Académique Documents
Professionnel Documents
Culture Documents
The project administration memorandum is an active document, progressively updated and revised as
necessary, particularly following any changes in project or program costs, scope, or implementation
arrangements. This document, however, may not reflect the latest project or program changes.
PROJECT ADMINISTRATION MEMORANDUM
1. Contents
2. Project Summary
3. Project Description
4. Design and Monitoring Framework
5. Cost Estimates and Financing Plan
6. Implementation Arrangements and Schedule
7. Consultants
8. Procurement
9. Disbursement
10. Project Performance Monitoring and Evaluation
11. Progress Reports
12. Audit Requirement
13. Detailed Status of Compliance with Covenants
14. Anti-Corruption Guidelines
15. Design Changes
16. Implementation of the Associated TA Project
17. Key Persons Involved in the Project
1
2. PROJECT SUMMARY
A. Introduction
2. In particular, the PAM outlines the implementation arrangements for the Project and
contains the basic requirements and procedures on recruitment of consultants, procurement of
goods, contracting of civil works, withdrawal of loan funds, disbursements, progress reporting,
performance monitoring and auditing requirements under the Project.
3. The contents and interpretation of the PAM were discussed with the EA, IAs and the
PMU during loan inception, and are subject to the provisions of the Report and
Recommendation of the President (RRP), Financing and Project Agreements , Co-Financing
Agreement and JBIC Loan Agreement . In case of conflict among the documents in meaning or
intent, the specific provisions of the Loan and Project Agreements shall prevail.
B. Processing History
2Project Summary
2
Project Description The Power Sector Expansion Project comprises (i) support to the
Electric Power Corporation’s (EPC) investment plan 2008–2015
through three investment components and a project management
component, and (ii) a technical assistance (TA) cluster for
Implementing the Samoa National Energy Policy.
Rationale Reliable power supply is essential for enhancing the quality of life
of all Samoans. Good performance of the power sector and
reliable electricity services are vital for promoting private sector
1
Approximately US$26,610,000 equivalent.
2Project Summary
3
Impact and Outcome The Project forms part of the Government’s power sector
development plan to improve the capacity of the sector to provide
sustainable and reliable electricity services to all consumers at
affordable prices. To achieve this objective, the Project will help
EPC to improve the quality, reliability, and cost-effectiveness of
power supply by (i) supporting EPC’s investment plan to meet
growing demand, (ii) improving the operational efficiency of EPC,
(iii) improving the financial performance of EPC, (iv) establishing
effective regulation of the power sector, (v) developing a demand-
side management strategy to promote energy efficiency and
conservation, and (vi) developing clean energy resources through
the establishment of a clean energy fund (CEF), a clean
development mechanism (CDM) subfund, and a designated
national authority (DNA).
Project Investment Plan The project investment cost is estimated at $100 million, including
taxes and duties of $2.23 million.
2Project Summary
4
Financing Plan
Total
Source ($ million) %
Asian Development Bank ADF Loan 26.61 26.61
Asian Development Bank ADF Grant 15.39 15.39
Japan Bank for International Cooperation 38.00 38.00
Government of Australia 8.00 8.00
Electric Power Corporation 12.00 12.00
Total 100.00 100.00
ADF = Asian Development Fund.
Source: Asian Development Bank (ADB) estimates.
Allocation and Relending The ADF loan, the ADF grant, and the JBIC loan will be relent by
Terms the Government to EPC. The relending will be based on such
terms and conditions as set forth in the subsidiary financing
agreement between the Government and EPC. Such terms and
conditions will include the relending to be released in two
tranches, an interest rate of 6.5%, and such conditions set forth in
the financing agreement. The first tranche, which will finance
subprojects completed by 30 June 2012, will have a 25-year term,
including a grace of period of 5 years. The second tranche, which
will finance the remaining subprojects, will have a 25-year term,
including a grace period of 8 years.
2Project Summary
5
Consulting Services Consulting services will be required for a project manager and
project implementation. Consultants will be selected and engaged
in accordance with ADB’s Guidelines on the Use of Consultants
(2007, as amended from time to time).
2Project Summary
6
Risks and Assumptions EPC’s investment plan and financing arrangements have been
prepared considering the impact on Samoa’s debt and EPC’s
ability to service its debt to the Government. The ADF grant will
ease the macroeconomic impact of the large financing
requirements in the power sector. The Government of Australia
will provide a grant to be provided as Government of Samoa
equity to EPC. This equity will enable EPC to meet its counterpart
financing requirements for the Project.
2Project Summary
7
E. Relending Terms
4. The ADF loan, the ADF grant, and the JBIC loan will be relent by the Government to
EPC. The relending will be based on such terms and conditions as set forth in the subsidiary
financing agreement between the Government and EPC. Such terms and conditions will
include the relending to be released in two tranches, an interest rate of 6.5%, and such
conditions set forth in the financing agreement. The first tranche, which will finance subprojects
completed by 30 June 2012, will have a 25-year term, including a grace of period of 5 years.
The second tranche, which will finance the remaining subprojects, will have a 25-year term,
including a grace period of 8 years.
5. The Government will utilize the ADF grant by converting a portion of the EPC loan
principal to grants conditional on timely and within-budget implementation of subprojects. The
interest payment from EPC to the Government on the ADF grant will provide ongoing financing
for a CEF and a CDM subfund to be established under the CEF.
2Project Summary
8
3. PROJECT DESCRIPTION
A. Project Objectives
1. The objective of the Project is to provide sustainable and reliable electricity services to
consumers at affordable prices by improving the capacity of the power sector to: (a) meet
growing electricity demands; and (b) improve the quality, reliability and cost effectiveness of
electricity supply. The Project is part of the Beneficiary’s power sector development program,
which also includes taking institutional and regulatory measures to improve the financial and
operational performance of the EPC and the overall performance of the sector.
B. Project Components
(iii) installing nine new 6.6kV/22kV distribution transformers to replace the existing
6.6kV/400V distribution transformers at Tanugamanono power station.
Support the EPC’s investment plan for improving power generation and
transmission on Savai’i and Upolu through the implementation of approximately
17 Subprojects, including 11 transmission Subprojects, 4 generation Subprojects,
a system control and data acquisition Subproject, and a voltage and current, and
stream flow gauging measurement equipment Subproject.
(ii) the appointment of a project manager and implementation consultants in the PMU.
3Project Description
9
C. Special Features
3. Donor Coordination. Donor coordination and consultations with AusAID, GEF, and
JBIC have been key features of project preparation. Because of the emphasis on regulatory
and governance aspects of the power sector in Samoa, the Government of Australia will help
finance the regulatory and policy reform component of the TA cluster for Implementing the
Samoa National Energy Policy. Development of the feasible and affordable investment plan
and policy dialogue has been undertaken with EPC and the Government jointly with AusAID
and JBIC. JBIC will provide joint cofinancing as the first project under the Accelerated
Cofinancing Scheme with ADB. 1 The Government of Australia will provide a grant as joint
cofinancing for the Project to address affordability of counterpart financing requirements,
which is a particular issue for EPC in the early years of the investment plan. Initial
consultations have been undertaken with GEF on the CEF. The consultations will continue as
part of the implementation of the establishment of the CEF, the CDM subfund, and the DNA.
6. Macroeconomic Sustainability. The provision of the ADF grant will ease the
macroeconomic impact of the large financing requirements for the power sector expansion
project. In addition, the Government of Australia will provide $8 million to the Government for
counterpart financing of the Project. 2
7. Financing Arrangements. The sector loan modality will help EPC to improve longer-
term investment planning through the provision of predictable financing. The sector loan
modality will also help mitigate the risk of further delays associated with supplementary loan
processing in the event of cost overruns. The Government utilization of a portion of the ADF
grant as an incentive scheme to EPC will help improve timely implementation of subprojects.
The Government will also utilize the interest rate payment from EPC on the grant to provide
ongoing financing of a CEF and a CDM subfund.
3Project Description
10
sales for a minimum of 2 years, and (iii) 75% of all EPC’s active electricity customers are
using prepayment meters. The use of this pilot mechanism constitutes an innovative approach
to promoting reforms in developing countries, especially in the Pacific region. This is the first
time that ADB is engaging in such a loan buy down mechanism.
3Project Description
4. DESIGN AND MONITORING FRAMEWORK
Outcome Assumptions
Improved quality, reliability, and cost- System average duration EPC’s quarterly progress Effective regulation of the power sector is
effectiveness of power supply interruption index reports and annual established
baseline established and financial report Effective monitoring and reporting of EPC’s
verified by 4th quarter costs
2008 and reduced by ADB mission’s back-to- Stakeholders support EPC’s activities
20% by 2015 office reports EPC implements independent consumer
satisfaction surveys
Average interruption Indicators published in Clean energy resources are cost effective
frequency index baseline EPC’s annual corporate Financing for clean energy project is
established and verified plans and financial available
by 4th quarter 2008 and reports by FY2009 and Implementation of demand-side and energy
reduced by 20% by 2015 onward conservation measures
Cost of generation EPC’s corporate plan
established and published
by 1st quarter 2009
Outputs Assumptions
1. EPC’s investment plan meets demand Power system capacity EPC’s annual corporate Counterpart financing is made available on
requirements for energy and power plans and financial time
meets demand reports Effective project management unit
requirements on Savai’i Timely recruitment of implementation
and Upolu Project progress and consultants
completion reports Timely completion of bid documents and
procurement of goods and services
ADB review missions and Implementation of effective stakeholder
field visits consultations
Effective and timely implementation of social
and environment requirements
Land acquisition is completed prior to
commencement of construction activities
Effective demand-side management
11
measures
4ProjectFramework
Design Summary Performance Data Sources/Reporting Assumptions and Risks
Targets/Indicators Mechanisms
12
2. Operational efficiency of EPC Baselines for technical EPC’s corporate plan SCADA system installed and operating
improves system losses are Transmission and generation investments
established and verified Project completion reports implemented on a timely basis
by 4th quarter 2008 and
are reduced by 10% by ADB review missions and
4th quarter 2010 and 20% field visits
by 4th quarter 2012
ADB reviews and
Baseline for nontechnical approvals of bid
system losses established documents
and verified by 4th quarter
2008 and reduced by EPC annual performance
10% by 2010. and monitoring reports to
the board of directors and
Ministry of Finance
3. The financial performance of EPC Consistent application of Number of consumers in Effective implementation of prepayment
improves disconnection policy arrears by more than 30 system and cut-off policy
days and number of those Stable or lower international fuel prices
consumers disconnected Tariffs are adequate to cover all operating
expenses, depreciation, taxes, and interest
Amount of accounts expense
receivables aged more Introduced safeguards for fuel management
than 60 and 90 days are are effective
written off Effective financial advisory services to EPC
Consumer’s acceptance of prepayment
Fuel audits conducted on EPC’s monthly fuel audits meters
all EPC’s diesel power Government commitment to either utilize
stations prepayment meters or to sufficient budgetary
allocations for electricity consumption by
Timeliness of tariff Government entities
adjustments in response
Political commitment to timely tariff
to costs
adjustments
EPC’s collection EPC’s audited annual
performance improves financial compliance
such that accounts reports to ADB
receivables are below 2
months of sales
Government consumers’
share of EPC’s accounts
receivables reduced from
4ProjectFramework
Design Summary Performance Data Sources/Reporting Assumptions and Risks
Targets/Indicators Mechanisms
55% in 2007 to less than
their share of total sales
by 31 December 2009
Share of electricity
consumers on
prepayment metering
increases from 5% in
2007 to 75% by 31
December 2012
Self-financing ratio is
minimum 12% for 2008–
2015; self-financing ratio
is minimum 20%
commencing 2016
Debt-service ratio is
minimum 1.3
4. Effective regulation of the power Electricity Act to govern Parliament consideration Wide political commitment to power sector
sector is established the power sector of the draft Electricity Act reforms
established by 31
December 2009
5. Energy demand-side management Energy conservation and Consultant’s reports Effective stakeholder consultations and public
demand-side awareness campaign
management public ADB review missions
awareness campaign
implemented
6. Development of clean energy Number of projects by Annual reports of the Effective promotion of clean energy
13
energy subsector clean energy fund Effective stakeholder consultations and
financed by the clean participation
4ProjectFramework
Design Summary Performance Data Sources/Reporting Assumptions and Risks
Targets/Indicators Mechanisms
14
energy fund Annual reports of the
designated national
Number of projects by authority
energy subsector eligible
for clean development
mechanism
Electricity produced by
clean energy resources
(baseline of 45 GWh in
2006)
4ProjectFramework
Activities with Milestones Inputs
2.4. Reporting (2008–2015)
2.4.1. EPC prepares and submits quarterly progress reports, updates of the investment plan,
and financial projections to ADB and Government
15
4ProjectFramework
16
1. The project investment cost is estimated at $100 million, including taxes and duties of
$2.23 million. The Project comprises two core investment subprojects, 17 candidate investment
subprojects under EPC’s investment plan, and a project management component which will be
implemented during the 2008–2015 investment period. The core subprojects comprise the
Hospital Feeder upgrading project – stage 1, through the construction of a 22 kV underground
cable from Togafuafua to Saleufi, and the supply and installation of single-and-three-phase
prepayment meters. The project management component comprises recruitment of a project
manager and implementation consultants, initially for a period of 3 years. The cost estimates are
summarized in Table 1 and detailed in Tables A6.1 and A6.2 at the end of this Section.
B. Financing Plan
2. The Government of Samoa has requested a loan of $26.61 million [Loan No. 2368-
SAM(SF)] and a grant of $15.39 million from ADF [Grant No. 0087-SAM] to help finance the
Project. The loan will have a 32-year term, including a grace period of 8 years, an interest rate
of 1.0% during the grace period, and 1.5% thereafter, and such other terms and conditions set
forth in the financing and project agreements. The beneficiary will be the Independent State of
Samoa.
3. The Government has requested a loan of $38 million equivalent in Japanese yen
from JBIC (Loan No. 8232) for joint cofinancing of the Project, to be administered by ADB. The
loan will have a 30-year term, including a grace period of 10 years, at an interest rate of 0.45%.
17
4. The ADF loan, the ADF grant, and the JBIC loan will be provided to the Independent
State of Samoa and then relent by the Government to EPC. The relending will be based on
such terms and conditions set forth in the subsidiary financing agreement between the
Government and EPC. Such terms and conditions will include the relending to be released in
two tranches, an interest rate of 6.5%, and such conditions set forth in the financing agreement.
The first tranche, which will finance subprojects completed by 30 June 2012, will have a 25-year
term, including a grace period of 5 years. The second tranche, which will finance the remaining
subprojects, will have a 25-year term, including a grace period of 8 years. The Government will
assume the foreign exchange risk arising from the ADB and JBIC loans. ADB and JBIC will
finance 80% of the estimated project costs. The Government of Australia will provide $8 million
representing 8% of the estimated project costs. EPC will provide $12 million as counterpart
financing, which represents 12% of the estimated project costs. Table 2 presents the financing
plan, and the detailed cost estimates by financier are detailed in Appendix 6 (Table A6.2).
Source Total %
Asian Development Bank ADF Loan 26.61 26.61
Asian Development Bank ADF Grant 15.39 15.39
Japan Bank for International Cooperation 38.00 38.00
Government of Australia 8.00 8.00
Electric Power Corporation 12.00 12.00
Total 100.00 100.00
ADF = Asian Development Fund.
Source: Asian Development Bank estimates.
6. The ADF grant of $15.39 million will ease the macroeconomic impact of the large
financing requirements for the Project. The grant will be relent to EPC on the same terms as the
ADB and JBIC loans. The interest payment from EPC to the Government on the grant portion
will provide ongoing financing for a CEF and a CDM subfund. 1 MOF will provide annual reports
to ADB on the interest payment directed to the CEF and CDM subfund. The Government will
utilize a portion of the grant as an incentive scheme for EPC for timely implementation of
subprojects under the investment plan. Seven percent of projects costs, or a maximum of $10
million of the EPC loan principal, can be converted to grants conditional on timely and to-budget
implementation of subprojects. MOF will report to ADB when EPC has met the conditions that
will trigger conversion to grants and advise of the amount of the loan principal to be converted
into grants to EPC.
1
The TA cluster for Implementing the Samoa National Energy Policy will assist in the establishment of a CEF and a
CDM subfund.
18
DETAILED COST ESTIMATES
Government of
ADF Loan ADF Grant JBIC Loan Australia
EPC
L2368 G0087 L8232 G0101 Cost
$ % $ % $ % $ % $ %
A. Investment Cost
Land Acquisition and
1. 0.00 0.0 0.00 0.0 0.00 0.0 1.53 35.0 2.84 65.0 4.38
Resettlement
2. Civil Works 3.47 47.5 0.00 0.0 3.09 42.2 0.00 0.0 0.75 10.3 7.31
Equipment Supply and a a
3. 18.99 30.8 8.42 13.7 28.98 47.0 5.22 8.5 0.00 0.0 61.61
Installation
4. Consultant Services 0.00 0.0 4.57 94.9 0.00 0.0 0.00 0.0 0.25 5.1 4.82
5. Taxes and Duties 0.00 0.0 0.00 0.0 0.00 0.0 0.00 0.0 1.89 100.0 1.89
Subtotal (A)b 22.46 12.99 32.07 6.76 5.73 80.00
B. Contingencies
c
1. Physical 1.31 28.1 0.76 16.2 1.87 40.1 0.39 8.4 0.33 7.2 4.67
d
2. Price 2.84 28.1 1.64 16.2 4.06 40.1 0.85 8.4 0.72 7.2 10.12
Subtotal (B) 4.15 2.40 5.93 1.25 1.06 14.79
Financing Charges During
C. e
Implementation
Interest During
1. 0.00 0.0 0.00 0.0 0.00 0.0 0.00 0.0 5.21 100.0 5.21
Construction
Subtotal (C) 0.00 0.00 0.00 0.00 5.21 5.21
f
Total Project Costs (A+B+C) 26.61 15.39 38.00 8.00 12.00 100.00
% Total Project Costs 26.6 15.4 38.0 8.0 12.0
ADF = Asian Development Fund, EPC = Electric Power Corporation, JBIC = Japan Bank for International Cooperation.
a
The overall financing percentage will be 22.2% for the ADF grant and the Government of Australia grant. The financing percentage for the ADF and Government
of Australia grant proceeds will be changed over years as follows: (i) the financing percentage for the ADF grant will be 7.7% (rounded to 7%) for FY2008–
FY2012 and 22.2% (rounded to 22%) thereafter; and (ii) the financing percentage for the Government of Australia grant will be 14.5% (rounded to 15%) for
FY2008–FY2012 and zero thereafter. For disbursement purposes, the financing percentages will be rounded.
b
In May 2007 prices.
c
Computed at 14% for hydropower, 10% for system control and data acquisition, and 5% for other subprojects.
d
Computed at average annual rate of 1.7% on foreign exchange costs and 3.9% on local currency costs over the 2008–2015 investment plan.
e
Includes interest during construction, computed at the 6.5% relending rate from the Government to the Electric Power Corporation and including an interest rate
of 1% during grace period and 1.5% thereafter, which will be settled through cash payments on the Asian Development Fund loan portion.
f
Includes taxes and duties of $2.18 million. Interest during construction for the ADF loan will be settled through cash payments.
Source: Asian Development Bank estimates.
20
A. Project Management
1. Ministry of Finance (MOF) will be the executing agency for the Project and has assigned
EPC as the implementing agency. A PSC will be established to provide overall project
direction. 1 The chief executive officer (CEO) of MOF will chair the PSC. Other PSC members
comprise (i) the general manager of EPC, (ii) the attorney general, and (iii) the CEOs of the
Ministry of Natural Resources and Environment, the Ministry of Women, Community and Social
Development, the Samoa Water Authority, and the Ministry of Commerce, Industry and Labour.
PSC meetings will be convened on a quarterly basis commencing in October 2007. Special
PSC meetings may be convened to consider extraordinary project issues. A project
management committee (PMC) will be formed within EPC to provide coordination between
project and non-project activities. The PMC will be chaired by the general manager and
comprise EPC management and the project manager. The PMC will convene on a weekly basis
commencing in October 2007.
2. EPC has established a Project Management Unit (PMU) for the day-to-day management
and implementation of the project. The PMU will include personnel seconded from existing EPC
staff resources or recruited specifically for the PMU. Project implementation consultants will be
recruited to provide technical support and on-the-job training for the PMU personnel over the
first 3 years of the Project. The PMU will be responsible for project planning, monitoring and
reporting, and cost and quality control. The PMU will (i) undertake project management and
administration, (ii) plan and implement cost effective and sustainable infrastructure investments
to meet consumer demand, (iii) maintain project accounts, (iv) oversee procurement procedures
to ensure compliance with Government and ADB policies and procedures, (v) liaise with ADB
for quarterly project progress updates and other reporting and communication matters, and (vi)
prepare the project completion report of the Government. The Government will ensure that,
throughout the project implementation period, EPC provides adequate allocations of counterpart
funds to ensure proper project implementation. EPC will provide adequate office space for the
PMU and implementation consultants and ensure that the facilities provided are operated and
maintained appropriately.
3. Preparation. The PMU will identify candidate subprojects and obtain approval from the
EPC board and MOF to assess the feasibility of the candidate subprojects. The PMU will
prepare a feasibility study for each candidate subproject in accordance with the detail and
quality required to enable ADB to assess the suitability of the candidate subproject. The
feasibility study will contain evidence of the candidate subproject’s eligibility under the agreed
criteria. The feasibility study will provide (i) technical analysis and description; (ii) subproject
rationale, scope, and components; (iii) cost estimates and financing plan; (iv) implementation
arrangements; (v) an environmental assessment; and (vi) a land acquisition and resettlement
assessment. The feasibility studies will include a set of relevant benchmark and performance
indicators for the subproject which will be monitored through the progress reports. The feasibility
study will also contain an update of EPC’s investment plan and an analysis of the impacts on
EPC’s 5-year financial projections, key financial ratios, and compliance with loan covenants.
1
Similar PSCs are being used for overall strategic guidance and coordination for infrastructure projects funded by
other international financing institutions.
21
4. Eligibility Criteria. The PSC, the EPC board, and ADB, in consultation with the PMU,
will appraise subprojects in accordance with the eligibility criteria and procedures outlined in
RRP, Appendix 7 found at the end of this Section.
5. Approval Process. Candidate subproject feasibility studies will be submitted to ADB for
review and approval. After ADB has endorsed the feasibility study, the PMU will submit the
feasibility study to the EPC board and the PSC for review and approval. Implementation of a
candidate subproject may only proceed following the endorsement of the candidate subproject
feasibility study by the PSC, the EPC board, and ADB. Civil works may only commence once
the land acquisition and resettlement plan (LARP) and initial environmental examinations (IEE)
have been approved by ADB, and the development concept approval of the Preliminary
Environmental Assessment Report (PEAR) is issued by the Planning and Urban Management
Agency (PUMA).
C. Implementation Period
6. The PMU will be established prior to loan effectiveness. Bid documents for core
subprojects have been prepared such that construction activities can start in the first quarter of
2008. The subprojects will be implemented over 8 years and are expected to be completed by
31 December 2015. The project implementation schedule is detailed in RRP, Appendix 8, and
appended at the end of this Section.
6ImplArrangements
22
RRP, Appendix 7
1. The Power Sector Expansion Project forms part of the Electric Power Corporation’s
(EPC) power sector expansion program to provide sustainable and reliable electricity services to
all consumers at cost-efficient prices. The project will improve the capacity to meet growing
electricity demand and improve cost-effectiveness of power supply by (i) improving the
operational efficiency and financial performance of EPC, (ii) improving quality and reliability of
electricity supply at least cost, and (iii) establishing an effective regulatory structure for the
power sector.
2. The project management unit (PMU) will identify candidate subprojects meeting the
criteria set forth in para. 3 below and will obtain approval from the EPC board to assess the
feasibility of the candidate subprojects and inform the project steering committee (PSC) of the
pending subproject feasibility study. The PMU will then prepare a feasibility study for each
candidate subproject. The candidate subproject feasibility report will, among other things,
provide (i) technical analysis and description; (ii) subproject rationale, scope, and components;
(iii) cost estimates and a financing plan; (iv) implementation arrangements; (v) an environmental
assessment; and (vi) a land acquisition and resettlement assessment. The feasibility report will
also contain an update of EPC’s investment plan and an analysis of the candidate subproject’s
impacts on EPC’s 5-year financial projections, key financial ratios, and compliance with Asian
Development Bank (ADB) covenants. Each feasibility report will be submitted to ADB for review
and approval and will contain sufficient evidence of the candidate subproject’s eligibility under
the agreed criteria and will be prepared in accordance with the detail and quality required to
enable ADB to assess the viability and suitability of the candidate subproject. The feasibility
reports will include a set of relevant benchmark and performance indicators for the subproject
which will be monitored through progress reports. After ADB has endorsed the feasibility study,
the PMU will submit the feasibility study to the EPC board and the PSC for review and approval.
Implementation of a candidate subproject may only proceed following the endorsement of the
candidate subproject feasibility report by the PSC, the EPC board, and ADB. The subproject
selection process is shown in Figure A7.
3. To be eligible for financing through the project, (structural) subprojects must be selected
in accordance with the following criteria.
(i) The subproject (a) contributes to the objectives of the Power Sector
Development Plan, (b) is identified as a high priority project in EPC’s annual
business plan, and (c) is included in EPC’s investment plan.
(ii) The subproject is technically feasible and meets the Government’s technical
standards and requirements.
(iii) The subproject is justified as the most feasible subproject to achieve the stated
objectives and is shown to be least-cost among feasible alternatives.
(iv) A land acquisition and resettlement plan (LARP) will have been prepared for the
subproject in accordance with the land acquisition and resettlement framework
(LARF), if required, and EPC will have submitted written confirmation to ADB that
the landowner and or lessee (in the case of freehold and state-owned land) or
23
the matai 2 (in the case customary land), acting on behalf of affected persons
under the subproject, is agreeable to the land acquisition and resettlement plan
terms and conditions.
(v) An environmental screening will have been conducted for the subproject and an
initial environmental examination (IEE), preliminary environmental assessment
report (PEAR), and environmental management and monitoring plan (EMMP) will
have been prepared for the subproject, in each case, in accordance with the
provisions of the environmental assessment and review framework.
(vi) ADB determines that EPC has the necessary staffing, implementation, and
financial management capacity to implement the subproject or, in the alternative,
EPC can provide specific assurances that assessed shortcomings can be
rectified, such as by adding qualified staff or providing timely in-service training.
(vii) The subproject's implementation timeframe is reasonable, and surveys and
design can be prepared and reviewed, and safeguard processes and procedures
followed and implemented, within the project period.
(viii) The financing plan clearly identifies confirmed sources of financing, including
counterpart financing, and includes the provision of budgetary resources to meet
(a) counterpart funding requirements for capital expenditures during the
construction phase, (b) resettlement costs, as applicable, (c) environmental
management costs, (d) loan repayment requirements, and (e) routine operations
and maintenance costs.
(ix) The subproject will not adversely impact on EPC’s ability to meet its financial
covenants under the ADB loan and grant.
(x) All required Governmental approvals shall have been obtained.
2
The title matai is an elected chief representing an extended family unit. The title may be bestowed on anyone in the
customary Samoan society.
6ImplArrangements
24
Figure A7: Subproject Selection Process
No.
EPC board
endorses
preparation of
feasibility study
candidate
subproject?
Yes.
ADB endorses
feasibility study?
No.
Yes.
25
kV = kilovolt, PMU = project management unit, SCADA = system control and data acquisition.
a
Implementation start is defined as commencement of design and documentation (after the feasibility study is prepared and approved by the Asian Development Bank and
the project steering committee).
Source: Asian Development Bank.
26
7. CONSULTANTS
A. General Principles/Policies
1. The policies and main procedures for recruiting consultants are set out in the Guidelines
on the Use of Consultants by Asian Development Bank and Its Borrowers (Guidelines).
Borrowers must comply with ADB’s requirements and follow ADB’s procedures. The Financing
Agreement states the roles and responsibilities of the Borrower, ADB, and any other parties
involved and the procedures that should be followed.
2. If a Borrower does not select the consultants in accordance with the Guidelines and the
relevant financing agreement, ADB will not finance the consulting assignment under the grant.
In these cases ADB declares misprocurement, and usually cancels the financing. In appropriate
cases, ADB may permit reissuing the request for proposals (RFP) after declaring
misprocurement.
3. When recruiting consultants with ADB funds, Borrowers are expected to promptly recruit
consultants who will provide high-quality services. The normal means of selection is through
competitive bidding among qualified firms. In carrying out the selection, Borrowers should,
whenever possible, short list consulting firms from different geographic regions in order to
spread the opportunities to work on consulting assignments among ADB’s member countries.
Borrowers may specifically recruit national consultants from their countries, when national
consultants are qualified for the assignments.
4. All the parties under ADB-financed consulting services contracts must observe the
highest ethical standards. If ADB determines that representatives of a borrower, a consultant, or
a beneficiary engaged in corrupt, fraudulent, collusive, or coercive practices during consultant
selection or the execution of a contract, ADB will take the appropriate steps set out in paragraph
1.23 of the Guidelines.
6. Consulting services will be required for (i) project management, (ii) preparation of
candidate subprojects, (iii) construction supervision, and (iv) contract management. A firm will
be selected through international competition using quality-and cost-based selection method to
provide project implementation consulting services. About 69 international person-months will
be required for project implementation. Individual consultants may be recruited for specific
assignments in accordance with ADB’s procedures. The project manager has recruited
internationally as an individual for an initial period of 36 months in accordance with ADB’s
procedures. 1 The outline terms of reference for the project manager and implementation
consultants are appended at the end of this Section (RRP, Supplementary Appendix A).
C. Advance Contracting
1
ADB assisted with the selection process on behalf of EPC for both the Project Manager and Project Implementation
Assistance consultancies. EPC is responsible for negotiating the contracts and supervising consulting services.
27
proceeds are eligible for retroactive financing. Retroactive financing is applicable to eligible
expenditures, which must have been incurred before loan effectiveness, but generally no earlier
than 12 months before signing of the financing and project agreements.
D. Procurement Plan
8. The Project’s Procurement Plan (RRP, Appendix 9) is attached at the end of this
Section. Within 1 year after the date of loan effectiveness, the EA should submit a revised
procurement plan to ADB for approval that captures all the ongoing procurement and those
planned for the following 18 months. The procurement plan should be updated annually for the
duration of the Project.
9. Table A9.3 of the Procurement Plan states that the Project will select the consulting firm
using the Quality-and Cost Based Selection Method (QCBS), Full Technical Proposal. The
threshold for using QCBS is $1,000,000 or greater and the quality-cost ratio for evaluation of
proposals will be 80:20.
10. Advertising. A notice describing each consulting assignment is posted in the ADB
Business Opportunity section of ADB’s website before shortlisting. The minimum posting time
for each assignment is 30 days. The website includes a link to a standard expression of interest
(EOI) form for loans that firms can download, fill out, and send directly to the EA. The EA may,
in addition, advertise in local newspapers and international trade publications.
11. QCBS is a method of selecting a consulting firm based on both the quality of the
technical proposals and the cost of the financial proposals. The general guidelines are as
follows.
12. The EA/IA first reviews the scope of the assignment, the detailed TOR, and EOIs
received for the assignment and then prepares a long list. This normally includes 15–20
technically qualified consulting firms with experience in similar projects. The EA normally
includes all the qualified consultants that expressed interest. The EA may also ask the user
division officer for a list of qualified consultants from ADB’s Consultant Management System
(CMS). The EA decides whether to include any of these consultants on the long list and may
also add other experienced consultants to the list.
13. The EA/IA then prepares a short list of six consultants. This may be done through a
consultant selection committee (CSC) set up by the borrower and including staff of the EA, or by
a CSC set up within the EA itself, depending on the normal procedure in the country concerned.
14. To ensure a wide geographic spread for projects requiring international consulting input,
the short list should contain firms from a broad range of ADB member countries. When possible,
short lists should include one firm from any one country, but no more than two firms are allowed
for any one country. In addition, there should be at least one firm from a developing member
country (DMC), unless no qualified DMC firm has expressed interest or one cannot be identified
from the CMS.
28
15. The EA/IA next prepares the RFP documents in ADB’s format. Templates for this are
available on the ADB website. The information in the RFP must include the following:
The successful consultant must disqualify itself, its affiliates, and its associates
from participating in the project in any other capacity. For example, firms of
independent consulting engineers are limited to the role of consulting engineers
and must not also act as contractors or manufacturers.
The EA may exclude a consultant if it is found to have a conflict of interest
(Guidelines paragraphs 1.10-1.11) or if the EA determines that a consultant
engaged in corrupt, fraudulent, collusive, or coercive practices (Guidelines
paragraph 1.23).
Firms that have expressed interest as a part of a joint venture or association will
be short-listed as such, and all firms that indicated their participation are
expected to be represented in the proposal. Additional firms may be included in
the joint venture or association when the proposal is submitted.
17. The RFP includes instructions on submitting financial proposals and other procedures
that are specific to the selection method the EA will use. It includes a data sheet, which, among
other information, states the EA’s budget for the assignment. This is either in maximum budget
or an estimated budget. A maximum budget is shown when costs are certain and it is unlikely
that financial proposals will exceed this budget. An estimated budget is shown when cost
estimates are not certain and it is possible that financial proposals may exceed it. When
preparing the RFP, the EA should ascertain that all costs that may be included in the
consultants’ contract are included in the estimated contract budget published in the data sheet.
These should include (besides consulting fees) per diems, travel costs, the costs of any vehicles
or equipment specifically associated with the consultancy, and any special items (for example
the cost of recruiting non-government organizations or providing training). Any fixed costs such
as provisional sums or contingencies should be clearly identified.
18. For QCBS in which the data sheet indicates a maximum budget, the RFP will clearly
state that financial proposals must be within this budget; otherwise the financial proposal will be
considered non-responsive and will not be awarded any points during the financial evaluation.
For QCBS in which the data sheet indicates an estimated budget, firms will not be penalized if
the financial proposal exceeds the budget.
29
19. When the EA submit its short-listing documents to ADB for approval, it must be in ADB’s
standard format, updated from the most recent version available on ADB’s website. The
Pacific Operations Division (PAHQ, the user division) reviews the EA’s short-listing criteria and
short list, to make sure that the criteria are reasonable and rational relative to the scope of work,
the TOR, and the budget available and that all the firms are technically qualified and have a
reasonable geographic spread.
TOR and background information provided to ensure that they are in line with the
project scope and consultant duties spelled out in the RRP and loan agreement;
EA’s budget for the assignment to ensure a realistic level of remuneration, per
diem rates, and out-of-pocket expenditures; relevant and adequate provisional
sums; and adequate contingencies;
selection method, the type of technical proposal, and whether these are in line
with the recommendations in the procurement plan;
validity and appropriateness of the criteria for evaluating the technical proposals,
changes made to the draft contract; and
proposed timing for consultant recruitment illustrated in the CRAM frame.
21. Once the documents are received, PAHQ reviews them and then sends its comments to
COSO for further review. COSO then completes the review and offers comments for transmittal
to the EA within a reasonable time. If necessary, PAHQ or COSO may consult the Office of the
General Counsel (OGC) on key issues. If there are outstanding issues, COSO or PAHQ may
also request a CSC meeting to review the documents. The user division informs the EA of any
deficiencies, shortcomings, or gaps in the documents and requests them to be revised
accordingly. Once the documents are in order, PAHQ informs the EA of its approval and
provides clearance for the EA to proceed with the issuance of the RFP.
22. The PAHQ staff concerned should ensure that all documentation listed in the relevant
checklist is in order and in conformity with ADB's standard templates, and that the user division
assessments and recommendations in connection with review of the EA's short-listing, technical
and financial evaluation have been undertaken in accordance with applicable ADB procedures
and guidelines. It is the responsibility of PAHQ to identify issues of concern or potential concern
to the relevant COSO officer at the time of, or prior to, submission of the relevant checklist. In
addition to checking the completeness and consistency of the relevant checklist submitted and
the assessments and recommendations made by PAHQ, COSO will undertake a detailed
review of all documents submitted by the EA
23. Based on the review done by PAHQ and COSO, COSO completes a checklist (sample
attached) to document the main areas of review and concerned COSO director signs the
checklist for record.
d. Requesting Proposals
24. The EA then sends RFPs to the consultants on the short list. The consultants
acknowledge receiving the RFPs and any notices from the EA of extensions to the deadline for
receiving proposals. The consultants also advise whether they intend to submit proposals. If
30
there are any queries from the consultants, the EA must provide all the short-listed consultants
with the same information without disclosing the source of the query.
25. After receiving the consultants’ proposals, the EA rejects any it receives after the stated
deadline. The EA then establishes a CSC, which evaluates the technical proposals using the
evaluation criteria approved by ADB. The CSC prepares minutes of its evaluation meeting and a
report on its evaluation, describing the strengths and weaknesses of each proposal.
26. If the EA’s procurement plan requires it to submit its technical evaluation documents to
ADB for approval, the EA submits its documents in ADB’s standard format available on the ADB
website or provided by the user division officer. The documents include
a summary evaluation sheet highlighting any proposal that scored less than 750
points out of 1,000,
a personnel evaluation sheet for each proposal,
comments on the strengths and weaknesses of each proposal, and
minutes of the evaluation meeting(s).
27. PAHQ reviews the documents and sends the documents and its comments to COSO for
further review. COSO then completes the review and offers comments for transmittal to the EA
within a reasonable time. The user division informs the EA of any deficiencies, shortcomings, or
gaps in the documents and requests them to be revised accordingly. Once the documents are in
order, the user division informs the EA of its approval. If there are outstanding issues, COSO or
the PAHQ may request a CSC meeting to review the documents.
28. Based on the review done by the user division and COSO, COSO completes a checklist
to document the main areas of review and concerned COSO director signs the checklist for
record.
29. The procedure for requesting and evaluating financial proposals varies depending on the
selection method.
30. If the EA’s procurement plan requires it to submit its financial evaluation and final
ranking documents to ADB for approval, the EA submits its documents in ADB’s standard
format downloaded from ADB website or provided by the user division officer. PAHQ reviews
the documents, provides comments, and submits them to COSO for further review. COSO
provides its comments within a reasonable time period. For bids under QCBS the documents
should be carefully checked to ensure that inadvertent mistakes have not been made when
adjusting the original financial bids to the evaluated financial price. A CSC may be formed to
review the documents and resolve the issue. Prior to approval, the EA is informed or any
deficiencies, shortcomings, or gaps in the documents and is requested to revise them
accordingly. PAHQ informs the EA of ADB’s approval once outstanding issues are resolved.
31. The EA then writes to the first-ranked consultant and advises that it wishes to negotiate
a contract. The EA normally conducts the negotiations face-to-face. The consultant must pay all
its representative’s costs to attend the negotiations. The letter
invites the consultant to send a representative to the EA’s offices, who will be
prepared to discuss the consultant’s proposal and has the authority to finalize
and sign a contract;
proposes a schedule and agenda;
asks the consultant to confirm the availability of all the team members nominated
in its technical proposal; and
summarizes any issues identified during the evaluation that require clarification,
any deficiencies to be corrected, any team members to be replaced, or any other
corrective action to be taken.
If there is likely to be a delay in negotiations, the letter may also request the
consultant to extend the validity of its bid for a reasonable time until negotiations
can be held.
32. The negotiations cover the TOR, the consultant’s methodology and work plan, the team
members and personnel schedule, the counterpart facilities the EA will provide the financial
terms, and the other terms and conditions in the contract. The procedure for negotiating the
financial terms depends on the selection method (see PAI 2.02, Part A). The EA prepares
minutes of the important points of agreement.
33. If the EA and the consultant cannot reach agreement, the EA may ask ADB’s agreement
to terminate the negotiations and start negotiations with the next-ranked consultant, in turn, until
it reaches an agreement.
34. If the EA’s procurement plan requires it to submit its draft negotiated contract and the
minutes of the contract negotiations to ADB for approval, the EA submits them in ADB’s
standard format, provided by the user division officer. The user division reviews and approves
them. The division
makes sure that the negotiated terms and conditions are satisfactory;
asks COSO, the Controller's Department (CTL), and OGC for comments, if
necessary; and
requests the EA to make changes or amendments as considered necessary.
35. Once the documents are considered to be in order, the user division advises the EA of
ADB’s approval.
36. After receiving ADB’s approval, the EA signs the contract, obtains the consultant’s
signature, and submits a copy to ADB for its records. The EA also submits some information for
ADB to publish on its website. This consists of
37. After completing the selection, it is the EA’s responsibility to brief the short-listed
consultants on the reasons for their ranking, when asked.
38. After receiving the signed contract, the user division checks that it is substantially the
same as the draft negotiated contract approved earlier. The division sends copies of the signed
contract to COSO, CTL, and OGC. The user division sends copies of all relevant
communications to COSO.
l. Terminating a Contract
40. The flowchart for recruiting consulting firms using QCBS is provided below.
33
Discusses TOR TOR developed Appraisal mission discusses TOR with the EA
Receives EOIs and prepares long list of consultants User division provides list of firms from DACON
Conducts CSC; submits documents (signed CSC meeting User division reviews EA submission; prepares checklist;
minutes; long list; short-listing criteria; narrative evaluation SUBMISSION 1 submits its evaluation to COSO; and requests for an informal
criteria; short-list; draft RFP with TOR, Data Sheet, meeting
Summary and Personnel Evaluation sheets and draft
contract; and draft CRAM sheet) t
Informs user division of RFP issuance User division informs COSO to post short-list on ADB website.
Evaluates technical proposals; submits technical evaluation SUBMISSION 2 User division reviews EA submission, prepares checklist,
report (minutes of EV meeting[s], summary & personnel submits to COSO, and requests for an informal meeting
evaluation sheets) to user division
COSO checks user division's submission for completeness
and schedules the informal meeting
Negotiates contract
Forwards draft negotiated contract and minutes to user SUBMISSION 4 User division approves draft negotiated contract and informs
division for approval EA of ADB approval
2. Individual Consultants
41. Individual consultants are more appropriate than firms when the assignment is
straightforward and does not require a team of experts and extra support from the consultant’s
home office. The EA’s main requirements are the consultants’ qualifications and experience.
The procedure/flowchart for recruiting individual consultants is provided at the end of
this Section.
42. Borrowers may engage individual consultants directly or through an organization such as
a consulting firm, an academic institution, a government agency, or an international agency.
Nationals of the country concerned who have extensive international experience may be
considered as international consultants for assignments that require an international level of
expertise. (Extensive international experience is generally defined as having been recruited for
three or more contracts at an international level, but also includes individuals of internationally
acknowledged expertise in their professional fields.)
44. ADB encourages assignments for national consultants from the project country when
qualified national consultants are available.
45. For international consulting assignments, borrowers should short-list consultants from
different geographic regions in order to ensure access to the best expertise available and to
spread the opportunities to work on consulting assignments among ADB’s member countries.
46. ADB’s anticorruption policy requires borrowers and consultants under ADB-financed
contracts to observe the highest ethical standards. If ADB determines that representatives of a
borrower, a beneficiary, or a consultant engaged in corrupt, fraudulent, collusive, or coercive
practices during consultant selection or the execution of a contract, ADB may take any of the
steps set out in the Guidelines, paragraph 1.23. Allegations of corrupt, fraudulent, collusive, or
coercive practices will be reported to the ADB’s Office of the General Auditor.
47. Several weeks before an individual consulting assignment is scheduled to start, the EA
prepares a short list of at least three qualified candidates. The EA normally includes no
more than one candidate from any ADB member country. At the EA’s request, the user division
will provide the names and qualifications of suitable candidates from the DICON. The EA may
also advertise for suitable candidates.
48. The EA ranks the candidates, and then normally submits their names and qualifications
and the draft contract it will use for the engagement to ADB for approval. The user division
asks the Controller's Department (CTL), Office of the General Counsel (OGC), or
other relevant departments and offices for comments, if necessary;
approves the EA's documents or identifies needed revisions;
prepares a note to file summarizing the issues raised and the decisions taken;
and
advises the EA of ADB’s decision.
49. After ADB approves the ranked short list and draft contract, the EA negotiates with the
first-ranked candidate. If the negotiations fail, the EA obtains ADB’s approval to negotiate in turn
with the next-ranked candidate until agreement is reached. The EA then normally sends a copy
of the draft negotiated contract to ADB for approval.
50. After ADB approves the draft negotiated contract, the EA concludes the negotiations,
signs the contract, and submits a copy to ADB for its records. After receiving the signed
contract, the user division checks that it is substantially the same as the draft already approved
and gives copies to COSO, CTL, and OGC. The division must send copies of all
communications regarding consultants to COSO.
d. Terminating Contracts
If stated in procurement plan, submits candidates' names, User division approves EA's
qualifications, and draft contract to ADB documents
53. The EA and the user division use CRAM frames for loans/grants to monitor the activities
in recruiting the consultant and to avoid delays. An example of a CRAM frame and a flow chart
of the CRAM process is provided at the end of this Section.
54. CRAM identifies the main activities in the recruitment process, the time normally
required for each activity, and target dates for completing each activity. The EA and user
division staff responsible for completing each activity and for monitoring the recruitment process
use CRAM to identify delays and to take prompt action to get the recruitment process back on
schedule.
55. When the EA schedules and advises ADB of the date of its CSC meeting to short-list
consulting firms for an assignment, the user division creates a CRAM frame for the
assignment. The system automatically generates a recruitment schedule, including the planned
dates for each activity and the cumulative number of days since short-listing. The number of
calendar days required for each activity is based on “norms” for each selection method and type
of technical proposal.
56. The user division sends a copy of the CRAM frame for the assignment to the EA. The
EA’s CSC short-listing meeting then discusses and confirms the CRAM schedule. If the EA is
required to submit its CSC meeting documents to ADB for approval, the EA includes the CRAM
frame.
57. If ADB approves the EA’s technical evaluation and financial evaluation/overall ranking (if
the EA uses QCBS), the user division sends the EA an updated CRAM frame. The responsible
EA staff member monitors the recruitment process and reports to the ADB user division officer
the date when each activity is completed and the reason for any delays. The ADB user division
officer enters the completion dates in column 6. Planned dates cannot be changed.
58. Columns 8 and 9 in the CRAM frame show the difference in days between the planned
and actual dates for completing each activity, and the difference between the planned and
actual days since short-listing. When an activity is completed later than the planned date, the
ADB user division officer enters in column 11 an explanation and the action the EA and ADB
need to take to get the recruitment back on schedule. The upper right corner of the CRAM
frame shows the date the frame was last edited.
38
USING CRAM FOR LOAN PROJECTS
Notes:
a. Activity Norms [column 3] are based on working days with the exception of activities 6 and 19 which are based on calendar days.
b. The base date for planning and monitoring is the date of CSC-SL meeting.
c. Planned dates, days and cumulative days (columns 5 and 6, respectively) are derived from the Norms and are computed as calendar days.
d. Actual achieved dtaes (column 7) are input by the responsible project officer from the concerned user division, and Actual days and cumulative days (columns 8 and 9 respectively) are computed as calendar days.
e. Deviations are computed in calendar days and cumulative calendar days (columns 10 and 11).
f. For simplified technical proposal, norm is 35 days (238 total); for biodata technical proposal, norm is 21 days (224 total).
40
8. PROCUREMENT
A. General
1. Except as ADB may otherwise agree, all goods and services and other items of
expenditure to be financed out of the proceeds of the Loan and the Grant, and the JBIC Loan
and the Government of Australia Grant, shall be subject to and governed by the ADB’s
Guidelines for Procurement (2007, as amended from time to time), copies of which have been
furnished to the Executing Agency and Implementing Agency.
B. Basic Principles
2. The five basic principles of the Guidelines include: (i) for Loans or grants from Special
Funds resources, the proceeds of ADB financing can be used only for procurement of goods
and works supplied form, and produced in, member countries of ADB; (ii) economy and
efficiency in the implementation of the project, including the procurement of the goods and
works involved; (iii) giving all eligible bidders from developed and developing countries the same
information and equal opportunity to compete in providing goods and works financed by ADB;
(iv) encourage the development of domestic contracting and manufacturing industries in the
country of the Borrower; and (v) transparency in the procurement process. The list of ADB
member countries is at the end of this Section.
3. The ADB Standard Bidding Documents (SBDs) for the Procurement of Goods and
Related Services including a User’s Guide to the SBDs can be downloaded from the ADB’s web
site at the following URL: http://www.adb.org/Procurement/bidding.asp. The use of the new
SBDs for the procurement of Goods and Related Services is mandatory. ADB’s Guidelines for
Procurement require that Borrowers must use the appropriate SBDs issued by the ADB for
International Competitive Bidding. ADB’s bid documents will be used for procuring ADB, JBIC,
and Government of Australia financed goods and services.
C. Procurement Plan
4. EAs are required to prepare a procurement plan covering the first 18 months of
procurement activity. The agreed procurement plan is attached as Appendix 9 to the RRP (copy
at the end of this Section). Within one year after the date of loan effectiveness the EA shall
submit a revised procurement plan to ADB for approval that captures all ongoing procurement
and that planned for the following 18 months. The plan shall be updated annually on the same
basis for the duration of the Project.
Provide a single point of reference for the procurement oversight and supervision
To create a tool that allows for process and review thresholds to be changed if
necessary over the lifetime of a project
Focus the EA on the need to plan and manage procurement
To provide a synopsis of the procurement opportunities to providers of goods,
works and consultants service.
Increase levels of transparency
41
6. Except as ADB may otherwise agree, Goods and Services shall only be procured on the
basis of the methods of procurement set forth below:
The methods of procurement are subject to, among other things, the detailed arrangements and
threshold values set forth in the Procurement Plan. The Beneficiary may only modify the
methods of procurement or threshold values with the prior agreement of ADB, and modifications
must be set out in updates to the Procurement Plan.
7. The procurement thresholds for goods and related services, and works and supply install
contracts are provided below.
9. Advertisement and Notification – All eligible member countries of the ADB (list is
provided at the end of this Section) shall be appropriately notified of opportunities to bid.
Invitations to bid shall be advertised in the ADB’s website as well as in a newspaper of general
circulation in the borrower’s country (at least in one English language newspaper).
10. The EA is required to prepare and submit to ADB a draft General Procurement Notice
(GPN). 1 The notice contains information concerning the borrower, amount and purpose of the
Loan/Grant, scope of procurement under ICB, and the name, telephone number, email address
(or fax number) and address of the Borrower’s agency responsible for procurement and the
address of the website where specific procurement notices will be posted. If known, the
scheduled date for availability of prequalification or bidding documents should be indicated. The
GPN appears in adb.org for at least one month, but preferably three months, before the first
prequalification (where prequalification is to be carried out) or bidding documents are made
1
The GPN for the Project was published in adb.org on 11 October 2007.
42
available for issue. A Specific Notice (SN) refers to the advertisement for prequalification
(where prequalification is to be carried out) or bidding for an individual contract. Publication of
the SN for an individual contract follows immediately after the publication of the invitation for
prequalification or bids in a local English newspaper of general circulation or on a well-known
website.
12. Invitations to prequalify shall be advertised and notified in accordance with the
procedures described above. The scope of the contract and a clear statement of the
requirements for qualification shall be sent to those who responded to the invitation. A minimum
period of six weeks shall be allowed for the submission of prequalification applications. There
shall be no limits on the number of bidders to be prequalified, and all firms found capable of
performing the work satisfactorily in accordance with the approved prequalification criteria shall
be prequalified and invited to submit bids. As soon as prequalification is completed, the bidding
documents shall be made available to the prequalified prospective bidders.
13. Bidding Procedures – ADB has adopted four bidding procedures from which the EA
may select to suit the procurement: single-stage, one-envelope; single-stage, two-envelope;
two-stage, two-envelope; and two-stage biddings. Choosing the appropriate bidding procedure
will depend on the complexity of the contract and the circumstances surrounding procurement.
14. For this procedure, bidders submit the price proposal and the technical proposal in one
envelope. These envelopes are opened in public on the date and at the time designated in the
bidding documents. The bids are evaluated, and following ADB approval, the contract is
awarded to the bidder who submitted the lowest evaluated substantially responsive bid.
15. Bidders submit two sealed envelopes simultaneously, one containing the technical
proposal and the other the price proposal.
Initially, only the technical proposals are opened on the date and at the time
advised in the bidding documents. The price proposals remain sealed and are
held in custody by the EA. The technical proposals are evaluated by the EA and
cannot be amended or changed. The objective is to allow the EA to evaluate the
technical proposals without referring to price. Bids that do not conform to the
specified requirements may be rejected, with ADB’s approval, as deficient bids.
Following ADB’s approval of the technical evaluation, and on the date and at the
time advised by the EA, the price proposals of the technically responsive bidders
43
are opened in public. The price proposals of the technically responsive bidders
are evaluated, and following approval by ADB, the contract is awarded to the
bidder who submitted the lowest evaluated substantially responsive bid.
16. Bidders submit two sealed envelopes simultaneously, one containing the technical
proposal and the other the price proposal
Initially, only the technical proposals are opened on the date and at the time
advised in the bidding documents. The price proposals remain sealed and are
held in custody by the EA. The technical proposals are evaluated, and if the EA
requires any amendments or changes they are discussed with the bidders, and
all bidders are advised in writing by the EA of the changes required. The
objective is to ensure that all technical proposals conform to the same acceptable
technical standard and meet the EA's technical requirements. Bids of bidders
who are unable or not prepared to amend their technical bids to conform to the
final technical standard required by the EA may be rejected, with ADB approval,
as deficient bids
The original and supplementary price proposals, and the revised technical
proposals, are opened in public on the date and at the time advised by the EA.
They are evaluated, and following ADB approval, the contract is awarded to the
bidder who submitted the lowest evaluated substantially responsive bid.
(for large and complex contracts where technically unequal proposals are likely to be
encountered)
17. Bidders first submit their technical proposals, in accordance with the specifications, but
without prices:
The technical proposals are opened on the date and at the time advised in the
bidding documents. The EA evaluates the technical proposals and discusses
them with the bidders. Any deficiencies, extraneous provisions, and
unsatisfactory technical features are discussed with the bidders, and all bidders
are advised in writing by the EA of the changes required. The bidders who meet
the qualification criteria are invited to revise or adjust their technical proposals to
meet the EA's technical requirements. The objective is to ensure that all technical
proposals conform to the same acceptable technical standard and meet the EA's
technical requirements. Bids of bidders who are unable or not prepared to amend
44
their technical bids to conform to the technical standard required by the EA may
be rejected, with ADB approval, as deficient bids.
After ADB approves the evaluation of technical proposals, the second stage is to
invite bidders who meet the qualification criteria to submit revised technical
proposals and price proposals that are opened in public on a date and time
designated by the EA. In setting the date, the EA is to allow time for bidders to
prepare revised technical proposals and price proposals. The revised technical
proposals and price proposals are evaluated and, following ADB’s approval, the
contract is awarded to the lowest evaluated substantially responsive bidder.
18. Invitation for Bids and Bidding Documents - Three copies of the Invitation for Bids
(IFB) and all related bidding documents for ICB (including instruction to bidders, conditions of
contract, specifications and bid forms) must be submitted to ADB for approval. The documents
much reach ADB at least 21 days prior to the proposed date for issuing bidding
documents to allow sufficient time for review and approval, and to allow time for a specific
notice to be published on adb.org.
19. Issuing the Invitations for Bids – As soon as the IFB is advertised in accordance with
the Procurement Guidelines, ADB is to be provided a report on such advertisement. The report
must include: the name of the web site or newspaper in which the IFB was advertised, date of
advertisement, and copy of the published advertisement.
20. For ICB, IFBs require a minimum bidding period of 6 weeks. This period is counted
from the publication date of the relevant invitation in the Business Opportunities section of
adb.org, or locally in English, or the date when documents are available for issue, whichever is
the latest, up to the date for submission of bids. The date, hour, and place for the latest delivery
of the bids are to be clearly stipulated in the IFB, as well as the manner for submitting such bids.
Besides allowing for submission in person, delivery of bids by registered mail or electronically
will similarly be acceptable and stated in the IFB.
21. Opening of Bids – Bids delivered after the deadline for submission are to be returned
unopened. Bids must be opened in public on the date and at the time and place stipulated in
the documents. The name of each bidder and the total amount of its bid, discounts, bid security
(if required), and other important information are to be read aloud and recorded. All these
information are to be included in the record of the opening of bids, together with the names of
the representatives present.
22. Examination and Evaluation of Bids - Must be consistent with the method, terms and
conditions of the bid documents and follow the procedures set out in the Procurement
Guidelines.
23. Conditions of Contract – General conditions of contract are provided in the Standard
Bidding Documents (SBD). Terms and conditions specific to the bidding are specified in the
bidding documents. The Procurement Guidelines include provisions related to currency of
payment, terms and method of payment, price adjustment, performance security, liquidated
damages, language, transportation and insurance and dispute resolution, force majeure,
applicable law and settlement of disputes. These provisions should be reviewed when
developing specific conditions of contract.
25. Proposal for Award – Where prior review is applied, as soon as the bids are evaluated
and the EA has determined the lowest evaluated bid, the evaluation results and the proposal for
award of contract are to be submitted to ADB for review and approval. The recommendation
must be approved by ADB before a contract is awarded or a letter of intent is issued. For this,
promptly after the bid evaluation but at least 30 days prior to expiration of bid validity, ADB
must be given three copies of:
an account of the public opening of the bids (together with the minutes of bid
opening),
a summary and detailed evaluation of the bids,
the proposal for award (together with the consultants' recommendations, where
applicable),
a draft contract if such a draft differs from the draft previously approved by ADB, and
an appropriate certificate of eligibility for the proposed contract.
27. Award of Contract - Where prior review is used, if the contract proposed to be executed
differs substantially from the draft approved by ADB or if any substantial amendment to the
contract is proposed, the proposed changes are to be submitted to ADB for prior approval.
Promptly after each contract is awarded, ADB is to be given three copies of the contract as
executed. Where post review is used, ADB will check the contract as executed for substantive
amendments to the recommendation of the evaluation and award process.
28. Modifications to contracts, will require ADB prior approval. Change orders that increase
the original contract amount by more than 15% in aggregate require prior approval. Material
extensions in time, and modifications or waivers of conditions of contract similarly require prior
approval of ADB. In all cases, contract amendments must be submitted to ADB for its records.
46
(b) Shopping
29. Shopping is a procurement method based on comparing price quotations obtained from
several suppliers (in the case of goods) or from several contractors (in the case of civil works),
with a minimum of three, to assure competitive prices, and is an appropriate method for
procuring readily available off-the-shelf goods or standard specification commodities of small
value, or simple civil works of small value.
30. Requests for quotations shall indicate the description and quantity of the goods or
specification of works, as well as desired delivery (or completion) time and place. Quotations
may be submitted by letter, facsimile or by electronic means. The evaluation of quotations shall
follow the same principles as of open bidding. The terms of the accepted offer shall be
incorporated in a purchase order or brief contract.
47
RRP, Appendix 9
Candidate Subprojects
Upolu Tanugamanono Power Station 0.87 ICB May 2008 Y
noise and emission control
program (W-DSI)b
Upolu Refurbishment of Alaoa 1.40 ICB Sep 2008 Y
hydropower station (W-SI)
Upolu Upolu diesel power station 31.77 ICB Oct 2009 Y
inclusive of plant and control
equipment (W-DSI)c
Upolu Upgrade of the Alaoa 6.6 kV 1.14 ICB Jul 2009 Y
transmission line to 22 kV project
(W-SI)
Upolu Upolu diesel power station to 1.49 ICB Apr 2009 Y
Fuluasou Substation 22 kV
underground cable project
(W-DSI)b
Upolu Hospital Feeder upgrading 6.35 ICB Oct 2009 Y
project – Stage 2 (W-DSI)b
Upolu 22 kV Fuluasou Substation 1.40 ICB Nov 2009 Y
project inclusive of equipment
(W-DSI)b
49
Suppliers/
Executing Agency ADB Contractors
Loan/advance contracting
approved
Finalize list of goods/
works to bid (from
procurement plan)
ADB review and
a
Approval
Prepare draft invitation
for bids and bidding
documents
a
ADB review and approval
Advertise invitation for
Advertise invitation for bids bids in www.adb
Locally in English
and issue bidding
documents; inform ADB
of the advertisement; Purchase bidding
(minimum bidding period documents from EA
6 weeks) and submit bid
PQ applications received
Evaluate PQ applications
ADB review and approval a
Recommend prequalified firms
Estimated
Cost Procurement
Location Contract Description ($ million) Method
1. Upolu Hospital Feeder Upgrading Project – Stage 1 0.25 ICB Goods
0.35 NCB Works
2. Upolu and Savaii Single- and three-phase Prepayment Metering 6.07 ICB
3. Upolu Project Manager 0.75 Individual Selection
4. Upolu Project Implementation Consultants 2.67 QCBS
5. Upolu Tanugamanono Power Station noise and emission 0.17 ICB Goods
control program
6. Upolu Refurbishment of Alaoa hydropower station 1.34 ICB
7. Upolu Fiaga diesel power station 19.00 ICB
8. Upolu Upgrade of the Alaoa 6.6kV distribution line 0.65 ICB Goods
0.49 NCB Works
9. Upolu Fiaga diesel power station to Tanugamanono 33kV 8.83 ICB
underground project and Fuluasou Substation
10. Upolu Hospital Feeder upgrading project – Stage 2 0.96 ICB Goods
0.67 Works
11. Upolu and Savaii Low voltage network improvement program 1.29 ICB Goods
12. Upolu 22kV overhead conductor upgrading program 6.03 ICB Goods
NCB Works
13. Savaii Hydropower scheme 10.65 ICB
14. Savaii Puapua-Asau transmission line 22kV reconductoring 0.44 ICB Goods
project
0.80 NCB Works
15. Upolu and Savaii Measurement equipment electric high voltage/current 0.06 Shopping
16. Upolu and Savaii Measurement equipment stream-flow gauging 0.05 Shopping
17. Upolu and Savaii SCADA 3.48 ICB
18. Savaii Refurbishment of Salelolonga Diesel Power Station 5.90 ICB
19. Upolu Vending System 0.25 Direct Contract
20. Upolu Public Dissemination 0.10 Single Source
21. Upolu Taelefaga and Samasoni Switchgears 1.60 ICB
A. Basic Principles
1. All disbursements of loan funds will be made in accordance with the ADB’s Loan
Disbursement Handbook (January 2007 as amended from time to time), a copy of which was
provided to the Grant Recipient and EA. The Handbook is also available electronically in the
Loan and Grant Financial Information Web Services (http://lfis.adb.org). Users are advised to
visit the site regularly to ensure they have the latest version of the Handbook.
2. The three main principles of disbursement for development projects are as follows:
(i) proceeds of loans or any other financing provided by ADB shall be used only for
the procurement in member countries of goods and services produced in
member countries unless specifically permitted by its Board of Directors;
(ii) the Grant Recipient shall be permitted by the ADB to draw its funds only to meet
expenditures in connection with the project as they are actually incurred; and
(iii) the proceeds of any loan made, guaranteed, or participated by the ADB are used
only for the purposes for which the loan was granted, and with due attention to
consideration of economy and efficiency.
3. The goods and services and other items of expenditures to be financed out of the
proceeds of the Loan and the Grant and the respective allocation of amounts of the Loan and
the Grant among different categories of such goods and services and other items of
expenditures shall be in accordance with the provisions of Schedule 3A below (Loan) and
Schedule 3B (Grant) of the Financing Agreement. Such Schedules may be amended from time
to time by agreement between the Beneficiary and ADB.
4. Withdrawals from the Loan Account and the Grant account in respect of goods and
services shall be made only on account of expenditures relating to:
(a) goods which are produced in and supplied from and services which are supplied
from such member countries of ADB as shall have been specified by ADB from time to time as
eligible sources for procurement, and
(b) goods and services which meet such other eligibility requirements as shall have
been specified by ADB from time to time.
5. As stipulated in the Grant Agreement, no withdrawals shall be made from the Grant
Account until:
(i) The Government of Australia Grant shall have been transferred to an account at
ADB and be available for the Project;
(ii) Prior to the commencement of civil works for any Subproject facility: (i) the
Planning and Urban Management Agency of the Ministry of Natural Resources
and Environment shall have approved the application for development consent of
the preliminary environmental assessment report (PEAR) for any Subproject
facility; and (ii) ADB shall have approved the initial environmental examination
(IEE) for any such Subproject facility; and
(iii) Notwithstanding any other provision of the Financing Agreement, no withdrawals
shall be made from the Loan Account for the Vaita’i Hydropower Subproject until
the Beneficiary shall have entered into a legally binding agreement, or obtained a
court order, for the compensation of the relevant customary landowners for the
acquisition of the requisite land for the Subproject, in the event where the Vaita’i
Hydropower Subproject is selected as a Subproject. Such agreement shall
9Disbursement
56
include terms and conditions with respect to the 20 meter-wide road reserve
required to accommodate the existing access road from Sili Village to the Vaita’i
Hydropower Subproject site, inclusive of shoulders and table drains.
C. Retroactive Financing
D. Disbursement Procedures
7. The proceeds from the ADF loan, the ADF grant, the JBIC loan, and the grant provided
by the Government of Australia for the proposed Project will be disbursed in accordance with
ADB’s Loan Disbursement Handbook (2007, as amended from time to time). The Government
will submit separate withdrawal applications for the ADF loan, ADF grant, JBIC loan, and the
Government of Australia grant. To promote efficiency in processing disbursements from four
different sources under the Project, a minimum value per withdrawal application is set at
$100,000 equivalent or an amount determined to be a reasonable minimum. 1 Reimbursement
and direct payment procedures will apply for consulting services, civil works, and equipment
supply and installation. Reimbursement procedures will apply to land acquisition and
resettlement. The disbursement and funding arrangements is in RRP, Appendix 10, appended
at the end of this Section.
(Samples of WA forms are at the end of this Section; editable worksheets are being
provided separately to the EA/IA)
8. For all withdrawals, ADB must receive a original W/A in the prescribed format. A W/A is
a written request from the Grant Recipient to ADB to pay funds against the Grant Recipient’s
grant account. A W/A consists of: (i) an application itself, in letter form; (ii) summary sheets for
each category claimed or relevant original SOE form, where applicable; and (iii) supporting
documents, if required 2 . The Grant Recipient’s duly authorized representative signs each W/A.
9. W/As, summary sheets and items listed on every summary sheet should be
consecutively numbered. A sample “Master List of Withdrawal Application” form is provided at
the end of this Section. The complete name, address and account number of the beneficiary
bank should be indicated. In case the beneficiary bank is not located in the country of the
requested currency of payment, the complete name and address of its correspondent bank
operating in that country must be indicated.
10. Currency of Payment. In principle, payment is made in the currency in which the cost of
goods and services has been paid or is payable. For expenditures incurred in the Grant
Recipient’s currency (local currency), the amount requested in the W/A must be in local
currency. A separate W/A is required for each currency. However, the monitoring of the
expenditures will continue to be in US dollars, which is the currency of the Grant.
1
The minimum value per withdrawal for consulting services is set at $30,000 equivalent or an amount determined to
be a reasonable minimum.
2
For the SOE form, the supporting documents are retained in EA office for audit review and should not be submitted
to ADB. If payment is exceeding SOE ceiling of US$50,000, the supporting documents should be submitted.
57
11. Other Instructions. The signed original copy of the WA is submitted to ADB. The
accompanying summary sheet should be signed by the Grant Recipient’s authorized
representative and/or project official. Supporting documents may be submitted as photocopies.
Alterations on the application forms are initialed by the Grant Recipient’s authorized
representative. The minimum value per withdrawal application is US$50,000 unless otherwise
approved by ADB. The Grant Recipient is to consolidate claims to meet this limit for
reimbursement and imprest fund.
12. Procurement Contract Summary Sheets (PCSS). The PCSS number is assigned by
ADB for identifying a particular contract approved by the Grant Recipient and submitted to ADB.
It is advisable for the EA to provide a contract number for each approved contract to facilitate
monitoring of payments. The PCSS includes: (i) ADB contract number; (ii) date of contract
approval; (iii) mode of procurement; (iv) name of contractor or supplier; (v) terms of payment
and currency of contract; and (vi) percentage of ADB financing. The PCSS number is shown
on the summary sheet. To obtain the number, refer to ADB’s monthly report named List of
Contract by Executing Agency, which is available in the LFIS website.
13. On receipt of the W/A, the Bank’s Controller’s Department reviews the adequacy of
documentation in consultation, where necessary, with the department responsible for project
administration (in this case the ADB’s Pacific Operations Division). On approval of disbursement
by the Controller’s Department, the payment is made by the Treasurer’s Department. The Grant
Recipient and EA can monitor status of individual WA, total disbursements under loan and
individual contracts, capitalization and other loan information in the regular report of Controller’s
Department posted on LFIS/GFIS website (htpp://lfis.adb.org). To obtain the access to the
website, a request form (Appendix 47 of the Loan Disbursement Handbook) must be filled out
and signed by authorized representative of the Grant Recipient (same person, who is authorized
to sign WAs) and submitted to ADB. Upon receipt of the application, ADB will email the
confidential user id and password to the requested user.
14. As mentioned earlier, under the project, only the following disbursement procedures will
be used: Reimbursement and direct payment procedures will apply for consulting services, civil
works, and equipment supply and installation. Reimbursement procedures will apply to land
acquisition and resettlement.
15. Under the direct payment procedure, the Bank makes payment directly to the supplier,
contractor, or consultant, on the basis of a withdrawal application submitted by the Loan/Grant
Recipient.
16. Basic Requirements. A signed W/A must be submitted to ADB together with a
summary sheet (form ADB-DRP-SS, Appendix 8 of LDH) and the required supporting
documents. A separate W/A is required for each different currency.
9Disbursement
58
(i) For payment of consultant’s services, the supporting documents are: (i) signed contract,
consultant’s claim or invoice, and (iii) summary for out-of-pocket expenses claimed.
(ii) Payment for civil works requires the claim or invoice from the contractor and a summary
of work progress certified by the project engineer and approved by the Grant Recipient’s
authorized representative.
(iii) Payment for goods and equipment requires the supplier’s invoice specifying the goods,
quantities, and prices as well as, transport documents, i.e., airway bill, bill of lading, or other
similar documents.
2. Reimbursement Procedure
18. The reimbursement procedure is one whereby ADB pays from the loan/grant account to
the Grant Recipient’s account, or in some cases, to the Project account for eligible expenditures
which have been incurred and paid for by the Grant Recipient or EA out of its budget allocation
or its own resources.
19. Under this procedure, ADB’s payments are made only to the Grant Recipient or EA and
not to a third party (e.g., supplier, contractor, etc.)
21. Basic Requirements. A signed W/A must be submitted to ADB together with a
summary sheet (Appendix 8 of LDH), and the required supporting documents .
22. A separate WA must be submitted for each currency. A separate summary sheet must
also be submitted for each loan category or subcategory grouping items claimed by contract
number.
23. The expenditures should have been incurred and paid for by the Grant Recipient out of
its own fund sources.
24. Supporting Documents. The supporting documents are the same as in direct payment
procedure, but the evidence of payment by the Grant Recipient or EA showing the amount paid,
date of receipt and payee should be attached. If supporting documents are written in local
language, there should be an English translation of important words/items in the documents
(e.g. the title of the document, name of supplier/contractor, description of goods and services,
amounts and dates).
25. Reimbursement Process for Land Acquisition and Resettlement. In addition to the
WA, a copy of the relevant inventory of losses identifying: (i) the affected persons, and where
applicable, the matai representing the affected person; (ii) the nature of the losses incurred by
the affected person; and (iii) evidence of the agreed compensation to the affected person in the
form of cancelled check, or a receipt signed by the affected person or, by the matai representing
the affected persons as identified in the inventory.
26. The most common causes of delays in processing withdrawal applications are:
27. In order to effectively monitor project implementation, EA/IAs are requested to prepare
accurate projections of contract awards, commitments and disbursements. Projections are to be
compared with actual achievements which will help identify impediments to implementation
progress and provide remedial measures. Accurate projections help ADB in planning its own
cash flow and portfolio management. Projections worksheet QP-10 (copy attached) are given to
EAs to complete and return to ADB at the start of each year.
I. Disbursement Reports
28. Grant Recipients and EAs are given loan information in the following regular reports.
These reports and other information are available online at the LFIS/GFIS website at
http://lfis.adb.org.
29. The loan/grant closing date is the last date for the Recipient to make withdrawals from
the loan/grant account. Action is taken by the Bank to close the account in consultation with the
Recipient when the Bank is satisfied that no further disbursements are likely to occur.
Expenditures incurred after the closing date will not be financed under the Loan/Grant.
30. The loan/grant account is closed after the Bank notifies the Recipient of the closure of
the account, cancels the unutilized loan balance and adjusts any unliquidated advances. For
purposes of this grant, the closing date for withdrawals from the grant Account shall be 31
December 2016 or such other dates as may from time to time be agreed between the Grant
Recipient and the Bank.
9Disbursement
60
31. Closing dates may be extended in justifiable cases and after ensuring that adequate
arrangements exist for completing the project within the extended timeframe. When extension of
the grant closing date is necessary, the Recipient submits a request to ADB, or in the absence
of such a request, the projects division, in this case, Pacific Operations Division (PAHQ),
proposes a revised closing date to the Recipient and ask the Recipient to confirm the proposal.
Upon receipt of confirmation from the Grant Recipient, the proposal is submitted for approval of
appropriate authority in the ADB.
32. When extension of the grant closing date is not justified or considered not necessary,
ADB may allow up to three months after the grant closing date for the Grant Recipient’s W/A to
reach ADB or for the Grant Recipient to liquidate fully all expenditures incurred before the grant
closing date, or refund any outstanding imprest account balances.
33. The proceeds of the Loan will be used only for the purposes for which the Loan was
approved. The ADB allows a reallocation of proceeds if: (a) the amount of the Loan allocated to
any Category appears to be insufficient to finance all agreed expenditures in that Category. The
Bank may, by notice to the Recipient, (i) reallocate to such Category, to the extent required to
meet the estimated shortfall, amounts of the Grant which have been allocated to another
Category but, in the opinion of the ADB, are not needed to meet other expenditures, and (ii) if
such reallocation cannot fully meet the estimated shortfall, reduce the withdrawal percentage
applicable to such expenditures in order that further withdrawals under such Category may
continue until all expenditures shall have been made; and (b) the amount of the Loan then
allocated to any Category appears to exceed all agreed expenditures in that Category.
61
RRP, Appendix 10
Introduction
1. The proceeds from the Asian Development Bank (ADB) loan and grant, the Japan Bank
for International Cooperation (JBIC) loan, and the grant provided by the Government of
Australia for the proposed Project will be disbursed in accordance with ADB’s Loan
Disbursement Handbook (2007, as amended from time to time). The Government will submit
separate withdrawal applications for the Asian Development Fund (ADF) loan, the ADF grant,
the JBIC loan, and the Government of Australia grant. To promote efficiency in processing
disbursements from four different sources under the Project, a minimum value per withdrawal
application is set at $100,000 equivalent or an amount determined to be a reasonable
minimum. 3 Reimbursement and direct payment procedures will apply for consulting services,
civil works, and equipment supply and installation. Reimbursement procedures will apply to land
acquisition and resettlement.
2. ADB loan proceeds will be utilized to finance civil works (48% of financing) and
equipment supply and installation (31% of financing). ADB grant proceeds will be utilized for
consulting services and equipment supply and installation. For consulting services, the financing
percentage of 95% will be applied to individual claims. The total financing of ADB grant
proceeds under the category of equipment supply and installation represents 13.7%. The
financing percentages that provide the basis for withdrawal for the ADB grant for equipment
supply and installation will apply on an annual basis in accordance with Table A10.1. 4
Reallocation of the ADB loan and grant proceeds among categories can be made in accordance
with ADB established procedures.
3. The JBIC loan will be utilized for civil works (42% of financing) and equipment supply
and installation (47% of financing), as detailed in Appendix 6 (Table A6.2). Disbursements for
the JBIC loan will be administered by ADB. Two withdrawal applications, signed by the
authorized signatory of the Government, together with relevant supporting documents, will be
submitted to ADB and JBIC simultaneously. Direct payment and reimbursement procedures will
be applied in accordance with the Loan Disbursement Handbook. ADB and JBIC may
reasonably request additional information or documentation related to disbursements under the
Project. Reallocation of the JBIC loan proceeds can be done among cost categories in
accordance with ADB established procedures, subject to prior approval of JBIC.
4. The Government of Australia will provide a grant for the purpose of counterpart financing
requirements of the Government of Samoa. The grant will be administered by ADB and will be
utilized to finance land acquisition and resettlement and equipment supply and installation. The
financing percentage of 35% will be applied to individual payment requests for land acquisition
and resettlement. The financing percentages for equipment supply and installation will be
applied in accordance with Table A10.2, which will provide the basis for withdrawal for the
Government of Australia grant. The total financing of the Government of Australia grant
proceeds for equipment supply and installation represents 8.5%.
Table A10.2: Annual Financing Percentages for the Government of Australia Granta
5. Disbursements of the Government of Australia grant for the purpose of financing eligible
project expenditures will be in accordance with the Loan Disbursement Handbook and other
arrangements as stipulated below. Requests for disbursements will be submitted to ADB.
6. Reimbursement procedures will apply to eligible expenditures for land acquisition and
resettlement. Land acquisition and resettlement will be carried out in accordance with the
Taking of Land Act (1964) and ADB’s Involuntary Resettlement Policy (1995). The expenditures
will be reimbursed based on submission of the following supporting documentation, or as
otherwise could be reasonably requested by ADB.
(ii) A copy of the relevant inventory of losses identifying (a) the affected person(s),
and, where applicable, the matai (footnote 1, Appendix 7) representing the
affected person; (b) the nature of the losses incurred by the affected person(s);
and (c) the agreed compensation payable to the affected person(s).
(iii) Evidence of the agreed compensation to the affected person(s) in the form of (a)
copy of the cancelled check (check that has been paid), which shows the check
number, the payee, the payment date, and the amount; or (b) a receipt signed by
the affected person(s) or, where applicable, by the matai representing the
affected person(s) as identified in the inventory of losses
7. The equipment supply and installation will be mostly paid through direct payment
procedure.
8. Reallocation of the Government of Australia grant proceeds can be done among cost
categories in accordance with ADB established procedures, subject to prior approval of the
Government of Australia.
9Disbursement
64
1. EPC will establish a PPMS to facilitate the reporting requirements. The PPMS will
assess progress and implementation of the Project, including (i) resettlement activities, (ii)
compliance with the EARF and subproject EMMPs, and (iii) compliance with ADB’s loan
covenants. The PPMS will also monitor the operational efficiency and financial position and
projections of EPC to enable benchmarking against other utilities.
2. The Power Sector Expansion Project will help provide sustainable and reliable electricity
services to all consumers in Samoa. The unreliable and poor quality electricity supply is
affecting all consumers and is becoming an increasing constraint to the expansion of the
tourism industry and economic growth. Once the benefits of the investment plan have been
realized, improvements in power supply cost effectiveness will reduce the need for tariff
increases.
4. As subprojects included under the investment plan are not stand-alone investments that
yield benefits in isolation from other investments in the power sector, the economic and financial
analyses were undertaken using a time-slice approach for EPC’s two power systems on Upolu
and Savai’i. The analyses are conducted for 23 years, including the investment period of 8
years. Oil prices were assumed to be constant at $60 per barrel (bbl) throughout the period of
analysis. Estimated annual CDM credits of $45,000 for the Savai’i hydropower project were
included in the analyses. The economic and financial analysis is in RRP, Appendix 12,
appended at the end of this Section.
5. Least-cost analyses were undertaken for the underground cabling program on Upolu
and for the hydropower project on Savai’i. Under conservative assumptions on the cost of
cyclone damage to the transmission lines, it would take about two cyclones for the underground
cabling program to become least-cost. During the first year of full operation, the hydropower
project on Savai’i would replace 96% of generation by the existing diesel power station at
Salelologa. With demand growth, this percentage will drop to 75% by 2020. The results show
that the hydropower project is least-cost if the average oil price over the period of analysis
exceeds $53.50 per bbl.
6. In the absence of an investment plan on Upolu, the economic analysis assumes that
EPC would serve demand from its existing generation capacity. Unserved demand initially
represents deficits in peak capacity. The transmission system will increasingly become a
65
bottleneck for power supply to consumers and system losses will increase. The economic
internal rate of return (EIRR) for the investments on Upolu is estimated at 13.6%. Benefits which
are difficult to quantify, such as those associated with the noise and emission control program at
the Tanugamanono power station and the protection of transmission lines against climate
change, have not been included in the analysis. The result is most sensitive to the estimated
capital costs. Capital cost increases of more than 14% would make the EIRR fall below 12%.
7. In the absence of investments on Savai’i, it is assumed that EPC would meet demand
with its existing diesel power station. No improvements in the power factor or system upgrades
would take place. The without-investment scenario is associated with increased system losses
and higher operations and maintenance costs. Under the base-case fuel price assumption of
$60 per bbl, the economic analysis yields an EIRR of 10.7%. As the hydropower project is a
major component of the investments on Savai’i, the economic results are most sensitive to
operations and maintenance costs, and in particular to assumptions on international fuel prices.
An international fuel price of $67 per bbl will increase the EIRR to 12%.
8. The financial analyses assume that all project capital and operations and maintenance
costs are borne by EPC. The financial benefits comprise projected sales based on tariff
projections, demand forecasts, and estimated carbon credits of $45,000 per year. The
incremental financial costs comprise capital, operations and maintenance, and system losses.
Financial benefits and costs were discounted by the weighted average cost of capital (WACC),
calculated at 4.5. The financial net present values discounted at the WACC for the investment
plan are ST44.1 million ($17.3 million) for the investments on Upolu and ST27.9 million ($10.9
million) for Savai’i. The financial rates of returns are 7.0% for the investments on Upolu and
12.1% for Savai’i. The financial result for Upolu is most sensitive to an increase in capital costs,
followed by a reduction in sales. The investment plan would remain financially viable if
investment cost increases do not exceed 31%. The financial result for Savai’i is most sensitive
to changes in fuel prices, but the international oil price would need to drop to below $27 per bbl
to undermine financial viability.
C. Impacts
9. To ensure that social, land acquisition, resettlement, and environment impacts are
mitigated under the Project, EPC will establish an environment and social unit (ESU) to plan,
implement, and coordinate land acquisition, resettlement, and environmental activities prior to
loan effectiveness. The ESU will initially be an integral part of the PMU but will eventually
become a permanent unit within EPC. The ESU will be responsible for establishing a register to
record and monitor temporary and permanent land acquisition and record consultations and
grievances relating to land acquisition and resettlement.
10. A LARF (Supplementary Appendix C) has been prepared in accordance with the Taking
of Lands Act (1964) and ADB’s Involuntary Resettlement Policy (1995), Handbook on
Resettlement (1998), Operations Manual F2 on Involuntary Resettlement (2006), Handbook on
Poverty and Social Analysis (2001), and Handbook for Incorporation of Social Dimensions in
Projects (1994). 1 The LARF will guide the preparation and procedures for land acquisition and
1
ADB. 1994. Handbook for Incorporation of Social Dimensions in Projects. Manila; ADB. 1998. Handbook
on Resettlement. Manila; ADB. 2001. Handbook on Poverty and Social Analysis. Manila; and ADB.
2006. Operations Manual. Section F2: Involuntary Resettlement. Manila.
66
resettlement plans (LARPs) for candidate subprojects under EPC’s investment plan.
Subprojects classified category A will require a LARP, category B subprojects will require a
short LARP, and category C subprojects will not require any LARP. Candidate subproject
LARPs will be prepared in full consultation with affected people and disclosed to them in draft
form and included in the feasibility studies for candidate subprojects. Compensation and
entitlements will be consistent with those in the entitlement matrix outlined in the LARF. All
affected people will be provided with compensation if (i) land is permanently or temporarily
acquired, (ii) their crops and trees are damaged or destroyed, or (iii) access to their traditional
lands is limited or blocked as a result of the subproject. Lack of legal documents pertaining to
their customary rights of occupancy, or lack of titles, will not affect affected people’s eligibility for
compensation.
11. The two core subprojects (the Hospital Feeder upgrading project – stage 1, and the
supply and installation of prepayment meters) will not have land acquisition and resettlement
impacts, are classified category C, and do not require LARPs.
12. A summary poverty reduction and social strategy was developed based on the findings
of an initial poverty reduction and social assessment and social surveys. During development of
EPC's investment plan, consultations with representatives of communities, government
ministries, and other stakeholders were undertaken. Focus-group consultations were held with
women. No specific impacts to women are envisaged. If land acquisition is required, women will
be incorporated into the consultation and decision-making process. A summary poverty
reduction and social strategy is presented in RRP, Appendix 13, also found at the end of this
Section.
3. Environment
13. An EARF (Supplementary Appendix D) has been prepared in accordance with the
Government’s environmental requirements as set out in the Planning and Urban Management
Act (2004), the Draft Planning and Urban Management (Environmental Impact Assessment)
Regulations (2007), and ADB’s Environment Policy (2002) and Environmental Assessment
Guidelines (2003). 2 The EARF will guide the preparation and approval procedures of
environmental assessments of candidate subprojects under EPC’s investment plan. Subprojects
with environmental category A are not envisaged and will not be eligible for ADB financing
under the Project.
14. Candidate subproject IEEs will be included in the feasibility studies for submission to
ADB. An EMMP will be required for subprojects classified as environmental category B or B-
sensitive. Subproject feasibility reports will identify adequate funding for EMMPs. Subproject
EMMPs will be reflected in the bid documents, incorporated into project design, and included in
civil works contracts for subprojects. The PMU and contractors will be guided by the EMMPs in
managing, monitoring, and reporting environmental impacts and compliance. Civil works may
only commence once the IEE report of subprojects are approved by ADB and the development
concept approval of the PEAR is issued by PUMA.
15. The Hospital Feeder upgrading project – stage 1 is classified environmental category B,
and the supply and installation of prepayment meters project is classified category C. An IEE
2
ADB. 2003. Environmental Assessment Guidelines. Manila.
67
has been prepared for the Hospital Feeder upgrading project – stage 1 (Supplementary
Appendix E). The summary initial environmental examination is in Supplementary Appendix F.
An IEE is not required for the prepayment metering project.
16. Debt Sustainability. EPC’s investment plan and financing arrangements have been
prepared considering Samoa’s debt sustainability. To ease the macroeconomic impact of the
large financing requirements in the power sector, ADB will provide an ADF IX grant of $15.39
million. The ADB and JBIC concessional loans are projected to increase Samoa’s external debt
burden from 37% of GDP in 2007 to about 39% in 2011.
17. Political Commitment to Power Sector Reform and Good Governance. Power
sector reform, including cabinet and parliamentary approval of an electricity act to govern all
stakeholders and the establishment of a regulatory agency, is critical to improving the
performance of the power sector and ensuring that investments translate into benefits for
electricity consumers. The TA cluster for Implementing the Samoa National Energy Policy will
assist the Government (i) in the consultation process, (ii) to draft and amend legislation, and (iii)
establish the regulatory agency. Assurances under the Project reflect the key milestones for
regulatory reform.
18. EPC’s Affordability. EPC’s affordability of the investment plan and debt repayment
capacity has been carefully considered in the selection and timing of subprojects. To ensure
that timely adjustments to tariffs can be made in response to increases in EPC costs, a formal
mechanism for determining tariffs within the context of an overall regulatory framework needs to
be established. Until a tariff mechanism can be established, the Government has introduced a
fuel surcharge which is subject to review by cabinet every 6 months. 3 Ongoing policy dialogue
and annual updates of EPC’s financial projections will help assess tariff requirements. To
address EPC’s poor collection performance, the Government will clear all arrears by
government ministries and state-owned entities prior to loan effectiveness, and prepayment
metering will be installed for EPC consumers. The assurances under the Project include that
75% of all consumers are on prepayment meters by the end of 2012. In the case of certain
basic social services where suspending electricity services may not be possible, budgetary
allocations for electricity consumption will be paid directly to EPC.
20. EPC’s Implementation Capacity and Cost Overruns. To manage the risk of delays,
consultations with the attorney general have been held to ensure that Government requirements
for loan effectiveness are addressed in a timely manner and draft bid documents have been
prepared to help ensure timely implementation of core subprojects. Approval of advance
procurement action will help ensure that construction activities can commence in accordance
with the implementation schedule. Advance recruitment of the project manager and
implementation consultants will help mitigate EPC’s capacity constraints in project preparation
3
More frequent reviews are being considered by cabinet.
68
and procurement activities. To the extent possible, EPC will apply plant design, supply, and
install contracts to reduce the burden of coordination of construction activities.
E. Project Review
21. ADB will undertake an inception mission 1 month after loan effectiveness or 1 month
after fielding of project implementation consultants, whichever is later. Review missions will be
undertaken at 6-monthly intervals (starting 6 months after the inception mission) for the initial 3
years of the Project. The review missions will include an evaluation of (i) project scope and
costs; (ii) implementation arrangements; (iii) progress in implementing the LARF, EARF, and
subproject IEEs and EMMPs as applicable; and (iv) achievement of scheduled targets and
identification of project risks. The review missions will also undertake ongoing policy dialogue on
(i) EPC’s operational efficiency and financial performance, (ii) the Government’s progress on
power sector reforms, and (iii) compliance with loan covenants. ADB will field a midterm review
4 years after loan effectiveness.
69
RRP, Appendix 12
ECONOMIC AND FINANCIAL ANALYSES
1. Samoa is a small and highly import-dependent country that relies largely on official
transfers and remittances for foreign currency revenues. Despite vulnerability to external
shocks, the Independent State of Samoa has experienced stable economic growth over the last
5 years. Real gross domestic product (GDP) grew at around 4% per annum, well above the
average growth rate of the Pacific region economies. The annual long-term growth rate is
expected to be around 3.5%. Economic growth is mainly driven by agriculture, construction,
finance, and business services. Samoa is also benefiting from an increase in tourism. Further
broadening of economic activity and private sector development are key strategies for
sustaining economic growth rates and reducing poverty.
2. The Government’s Strategy for the Development of Samoa 2005–2007 lays the
foundation for sustainable and broad-based economic growth supported by continued reforms
and private sector development to improve the quality of life for all people in Samoa. Ensuring
that sufficient power is available to meet growing demand is essential to achieving a broader
economic base and reducing the country’s vulnerability to external shocks.
3. The power sector in Samoa has undergone a rapid transformation over the last decade
towards an energy supply based on imported petroleum and hydropower-generated electricity.
This transformation has been driven by economic growth that has resulted in increasing
demand for electricity and transportation. Energy demand in Samoa is met by three main
sources: biomass (47%), fossil fuel (45%), and hydropower (8%). Biomass is mainly used for
cooking whereas imported petroleum is used for transportation and power generation. Imports
of petroleum products account for 15% of Samoa’s total import expenditure. Power generation
accounts for about 20% of total imported petroleum.
4. More than 90% of the country’s electricity demand is on Upolu, which is also the main
source of growth in Samoa. Peak electricity demand reached 17.6 megawatts (MW) in 2007.
Annual peak demand is expected to grow by 7% in the short term and by 4% beyond 2009
(Table A12.1). By 2008, the Electric Power Corporation (EPC) will not be able to reliably meet
demand. 4 In the short term, EPC will utilize existing self-generation by large consumers to meet
peak demand. 5 By 2010, the existing run-of-the-river hydropower station at Alaoa will be
refurbished and by 2011 EPC will need to commission additional generation capacity to meet
both energy and peak demands.
4
Assumes a reliability criteria of the available capacity minus the capacity of the largest generator.
5
The capacity of existing self-generation is estimated to be about 8 MW.
70
Investment Plan
6. The investment plan covers the two power systems on Upolu and Savai’i. EPC’s
investment plan will meet forecast demand requirements up until 2019, when new capacity will
be required on Upolu, and help EPC improve its collection performance through the installation
of prepayment meters. The investment plan comprises three generation and nine transmission
projects on Upolu, and one generation and three transmission projects on Savai’i. Investment in
single- and three-phase prepayment meters, system control and data acquisition (SCADA), and
portable equipment for measuring voltage and current and for stream-flow gauging are included
for both the Upolu and Savai’i power systems.
7. Identified generation projects are based on analysis of the power and energy balances
for each of the power systems. Investments in the transmission networks are driven by the need
to improve reliability, reduce losses, and meet peak requirements, and have been identified
based on detailed load-flow analysis of the performance of individual transmission lines, and the
system as a whole. The timing of investments in generation on Upolu is initially driven by peak
capacity requirements. The existing generation capacity can meet energy requirements to 2013
71
8. Projects under the investment plan are prioritized to improve reliability and security of
power supply to the main load center in Apia and to improve EPC’s revenue collection. EPC
plans to improve utilization of the existing transmission system, and reliability of supply, by
replacing the existing 6.6 kilovolt (kV) overhead transmission lines with a 22 kV underground
cable. This is the first phase of a three-phase underground program that aims to secure
electricity supply to the main load centers and the hospital, and protect the key transmission
lines against cyclone damage. The underground program is expected to be fully completed by
2013. EPC’s revenue collection will be improved through the installation of prepayment meters
to all consumers on Upolu and Savai’i. The supply, installation, and operation of the SCADA
system will enhance the control systems and improve operational system efficiency on both
Savai’i and Upolu. Transmission upgrades and expansion of the low voltage distribution network
will take place throughout the investment plan, commencing in 2008. EPC’s investment plan is
detailed in Appendix 3 and Supplementary Appendix G.
Least-Cost Analysis
9. Projects under the investment plan were included and sequenced to account for EPC’s
financial and implementation capacity. Feasible alternatives for the proposed generation
projects are limited. The generation projects included for expansion on Upolu include the
refurbishment of the existing 1 MW Alaoa hydropower station by 2010 and a new 12.9 MW
diesel power station for which commissioning of three 4.3 MW diesel generators would be
sequenced between 2011 and 2014. Up until 2011, EPC may face capacity shortages in reliably
meeting peak demand during the dry season. Utilization of existing stand-by self-generation
capacity enables EPC to manage the risk of capacity shortages until adequate transmission
capacity has been commissioned. Two possible hydropower sites at Lotofagauta and Tia'vea
were identified on Upolu. However, given technical, capacity, cost, and social uncertainties with
these projects, they were not included in EPC’s investment plan for 2008–2015.
10. A least-cost analysis for generation options on Savai’i was undertaken to ascertain
whether the proposed 1 MW firm capacity run-of-the-river hydropower scheme would represent
the least economic cost option for meeting demand to 2030. The capital costs include cost for
resettlement and land acquisition. Taxes, duties, and value-added government sales tax were
excluded for all capital, insurance, and operations and maintenance costs.
11. Average annual output is estimated at 11.8 GWh, which would provide 96% of
generation requirements on Savai’i in 2015. With demand growth, the share of hydropower
would reduce to 75% by 2020. The balance of generation requirements would be met by the
existing diesel power station, which would mostly be used to meet peak demand. The hydro-
diesel mix option was compared to a diesel-only option, where the existing power station would
be maintained to meet demand growth to 2030. Commencing in 2015, 3,355 tons (t) of diesel
fuel would be saved annually; by 2017, savings would increase to 3,446 t annually. The result of
the least-cost analysis is presented in Table A12.2. The results of the sensitivity analysis
6
This energy balance deficit assumes that transmission investments are undertaken as per the
investment plan to reduce system losses.
72
suggest that the hydro-diesel mix option would become unviable at an international oil price
about $53.5 per barrel (bbl), equivalent of an economic cost of ST1.316 per liter (l).
12. The underground cabling program on Upolu aims at enhancing transmission capacity
and improving reliability to the main load centers in Apia, the industrial area at Vailima, and the
hospital. The program will commence in 2008 and be fully completed by the end of 2014. It
includes (i) two stages of upgrading and underground cabling of the existing 6.9 kilometers (km)
of the Hospital Feeder (1.1 km of which is currently underground), (ii) upgrading the capacity
and underground cabling of the Vaitele Feeder, and (iii) underground cabling of a new 22 kV
transmission line from the proposed Vaitele Substation to the wharf area and through the
industrial area at Vailima to the airport.
13. The first stage of the Hospital Feeder upgrade will improve utilization of the Vaitele
Feeder and reduce the load on the Hospital Feeder. Load-flow analysis show that the Hospital
Feeder is currently experiencing overloads and voltage drops, and is increasingly becoming a
bottleneck to reliable electricity supply both to Apia’s main commercial and government district
and to the hospital. By 2011, overloading on this transmission line will be 30% and the voltage
drops will have increased from 11% in 2006 to 20% by 2016, when the overloading will be about
70%. Losses are estimated to increase from 6% in 2006 to 11% by 2016.
14. Since the early 1990s, Samoa has experienced four serious cyclones. The two cyclones
in the early 1990s caused damage estimated at $120 million (26% of GDP) and $200 million
(46% of GDP). With global warming, the incidence and severity of cyclones can be expected to
increase in the future. The 2004 cyclone caused damage to key infrastructure assets alone
estimated at $25 million, excluding the cost to the power sector and impacts on economic
activity. EPC estimated the cost of damage to power sector assets at $2.8 million in addition to
a loss of 2.73% of total sales for 2004.
15. The difference in economic net present value costs for the underground cabling program
versus overhead transmission lines is $4.04 million. Assuming that the costs of damage from a
cyclone would amount to 25% of the investment cost in overhead transmission lines, it would
take about two cyclone events for the underground program to become least cost. Cost saving
associated with the longer economic life of underground cables, reduced operation and
maintenance costs, and loss of economic production and activity, including the opportunity cost
of self-generation caused by disruptions in power supply associated with cyclone damage, have
been excluded from the analysis. Underground cabling of key transmission lines forms part of
the Government’s national risk management strategy to improve resilience against natural
hazards and climate change.
73
Economic Analysis
16. As subprojects included under the investment plan are not stand-alone investments that
yield benefits in isolation from other investments, the economic analysis was undertaken for
EPC’s two power systems on Upolu and Savai’i using a time-slice approach. The analysis is
conducted from 2008 to 2030 with an investment period from 2008 to 2015. The economic
capital costs include investment costs and costs for project management and implementation,
environment management and mitigation, and resettlement and land acquisition. It was
assumed that the economic opportunity cost of land is 25% of the financial compensation.
17. The net economic benefits for the two power systems on Upolu and Savai’i were derived
by comparing the performance of the power systems on Upolu and Savai’i under a with-
investment plan scenario and a without-investment plan scenario. On Upolu, 97% of the capital
cost for prepayment meters and 78% of the SCADA costs and project management and
implementation were allocated to the system, with the remaining 3% of the capital cost for
prepayment meters and 12% of SCADA costs and project management and implementation
allocated to Savai’i. It was assumed that EPC staff costs (the second largest operation and
maintenance cost after fuel) would remain the same under both the with-investment and
without-investment scenarios.
18. In the absence of an investment plan on Upolu, the economic analysis assumes that
EPC would serve demand from its existing generation capacity. Unserved demand initially
represents deficits in peak capacity. The transmission system will become an increasing
hindrance to power supply to consumers and system losses will increase until generation
capacity reached its maximum output in 2017. 7 With increased system losses and growing
demand, energy deficits will commence in 2013. Incremental benefits were valued at the
willingness to pay, estimated at ST0.99 per kWh. 8 The economic internal rate of return (EIRR)
for the investments on Upolu is estimated at 13.6%. Benefits which are difficult to quantify, such
as those associated with the noise and emission control program at the Tanugamanono power
station and with protection of transmission lines against climate change, have not been included
in the analysis. The result is most sensitive to the estimated capital costs, followed by the
assumptions of benefits. Capital cost increases of more than 14% would make the EIRR fall
below 12%. A 20% reduction in benefits would reduce the EIRR to just below 12%.
19. The with-investment scenario on Savai’i would yield benefits associated with reduced
fuel and operation and maintenance costs and an annual economic benefit of $45,000 in
carbon-market credits associated with the reduced diesel usage resulting from the hydropower
project. The without-investment scenario assumes that no new investments will take place on
Savai’i. Demand would be met by the existing diesel power station at increased fuel and
operation and maintenance costs. The calculations do not include benefits associated with
reduction of noise and fumes from the existing power station at Salalologa. The analysis under
the base-case fuel price (the equivalent of $60 per bbl) yields an EIRR of 10.7%. The result is
most sensitive to changes in operation and maintenance costs followed by capital costs. If the
international oil price over the period averaged $67 per bbl, the EIRR increases to 12%. A
7
The existing overhead lines to main load centers in Apia would also remain vulnerable to cyclones.
8
The methodology for calculating the willingness to pay followed the approach outlined in ADB’s
Economics and Research Department Technical Note No.3, Measuring Willingness to Pay for
Electricity. The estimated weighted average willingness to pay for domestic and nondomestic
consumers is ST0.99 ($0.388) per kWh.
74
capital cost increase of more than 4% would reduce the EIRR to below 10%. The details of the
economic analysis are in Supplementary Appendix I.
Financial Analysis
20. The financial analysis was undertaken based on a comparison of the financial costs and
benefits associated with the investment plan for the two separate power systems on Upolu and
Savai’i. Financial benefits comprise (i) projected revenue based on tariff projections, (ii) load
forecasts, and (iii) estimated carbon credits of $45,000 per year. The incremental financial costs
comprise capital, operation and maintenance (including fuel), and system losses. Financial
benefits and costs were discounted by the weighted average cost of capital (WACC), calculated
at 4.5% (Table A12.3). The WACC is calculated in real terms for EPC’s investments for 2008–
2015. The financing sources comprise EPC’s equity contributions (financed through retained
earnings), the Government’s equity contributions (financed by the Government of Australia), and
foreign exchange loans from the Asian Development Bank (ADB) and the Japan Bank for
International Cooperation (JBIC) relent to EPC in local currency at an interest rate of 6.5%. The
cost of EPC’s equity is estimated at 15.2% on the basis of a risk-free rate of 9.6% of New
Zealand dollar denominated bonds issued by the Government of New Zealand, and adjusted for
Samoa. Assumptions underlying the WACC computations include that EPC will not be required
to pay tax, and an average domestic inflation of 3.6%.
Government
Government and
Item Relending of Loans Total
EPC Equity
ADB JBIC
Amount ($ million) 42 38 20 100
Weighting (%) 42.00 38.00 20.00 100
Nominal Cost (%) 6.50 6.50 15.20
Tax Rate (%) 0.00 0.00 0.00
Tax Adjusted Nominal Cost (%) 6.50 6.50 15.15
Inflation Rate (%) 3.58 3.58 3.58
Real Cost (%) 2.82 2.82 11.16
Weighted Average Cost of Capital (%) 1.18 1.07 2.23 4.48
ADB = Asian Development Bank, EPC = Electric Power Corporation, JBIC = Japan Bank for International
Cooperation.
Source: ADB estimates.
21. The financial net present values discounted at the WACC for the investment plan is
ST44.1 million ($17.3 million) for the investments on Upolu and ST27.9 million ($10.9 million) for
Savai’i. The financial rates of returns are 7.0% for Upolu and 12.1% for Savai’i. The financial
result for Upolu is most sensitive to an increase in capital costs, followed by a reduction in
benefits (sales). The investment plan would remain financially viable if capital cost increases do
not exceed 31%. The financial result for Savai’i is most sensitive to changes in fuel prices, but
the international oil price would need to drop to below $27 per bbl to undermine financial
viability. The details of the financial analysis are in Supplementary Appendix J.
75
RRP, APPENDIX 13
Is the sector identified as a national Yes Is the sector identified as a national Yes
priority in country poverty analysis? priority in country poverty partnership
No agreement? No
Contribution of the sector or subsector to reduce poverty in Samoa:
Despite vulnerability to external shocks, the Independent State of Samoa has experienced stable economic growth
over the last 5 years. Real gross domestic product grew at around 4% per annum, well above the average growth rate
of the Pacific region economies. Economic growth is mainly driven by agriculture, construction, finance, and business
services. Samoa is also benefiting from an increase in tourism. Further broadening of economic activity and private
sector development are key strategies for sustaining economic growth rates and reducing poverty. The Government’s
Strategy for the Development of Samoa 2005–2007 lays the foundation for sustainable and broad-based economic
growth supported by continued reforms and private sector development to improve the quality of life for all people in
Samoa. Ensuring that sufficient power is available to meet growing demand is essential to achieving a broader
economic base and reducing the country’s vulnerability to external shocks.
With the rural electrification program nearing completion, 95% of the population has access to electricity. Good
performance of the power sector and reliable electricity services are vital for promoting private sector investments to
diversify the economy and achieve sustainable economic growth. Electricity is also an intermediate input to the
provision of basic social services, including health, education, and water supply. Inadequate and unreliable power
supply is an increasing hindrance to economic growth and is affecting all consumers in Samoa. Poor people are
disproportionately affected by poor reliability and quality of power supply, and by inefficiencies in the power sector.
The Electric Power Corporation’s (EPC) investment plan includes prepayment meters for all consumers on Savai’i and
Upolu. Prepayment meters allow households to be more aware of their electricity consumption and better manage
their consumption to match income streams. EPC has so far installed 1,200 prepayment meters on Upolu and social
acceptance is high.
A rapid social assessment (RSA) was conducted within the Sili area on the south coast of Savai'i. Community
participation through key respondent interviews and focus-group discussions in the project areas highlighted several
major perceived sector issues.
(i) Electricity is a major cost to most households in Savai'i. RSA survey data analysis showed that households on
Savai'i allocate on average 10% of monthly income to purchase electricity. Of the residential households surveyed,
32% stated that they are unable to pay electricity bills on time due to household cash flow constraints, and 14% had
had their electricity supply disconnected due to late payment. A number of households (16%) stated that their
neighbors had opted not to reconnect the electricity supply as they are unable to pay their monthly electricity bills.
(ii) The majority of residential and commercial consumers (67%) rated the quality of EPC’s services as good, 31%
rated EPC's service as average, and 2% were dissatisfied. Survey respondents expressed concern over the growing
frequency of electricity supply interruptions and 84% stated that the quality of electricity services on Savai'i needs to
improve. During the second half of 2006, there were 32 power supply interruptions which lasted for an average of 40
minutes each.
(iii) About 97.3% of the RSA respondents agreed that electricity is important to households and businesses because of
the benefits provided by electricity and its contribution to the maintenance of peace and order in the villages through
the provision of street lighting. Most households surveyed (74%) stated that they were unwilling to pay high electricity
tariffs for improved electricity services.
(iv) Perceived benefits of the electrical services include (a) prolonging the study time of school children, (b) savings on
76
expenses and making household chores convenient, (c) enjoyment in watching television programs or listening to
radio programs, and (d) enhancement of skills which are dependent on electricity, such as refrigeration and electronic
repairs and steel fabrication.
C. Participation Process
A stakeholder analysis was prepared as part of the community and household consultations for the Vaita'i Hydropower
Subproject. A physical scale model was displayed to the communities and used to explain the impacts of the Vaita'i
hydropower project during a series of community meetings undertaken in March 2007. A project information booklet
was provided in the Samoan language to ensure that the impacts of the project could be clearly understood. Separate
consultations were also undertaken with women. In general, affected people responded positively to the project but
consensus has not been reached. Therefore, the project is postponed until 2013 or until such time as the communities
accept the project. Until acceptable renewable generation sources can be developed on Savai’i, the people of Savai’i
will have access to electricity supplied from the existing diesel power station at Salalologa. EPC’s investment plan
includes a control system and a power factor improvement project for the power system on Savai’i. This is expected to
lead to improvements in quality and reliability of electricity supply provided that existing diesel generators are operated
and maintained adequately.
Candidate subprojects will require community acceptance prior to implementation. An environmental and social unit
will be formed within EPC and will operate within the project management unit. The environmental and social unit will
be responsible for stakeholder consultations and manage project environmental, land acquisition, and resettlement
activities. Project information booklets will be prepared for each candidate subproject and disclosed to affected people
in the wider community.
Further stakeholder analysis will be undertaken as part of the power sector reform in order to fully understand and
take into account the views, interests, and impacts on all stakeholder groups. This analysis will be supported through
the technical assistance (TA) cluster for Implementing the Samoa National Energy Policy.
The participation strategy outlining the community consultation and participation framework for the Power Sector
Expansion Project is included in the land acquisition and resettlement framework. EPC consults with landowners prior
to land acquisition. Representatives from EPC inform the affected parties, in advance, of EPC’s intention to acquire
land and compensation matters. Further consultations take place during and after detailed design and prior to the
preparation of a full census of affected people and inventory of losses. The subproject land acquisition and
resettlement plans will be made available to affected people. The objectives of the subproject, the amount of land
required, compensation entitlements, and grievance redress mechanisms will be disclosed to affected people in the
local language.
The TA cluster for Implementing the Samoa National Energy Policy incorporates the preparation and implementation
of stakeholder participation and consultations into the reform process and awareness-building for development of
renewables.
D. Gender Development
Social investigations show that poor and vulnerable groups are adequately catered for within traditional Samoan
society and will receive an equitable share of any compensation. No specific remedial actions are thought necessary.
Has an output been prepared? Yes No: No Adverse gender impacts are foreseen.
77
A. Introduction
1. Loan regulations and financing and project agreements require the borrower and
executing agency (EA) to provide ADB with reports and information it reasonably requests.
These include the EA’s periodic progress reports that enable the borrower, EA, and ADB to
monitor project progress, become aware of problems during implementation, and assess
whether the immediate project objectives will be met.
3. The content of the progress report includes sufficient information in summary form to be
useful to ADB as a funding agency. The purpose of the report is to enable the borrower, EA,
and ADB to monitor the latest progress, become aware of current problems, and assess
whether the project’s immediate objectives will be met. More detailed reports are prepared by
consultants or contractors for the project management unit (PMU) or for the EA’s management.
These reports are held at the PMU and are made available for ADB review, midterm review, and
project completion review missions.
4. The progress report sent to ADB is an executive summary of the detailed reports; with
format and content permitting ADB staff to readily capture key information for inputting into the
project performance report (PPR). When ADB requires detailed information (such as
background to a particular problem), this is included as an appendix. Simple charts such as a
bar or milestone charts to illustrate implementation progress, a chart showing actual versus
planned expenditures, and the relationship between physical and financial performance are
included. A framework and guidelines for calculating project progress and a sample
implementation schedule are also provided at the end of this Section.
5. EPC will submit QPRs for individual subprojects to ADB. These reports will include a
description of (i) the physical progress of the subproject; (ii) any difficulties encountered and or
anticipated along with corrective actions; (iii) the implementation progress on the land
acquisition and resettlement framework (LARF), environmental assessment and review
framework (EARF), and subproject IEE’s and EMMPs as applicable; (iv) the reasons for any
delays in project implementation and recommendations for corrective actions; and (v) the
summary of financial accounts comprising project expenditures during the previous quarter,
year to date, and total to date. The quarterly progress reports will also include key performance
and benchmark indicators as identified in the approved subproject feasibility studies. As
needed, the progress reports will include updates of the procurement plan. EPC will submit
subproject completion reports within 3 months of subproject completion. The subproject
completion report will (i) provide an assessment of the execution and operation of the
subproject, (ii) provide the status of compliance with loan covenants, and (iii) include results on
79
subproject outcomes and performance. A sample format of a QPR is attached at the end of
this section.
6. In addition to the QPR, MOF will provide annual reports to ADB on the interest payment
from the relent grant to EPC directed to the CEF and CDM subfund. MOF will report to ADB
when EPC has met conditions for the grant incentive scheme and advise as to the amount of
the loan principal to be converted into grants to EPC.
11ProgRpts
80
Annex 1
SAMPLE
B. Utilization of Funds (ADB Loan/Grant, GOA Grant, JBIC Loan, and Counterpart Funds)
C. Project Purpose
D. Implementation Progress
information relating to other aspects of the EA’s internal operations that may
impact on the implementation arrangements or project progress;
the borrower's compliance with policy loan covenants such as sector reform
initiatives and EA reforms, and the reasons for any noncompliance or delay in
compliance;
the borrower’s and EA’s compliance with financial loan covenants including the
EA’s financial management, and the provision of audited project accounts or
audited agency financial statements; and
the borrower’s and EA’s compliance with project-specific loan covenants
associated with implementation, environment, and social dimensions.
Summarize the major problems and issues affecting or likely to affect implementation progress,
compliance with covenants, and achievement of immediate development objectives.
Recommend actions to overcome these problems and issues (e.g., changes in scope, changes
in implementation arrangements, and reallocation of loan proceeds).
11ProgRpts
82
Annex 2
Framework and Guidelines in Calculating Project Progress
A. Introduction
3. Each activity in the implementation schedule will be weighted according to its overall
contribution (using time as a reference) to progress of project implementation. These weights
will then be used to calculate the percentage of project progress along the entire time span of
the project. This is to provide a holistic view of the pace of implementation.
4. As implementation activities and their corresponding weights will vary according to the
type of project, sector, and country, sector divisions or RMs will be responsible for determining
and including them in the project administration memorandum. The actual project
implementation progress of these activities should be reported regularly through the EA’s
quarterly project progress report. To ensure ADB-wide consistency, the following framework has
been established; its application will be monitored through the PPR.
5. Sector divisions or RMs concerned should identify major implementation activities and
include them in the implementation schedule, which is attached as an appendix in the report
and recommendation of the President (RRP). The implementation schedule should follow the
critical path of the project’s major activities in project implementation taking account of various
country, sector, and project constraints.
2. Assignment of Weights
6. Corresponding weights for each activity should be assigned to ensure that “project
progress" measures the percentage of achievement (non-financial except when the project has
credit components) for all events during the entire duration of the implementation schedule. To
avoid disproportionate assignment of weights, to the extent possible these should be evenly
distributed along the implementation schedule. When activities are concurrent, avoid “double
counting.”
7. Once all activities are identified and corresponding weights assigned, project progress
should be calculated using the following steps:
(ii) Multiply these percentages by the assigned weight of each activity to arrive at the
weighted progress.
(iii) Add up the resulting weighted progress of all activities to determine the project
progress.
a
ACTIVITIES
C
d
c
D
e f
11ProgRpts
84
A. General Principles
1. Article 14 (xi) of ADB's Articles of Agreement (the Charter) provides that ADB loan
proceeds be used only for the purposes for which the loan was approved with due attention to
economy and efficiency. To meet these requirements, executing agencies (EAs) are to submit
audited project accounts (APA) regularly during project implementation, and, in some cases,
until the loan has been fully repaid. In addition, EAs of revenue-earning entities are to submit
audited agency financial statements (AFS). This enables ADB to monitor loan use and satisfy
itself of the project entity's financial viability.
3. ADB’s financial reporting and auditing requirements were reviewed in 2004 and adjusted
to reflect the ongoing Harmonization Agenda. ADB’s revised audit requirements as defined in
the Guidelines for the Financial Governance and Management of Investment Projects financed
by Asian Development Bank (the Financial Guidelines), are consistent with both the OECD-DAC
Good Practices Paper on Financial Reporting and Auditing (Dec 2002) and the Framework for
Collaboration Among Participating Multilateral Development Banks on Financial Reporting and
Auditing (Feb 2003).
4. ADB will strictly monitor compliance with APA/AFS submissions and apply sanctions, as
follows:
(a) Three Months before the Due Date. A reminder will be sent to the EA/IA before
APA/AFS becomes due.
(b) On the Due Date. When the APA or AFS is not received by the due date, ADB
writes to the EA/IA stating that the APA or AFS is overdue and, if it is not
received within six months, requests for new contract awards and disbursement,
processing of new reimbursement, and issuance of new commitment letters will
not be processed.
(c) Six Months after Due Date. When the APA or AFS is not received within six
months after the due date, the sector division will hold processing of requests for
new contract awards and disbursement such as processing of new
reimbursement, and issuance of new commitment letters. The sector division will
inform the EA/IA of ADB’s actions and advises that if the situation is not
remedied within next six months, the loan may be suspended. The Operations
Coordination Division/Unit (OCD/U), Central Operations Services Office (COSO),
Loan Administration Division (CTLA), Office of the General Counsel (OGC) and
Office of Cofinancing Operation (OCO) if the project is co-financed should
likewise be informed.
(d) Twelve Months after the Due Date. When the APA/AFS is not received within
12 months after the due dates, the sector division determines whether the loan is
12AuditReqts
86
to be suspended and advises the OCD/U accordingly. With joint reference to the
Regulations,2 the regional department recommends loan suspension to the vice-
president for the region concerned and advises COSO, CTLA, OCO if the project
is co-financed, and OGC of the vice-president’s decision..
4. EPC will engage independent auditors acceptable to ADB to audit its annual financial
statements and annual project accounts. The scope of work for the auditors will be extended to
include audit of EPC’s compliance with ADB’s financial loan covenants. Audit reports will be
submitted to ADB together with the respective financial reports and the memorandum of issues
identified during the audit process. Annual financial reports will be prepared using international
financial reporting standards, and audits will be conducted using international standards on
auditing. EPC will maintain separate accounts for the Project. Within 6 months of the end of the
financial year, EPC will submit annual audited project accounts and annual audited financial
statements to ADB. The annual financial statements, which will be consolidated for all of EPC’s
operations, will record equity contributions by the Government of Samoa. 1
5. By 28 February each year (commencing 28 February 2008), EPC will also prepare and
provide ADB 5-year financial projections in a form agreed with ADB. The financial projections
will reflect updates in EPC’s investment plan.
1
Recorded equity contributions will include annual disbursed amounts of the $8 million grant from the Government
of Australia.
87
Financing Agreement (FA) (a) The Beneficiary/EPC shall carry out the
Art IV, Sec. 4.01; Project with due diligence and efficiency
and in conforming with sound
Project Agreement (PA) administrative, financial, engineering,
Art. II, Sec. 2.01 environmental and public utilities
practices.
(b) In the carrying out of the Project and
operation of the Project facilities, the
Beneficiary/EPC shall perform, or cause
to be performed, all obligations set forth
in schedule 5 to this Financing
Agreement.
PA, Art II, Section 2.03 (a) In the carrying out of the Project, EPC shall
employ competent and qualified consultants
and contractors, acceptable to ADB, to an
extent and upon terms and conditions
satisfactory to ADB.
PA, Art II, Section 2.03 (b) Except as ADB may otherwise agree, all
goods and services and other items of
expenditures to be financed out of the
proceeds of the Loan and the Grant, and the
JBIC Loan and the Government of Australia
Grant, shall be procured in accordance with
provisions of Sch 4 to the Financing
Agreement. ADB may refuse to finance a
contract where goods and services and other
items of expenditures have not been
procured under procedures substantially in
accordance with those agreed between the
Beneficiary and ADB or where the terms and
conditions of the contract are not satisfactory
to ADB.
FA, Art IV, Sec. 4.03 The Beneficiary shall enable ADB’s
PA, Section 2.10 representatives to inspect the Project, the
goods financed out of the proceeds of the
Loan and the Grant, and the JBIC Loan and
the Government of Australia Grant, and any
relevant records and documents.
FA, Art IV, Sec. 4.04 The Beneficiary shall take all action which
shall be necessary on its part to enable the
EPC to perform its obligations under the
13.Covenants
88
PA, Art II, Sec. 2.04 The EPC shall carry out the Project in
accordance with plans, design standards,
specifications, work schedules and
construction methods acceptable to ADB.
The EPC shall furnish, or cause to be
furnished, to ADB, promptly after their
preparation, such plans, design standards,
specifications and work schedules, and any
material modifications subsequently made
therein, in such detail as ADB shall
reasonably request.
FA, Art IV, Sec. 4.05 (a) The Beneficiary shall exercise its rights
under the Subsidiary Financing
Agreement in such a manner as to
protect the interests of the Beneficiary
and ADB and to accomplish the purposes
of the Loan and the Grant, and the JBIC
Loan and the Government of Australia
Grant.
(b) No rights or obligations under the
Subsidiary Financing Agreement shall be
assigned, amended, or waived without
the prior concurrence of ADB.
PA, Art II, Sec. 2.05 (a) The EPC shall take out and maintain
responsible insurers, or make other
arrangements satisfactory to ADB, for
insurance of the Project facilities to such
extent and against such risks and in
such amounts as shall be consistent
with sound practice;
(b) Without limiting the generality of the
foregoing, the EPC undertakes to
insure, or cause to be insured, the
goods to be imported for the Project and
to be financed out of the proceeds of
the Loan or the Grant against hazards
incident to the acquisition, transportation
and delivery thereof to the place and
use or installation, and for such
insurance any indemnity shall be
payable in a currency freely usable to
replace or repair such goods.
PA, Art II, Sec. 2.06 The EPC shall maintain, or cause to be
maintained, records and accounts adequate
to identify the goods and services and other
items of expenditures financed out of the
proceeds of the Loan and the Grant, to
disclose the use thereof in the Project, to
record the progress of the Project and to
reflect, in accordance with consistently
maintained sound accounting principles, its
operations and financial condition.
PA, Art II, Sec. 2.07 (a) ADB and EPC shall cooperate fully to
ensure that the purposes of the Loan
and the Grant, and the JBIC Loan and
89
13.Covenants
90
13.Covenants
92
Effectiveness Conditions -
FA, Art. VI, Sec 6.01. The following are specified as additional
conditions to the effectiveness of this
Financing Agreement for the purposes of
Section 9.01(f) of the Loan Regulations and
Section 9.01 (e) of the Grant Regulations,
respectively:
13.Covenants
94
FA, Art. VI, Sec. 6.03. A date ninety (90) days after the date of this First extension –
Financing Agreement is specified for the Second extension -
effectiveness of the Financing Agreement for
the purposes of Section 9.04 of the Loan
Regulations and Section 9.04 of the Grant
Regulations.
13.Covenants
96
13.Covenants
98
13.Covenants
100
13.Covenants
102
13.Covenants
104
13.Covenants
106
13.Covenants
108
A. Anticorruption Policy
1. ADB defines corruption as the abuse of public or private office for personal gain.
This means any behavior in which people in the public or private sectors improperly and
unlawfully enrich themselves or those close to them, or induce others to do so, by
misusing their position. The purpose of ADB’s Anticorruption Policy, approved in July
1998, is to reduce the burden corruption exacts from the governments and economies of
the region. The policy has three objectives:
ensure ADB-financed projects and its staff adhere to the highest ethical
standards.
(b) will reject a proposal for award if it determines that the bidder
recommended for award has, directly or through an agent, engaged in
corrupt, fraudulent, collusive, or coercive practices in competing for a
contract;
110
(d) will sanction a party or its successor, including declaring ineligible, either
indefinitely or for a stated period of time, to participate in ADB-financed
activities if it at any time determines that the firm has, directly or through
an agent, engaged in corrupt, fraudulent, collusive or coercive practices in
competing for, or in executing an ADB-financed contract; and
(e) will have the right to require that a provision be included in bidding
documents and in contracts financed by ADB requiring bidders, suppliers
and contractors to permit ADB or its representatives to inspect their
accounts and records and other documents relating to the bid submission
and contract performance and to have them audited by auditors
appointed by ADB.
2. To report allegations of fraud and corruption, please contact the Integrity Division
of the Office of the General auditor (OGAI). You should provide the names of persons
involved, as well as any corroborating evidence. Correspondence should be marked
“Strictly Confidential”. OGAI will screen any documentation or allegation or evidence of
fraud or corruption to determine whether it warrants further investigation. OGAI will treat
sources of allegations of fraud or corruption with the utmost confidentiality and
discretion. OGAI may be reached by email, telephone or facsimile at:
Email: anticorruption@adb.org
Telephone: (632) 632-5004
Facsimile: (632) 636-2152
Information concerning the identity of a complainant is strictly controlled and will not be
released to other ADB staff or to anyone outside ADB without the consent of the
complainant.
management capabilities and reporting through the provision of RFMAs 1 will improve the
Government’s oversight of EPC.
5. ADB’s Anticorruption Policy was explained to and discussed with EPC and the
Government. Consistent with its commitment to good governance, accountability, and
transparency, ADB reserves the right to investigate, directly or through its agents, any
alleged corrupt, fraudulent, collusive, or coercive practices relating to the Project. To
support these efforts, relevant provisions of the Anticorruption Policy are included in the
loan and grant regulations and the bidding documents for the Project. In particular, all
contracts financed by ADB in connection with the Project shall include provisions
specifying the right of ADB to audit and examine the records and accounts of EPC and
all contractors, suppliers, consultants, and other service providers as they relate to the
Project.
1
The RFMAs will be provided through the TA cluster for Implementing the Samoa National
Energy Policy.
112
1. A TA cluster for Implementing the Samoa National Energy Policy forms part of the
Government’s power sector development plan to improve access to sustainable and reliable
electricity services to all consumers in Samoa. The TA cluster supports the Government’s
priorities for the power sector through the following four components:
(1) Component 1. Comprises the establishment of a Clean Energy Fund (CEF) and
a clean development mechanism (CDM) subfund;
(2) Component 2. Establish and build capacity of a Designated National Authority
(DNA) to enable Samoa to benefit from the CDM;
(3) Component 3. Regulatory and Policy Reform in the Power Sector comprises
support for the development of (i) demand-side management and energy
conservation strategy; (ii) a legal framework to govern all stakeholders in the
power sector, and (iii) establishment of a regulator; and
(4) Component 4. Resident Financial Management Advisors to EPC
Total
Item
Cost
A. Government of Finland Financinga
1. Consultants
a. Remuneration and Per Diem
i. International Consultants 170.00
ii. National Consultants 40.00
b. International and Local Travel 39.00
c. Reports and Communications 2.00
2. Publications and Printed Materials 5.00
3. Workshops 12.00
4. Miscellaneous Administration and Support Costs 5.00
5. Contingencies 77.00
Subtotal (A) 350.00
B. Government Financing
1. Office Accommodation 35.00
2. Remuneration and Per Diem of Counterpart Staff 30.00
Subtotal (B) 65.00
Total 415.00
a
Administered by the Asian Development Bank.
Source: Asian Development Bank estimates.
114
Total
Item
Cost
A. Asian Development Bank Financinga
1. Consultants
a. Remuneration and Per Diem
i. International Consultants 100.00
b. International Travel 24.00
c. Reports and Communications 1.00
2. Public Awareness 3.00
3. Workshops and Training 5.00
4. Miscellaneous Administration and Support Costs 2.00
5. Representative for Contract Negotiations 6.00
6. Contingencies 9.00
Subtotal (A) 150.00
B. Government Financing
1. Office Accommodation 20.00
2. Remuneration and Per Diem of Counterpart Staff 10.00
Subtotal (B) 30.00
Total 180.00
a
Financed by the Japan Special Fund, funded by the Government of Japan.
Source: Asian Development Bank estimates.
Total
Item
Cost
A. Government of Australia Financinga
1. Consultants
a. Remuneration and Per Diem
i. International Consultants 545.00
b. International and Local Travel 168.00
c. Reports and Communications 9.00
2. Public Awareness Campaign 10.00
3. Workshops and Presentations
a. Facilitators/Invited Experts 50.00
b. Workshops 7.00
4. Miscellaneous Administration and Support Costs 5.00
5. Representative for Contract Negotiations 6.00
6. Contingencies 100.00
Subtotal (A) 900.00
B. Government Financing
1. Office Accommodation 70.00
2. Remuneration and Per Diem of Counterpart Staff 70.00
3. Others 20.00
Subtotal (B) 160.00
Total 1,060.00
a
Administered by the Asian Development Bank.
Source: Asian Development Bank estimates.
115
Total
Item
Cost
A. Asian Development Bank Financinga
1. Consultants
a. Remuneration and Per Diem
i. International Consultants 288.00
b. International Travel 120.00
c. Reports and Communications 4.00
2. Training Workshops 2.00
3. Miscellaneous Administration and Support Costs 2.00
4. Contingencies 34.00
Subtotal (A) 450.00
B. Government Financing
1. Office Accommodation 50.00
2. Remuneration and Per Diem of Counterpart Staff 30.00
Subtotal (B) 80.00
Total 530.00
a
Financed by the Japan Special Fund, funded by the Government of Japan.
Source: Asian Development Bank estimates.
116
RRP, Appendix 11
1. During the Asian Development Bank (ADB) loan Fact-Finding Mission for the proposed
Power Sector Expansion Project in May 2007, the Government of the Independent State of
Samoa (the Government) confirmed its request for a technical assistance (TA) cluster for the
development of sustainable and reliable electricity services to support economic growth.
Following the Government’s request, an understanding was reached on the TA cluster impact,
outcome, outputs, implementation arrangements, cost, financing arrangements, and terms of
reference. 1 The TA cluster is included in the country operations business plan (2007–2009) for
Samoa. 2
2. The TA cluster forms part of the Government’s power sector development program and
is included in the proposed Power Sector Expansion Project. The objective is to improve access
to sustainable and reliable electricity services for all consumers in Samoa by improving the
quality, reliability, and cost-effectiveness of power supply. The TA cluster will (i) promote the
development of clean energy resources in Samoa through the establishment of a clean energy
fund (CEF); (ii) enable Samoa to participate in, and benefit from, carbon-market trading through
the establishment of, and capacity building for, a designated national authority (DNA); (iii)
develop effective regulation of the power sector and promote demand-side management and
energy conservation through support for regulatory and policy reform in the power sector; and
(iv) help improve EPC’s financial performance through resident financial management advisors
(RFMAs). The technical assistance report is in Supplementary Appendix B.
3. The TA cluster supports the Government’s priorities for the power sector through four
components: Component 1 comprises the establishment of a CEF and a clean development
mechanism (CDM) subfund; Component 2 will establish and build capacity of a DNA;
Component 3 will support the Government in undertaking regulatory and policy reform in the
power sector; Component 4 will provide RFMAs to EPC. Capacity building and stakeholder
consultations are integral parts of all components.
4. Component 1: Establishment of the CEF. The CEF will help improve the coordination
of financing sources for clean energy resources in Samoa and is envisaged as a revolving fund.
Component 1 will (i) help establish the governance and operational structure, human resources,
and working and reporting guidelines of the CEF and a CDM subfund, (ii) identify a project
pipeline, and (iii) increase public awareness on clean and renewable energy. The CDM subfund
will help finance initial transactions costs associated with getting eligible projects additional
financing under the CDM. This may include preparation of project design documents, validation
of project design documents by an operational entity or independent third party validator, and
registration of projects with the CDM executive board.
5. Component 2: Establishment of, and Capacity Building for, the DNA. The
establishment of a DNA will enable Samoa to benefit from the CDM. Component 2, which will be
implemented jointly with Component 1 to ensure that the two components are well coordinated,
will, through a consultative process; (i) establish the operational structure and resource
requirements; (ii) develop working guidelines and procedures for the DNA, (iii) provide capacity
building and hands-on training for stakeholders and DNA staff in procedural requirements using
1
The TA first appeared in ADB Business Opportunities on 4 July 2007.
2
ADB. 2007. Country Operations Business Plan (2007–2009): Independent State of Samoa. Manila.
118
a pilot project (identified in the project pipeline under Component 1); and (iv) raise public
awareness on the role, functions, and requirements of the DNA.
JICA
Ken Kato (Mr.) Assistant Director Kato.Ken@jica.go.jp Tel: +81-3-5352-5607
Operations Management Fax: +81-3-5352-5032
Division
Operations Strategy
Department
Sachie Terasaki (Ms) Country Officer Terasaki.Sachie@jica.go.jp TEL: +81-3-5352-5624
Pacific Division (Pacific FAX: +81-3-5352-5490
Islands), Southeast Asia 1
and Pacific Department
Yumiko HORIWAKI (Ms.) Division 1, Loan and Grant Horiwaki.Yumiko@jica.go.jp tel:+81-(0)3-5218-9232
Administration Dept. fax:+81-(0)3-5218-3974
Government of Australia
Ms. Heather Dixon 2nd Secretary heather.dixon@dfat.gov.au Tel: +685 23411 ext 712
Development Cooperation Fax: +685 26872
AusAID
Australian High Commission
Beach Road, Apia, SAMOA
PO Box 704, Apia, Samoa
Section 17