DURATION (DAYS) COST COST/DAY

ACTIVITY
NORMAL CRASH NORMAL CRASH
1-2 1 1 6,750 6,750 6,750
2-3 2 2 6,525 2,803 3,263
2-4 5 4 9,056 9,056 1,811
2-5 2 2 37,900 37,900 19,950
3-5 6 6 10,650 10,650 1,775
4-5 10 9 78,750 13,209 7,875
4-7 0 0 43,650 43,650 43,650
3-6 12 12 22,800 22,800 1,849
5-6 9 9 99,475 99,475 11,053
5-7 5 4 35,600 35,600 7,120
5-8 8 8 13,975 12,343 1,747
6-8 0 0 60,600 60,600 60,600
6-9 2 2 14,825 14,825 7,413
7-8 1 1 40,700 40,700 40,700
7-10 12 11 6,600 2,835 550
8-10 7 7 37,100 37,100 5,300
8-11 8 8 212,900 25,482 26,613
9-11 4 4 35,600 35,600 8,900
10-11 2 2 13,975 13,975 6,988
10-13 12 11 59,200 59,200 4,933
11-12 2 2 14,825 14,825 7,413
9-14 3 3 37,900 37,900 12,633
12-14 2 2 6,600 6,600 3,300
12-13 3 3 37,100 37,100 12,367
13-15 8 7 208,700 27,818 26,089
14-15 2 2 42,600 42,600 21,300