Vous êtes sur la page 1sur 16

How to achieve good levels

of airtightness in masonry homes


Dr David Johnston & Dominic Miles-Shenton

Airtightness and air leakage


Introduction
In the UK, as in most industrialised countries, Air leakage
the domestic sector contributes substantially to Air leakage is the uncontrolled exchange of air both into (infiltration) and
national energy use and CO2 emissions. Currently, out of (exfiltration) a building through cracks, gaps and other unintentional
there are over 25 million dwellings in the UK openings in the building envelope. The rate of air leakage depends upon the
accounting for just under 30% of the UK’s total air permeability of the construction, the wind speed and direction, and the
CO2 emissions. This is a substantial figure given that temperature difference between the inside and outside of the building, as well
the UK housing stock is categorised by long physical as within the building.
lifetimes and slow stock turnover. Therefore, if we
are to mitigate against climate change and achieve Airtightness
the Government’s target of an 80% reduction in Airtightness is the measurement criteria used to evaluate the air leakage of a
national CO2 emissions by 2050 based on 1990 building. It determines the uncontrolled background ventilation or leakage rate
levels, then significant reductions in the carbon of a building which, together with purpose-provided ventilation, makes up the
emissions from dwellings both new and existing will total ventilation rate for the building. Traditionally, air leakage was expressed
be required. in air changes per hour (ach or h-1), however currently air permeability is used
(m3/(h.m2) as it takes into consideration the effects of shape and size. The
One factor that can have significant impact on more airtight a building, the lower the air permeability.
the energy use and CO2 emissions attributable to
dwellings is airtightness. The current regulatory In the UK, airtightness is measured at an artificially induced pressure of 50Pa
requirement for airtightness is a design air (n50).
permeability of 10 m3/(h.m2) @ 50Pa. This is
linked to the target carbon dioxide emission Measuring airtightness
rate (TER1). However, in order to cost effectively The airtightness of a building envelope can be measured using the fan
achieve a satisfactory carbon emission rate or a pressurisation (blower door) technique or the tracer gas technique. The fan
particular level within the Code for Sustainable pressurisation technique is the simplest, quickest and most widely used (see
Homes, designers are likely to make trade-offs Figure 1). It involves sealing a portable variable speed fan into an external
between fabric and system performance, and an doorway using an adjustable door frame and panel. A fan speed controller
air permeability of 5 m3/(h.m2) or less is likely to is then used to pressurise and/or depressurise the building. The airflow rate
become a more typical design requirement. that is required to maintain a number of particular pressure differences across
the building envelope is then measured and recorded on a pressure and flow
This guide gives an introduction to the topics gauge. The leakier the building, the greater the air flow required to maintain a
of airtightness and air leakage and discusses the given pressure differential.
basic principles of airtightness. It also illustrates a
number of areas within masonry construction that
may contribute to air leakage and identifies ways in
which air permeability of less than 5 m3/(h.m2) @
50Pa could be consistently achieved in typical UK
volume housing.

1 The TER is the minimum energy performance requirement for new dwellings approved by the
Secretary for State. It is expressed in terms of kgCO2/m2 per annum emitted as a result of the
provision of heating, hot water, ventilation and internal fixed lighting for a standardised household
when assessed using approved calculation tools.
Figure 1 Table 1
Measuring airtightness using the fan pressurisation technique. Common examples of direct and indirect air leakage points.

Direct leakage points Indirect leakage points


Around trickle ventilators and On external and party walls at the
through poorly- closing trickle ground floor/skirting board junction.
ventilators.
Around and through the loft hatch. Under kitchen and utility room units.
Through gaps at bay windows. Around staircases.
Around poorly fitting windows and Into intermediate floor voids.
doors.
Around sliding mechanism of patio Into service voids (e.g. behind bath
doors. panels)
At thresholds. At intermediate floor perimeters..
Around services at the point where At service penetrations where they
they penetrate through the primary penetrate the dry-lining and/or
air barrier. internal finish.

Therefore, it is much more effective and a much more robust


Identifying air leakage approach to design and construct airtight dwellings in the first
The most widely-used technique for identifying the main areas of air instance, rather than to try and carry out post construction remedial
leakage within a domestic building is smoke detection. This technique airtightness work by for instance plugging gaps in surface defects
involves either pressurising or depressurising the building, and then (secondary sealing) once the dwelling has been built.
locating the areas of air leakage using a manual or electronically
operated hand-held smoke puffer. In the majority of cases, the Airtightness and ventilation
dwelling is pressurised and leakage detection is performed from Buildings are ventilated via a combination of purpose-provided
within the dwelling, as it is much easier to identify where the smoke ventilation and infiltration. Purpose-provided ventilation is the
leaks out of the habitable space, rather than into the habitable space. controllable air exchange between the inside and outside of a building
However, it is important to realise that in most cases, the smoke by means of a range of natural and/or mechanical devices. Infiltration
puffers are only able to identify the point where the smoke leaks out is the uncontrollable air exchange between the inside and outside of
of the habitable space, rather than the path that the smoke takes a building through a wide range of air leakage paths in the building
from the inside to the outside of the building. structure.

Infrared thermal imaging can also be used to identify areas of air The level of airtightness achieved within a building will have an
leakage. Although it can provide additional information which is important influence on the ventilation rates that can be achieved
not always possible to recognise purely by smoke detection, it is and the type of ventilation strategy that should be adopted. Careful
considerably more complex and problematic. There are also limitations consideration should be given to the ventilation strategy, particularly
as to when and where it can be used as a detection technique. if a design air permeability target of 5 m3/(h.m2) @ 50Pa or less
is adopted. However, irrespective of whatever ventilation strategy
Direct and indirect air leakage is adopted, the aim should always be to minimise the amount of
Air will leak through porous building materials and unintentional uncontrolled and usually unwanted infiltration by making the building
cracks, gaps and openings in the building envelope. This leakage can envelope as airtight as possible, and then ventilate the building
occur directly and indirectly. Direct air leakage points are points in the appropriately by providing sufficient purpose-provided ventilation. In
envelope where the air leakage occurs directly through the primary other words, ‘build tight, ventilate right’. It should be remembered that
air barrier from inside the insulated envelope to outside or vice versa. a dwelling cannot be too airtight, but it can be under ventilated.
Indirect air leakage points are points in the envelope where the air
leakage occurs indirectly through the primary air barrier via a series of Methods of achieving sufficient purpose-provided ventilation are
interconnected voids from inside the insulated envelope to outside or currently contained within the Building Regulations 2000 Approved
vice versa. Common examples of direct and indirect air leakage points Document Part F 2010 edition [8]. This includes separate guidance
are given in Table 1. for those dwellings that are designed to have an air permeability
greater than 5 m3/(h.m2) @ 50Pa and an enhanced provision for those
Experience indicates that the majority of air leakage within UK dwellings designed to have an air permeability less than or equal to 5
dwellings occurs through indirect rather than direct leakage points. m3/(h.m2) @ 50Pa.
These indirect air leakage paths are often complicated, making it very
difficult, if not impossible, to trace and seal them effectively.

2
How to achieve good levels of airtightness in masonry homes

Airtightness Requirements It is also important to realise that in the past, when dwellings were
relatively poorly insulated, airtightness had comparatively little
influence on the overall energy performance of the building. However,
Approved Document Part L1A 2010 as dwellings have become better insulated, the relative importance
of airtightness has increased. In very well insulated dwellings, the
Airtightness is currently addressed in Approved Document Part proportional effect that airtightness has on the performance of a
L1A 2010 (ADL1A 2010) of the Building Regulations [9]. ADL1A dwelling can be significant.
2010 requires that the building fabric should be constructed to a
reasonable quality of construction so that the air permeability is For example, in a notional semi-detached dwelling with a total heat
within reasonable limits. Guidance on a reasonable limit for the loss of just under 140W/K (roughly equivalent to a 2006 Part L1A
design air permeability2 is given as 10 m3/(h.m2) @ 50Pa. In the compliant dwelling) and an air permeability of 10 m3/(h.m2) @ 50
majority of cases, complying with the regulation will require some Pa, the ventilation heat loss is likely to account for around a third of
degree of compulsory pressure testing3. Details of the testing regime the dwelling’s total heat loss (see Figure 2). If no additional measures
associated with each method of compliance can be found within are taken to reduce fabric heat loss beyond this level, and measures
ADL1A 2010 (see [9]). For dwellings that have not been pressured are taken to reduce air permeability, then significant reductions
tested, the assessed air permeability is the average test result obtained in ventilation heat loss are possible. If the air permeability of the
for dwellings of the same type which have been tested plus a margin dwelling is reduced to 1 m3/(h.m2) @ 50 Pa and an mechanical
of 2 m3/(h.m2), to account for the likely variability of air leakage that ventilation and heat recovery (MVHR) system is installed, then
would be achieved by on-site testing. The outcome of this change the ventilation heat loss could be reduced to just over 20W/K,
to the Regulations is that the design air permeability rate should not representing approximately one fifth of the dwellings total heat loss.
be more than 8 m3/(h.m2), so that untested dwellings achieve an
assessed air permeability no greater than the backstop value of 10 Figure 2
m3/(h.m2). As a consequence, designs reliant on low air permeability Comparison of fabric and ventilation heat losses for a ‘notional’
(80m2) semi-detached house.
should ideally be pressure tested to avoid this performance penalty.
Compliance with ADL1A 2010 also requires that the pressure tests 160
Fabric Ventilation
are undertaken in accordance with the procedure set out in the Air
140
Tightness Testing and Measurement Association (ATTMA) Technical
Standard 1 – Measuring Air Permeability of Building Envelopes [1] . 120
Heat loss (W/K)

100
Airtightness and the energy
80
performance of dwellings
60

Airtightness is crucial to improving the energy performance of


40
dwellings. Currently, in the UK, the temperature of the outside air
20
is nearly always lower than the temperature of the air inside the
building, thus, any air leakage from the inside to the outside of the 0
building is likely to result in: 10 (natural 7 (natural 5 (natural 3 (natural 2 (mechanical 1 (mechanical
ventilation) ventilation) ventilation) ventilation) extract ventilation with
■■ A significant reduction in the effectiveness of the thermal ventilation) heat recovery)

insulation, due to air leakage past the insulation (thermal Air permeability (m3/(h.m2) @50Pa) and ventilation strategy adopted

bypassing), resulting in increased heat loss .


■■ An increase in the building’s ventilation and fabric heat losses, As Building Regulations become more stringent, achieving the desired
resulting in an increase in space heating requirement. CO2 Target Emission Rate (TER), is likely to require designers to
■■ Increased energy usage and higher carbon emissions. take a more holistic approach in which reductions in the design air
permeability are coupled with investments or trade offs in additional
thermal insulation, alternative heating systems or renewable
technologies. If this is the case, an air permeability of less than 5 m3/
(h.m2) @ 50Pa is likely to become a common design requirement. For
instance, the fabric energy efficiency standard for zero carbon homes
published in 2009 suggests an air leakage target no greater than 3
m3/(h.m2) @ 50Pa, [7]. At such levels of air leakage, factors such as
2 Design air permeability is defined in ADL1A 2006 as the value of air permeability that is the ventilation strategy chosen, heat exchanger efficiency and specific
selected by the designer for use in the calculation of the DER. fan power all become important and can have a significant impact on
3 Details of the pressure testing requirements are contained within Regulation 20B of The the CO2 emissions achieved.
Building Act 1984 (ODPM, 2006c).

3
Measured airtightness of new UK housing
There is a limited amount of published data available on the air Principles of airtightness
leakage of dwellings that have been built to comply with Part L1A
2006. Measurements undertaken by the NHBC on 1293 dwellings of High levels of airtightness are only likely to be achieved by
different size, type, and construction [7] indicate that although the understanding and adopting a number of basic principles throughout
majority of the dwellings (>95%) achieved an air permeability below the design, procurement and construction of the dwelling. These
the regulatory standard of 10 m3/(h.m2) @ 50Pa first time, a wide principles are as follows.
range of airtightness was still observed (see Figure 3). The mean of
the sample was approximately 6 m3/(h.m2) @ 50Pa. The results are Design stage
broadly consistent with those obtained by Building Sciences Limited Defining a continuous and robust primary air barrier is crucial at the
[2] on a separate group of 750 dwellings. design stage. This can be achieved by:
■■ Identifying a line through the building that will act as the main barrier
Figure 3 to air leakage. This is known as the dwelling’s ‘primary air barrier’.
Air permeability of 1293 dwellings built to ADL1A 2006.
After NHBC [7]. ■■ Ensure that the primary air barrier is continuous around the
thermal envelope and, where possible, in contact with the
300 insulation layer. This will not only minimise air leakage but also the
possibility of thermal bypass4.
■■ Check the continuity of the primary air barrier by undertaking a
250
‘pen-on-section’ test (see Figure 4). This involves using a line to
mark the location of the primary air barrier on a set of General
200 Arrangement drawings. The line should be continuous and
separate the heated (conditioned) spaces from the unheated
No. of dwellings

(unconditioned) spaces.
150
■■ From the ‘pen-on-section’ test, identify areas where additional
detailing will be required and identify those trades that are
100 responsible for the design and construction of the air barrier.
■■ Produce large scale drawings (1:5) of any areas of complexity or

500
changes in plane identified by the ‘pen-on-section’ test and identify
how continuity of the primary air barrier will be maintained at
these areas.
0
■■ Minimise the number of service penetrations through the primary
0-1

1-2

2-3

4-5

5-6

6-7

7-8

8-9

9-10

10-11

11-12

12-13

14-15

15-16

16-17
3-4

13-14

air barrier. Consider the adoption of service zones or voids that


Air permeability (m3/h.m2) @ 50Pa) may group services together.
■■ Try and make the primary air barrier as simple as possible. Try and

A more detailed analysis of the results obtained for masonry dwellings avoid or at least minimise changes of plane and complex detailing.
within both datasets suggests that, on average, dwellings with a wet ■■ Consider the impact that materials with different tolerances may
plastered finish are more airtight than dry-lined dwellings. have on the primary air barrier. Ensure that any issues are resolved
at the design stage prior to commencing construction.
■■ Ensure that the primary air barrier is robust, impermeable and
durable.
■■ Do not be over reliant on secondary sealing, for example using
sealant to seal the junction between intermediate floors and the
skirting board, to provide part of the primary air barrier.

4 Further information on thermal bypassing can be obtained from references [12] and [13].

4
How to achieve good levels of airtightness in masonry homes

■■ Ensuring that operatives know what they are required to achieve


Figure 4
Example of a pen-on-section test undertaken on a set of GA drawings. and what constitutes an acceptable standard. The definition and
visibility of the air barrier is crucial.

Quality control
Testing, monitoring, and feedback are essential to any quality control
process. Specific ways in which process can be improved include:
BATH AC STAIRS BED.3 Red line ■■ Formally describing the quality control process and clearly setting
indicates
out the different roles and responsibilities for reporting, recording,
location of
primary air investigation and action.
barrier
HALL
■■ At key stages of the construction, check the integrity of the
L.ROOM primary air barrier and undertake airtightness measurements
before the construction progresses to a stage where it becomes
impossible to efficiently undertake remedial action.
■■ Maintain a photographic record of observations made during
It is important to realise that approaches that rely on high levels of the construction process. This not only allows a more precise
workmanship coupled with secondary sealing are likely to be less retrospective analysis in the event of future investigations, but
robust than those that rely on the identification and execution of a also provides useful material for training and improving awareness
continuous primary air barrier. among site staff of the impact of their actions.
■■ As far as possible, construction specifications should ensure
Sequencing of construction processes standardisation of detailing to enable site teams to become
Give explicit consideration to sequencing during the design, familiar with the materials, components and tolerancing needs.
procurement and construction by: Where modifications are required these should be undertaken in a
■■ Attempting to install the primary air barrier over as large an area controlled way accompanied by effective detailed documentation.
as possible in one single operation. For example, installation of
the top floor ceiling prior to the erection of the internal partitions Communication
minimises the number of penetrations through the ceiling. Communication of detailed design information and feedback on
airtightness performance is crucial if high standards of airtightness are
■■ Ensuring that the primary air barrier can be completed, inspected,
to be achieved. Effective communication requires:
tested and repaired prior to any part of it being covered up by
other materials or finishes. For example, where a parging coat ■■ Design information to be provided to all subcontractors and trades

forms the primary wall air barrier, it should be applied to walls that may have an impact on the integrity of the primary air barrier,
before any subsequent trades commence. through an appropriate mixture of documentation and briefings.
The design information should include procedural specifications as
■■ Sleeve and seal service penetrations through the primary air barrier
well as drawings depicting the final form. In particular, all drawings
during installation wherever possible, to avoid the need to break and specifications should define the primary air barrier and detail
out subsequent new construction. drawings should show how the air barrier is to be maintained at
■■ Ensuring that the method of sealing service penetrations through junctions and penetrations.
the primary air barrier is robust enough to enable later fitting-out ■■ Any modifications or deviations from the design made on site
work to take place without compromising the installed seal. For (including ad-hoc design alterations, product substitutions and
example, electricity cables that penetrate the primary air barrier procedural changes) should be fed back to the designers to be
should be fitted with an appropriate seal that allows for the cables reassessed where necessary – particularly where there may be
to be manipulated during and after the installation of the terminal implications for the air barrier integrity, thermal performance or
fitting without detriment to the seal. condensation risk.

Site supervision and workmanship Potential defects associated with the


Ensure that there are high standards of site supervision and construction of the primary air barrier
workmanship on-site. This can be achieved by: ■■ The type and formation of the primary air barrier has a critical
■■ Providing airtightness training as an integral part of site induction. influence on the airtightness achieved. Observations obtained
Both generic and trade-specific airtightness training should be from masonry dwellings during their construction have highlighted
provided to all operatives on-site. Training should explain why a number of recurrent areas that may contribute or lead to air
airtightness is important, how it is being tested, what quality control leakage.
processes are in place and what happens when things go wrong.

5
Design Options Parging layer and wet plastered finish
An alternative and potentially more robust solution to using
plasterboard dry-lining as the primary air barrier, is to apply a sand
Plasterboard dry lining and cement or gypsum based plaster parging layer to the internal face
Plasterboard dry-lining is currently a common source of air leakage in
of all of the external walls prior to the application of the dry-lining,
new masonry dwellings. Experience suggests that when plasterboard
Alternatively, a wet plaster finish can be applied as an alternative to
on dabs is used as the primary air barrier for external and separating
dry lining.
walls, it can be difficult to achieve an airtight seal around the edges.
The adhesive dabs that are used to seal the perimeter of the boards
A typical internal render mix is cement:sand:lime 1:4:1/2. with typical
are often discontinuous (see Figure 5) allowing the air behind the
plasterboard to move around freely and link with various other leakage thickness for a parge coat between 3mm and 6mm. A wet plaster
paths within the dwelling. mix will be thicker, with two or three coats and will take longer to dry
out. However, it does offer the additional benefit of increased thermal
Even when considerable time and effort is spent on ensuring that mass, which has the potential to reduce operational CO2 emissions
continuous ribbons of adhesive are applied around the perimeter and enhance summertime comfort. Typical plastering or parging mixes
of the boards, these are very rarely completely solid. In addition, a are given in BS EN 13914-2:2005, and additionally there is a wide
continuous channel for air movement is left around the perimeter range of proprietary bagged plaster mixes, some of which are designed
of the wall between the ribbons and the perimeter junctions with to be spray applied.
adjacent walls, the ceiling and the floor.
The advantage of both of these techniques is that they have the
Figure 5 potential to seal any badly pointed joints or shrinkage cracks in the
Discontinuous ribbons of plasterboard adhesive on an external wall.
inner leaf of masonry preventing air moving through the masonry
walls. In addition, from a quality control perspective, it is relatively
easy to see where the layer has been applied, making inspection easier.
However, care should be taken to ensure that the parging layer or wet
plastered finish is continuous and links with the air barrier in the floor,
ceiling and around openings. It is not uncommon to find areas where
this layer is not continuous (see Figure 6), particularly if the layer has
been applied after installation of elements such as intermediate floors,
partitions, stairs or services. Discontinuities can also occur at the
interface between the walls and the intermediate floor where the floor
deck, strutting and joists have been fitted prior to the application of
the parging layer (see Figure 7)

Figure 6
Incomplete parging layer behind services and stairs.

If plasterboard dry lining is used to form part of the primary air barrier,
it is likely to result in long-term airtightness performance issues as a
result of drying, shrinkage and settlement.

6
How to achieve good levels of airtightness in masonry homes

A number of proprietary products are available, such as joist seals,


Figure 7
Discontinuity in parging layer behind floor joist. joist caps and joist ends, that are intended to provide an airtight
seal between built-in joists and the inner leaf of the masonry wall
by limiting the effects of shrinkage at the joist and the surrounding
mortar joints. However, instead of addressing the problems associated
with built-in joists, what these products do is to effectively move the
problem somewhere else. For instance, the problem of how to provide
an airtight seal is moved to the junction between the joist seal and
the mortar and the junction between the joist seal gasket and the
inner leaf of the masonry wall.

Difficulties can also arise where the joists run parallel with the walls
(see Figure 9). In such situations, the joists are slightly offset from the
inner leaf of the external or party wall to allow electrical cables to be
run from one floor to the next. The offset is typically so small that
it is not possible to apply mortar, mastic or a parge coat to the area
between the joist and the wall to seal this junction.

Sealing around built-in joists Figure 9


Achieving an airtight seal around built-in intermediate floor joists Offset joist running parallel with the parged wall.

on masonry cavity construction tends to be difficult, partly due to


movement and shrinkage but also due to the construction processes
that are adopted when building-in the joists. Restricted access to the
junction between the blockwork and the built-in joists, particularly
where the joists run parallel to the external and/or separating walls,
make it difficult to ensure adequate sealing.

For example, where a substantial height of brickwork in the outer


leaf is constructed before the inner leaf of blockwork above the
intermediate floor, it is difficult for the bricklayers to achieve full
perpends and bedding layers around and between the built-in
joists and strike off any excess mortar, as the blockwork has to be A number of alternative approaches to using built-in joists are
constructed from inside the dwelling.. Any excess mortar has to be available that are potentially more robust. These include the use of
chipped away leaving uneven surfaces that are difficult to seal with joist hangers, the use of continuous corbelling to support intermediate
mastic around the joists. The gaps at perpends are also difficult to fill floors or the use of an alternative floor construction such as hollow
because of their proximity to the floor decking (see Figure 8). core concrete planks or a beam and block system.

Figure 8
Excess mortar around built-in joists and gaps in perpends prior
Sealing around openings
to dry-lining. Experience suggests that it is also difficult to prevent air leakage
around openings. It is common for air movement to be observed
around window sills, either directly through small cracks and gaps
to outside or indirectly into the void behind the plasterboard. For
example, Figure 10 shows the installation of a dry-fitted sill board
with a visible gap between the sill board and the external wall (in
this case the wall is also parged). If the wall is dry lined, this gap is
likely to remain, allowing air to move freely into the gap behind the
plasterboard dry lining.

7
been observed between the external door and the surrounding frame
Figure 10
Daylight visible through gaps beneath a window sill and subsequent (see Figure 14). Air leakage has also been observed through recessed
air leakage at the finished detail. lighting installed in the top floor ceiling (see Figure 15).

Figure 12
Leakage through poorly fitting trickle vent.

Thresholds are also a common source of air leakage. Typically, air


movement occurs at the frame/wall junction, under the threshold
itself and at the junction between the skirting board, the floor and the
doorframe (see Figure 11).

Figure 13
Figure 11 Leakage through poorly sealed loft hatch.
Air leakage at threshold at the junction between the skirting board
and the door frame.

Figure 14
Observable gap between external door and frame.
Air leakage around window sills and at thresholds can be minimised
by ensuring that the air barrier is continuous and connects with the
window sill and doorframe.

Through components
Components that penetrate the air barrier such as windows, doors,
rooflights, loft hatches and recessed lighting can be a significant
source of air leakage resulting in a direct path from the inside to
the outside of the dwelling. For example, trickle vents are often of a
poor fit or do not close properly allowing air movement through the
vent itself when closed, or through the gap between the vent and
the window (see Figure 12). Also the seals on window casements,
rooflights and loft hatches are not always fully compressed when
closed allowing air movement (see Figure 13). Leakage has also
been observed around the sliding movement of patio doors, at the
junction of French doors, and in the most severe cases, gaps have

8
How to achieve good levels of airtightness in masonry homes

Figure 15 Figure 17
Leakage through recessed lighting on top floor ceiling. Alternative sequencing of construction of partitions and ceiling, with
complete ceilings installed prior to partitions and services.

Service penetrations
Significant air movement has been observed around unsealed or
inadequately sealed service penetrations, at the point where the
service penetration punctures the air barrier, which provides a direct
leakage path to unconditioned zones under the ground floor, in the
A number of these issues can be addressed using appropriately external cavity or into the roof space.
specified components that are designed to be airtight.
Penetrations through the ground floor are often inadequately sealed.
Internal partition/ceiling junction This can be due to them occurring in hidden areas, as a result of
It is common practice to erect the top floor partition walls before access restrictions or from an unsuitable choice of sealing material.
installing the plasterboard ceiling. This practice creates numerous Figure 18 provides examples of air movement around a soil pipe
potential air leakage paths into the loft space. These leaks can occur positioned too close to an internal block wall to seal to an acceptable
through penetrations and gaps in the studwork, at the junctions standard, and penetrations around water mains relying on permeable
between the studwork and top floor ceiling, and particularly at materials (compacted mineral wool) to prevent air movement.
junctions between partition walls.
Figure 18
Leakage at ground floor penetrations.
An example of the problems that this can create and that remain even
after the installation of the plasterboard ceiling is illustrated in Figure
16. An effective way of avoiding this problem in housing is to erect
the ceiling before the partition, as shown in Figure 17. However, if the
top floor is to be dry-lined, potential air movement around the ceiling
perimeter will still need to be addressed, to ensure continuity between
the wall and ceiling air barrier. In the case of apartments, it may not
be practicable to install the ceiling prior to the partitions for fire safety
reasons.

Figure 16
Partitions-first sequence of top-floor ceiling construction, from below
and above, showing potential air leakage paths.
Figure 19 shows examples of electrical, ventilation and plumbing
penetrations permitting air movement between the conditioned
space and the external wall cavity. Although all these penetrations
are sealed at the external leaf to prevent water ingress, gaps behind
the electrical consumer unit, cooker-hood extract and wash basin
waste pipe have not been sealed where the services break through the
primary air barrier, the inner leaf blockwork. Such infiltration paths are
commonplace in wet areas where the build sequence results in kitchen
units, boxing-in or sanitary ware being installed before the penetration
has been sealed to an airtight standard.

9
Figure 19 Figure 21
Leakage at penetrations through external walls. Direct leakage paths between the soil stack and ventilated loft space.

Internal soil stacks invariably provide links for air movement around
Penetrations into the roof space provide further examples of direct the dwelling by connecting voids in bath or shower rooms with other
air leakage. Figure 20 demonstrates some common examples, with service voids, intermediate floor voids and the plenum behind the
air movement around and through electrical penetrations and around dry-lining, allowing an escape route where the soil pipes penetrate
plumbing penetrations in inaccessible areas at the back of a cylinder the primary air barrier. The linking of these voids can result in very
cupboard. convoluted leakage paths, where the point at which air leakage from
the dwelling is detected may be far removed from where the actual
Figure 20 air barrier is punctured or discontinuous.
Leakage at penetrations through the top-floor ceiling.

Figure 22 shows how similar problems can occur with external soil
pipes, in this case the pipe has not been sealed at the air barrier (the
inner leaf blockwork) prior to the tiled finish being applied. Although
the soil pipe has been sealed to the tiles in the final completed
photograph, air movement between the external cavity and the void
behind the dry-lining is unrestricted.

Figure 22
Service penetration through an external wall, linking the void behind
Observations suggest that one of the biggest contributors to overall air the plasterboard to the external cavity.
leakage can be air movement via the soil stacks. The importance of this
leakage path derives from both the number of times it occurs and also
from the apparent speed and volume of airflow relative to other leakage
paths. Where the soil stacks are sited internally, leakage can occur at the
ground floor termination or can provide a direct infiltration route from
the inside of a dwelling to the loft space (Figure 21)

A recurring problem is that service penetrations that are subsequently


hidden behind boxing or panels (for example the bath panel, shower
tray, shower pod, in an under sink unit, in an airing cupboard or
in an under stairs cupboard) are often left unsealed, whilst visible
penetrations in the same dwelling have been sealed. This suggests
a lack of understanding of the importance of these areas, with
the selection criteria being cosmetic appearance, rather than good

10
How to achieve good levels of airtightness in masonry homes

airtightness, when deciding to seal or not. An example is shown below components abut masonry elements (see Figure 24). Dissimilar
in Figure 23. The positioning of the shower tray creates a potential air materials may possess vastly different drying rates and associated
leakage path from beneath the shower tray, through the metal stud shrinkage, and gaps readily appear, particularly where a less flexible
partitioning, directly into the ventilated loft-space. In other cases the sealant (such as decorators’ caulk) has been used. It is therefore
air leakage path if often into any number of inter-connected voids important that when used, sealants and other products such as
that eventually lead outside. The waste pipe penetration beneath expanding foam are correctly specified and applied to help ensure a
the shower is unlikely to be sealed creating additional links between good bond is achieved.
the intermediate floor void, service void and partition wall void,
exacerbating the problem. Figure 24
Service penetration through an external wall, linking the void behind
the plasterboard to the external cavity.
Figure 23
Voids beneath a shower tray linking adjacent cavities and contributing
to complex air leakage paths.

Air leakage through service penetrations can be minimised by ensuring


Possibly the most important point to note about secondary sealing
that all penetrations are appropriately sealed where they pass through
is that although it can provide some short-term benefit in reducing
the air barrier. This can be achieved by using gaskets to provide an
air leakage, it may not provide a robust long-term solution. It can
airtight seal around pipes.
assist in achieving the desired result in a pressurisation test, but
airtightness performance may soon deteriorate upon occupation,
Secondary sealing and post-occupancy reparatory works can be costly. In addition, if
Secondary sealing is the process whereby visible gaps in surface
a high standard of airtightness is necessary to achieve the design
finishes are sealed to limit air movement within construction voids,
performance of a dwelling, any such deterioration is likely to impact
such as behind plasterboard dry lining. In most cases, the sealing
on the effectiveness of an MVHR system if used.
provides a secondary defence against air leakage and does not involve
sealing at the primary air barrier.

Anecdotal evidence from a very small sample of reasonably airtight


dwellings at Stamford Brook (see [12]) found that the impact of
secondary sealing on airtightness can result in a reasonably significant
temporary reduction in air leakage, typically between a 10 and 30%
improvement over a parged masonry dwelling with no additional
sealing. However, more importantly, the work also found that secondary
sealing can be prone to degradation over a relatively short time period.
The main reasons for this sudden deterioration being inadequate surface
preparation and usage of inappropriate sealing materials.

After just one heating season drying, shrinkage and settlement gaps
at the intermediate floor perimeter were observed around the sealant
used to seal between the intermediate floors and the skirting board.
Surface preparation in these areas is key, as cracks can become wide
enough to exceed the adhesive and elastic properties of the sealant.
Dust, if not removed from this junction prior to application of the
sealant can result in premature failure of the sealant. Large gaps
are also often observed at failed seals between adjacent materials
with differing physical properties, most commonly where wooden

11
Achieving air permeability rethink of the airtightness design of new UK dwellings will be required
that incorporates the identification of a continuous and robust

below 5 m3/(h.m2) @ 50Pa primary air barrier at the design stage. This is likely to result in a
move away from current practice in masonry construction where little
attempt is made to explicitly identify the primary air barrier, resulting
The target air permeability which is set in order to construct dwellings in the external wall air barrier defaulting to the plasterboard dry-
that achieve an air permeability below 5 m3/(h.m2) @ 50 Pa will lining. Alternative solutions for the external and party wall air barrier
depend on the consistency with which air permeability can be are available, such as a wet-plastered internal finish, a mechanically
achieved in practice. This target is determined by the failure rate applied plaster finish or the extension of the acoustic parge coat that
that is deemed acceptable by the individual builder and the resulting is applied behind the dry-lining on party walls to all external walls.
distribution of air leakage. In order to explore the likely target that However, changes to current design and construction practice are
will be required to consistently achieve an air permeability below 5 unlikely to consistently achieve the required levels of airtightness
m3/(h.m2) @ 50 Pa, the existing distribution of air leakage measured on their own. Instead, it is likely that these changes will have to be
by the NHBC [7] has been scaled using a simple model developed by coupled with changes to the way in which the design and construction
Lowe, Johnston & Bell [5]. is tested, managed and monitored.

Figure 25 illustrates the resulting air leakage distribution assuming a


failure rate of less than 5% and a maximum air permeability target of
5 m3/(h.m2) @ 50Pa. The resulting average air permeability rate that
would need to be achieved by testing the dwelling would be around
3.6 m3/(h.m2) @ 50Pa. Achieving this average will be demanding as
this level of air permeability is currently very tight by UK standards.
Although air permeability of 3 m3/(h.m2) @ 50Pa or lower have been
achieved in a number of UK dwellings, the numbers involved are small,
with the majority of the dwellings tending to be one-off constructed
by fastidious individuals. The challenge will be to replicate these levels
of airtightness in typical volume housing.

In recent years good progress has been made towards this goal, with
the large housing developers learning invaluable lessons following the
introduction of pressure testing in the Building Regulations.
Figure 25
Distribution of air leakage rates assuming a maximum air permeability
target of 5 m3/(h.m2) @ 50Pa and an initial failure rate of less than 5%.

450

400

350

300
No. of dwellings

250

200

150

100

50

0
0-1
1-2
2-3

4-5
5-6
6-7
7-8
8-9
9-10
10-11
11-12
12-13

14-15
15-16
16-17
3-4

13-14

Air permeability (m3/h.m2) @ 50Pa)

In order to consistently achieve an average air permeability of around


3.6 m3/(h.m2) @ 50Pa in typical UK volume housing, a fundamental

12
How to achieve good levels of airtightness in masonry homes

Stamford Brook Case Study different on-site trades to ensure that all operatives were aware
of the construction requirements and the consequences of poor
workmanship. In addition to this training, informal feedback was
An example of the variation in air permeability that can be achieved provided to the developers after each individual pressure test.
in a large masonry housing complex was observed at Stamford Brook
near Altrincham, Cheshire (see [12]. The development comprises
over 700 masonry cavity dwellings designed to an energy efficiency In total, 44 dwellings were pressure tested at Stamford between
standard some 25% to 35% in advance of the 2002 Building February 2005 and June 2007 (see Figure 27). The air permeabilities
Regulations for England and Wales (10% to 15% in advance of the of the tested dwellings ranged from 1.8 to 9.7 m3/(h.m2) @ 50Pa.
2006 regulations). As part of the standard, a demanding maximum Although the mean air permeability of the dwellings tested was 4.5
air permeability target of 5 m3/(h.m2) @ 50Pa was set for the m3/(h.m2) @ 50Pa, which is below the maximum air permeability
dwellings. The main airtightness strategy adopted at Stamford Brook target of 5 m3/(h.m2) @ 50Pa set for the dwellings, 14 of the 44
was the application a thin 2~6mm cementitious or gypsum-based dwellings (32%) achieved air permeability in excess of 5 m3/(h.m2)
parging layer (see Figure 26) to the inner leaf blockwork on all of @ 50Pa. A closer inspection of the results revealed that the best air
the external and party walls. This linked to the air barriers formed permeability results were achieved in the less complex apartments
by the plasterboard lining to the uppermost ceiling and the in-situ and 2-storey dwelling types, whilst the worst results were obtained
reinforced concrete suspended ground floor. The purpose of the in the more complex 2½ storey room-in-roof dwelling types. The
parging layer was to decrease the air permeability of the blockwork, reasons for the difference in performance were felt to be attributable,
by filling any remaining gaps in perpends and bedding layers, and to in the main, to specific design issues that were particular to the 2½
provide conceptual clarity of where and what the primary air barrier storey room-in-roof dwelling types. These details related to continuity
was on the inner leaf blockwork. Other airtightness measures adopted of the air barrier around the junction between the wall and sloping
included the use of timber head plates over the top of the head section of ceiling
channel in top floor partition walls, the installation of window and
doors that incorporated high quality casement and trickle vent seals, Figure 27
Distribution of air leakage rates at Stamford Brook.
the sealing of electrical ceiling penetrations to timber supports prior
to dry lining, and the installation of plywood heads to service voids 14

and risers to constrain air movement between the service voids and
12
the roof space.
10
No. of dwellings

Figure 26
8
Parging layer.
6

0
0-1
1-2
2-3

4-5
5-6
6-7
7-8
8-9
9-10
10-11
11-12
12-13

14-15
15-16
16-17
3-4

13-14

Air permeability (m3/h.m2) @ 50Pa)

Analysis of the results by test date also reveals some interesting results.
The first pressure tests undertaken on the dwellings between February
and May 2005 resulted in air permeability of between 2 to 3 m3/(h.m2)
@ 50Pa. However, by April 2006 the mean air permeability results had
drifted upwards to over 5 m3/(h.m2) @ 50Pa (see Figure 28). There were
a number of possible reasons for this, such as a shift in focus away from
airtightness, inadequate quality control procedures, training issues and

As well as the adoption of a number of physical airtightness measures,


the management teams, site operatives and sub-contractors were
also provided with a comprehensive formal training package on
the requirements and procedures for ensuring airtightness. The
training covered the airtightness design measures for each of the

13
changes in personnel. Measures were subsequently taken to address
these issues resulting in a significant improvement, particularly in the
performance of the more complex 2½ storey dwellings.

Figure 28
Trend in Pressure Test Results: February 2005 to May 2007.

2 storey semi/end terrace


Apartment
3 storey semi/end terrace
2 1/2 storey semi/end terrace
2 storey mid-terrace
2 storey detached
3 storey mid-terrace
12 2 1/2 storey mid-terrace
2 1/2 storey detached

10
Mean Air Permeability (m3/(h.m2) @ 50Pa)

0
Jan-05

Apr-05

Jun-05

Sep-05

Nov-05

Feb-06

Apr-06

Jun-06

Sep-06

Nov-06

Feb-07

Apr-07

Jul-07

Test Date

In conclusion, the results from Stamford Brook demonstrate that air


permeability’s of less than 5 m3/(h.m2) @ 50Pa can be achieved in
masonry cavity construction, even in dwellings of relatively complex
form, and permeability’s as low as 2 m3/(h.m2) @ 50Pa are possible.
However, consistently achieving such levels of air permeability not
only relies upon the appropriate application of the technology, but
also depends upon well-managed processes and procedures on site.

14
How to achieve good levels of airtightness in masonry homes

Some common air leakage and ventilation paths

1 Under floor ventilator grilles and floor/wall junction 9 Service penetrations in ceiling
2 Gaps in and around suspended timber floors 10 Vents penetrating the ceiling/roof
3 Leaky windows or doors 11 Bathroom wall vent or extract fan
4 Pathway through floor/ceiling voids into cavity walls and then to outside 12 Gaps around the bathroom waste pipes
5 Gaps around windows 13 Kitchen wall vent or extractor fan
6 Gaps at the ceiling-to-wall joints at the eaves 14 Gaps around kitchen waste pipes
7 Open chimney 15 Gaps around wall-to-floor joints
8 Gaps around attic hatches 16 Gaps in and around electrical fittings in hollow walls.

Table 2
Air permeability standards

Maximum air permeability (m3/hm2) at 50 Pa


Approved Document L1A of the Building Regulations (England and Wales), Technical booklet F1 (Northern Ireland) 10
and Building (Scotland) Regulations 2004 technical handbook section 6: energy – poorest acceptable standard
Energy Saving Trust (naturally ventilated) 5
Energy Saving Trust (mechanically ventilated) 3
The Netherlands 6
Germany (air changes per hour at 50 Pa) 1.8-3.8 (n50 h-1)
PassivHaus (air leakage rate) ‹1
Super E (Canada) (air changes per hour at 50 Pa) 1.5 (n50 h-1)

15
How to achieve good levels of airtightness in masonry homes

References
1 ATTMA (2007) Technical Standard 1. Measuring Air Permeability of Building Envelopes [Internet]. Airtightness Testing and Measurement Association.
Issue 2, 13th July 2007. Available from: http://www.attma.org [Accessed 7th April 2009].
2 BSL (2009) Private communication.
3 CLG (2009a) Proposals for amending Part L and Part F of the Building Regulations – Consultation.
Volume 3: Proposed technical guidance for Part F [Internet] London, Communities and Local Government. Available from|:
http://www.communities.gov.uk/publications/planningandbuilding/partlf2010consultation [Accessed 20th July 2009].
4 CLG (2009b) Proposals for amending Part L and Part F of the Building Regulations – Consultation.
Volume 2: Proposed technical guidance for Part L [Internet] London, Communities and Local Government. Available from|:
http://www.communities.gov.uk/publications/planningandbuilding/partlf2010consultation [Accessed 20th July 2009].
5 LOWE, R. JOHNSTON, D. & BELL, M. (2000) A Review of Possible Implications of the Introduction of Mandatory Pressurisation Testing for New
Dwellings in the UK. Building Services Engineering Research and Technology (BSER&T), Volume 21, No. 3, pp.27-34.
6 MILES-SHENTON, D., WINGFIELD, J. & BELL, M. (2007) Evaluating the Impact of an Enhanced Energy Performance Standard on Load-Bearing Masonry
Construction – Interim Report Number 6 – Airtightness Monitoring, Qualitative Design and Construction Assessments, PII Project CI 39/3/663. Leeds, UK,
Leeds Metropolitan University.
7 Defining a Fabric Energy Efficiency Standard for Zero Carbon Homes. Zero Carbon Hub, November 2009.
NHBC (2008) NHBC’s Technical Newsletter - Standards Extra 41. May 2008, Milton Keynes, UK, National House Building Council (NHBC).
8 Building Regulations, The Building Regulations 2000 Approved Document Part F: Ventilation. 2010 Edition.
9 Building Regulations, Approved Document L1A: Conservation of Fuel and Power in New Dwellings. 2010 Edition.
10 ODPM (2006c) The Building Act 1984: The Building and Approved Inspectors (Amendment) Regulations 2006 (SI2006/652),
London, UK, The Stationary Office.
11 OLIVIER, D. (1999) Air Leakage Standards. Unpublished DTLR Report.
12 WINGFIELD, J. BELL, M. MILES-SHENTON, D. SOUTH, T. and LOWE, R. J. (2008) Evaluating the Impact of an Enhanced Energy Performance Standard on
Load-Bearing Masonry Domestic Construction. Report Number 8 - Final Report. Lessons from Stamford Brook: Understanding the Gap between Designed and
Real Performance. PII Project CI 39/3/663. Leeds, UK, Leeds Metropolitan University.
13 WINGFIELD, J. MILES-SHENTON, D. and BELL, M. (2009) Evaluation of the Party Wall Thermal Bypass in Masonry Dwellings. Leeds, UK, School of the Built
Environment, Leeds Metropolitan University.
14 DETR (2000) Review of Part L of the Building Regulations for Energy Conservation - Air Leakage Statistics for New Dwellings. London, Department of the
Environment Transport and the Regions Building Regulations Advisory Committee.

Acknowledgements:
We gratefully acknowledge the help and advice given by the Home Building Federation (HBF) in the production of this document.

Published by MPA – The Concrete Centre


Riverside House, 4 Meadows Business Park,
Station Approach, Blackwater, Camberley, Surrey
GU17 9AB
For details of other publications and design
Tel: +44 (0)1276 606800
guidance from The Concrete Centre please visit
Fax: +44 (0)1276 606801
www.concretecentre.com/publications.
www.concretecentre.com

Ref: TCC/04/11 All advice or information from MPA – The Concrete Centre is intended only for use in the UK by those who will evaluate the significance
and limitations of its contents and take responsibility for its use and application. No liability (including that for negligence) for any
ISBN 978-1-904818-98-4 loss resulting from such advice or information is accepted by MPA – The Concrete Centre or its subcontractors, suppliers or advisors.
Readers should note that publications from MPA – The Concrete Centre are subject to revision from time to time and they should
Published February 2011
therefore ensure that they are in possession of the latest version.
© MPA – The Concrete Centre™

Vous aimerez peut-être aussi