Académique Documents
Professionnel Documents
Culture Documents
Structure of Presentation:
• Background
• Key Initiatives
• Results
2
Delhi Vidyut Board in the Year - 2002:
60
50
40
30
20
10
0
1983-84
1985-86
1987-88
1989-90
1991-92
1993-94
1995-96
1997-98
1999-00
2001-02
4
Key Parameters - In Year 2002
Geographic Description:
BSES
Yamuna
BSES NDMC
Rajdhani MES
6
NDPL Profile:
Particulars As on Jul’2002 As on date
Turnover Rs. 1,095 Cr Rs. 2,759 Cr (FY 0910)
Peak Load 850 MW 1,313 MW (Jul’10)
Energy Requirement 5,237 MU 6,911 MU
Total Registered Consumers 0.8 Million 1.21 Million
Number of Employees 5,400 3,950
Area of Distribution 510 Sq Kms 510 Sq Kms
Population Serviced (approx) 4.2 Million 4.8 Million
Structure of Presentation:
• Background
• Key Initiatives
• Results
8
Strategic Roadmap:
Strategic Decision:
• Decentralization of O & M activities / function
• Energy Accounting
10
Structure of Presentation:
• Background
• Key Initiatives
• Results
11
12
Components of AT & C Losses:
13
14
Loss Reduction Strategy – Technical Solutions
High Loss
Implemented in more
High HVDS than 250 areas, more
Resistance under implementation.
Areas
High Loss
Approx. 2,500 Kms of
Low LT ABC LT ABC laid, more
Resistance under implementation
Areas
Electronic
Metering Schemes implemented
Meters, AMR,
Initiatives successfully, more
Pre-Paid
under implementation
Metering
15
16
Energy Accounting – Flow Chart
Tier 1: Transmission level 66 or 33 KV STU to DISCOM
M By STU
66/33/11 KV
11
KV FEEDERS TO ZONES
M M
Feeder Meter
At Consumer Premises
With HT Load 11KV/415 V DT
M
Tier 3 : Distribution level For Energy Accounting
At Consumer
M M Premises
17
18
Business Process Re-engineering (BPR)
Consumers
CCG
RAG
Policy Regulatory Bench Data Revenue Infrastructure
Advocacy Compliance Marking Analysis Protection Support
19
20
Automatic Meter Reading (AMR):
I. METERING METER
GSM-MODEM GSM-Network
II. COMMUNICATION
PSTN-MODEM
PSTN-Network
S/W
USERS
DEBS
LAN
III. BACK OFFICE DB
21
22
Automation Roadmap: Journey so far …
• GIS - Completed
• GSAS - Completed
• SCADA - In Operation
23
24
Technical / Process Related Initiatives:
25
26
Initiatives in association with Govt.:
27
28
Initiatives / Programmes related to Society:
New Initiatives:
30
Structure of Presentation:
• Background
• Key Initiatives
• Results
31
32
Loss Reduction (Trend):
Parameters FY 02-03 FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 FY 09-10
Energy Input (MU) 5,237 5,552 5,549 5,695 5,986 6,281 6,327 6,911
Units Billed (MU) 2,813 3,196 3,667 4,154 4,351 4,975 5,225 5,816
Amt. Billed
1,126 1,272 1,565 1,883 2,032 2,323 2,468 2,722
(Rs Cr)
AT&C Loss
47.79 44.86 33.79 26.52 23.72 18.38 15 .04 14.47
(%)
Billing Efficiency
53.72 57.56 66.08 72.95 72.68 79.21 82.58 84.16
(%)
Collection
97.18 95.78 100.2 100.73 104.94 103.04 102.87 101.34
Efficiency (%)
33
66 kV KM 176 309 76
Transmission
33 kV KM 156 318 103
Lines
11 kV KM 2,245 3,555 58
Total (KM) KM 2,578 4,182 62
34
Results – Few other parameters
OPERATIONAL:
Capital Investment (Rs Crores) 1,210 Add. 2,500
(Valuation)
Transformer Failures w.r.t Installed Capacity (%) 11 1.2
Percentage Share in Load Shedding (In Delhi) 40 <1
COMMERCIAL:
Average Days for New Connection Energization (Days) 51.8 8.0
Number of Electronic Meters - > 1.2 Million
% Provisional Billing 22.5 <1
DT – Wise Energy Auditing (%) - 100
Special Courts (Nos) - 2
AT&C Losses (%) 53 < 14.0
35
Structure of Presentation:
• Background
• Key Initiatives
• Results
36
Awards & Recognitions - To name a few
40
Awards & Recognitions - To name a few
41
42
Structure of Presentation:
• Background
• Key Initiatives
• Results
43
44
Issues / Areas requiring attention of Regulator :
• Regulatory Asset:
a) Against economic principles
b) Sends improper economic signal
c) Unnecessary burden of carrying cost
d) Deferment of problem, not a solution
e) Hence, use of this facility should be minimum and should not be
repetitive
45
46
Harmonization of regulations in power sector :
• Fuel price variance:
a) Immediate pass through for Generator
b) Annual / Periodic pass through for DISCOM
• Large disparity on treatment of various parameters:
a) O & M Costs (Normative Vs Actual)
b) Consolidated O & M Costs
c) Separate allowance for employee / A & G / R & M Costs
d) R & M Costs: Yearly inflation / % of Gross Fixed Asset
e) Employee and A & G Costs: Yearly inflation / Yearly inflation
together with increased growth (MU / Consumers)
47
48
Harmonization of regulations in power sector :
• Large disparity on treatment of various parameters:
h) Start Date for depreciation:
- From the year of Capitalization
- From the succeeding year after capitalization
i) Provisioning of bad debts:
- No provision
- Based on actual bad debts
- As a % of approved ARR
j) Return:
- Return on Equity
- Return on Capital
49
Thank You
50