of bar after bending the
bar at 135 degrees.
Hooks are also very important in column ties. The minimum length of
hooks in ties is 6 times the dia of bar after bending the bar at 135
degrees.
CONSTRUCTION PRACTICE
PLACING OF REINFORCEMENT
Simple supported beams - The main reinforcement bars must be placed
at the bottom face of the beam at a clear cover of 25 mm.
Cantilever beams - The main reinforcement bars must be placed at the
top face of the beam at a clear cover of 25 mm.
Simple supported slabs - The main reinforcement bars must be placed
at the bottom face of the slab at a clear cover of 20 mm.
Cantilever slabs - The main reinforcement bars must be placed at the
top face of the slab at a clear cover of 20 mm.
Simple supported slab with projection - It is a very common sight in
most buildings. The main reinforcement in the simple supported span is
placed at the bottom, while that in the cantilever portion is placed near
the top face. The top reinforcement must be taken inside the main span
up to a minimum distance of 60 times the dia. of the bars.
Clear Cover to Reinforcement
The amount of clear cover depends upon the exposure conditions in
which concrete is to be used as shown in the following table. The
purpose is to avoid corrosion of steel bars and therefore, cracking of
concrete.
CONSTRUCTION PRACTICE
The amount of clear cover depends upon the exposure conditions in
which concrete is to be used as shown in the following table. The
purpose is to avoid corrosion of steel bars and therefore, cracking of
concrete.
NEGLIGENCE
CONSTRUCTION PRACTICE
TIME MANAGEMENT - Time is Money - SAVE IT Plan the work for
the next week very carefully.
Don't buy more cement than is required in the next few days.
However, do buy steel in bulk and save money.
REMEMBER the work may stop for want of a small item and the
entire labor may be a waste for the day.