FORM 1
(I) Basic Information
Name of the Project: A green field 2200 TPD Ammonia and 3850 TPD Urea plant
along with CPP, Panagarh, Burdwan Dist, West Bengal by
Matix Fertilizers and Chemicals Limited.
Location/site Proposed Fertilizer Plant based on CBM is located at
alternatives under Panagarh, 18Kms ENE of Durgapur in Burdwan district of
consideration: West Bengal on the northern bank of river Damodar within
160 kms WNW of Kolkata.
The coordinates of the Apex Points of the project site is given
below:
Point Latitude Longitude
0 0
1 23 26’53.90”N 87 28’40.08”E
2 23°26'30.80"N 87°28'37.30"E
3 23°26'11.36"N 87°29'58.76"E
4 23°26'24.58"N 87°29'41.09"E
5 23°26'46.97"N 87°29'49.95"E
6 23°26'37.94"N 87°29'12.96"E
Size of the Project: The proposed complex shall have, 2200TPD Ammonia and
3850TPD single stream Urea
Expected cost of the Approx INR 5000Crores
project:
Contact Information: Mr. P.R Dhariwal
CEO & MD,
Matix Group
Plot No. A-16 & 17,
Part - B, Cross Lane,
MIDC, Anderi (East),
Mumbai - 400 093
Tel. +91-22-66712046
Screening Category: Category A, Serial No. 5 (a) of EIA Notification, 2006
(II) Activity
1. Construction, operation or decommissioning of the Project involving actions, which
will cause physical changes in the locality (topography, land use, changes in water
bodies, etc.)
Yes/ Details thereof (with approximate quantities
S.No. Information/Checklist confirmation No /rates, wherever possible) with source of
information data
1.1 Permanent or temporary change in land Yes Proposed fertilizer plant will be located in an
use, land cover or topography including area of ~ 600acres. Present Land is an
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
July 2009 2
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
July 2009 3
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or in short supply)
2.1 Land especially undeveloped or Yes Proposed fertilizer plant will require ~
agricultural land (ha) 600acres of land which is presently an
agriculture land, the land belongs to farmers
and is under the process of acquisition by West
Bengal Industrial development Corporation for
industrial park of 4000acres approxy.
2.2 Water (expected source & competing Yes Water will be pumped from Damodar river.
users) unit: KLD 1413 m3/hr
2.3 Minerals (MT) No Not Anticipated
2.4 Construction material– aggregates, Yes Construction materials like stone, aggregates,
stone, sand, soil (expected source – steel and cement will be sourced through local
MT) dealers.
2.5 Forests and timber (source – MT) No Not anticipated
2.6 Energy including electricity and fuels Yes Grid power 5MVA from WBSEB shall be
(source, competing users) Unit: fuel taken as construction power.
(MT), energy (MW) 33 MW Captive power plant is proposed.
Emergency Power will be provide as back up
for safe shut down of plant
2.7 Any other natural resources (use Yes CBM gas only
appropriate standard units)
3. Use, storage, transport, handling or production of substances or materials, which could be
harmful to human health or the environment or raise concerns about actual or perceived risks
to human health.
3.1 Use of substances or materials, which Yes Spent catalysts & Ammonia-
are hazardous (as per MSIHC rules) to Adequate precautions will be taken.
human health or the environment (flora,
fauna, and water supplies)
3.2 Changes in occurrence of disease or No Not Anticipated
affect disease vectors (e.g. insect or
water borne diseases)
3.3 Affect the welfare of people e.g. by Yes Local workforce will be employed during
changing living conditions? construction period. This will help in
improvement of socio-economic status
3.4 Vulnerable groups of people who could No Not Anticipated
be affected by the project e.g. hospital
patients, children, the elderly etc.,
July 2009 4
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
July 2009 5
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
July 2009 6
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
July 2009 7
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
8 Densely populated or built-up area Yes Panagarh is approx. 3 km from the site
July 2009 8
Form 1 for EIA_ Matix Fertilizers & Chemical Ltd. Green Field Project
July 2009 9