Académique Documents
Professionnel Documents
Culture Documents
Large capacity transformers have evolved to meet the changing needs of electric power
companies. For example, the need to reduce the transportation cost to the site and the
trend towards smaller installation spaces have led to the introduction of on-site assembly
technology.
In addition, plans to double the voltage rating will increase considering future
long-distance transmission, and the need for a routine supervisory system will grow as
transformer operating conditions become severe due to extended operating life of
equipment, overload operation, etc.
Hitachi is meeting these needs with its computer analysis technology and
verification testing using trial production. The result of our efforts is highly efficient large
capacity transformers. In particular, we have ]ust completed delivery of a 281.25-kV
(525-kV) 1,060-MVA double-rating voltage transformer for the Hitachinaka Power
Station of Tokyo Electric Power Co., Inc., as well as Hitachi’s first- ever on-site
assembly of transformers (500 kV 1,000 MVA) for the Chizu Substation of the Chugoku
Electric Power Co., Inc. Hitachi uses the newest diagnostic technology for its apparatus
supervisory system and provides rational maintenance and support.
Brief Introduction About Transformers
A transformer is a static device that transfers electrical energy from one circuit to
another through inductively coupled conductors—the transformer's coils. A varying
current in the first or primary winding creates a varying magnetic flux in the
transformer's core and thus a varying magnetic field through the secondary winding. This
varying magnetic field induces a varying electromotive force (EMF) or "voltage" in the
secondary winding. This effect is called mutual induction.
Taking the ratio of the two equations for Vs and Vp gives the basic equation[30]
for stepping up or stepping down the voltage
Np/Ns is known as the turns ratio, and is the primary functional characteristic of
any transformer. In the case of step-up transformers, this may sometimes be stated as the
reciprocal, Ns/Np. Turns ratio is commonly expressed as an irreducible fraction or ratio:
for example, a transformer with primary and secondary windings of, respectively, 100
and 150 turns is said to have a turns ratio of 2:3 rather than 0.667 or 100:150.
Ideal power equation of a Transformer
giving
the ideal transformer equation
Detailed operation
The current required to create the flux is termed the magnetizing current; since
the ideal core has been assumed to have near-zero reluctance, the magnetizing current is
negligible, although still required to create the magnetic field.
The changing magnetic field induces an electromotive force (EMF) across each
winding. Since the ideal windings have no impedance, they have no associated voltage
drop, and so the voltages VP and VS measured at the terminals of the transformer, are
equal to the corresponding EMFs.
The primary EMF, acting as it does in opposition to the primary voltage, is
sometimes termed the "back EMF".This is due to Lenz's law which states that the
induction of EMF would always be such that it will oppose development of any such
change in magnetic field.
Practical considerations
Leakage flux
Leakage inductance
The ideal transformer model assumes that all flux generated by the primary
winding links all the turns of every winding, including itself. In practice, some flux
traverses paths that take it outside the windings. Such flux is termed leakage flux, and
results in leakage inductance in series with the mutually coupled transformer windings.
[33]
Leakage results in energy being
alternately stored in and discharged from
the magnetic fields with each cycle of the
power supply. It is not directly a power
loss (see "Stray losses" below), but results
in inferior voltage regulation, causing the
secondary voltage to fail to be directly
proportional to the primary, particularly
under heavy load. Transformers are
therefore normally designed to have very
low leakage inductance.
However, in some applications,
leakage can be a desirable property, and
long magnetic paths, air gaps, or magnetic bypass shunts may be deliberately introduced
to a transformer's design to limit the short-circuit current it will supply. Leaky
transformers may be used to supply loads that exhibit negative resistance, such as electric
arcs, mercury vapor lamps, and neon signs; or for safely handling loads that become
periodically short-circuited such as electric arc welders.
Air gaps are also used to keep a transformer from saturating, especially audio-
frequency transformers in circuits that have a direct current flowing through the
windings.
Leakage inductance is also helpful when transformers are operated in parallel. It
can be shown that if the "per-unit" inductance of two transformers is the same (a typical
value is 5%), they will automatically split power "correctly" (e.g. 500 kVA unit in
parallel with 1,000 kVA unit, the larger one will carry twice the current).
Effect of frequency
If the flux does not contain even harmonics the following equation can be used
for half-cycle average voltage Eavg of any wave shape:
The time-derivative term in Faraday's Law shows that the flux in the core is the
integral with respect to time of the applied voltage. Hypothetically an ideal transformer
would work with direct-current excitation, with the core flux increasing linearly with
time. In practice, the flux would rise to the point where magnetic saturation of the core
occurs, causing a huge increase in the magnetizing current and overheating the
transformer. All practical transformers must therefore operate with alternating (or pulsed)
current.
The EMF of a transformer at a given flux density increases with frequency. By
operating at higher frequencies, transformers can be physically more compact because a
given core is able to transfer more power without reaching saturation and fewer turns are
needed to achieve the same impedance. However, properties such as core loss and
conductor skin effect also increase with frequency. Aircraft and military equipment
employ 400 Hz power supplies which reduce core and winding weight. Conversely,
frequencies used for some railway electrification systems were much lower (e.g. 16.7 Hz
and 25 Hz) than normal utility frequencies (50 – 60 Hz) for historical reasons concerned
mainly with the limitations of early electric. As such, the transformers used to step down
the high over-head line voltages (e.g. 15 kV) are much heavier for the same power rating
than those designed only for the higher frequencies.
Operation of a transformer at its designed voltage but at a higher frequency than
intended will lead to reduced magnetizing current; at lower frequency, the magnetizing
current will increase. Operation of a transformer at other than its design frequency may
require assessment of voltages, losses, and cooling to establish if safe operation is
practical. For example, transformers may need to be equipped with "volts per hertz" over-
excitation relays to protect the transformer from over voltage at higher than rated
frequency.
One example of state-of-the-art design is those transformers used for electric
multiple unit high speed trains, particularly those required to operate across the borders of
countries using different standards of electrification. The position of such transformers is
restricted to being hung below the passenger compartment. They have to function at
different frequencies (down to 16.7 Hz) and voltages (up to 25 kV) whilst handling the
enhanced power requirements needed for operating the trains at high speed.
Knowledge of natural frequencies of transformer windings is of importance for
the determination of the transient response of the windings to impulse and switching
surge voltages.
Energy losses
An ideal transformer would have no energy losses, and would be 100% efficient.
In practical transformers energy is dissipated in the windings, core, and surrounding
structures. Larger transformers are generally more efficient, and those rated for electricity
distribution usually perform better than 98%.
Experimental transformers using superconducting windings achieve efficiencies
of 99.85%. The increase in efficiency from about 98 to 99.85% can save considerable
energy, and hence money, in a large heavily-loaded transformer; the trade-off is in the
additional initial and running cost of the superconducting design.
Losses in transformers (excluding associated circuitry) vary with load current, and
may be expressed as "no-load" or "full-load" loss. Winding resistance dominates load
losses, whereas hysteresis and eddy currents losses contribute to over 99% of the no-load
loss. The no-load loss can be significant, so that even an idle transformer constitutes a
drain on the electrical supply and a running cost; designing transformers for lower loss
requires a larger core, good-quality silicon steel, or even amorphous steel, for the core,
and thicker wire, increasing initial cost, so that there is a trade-off between initial cost
and running cost. (Also see energy efficient transformer).
Transformer losses are divided into losses in the windings, termed copper loss,
and those in the magnetic circuit, termed iron loss. Losses in the transformer arise from:
Winding resistance
Current flowing through the windings causes resistive heating of the conductors.
At higher frequencies, skin effect and effect create additional winding resistance and
losses.
Hysteresis losses
Each time the magnetic field is reversed, a small amount of energy is lost due
to hysteresis within the core. For a given core material, the loss is proportional to the
frequency, and is a function of the peak flux density to which it is subjected.
Eddy currents
Ferromagnetic materials are also good conductors, and a core made from such a
material also constitutes a single short-circuited turn throughout its entire length. Eddy
currents therefore circulate within the core in a plane normal to the flux, and are
responsible for resistive of the core material. The eddy current loss is a complex function
of the square of supply frequency and inverse square of the material thickness. Eddy
current losses can be reduced by making the core of a stack of plates electrically insulated
from each other, rather than a solid block; all transformers operating at low frequencies
use laminated or similar cores.
Magnetostriction
Magnetic flux in a ferromagnetic material, such as the core, causes it to physically
expand and contract slightly with each cycle of the magnetic field, an effect known
as magnetostriction. This produces the buzzing sound commonly associated with
transformers, and can cause losses due to frictional heating.
Mechanical losses
In addition to magnetostriction, the alternating magnetic field causes fluctuating
forces between the primary and secondary windings. These incite vibrations within
nearby metalwork, adding to the buzzing noise, and consuming a small amount of power.
Stray losses
Leakage inductance is by itself largely lossless, since energy supplied to its
magnetic fields is returned to the supply with the next half-cycle. However, any leakage
flux that intercepts nearby conductive materials such as the transformer's support
structure will give rise to eddy currents and be converted to heat. There are also radiative
losses due to the oscillating magnetic field, but these are usually small.
Dot convention
It is common in transformer schematic symbols for there to be a dot at the end of
each coil within a transformer, particularly for transformers with multiple primary and
secondary windings. The dots indicate the direction of each winding relative to the
others. Voltages at the dot end of each winding are in phase; current flowing into the dot
end of a primary coil will result in current flowing out of the dot end of a secondary coil.
Equivalent circuit
Construction
Cores
Laminated Cores
Toroidal cores
Ferrite toroidal cores are used at higher frequencies, typically between a few tens
of kilohertz to hundreds of megahertz, to reduce losses, physical size, and weight
of switch-mode power supplies. A drawback of toroidal transformer construction is the
higher labor cost of winding. This is because it is necessary to pass the entire length of a
coil winding through the core aperture each time a single turn is added to the coil. As a
consequence, toroidal transformers are uncommon above ratings of a few kVA. Small
distribution transformers may achieve some of the benefits of a toroidal core by splitting
it and forcing it open, then inserting a bobbin containing primary and secondary
windings.
Air cores
Windings
Applications
Transformers are also used extensively in electronic products to step down the
supply voltage to a level suitable for the low voltage circuits they contain. The
transformer also electrically isolates the end user from contact with the supply voltage.
Signal and audio transformers are used to couple stages of amplifiers and to match
devices such as microphones and record players to the input of amplifiers. Audio
transformers allowed telephone circuits to carry on a two-way conversation over a single
pair of wires. A balloon transformer converts a signal that is referenced to ground to a
signal that has balanced voltages to ground, such as between external cables and internal
circuits.
The principle of open-circuit (unloaded) transformer is widely used for
characterization of soft magnetic materials, for example in the internationally
standardized Epstein frame method.
Moreover, there
are transportation
restrictions
especially
regarding
substations in
mountainous
areas, etc., for
which the
introduction of an
on-site assembly
system is seen as
a solution to this
problem while
also minimizing
installation space.
Of equal
importance is the
need for stable
operation over
long period. Large capacity transformers have evolved to meet the changing needs of
electric power companies..
In addition, plans to double the voltage rating will increase considering future
long-distance transmission, and the need for a routine supervisory system will grow as
transformer operating conditions become severe due to extended operating life of
equipment, overload operation, etc.
This paper reviews Hitachi’s efforts to meet the challenges described above. In
particular, we discuss our 281.25-kV(525- kV) 1,060-MVA double-rating voltage
transformer for power stations and our 500-kV 1,000-MVA site- assembled
transformer for substations. We also discuss the latest apparatus supervisory system we
provide, which can support preventive maintenance systems.
HISTORY OF HITACHI’S LARGE-CAPACITY TRANSFORMERS
.
On- site assembled
transformers for
substation began in
1989 with the 220-kV
250-MVA site-
assembly transformer.
The technique
used in 1989 is similar
to the present one. The
500-kV 1,000-MVA
site- assembled
transformer was
completed in 2000
Structure
The high voltage winding consists of
two windings. Two high-voltage
windings are used in parallel for the
281.25-kV connection and are used in
series for the
525-kV connection. By changing the
internal lead line, the connection can be changed. The composition of the windings is
shown in Fig.
Core
The three-phase five-legs core of the
conventional large capacity
transformer was adopted. The
optimum joint structure was used to
ensure the magnetic flux would be
uniform and the local loss would not
become concentrated. The cross-
sectional ratio of the up-and- down
yoke and side yoke was also
optimized.
Winding
The windings are arranged in the order
of tap winding, high-voltage winding
2, low-voltage winding, and high-
voltage winding 1 from the inner side.
In order to make the short-circuit
impedance the same for both operating
voltages, the current distribution needs
to be made the same. For the parallel 281.25- kV connection of the high-voltage winding
1 and 2, the low-voltage windings among the high-voltage windings 1 and 2 are
connected so that current distribution ratio can be about 50%. Furthermore, analysis of
the main gaps ensured that the impedance between each high-voltage winding and the
low- voltage winding would be almost equal. To design the insulation of the high-voltage
windings, the generating voltages between coils and an internal connection point were
analyzed using EMTP (electro-magnetic transients program). The EMTP analysis was
carried out not only for standard waves but also for long-tail waves, and attenuation
oscillating waves. A low- voltage helical winding consisting of many parallel transposed
rectangular wires was adopted, and it was designed to control circulating current by using
the optimum transposition method.
Reliability Verification
To verify the reliability of the transformer, the current distribution ratio of the two high-
voltage windings and the voltage distribution characteristics of the windings in air against
low-voltage surge were checked in the manufacturing stage. It was found that there were
no problems regarding performance. In the shop test, the connection was changed after
the test for the 525-kV connection and the test for the 281.25- kV connection was carried
out. Good results were obtained for both connection states.
(1) The main leg non-division method is adopted for the core. This minimized the
transportation size and
mass, without
deteriorating the core
characteristics (see Table
2).
Transportation Test
Preventive maintenance for the substation can be enhanced with the supervisory
equipment for oil level, oil temperature, diagnosis of unusual events, etc. An example is
the operation supervisory technology of the on-load tap changer, which is much more
troublesome than other transformer parts.
Hitachi has created supervisory equipment that can diagnose unusual states of the on-load
tap changer at an early stage by detecting driving torque, operation time, motor current,
etc. In the measurement system shown in Fig. 6, a torque sensor and a torque
measurement value are transmitted to a distant central control room by using a telephone
circuit. Locating the fault position in addition to detecting the fault phenomenon is also
possible through accumulation of the transmitted torque data. Moreover, abnormalities
originating in deformation of the tap changer drive system, jams between a shaft and
bearings, and wear are detectable by analyzing the trend and pattern of the driving torque
data.
Ukraine is one of the few already have developed ultra-high pressure, ultra high voltage
power transmission technology experience in the world. Wukelanzha Broken heat
transformer transformer Institute is the world's largest institute, the Institute's major areas
of work are: to carry out research, design, software work, develop new products, design
of tooling equipment and production technology, manufacturing, samples and small
number of products, electrical equipment testing and repair of complex electrical
equipment, to study and propose national standards, product certification and consulting
services. Its been an important product development and pilot projects are: DC ± 750 kV,
320 MVA transformers, smoothing reactors, isolation; 750 kV shunt reactors; 667 MVA,
1 150/500 kV auto-transformer model; 1 800 / 500 kV auto-transformer model; 750 ~ 1
800 kV tube; DC 600 kV pulse device; 220 ~ 500 kV neutral bushing; dry-type
transformers environmental testing capacity of 1 600 kVA; 750 kV and below the
electromagnetic current transformer control; 500 kV and below electromagnetic voltage
transformer; 750 kV capacitor voltage transformer
Russia has made the 20th century, 70 years of single-phase 417 MVA / 1 150 kV, three-
phase 1 000 MVA/500 kV transformers, 80 to make single-phase 667 MVA / 1 150 kV
and three-phase 1 250 MVA/330 kV transformer.
1955 to 1990, factory production has been greatly improved parameters of power
transformers, voltage increased from 220 kV to 1 150 kV, three-phase transformer
capacity increased from 240 MVA to 1250 MVA, single-phase transformer capacity
increase from 250 MVA to 667 MVA.
Wukelanzha Broken Heat Transformer Factory (ZTR) is the world's largest transformer
factory, which produces power and distribution transformers, reactors, reactor division,
voltage transformers, current transformers, DC transformer, enclosed bus ( single or three
phase) and so on. ZTR products produced by 70% for export, 75 countries have imported
the plant's transformers, of which China imported 73 units from the plant 500 kV power
transformers. ZTR main products produced are: ① 6 phase 1250 MVA/347 kV
transformer station (1980 production); phase 1 000 MVA/500 kV generator step-up
transformer 21 sets; three-phase three-winding 300 MVA, 500 / 154/38 kV transformer.
② Single-phase 417 MVA, 750/500 kV transformer of 67 units (1978 production);
single-phase 533 MVA, 500/330 kV single-phase 417 MVA, 1 150/500 kV transformer
station of the 1 (1981 production); Single phase 667/180 MVA, 1 150/500 kV auto-
transformer 26 units (20 of 1979 production, 1972 production of 6 sets). ③ 320 MVA, ±
750 kV converter transformers. ④ 120 Mvar, 800 kV and 300 Mvar, 1 150 kV shunt
reactors and the neutral reactor. ⑤ OLTC330 kV, 2 000 A. ⑥ single-phase 60 Mvar, 500
kV station of Reactor 1 (1989 production). ⑦ 417/50 MVA transformer 143 units (105
units produced in 1972, producing 38 in 1973). ⑧ 3-phase 25 Mvar, 110 kV station of
Reactor 1 (1997 production). ⑨ single-phase 500 MVA, 765/345 kV ± 13% (1.3% per
level) autotransformer exported to Brazil, P0 = 200 kW, Pk = 700 kW. ⑩ distribution
transformers and special transformers. 35 kV, 31.5 kA closed bus.
ZTR core banding produced by adhesive tape binding, core paper tube columns filled thin
cardboard, then tied adhesive tape, strip tension with core clamps, and Siemens, ABB
transformer company produced similar structure. Winding voltage 500 kV and above all
do not use the oil flow-oriented structure, so the winding inner diameter, outer diameter
has a lock hold, see block oil line there in a pie plate. Transformer accessories has been
lagging behind the oil drain valve is used in valve, fuel tank processing more crude oil
tank at the top of the slope greater difficulties workers to operate. Transformer using
magnetic shielding, silicon steel sheet width of about 80 mm, thickness 15 ~ 30 mm, end
welded together by welding the steel sheet. Transformer bushing structure is relatively
backward, the upper casing are pressed with a wire cover, no Pressure the ball, the casing
by hydraulic oil also set up a small pillow.
To meet the growing demand for electricity in the 21st Century, Tokyo Electric Power
Company (TEPCO) in Japan developed the first set 1 000 kV transmission system, and is
Shin-Haruna 1 000 kV substation test site to test 1 000 kV operation of equipment
performance and reliability sex. Mitsubishi Electric has developed a variety of 1 000 kV
electrical equipment. Ako Toshiba factory produced a 1 000 kV for the qualification
testing single-phase shell-load tap transformer. Toshiba produced the following 1 000 kV
transformer specifications, construction, installation and testing conditions are
introduced.
Specifications
Table 1 1 000 kV single-phase load tap the basic parameters of shell-type transformers
rated capacity / MVA 3 000 / 3
Voltage range
Test voltage
Lightning impulse withstand voltage primary side of the 1 950 kV, secondary side of the
1 300 kV
18% impedance
Noise Level 65 dB
Note: E = 1 100 / kV
High and medium voltage side of the capacity choices of the maximum transmission
capacity to meet the requirements. The third winding capacity 1 200 MVA (40% of the
high and medium voltage side of the capacity) is to meet the choice of 1 000 kV
transmission lines, as in the maximum required capacity. Low-voltage winding rated
voltage 500 kV transformer that if selected as 63 kV, it will lead to a large fault current,
select the 147 kV and low voltage side in order to make the winding volume of associated
equipment will not increase. Impedance value (the percentage of short-circuit voltage) to
select 18% of the maximum taking into account the stability of the grid, which is
inhibited by the ground fault current and transformer design of the economy and other
factors. Since 1 000 kV substation will be built in mountainous areas, so all parts must be
used for transformers or large trailer to transport the railway. In order to meet the
transport constraints, 1 000 kV transformer split into two main parts of units, each unit is
equipped with an automatic on-load tap device. AC power frequency withstand voltage
long-term option is for the future 1 000 kV transmission system fault analysis obtained,
during the test may not appear in the partial discharge. Lightning impulse withstand test
voltage arresters by high-performance 1 000 kV transmission system analysis of the
resulting transient voltage. Select high-pressure side of the 1 950 kV, medium voltage
side of the selected 1 300 kV. 65 dB noise level primarily to enable the substation to
minimize the noise, can be installed around the transformer steel barriers to
implementation.
CONCLUSION
REFERENCES