Vous êtes sur la page 1sur 2

MONITORING PEMANCANGAN

TOWER A,B,E DAN F REVITALISASI RUSUN PENJARINGAN

BULAN SEPTEMBER 2020

SPESIFIKASI Pancang Indikator Pile 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

B. REALISASI ( pcs ) m'

B.1 TOWER A 257 2570 REALISASI PEMANCANGAN RENCANA PEMANCANGAN

1. Pile Cap 1 74 740

-Tipe 1 (12 D 19 ) 17 170 1 5 7 4

-Tipe 2 (8 D 16 ) 12 120 0 2 3 5 2

-Tipe 3 (4 D 16 ) 45 450 4 8 10 10 10 3

2. Pile Cap 2 41 410

-Tipe 2 (8 D 16 ) 10 100 0 4 5 1

-Tipe 3 (4 D 16 ) 31 310 0 4 5 9 10 3

3. Pile Cap 3 36 360

-Tipe 2 (8 D 16 ) 8 80 1 2 4 1

-Tipe 3 (4 D 16 ) 28 280 0 1 5 8 10 4

4. Pile Cap 4 15 150

-Tipe 2 (8 D 16 ) 4 40 1 1 2

-Tipe 3 (4 D 16 ) 11 110 0 3 5 3

5. Pile Cap 5 86 860

-Tipe 1 (12 D 19 ) 33 330 1 2 10 11 6 3

-Tipe 2 (8 D 16 ) 14 140 0 5 4 5

-Tipe 3 (4 D 16 ) 39 390 1 10 1 10 14 3

6. Pile Cap 6 5 50

-Tipe 3 (4 D 16 ) 5 50 1 4
MONITORING PEMANCANGAN
TOWER A,B,E DAN F REVITALISASI RUSUN PENJARINGAN

BULAN SEPTEMBER 2020

SPESIFIKASI Pancang Indikator Pile 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

B.2 TOWER B 257 2570

1. Pile Cap 1 74 740

-Tipe 1 (12 D 19 ) 17 170 0 7 5 5

-Tipe 2 (8 D 16 ) 12 120 0 5 5 2

-Tipe 3 (4 D 16 ) 45 450 1 8 10 10 10 6

2. Pile Cap 2 41 410

-Tipe 2 (8 D 16 ) 10 100 0 4 5 1

-Tipe 3 (4 D 16 ) 31 310 1 4 5 9 10 2

3. Pile Cap 3 36 360

-Tipe 2 (8 D 16 ) 8 80 0 4 2 2

-Tipe 3 (4 D 16 ) 28 280 1 8 8 10 1

4. Pile Cap 4 15 150

-Tipe 2 (8 D 16 ) 4 40 0 2 2

-Tipe 3 (4 D 16 ) 11 110 0 2 9

5. Pile Cap 5 86 860

-Tipe 1 (12 D 19 ) 33 330 5 6 5 12 2 3

-Tipe 2 (8 D 16 ) 14 140 0 5 3 6

-Tipe 3 (4 D 16 ) 39 390 0 11 1 3 15 9

6. Pile Cap 6 5 50 0

-Tipe 3 (4 D 16 ) 5 50 0 5

TOTAL 1028 10280 18 8 21 29 15 23 13 9 10 29 24 29 19 20 22 19 20 20 20 19 19 20 20 20 20 13 15

KOMULATIF 18 8 29 58 73 96 109 118 128 157 181 210 229 249 271 290 310 330 350 369 388 408 428 448 468 481 514