Wapda 630kva-------504kw Orient rental generator 635kva-------508kw Generator house rental generator 200kva------160kw Plant total load 625kva-------500kw Previously we cannot run our whole plant on wapda 630kva at same time so we modify our system to run our 200kva generator and wapda together to meet our plant energy requirement.
Plant new scenario/modification:
Modification in LT01 panel split the power MCCB circuit breakers to 200kva generator to run our whole plant at same time. this modification specially for mafroda kinnow process for this process we did not need new generator and we can process our mafroda plant within our resources. Below is the process of modification. Disconnect Q12 in main LT01 bus bar Switch off mafroda breaker from busbar and tag out. Q09 Use spare breaker Q12 as mafroda supply coupler in LT01 LT panel. Make new power loops between Q12 to Q11 for power incoming. Power loop between Q12 with Q09 for power outgoing.
Benefits of this system:
We can run our whole plant at once on wapda and 200kva separately. Extra change over cost saving. Generator capacity enhancement cost saving. System reliability. Mafroda Smooth operation. Reduce production downtime.