Ingeniería Sanitaria II
Integrantes
Catedrática
Tegucigalpa M.D.C.
29 de noviembre de 2010
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Contenido
Resumen Ejecutivo.................................................................................................................3
Introducción............................................................................................................................4
Objetivos.................................................................................................................................5
1. Introducción...................................................................................................................6
Conclusiones y Recomendaciones........................................................................................32
Anexos..................................................................................................................................34
Anexos
2
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Resumen Ejecutivo
Se denomina alcantarillado (de alcantarilla, que procede del diminutivo hispano-árabe al-
qánṭara, «el puentecito») o también red de alcantarillado, red de saneamiento o red de
drenaje al sistema de estructuras y tuberías usado para la recogida y transporte de las aguas
residuales y pluviales de una población desde el lugar en que se generan hasta el sitio en
que se vierten al medio natural o se tratan.
Las redes de alcantarillado son estructuras hidráulicas que funcionan a presión atmosférica,
por gravedad. Sólo muy raramente, y por tramos breves, están constituidos por tuberías que
trabajan bajo presión o por vacío. Normalmente están constituidas por canales de sección
circular, oval o compuesta, enterrados la mayoría de las veces bajo las vías públicas.
Introducción
3
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
4
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Objetivos
5
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
1. Introducción
En la mayoría de las ciudades se tiene la necesidad de evacuar las aguas de lluvia para
evitar que se inunden las viviendas, los comercios, las industrias y otras áreas de interés.
Por otra parte, la construcción de edificios, casas, calles estacionamientos y otros modifican
el entorno natural en que habita el hombre y, tiene como algunas de sus tantas
consecuencias, la creación de superficies poco permeables (que favorece a la presencia de
una mayor cantidad de agua sobre el terreno) y la eliminación de los cauces naturales (que
reduce la capacidad de desalojo de las aguas pluviales y residuales).
6
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
El uso racional del agua implica emplearla eficientemente en las diversas actividades del
hombre, disminuir su desperdicio y contaminación. La base de todo esto consiste en
fomentar en la población, industria y autoridades la conciencia de que el agua es limitada
en su disponibilidad, ya sea por la cantidad o por la calidad que se requiere. Por ello, debe
usarse adicionalmente este recurso, conservando las fuentes y evitando su deterioro.
El agua de lluvia puede ser utilizada con un tratamiento ligero o incluso sin tratamiento,
cuando se cuenta con las estructuras necesarias de conducción y almacenamiento sin alterar
lo más mínimo su calidad. El empleo del agua pluvial puede ser muy provechoso en las
zonas urbanas, sin embargo, requiere de obras y el establecimiento de normas adicionales
de operación. En general, es importante que el profesional encargado de diseñar los
7
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
8
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
posibles daños al último tramo de tubería que pueden ser causados por la corriente a
donde descarga el sistema o por el propio flujo de salida de la tubería.
Cuando llueve en una localidad, el agua no infiltrada escurre por las calles y en el terreno
natural hacia las partes bajas, donde finalmente puede almacenarse o conducirse hacia los
9
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
arroyos naturales. A fin de evitar que el agua se acumule o sus corrientes causen daños y
molestias a la población, se construye el alcantarillado pluvial por medio del cual se
conducen las aguas de lluvia hacia sitios más seguros para su vertido.
1. Los colectores de mayor diámetro se ubican en las calles más bajas para facilitar el
drenaje de las zonas altas con atarjeas o colectores de menor diámetro.
2. El trazo de los colectores y las atarjeas se ubica sobre el eje central de las calles,
evitando su cruce con edificaciones. Su trazo debe ser lo más recto posible
procurando que no existan curvas. Cuando la calle sea amplia, se pueden disponer
dos atarjeas, una a cada lado de la calle.
3. La red de alcantarillado debe trazarse buscando el camino más corto al sitio de
vertido.
4. Las conducciones serán por gravedad. Se tratará de evitar las conducciones con
bombeo.
10
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Durante el diseño se lleva a cabo el cálculo del funcionamiento hidráulico del conjunto de
tuberías a fin de revisar que los diámetros y pendientes propuestos sean suficientes para
conducir el gasto de diseño de cada tramo.
De elaborar múltiples diseños, se puede apreciar que el dimensionamiento de las tuberías
depende principalmente del tamaño del área por servir y de su coeficiente de escurrimiento,
de la intensidad de la lluvia de diseño, y del periodo económico de diseño.
Durante el diseño de una red de alcantarillado, se pretende que los costos de construcción
no sean elevados y, por otra parte, que la red sea funcional en aspectos relacionados con la
operación y el mantenimiento de la misma.
En general, puede afirmarse que una red de alcantarillado ha sido bien diseñada cuando:
11
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
I = a/ (b + t)
Donde:
12
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
13
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Después de graficar las rectas para intensidades de lluvia para duración de 10’,30’,60’ y
120’ se obtuvieron los datos de precipitación para periodos de retorno de 2, 5, 10 y 25 años
con cada duración respectivamente:
A continuación se hizo un análisis según Talbot obteniendo una serie de ecuaciones, que al
ser resueltas dieron como resultado los valores de a y b correspondientes a cada periodo de
retorno y los puntos para realizar la curva I-F-D
I = a/ (b + t)
I=7346.39(20.72+t)
14
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
15
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
La cantidad de tragantes presentes en cada tramo del diseño dependerán del caudal pico en
ese tramo, después de compararlo con el caudal máximo que puede transportar la calle
teniendo un tirante de 10 cm, se determinara si se necesitan tragantes intermedios.
• Únicamente en aquellas calles con pavimento o que vayan a recibir algún tipo de
tratamiento superficial
• Sólo cuando las calles tengan bordillo o que conozcan las cotas definitivas de la
rasante.
• Se usarán tragantes de tipo horizontal en pendientes de 5% o mayores y tragantes
tipo vertical en pendientes menores de 5%.
1. Después de haber colocado el tragante en 47, se determina el área que tributa a ese
tragante.
16
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
En este caso el área grande que se muestra en la figura es parte de la cuenca y toda el agua
que llegue a la parte posterior de cada casa no traspasara el terreno, sino que será conducido
a través de una cuenta por toda la longitud atrás de los lotes hasta el tragante en 47, también
tributan 2 casas, que viene siendo el área pequeña en la ilustración.
C= A1 × C1 +A2 × C2 Atotal
3. A continuación se calcula el tiempo critico, es decir el tiempo que tarda una gota de
agua en llegar de un punto muy alejado al tragante, teniendo en consideración que si
la gota viaja por la cuenca el cálculo se debe hacer utilizando la fórmula de Kirpich,
y si ya viaja por la cuneta de la calle utilizando Manning.
La primera parte del recorrido es por la cuenca, entonces:
17
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
t=LV v=1n*R2/3*S1/2
L=8m
S=12.5%
Rh=0.049
t=8m10.035*0.0492/3*0.121/2=5.91s*1min60s=0.1min
Tt=4.28min+0.1min=4.38min
I= 7346.39tc+20.72
I= 7346.394.38+20.72=292.74 mmh
Qp= C*i*A
Donde:
• c , la ponderación de coeficiente de escorrentía.
• i, la intensidad de lluvia
• A, el área total que tributa al tramo.
18
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
* 3.6 × 106 Se utiliza como factor de conversión para que las unidades del caudal pico
sean congruentes y el resultado de en m3s
1. Resta comparar el Caudal pico con el Caudal máximo que puede transportar la calle
y este se calcula de la siguiente manera:
Am=123.33m0.1m2=0.334m2
La figura anterior representa la mitad de la calle del tramo que se está analizando, todas las
calles del circuito son iguales.
Pm=3.332+0.12+0.1*2=6.81m m
Radio Hidráulico: este valor en todos los tramos va a ser constante, debido a que las
dimensiones de todas las calles que componen el complejo habitacional son iguales. El
radio hidráulico está regido por el porcentaje de inclinación que tiene la calle y por la altura
máxima de la acera, por lo tanto el ancho de la calle no es de suma importancia.
Donde:
19
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Pendiente S se obtiene por la diferencia de elevaciones dividida por la distancia del tramo
y multiplicada por 100 ya que se expresa en porcentaje.
S= 1147-11468×100=12.5 %
Donde:
Caudal máximo: es la cantidad límite de agua que puede trasportar por las cunetas que
tiene la calle. Se calcula multiplicando la velocidad (fórmula de manning) por el área
mojada.
Qmax=V*A
Qmax=1.35*0.334=0.45 ms
Si el resultado del caudal pico tuviera un valor mayor al del caudal máximo, entonces se
vuelve a diseñar el tramo con la cantidad de tragantes que se necesiten, siempre utilizando
el mismo procedimiento anterior.
20
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
1-47 144.34 24563. 24707. 0.75 0.20 0.20 302.59 8.00 1170.00 1147.00 1147.00 1146.00
03 37
47-2 863.66 863.66 0.75 0.20 0.75 8.00 38.57 1150.00 1148.25 1148.25 1148.00
11-2 2931.5 2931.5 0.75 0.20 0.75 8.00 190.00 1152.00 1150.00 1150.00 1148.00
1 1
2-3 784.00 784.00 0.75 0.20 0.75 8.00 49.00 1147.25 1147.00 1148.00 1140.00
3-6 1472.1 1472.1 0.75 0.20 0.75 8.00 76.04 1143.00 1142.00 1143.00 1142.00
7 7
8-6 2544.9 2544.9 0.75 0.20 0.75 8.00 84.37 1148.25 1147.00 1148.25 1142.00
4 4
9-14 1596.0 1596.0 0.75 0.20 0.75 8.00 55.16 1148.25 1148.00 1148.00 1139.00
6 6
12-14 1450.3 1450.3 0.75 0.20 0.75 8.00 49.00 1141.00 1140.00 1140.00 1139.00
4 4
14-15 447.63 447.63 0.75 0.20 0.75 8.00 28.00 1139.25 1139.00 1139.00 1138.75
21
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
6-15 655.49 655.49 0.75 0.20 0.75 8.00 41.00 1142.25 1142.00 1142.00 1139.00
15-16 0.00 0.00 0.75 0.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
17-16 1310.2 1310.2 0.75 0.20 0.75 8.00 60.00 1147.25 1147.00 1147.00 1137.00
5 5
18-19 944.31 944.31 0.75 0.20 0.75 8.00 35.26 1140.25 1140.00 1140.00 1135.00
22-16 1352.6 1352.6 0.75 0.20 0.75 8.00 82.86 1139.00 1138.00 1138.00 1137.00
4 4
16-19 1214.5 1214.5 0.75 0.20 0.75 8.00 32.00 1137.25 1137.00 1137.00 1135.00
7 7
21-20 1217.0 1217.0 0.75 0.20 0.75 8.00 32.00 1136.25 1136.00 1136.00 1133.00
7 7
19-20 733.82 733.82 0.75 0.20 0.75 8.00 42.00 1135.25 1135.00 1135.00 1133.00
22-23 670.58 670.58 0.75 0.20 0.75 8.00 32.36 1137.25 1137.00 1137.00 1133.00
20-23 911.46 911.46 0.75 0.20 0.75 8.00 56.00 1133.50 1133.00 1133.00 1132.00
25-26 1724.6 1724.6 0.75 0.20 0.75 8.00 77.00 1156.00 1155.00 1155.00 1149.00
4 4
22
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
1-47 4.28 0.10 4.3 292.74 0.40 0.049 1147.00 1146.00 0.03 8.00 12.5 0.334 1.35 0.45
8 5 0
47-2 0.17 2.11 2.2 319.39 0.06 0.049 1148.25 1148.00 0.03 38.57 0.65 0.334 0.31 0.10
8 5
11-2 0.16 6.87 7.0 264.70 0.16 0.049 1150.00 1148.00 0.03 135.00 1.48 0.334 0.47 0.16
3 5
2-3 0.37 0.55 0.9 339.57 0.06 0.049 1148.00 1140.00 0.03 51.51 15.5 0.334 1.51 0.50
1 5 3
3-6 0.22 3.38 3.6 302.10 0.09 0.049 1143.00 1142.00 0.03 102.18 0.98 0.334 0.38 0.13
0 5
8-6 0.20 1.43 1.6 328.80 0.17 0.049 1148.25 1142.00 0.03 92.12 6.78 0.334 1.00 0.33
2 5
9-14 0.37 0.62 0.9 338.50 0.11 0.049 1148.00 1139.00 0.03 57.86 15.5 0.334 1.51 0.50
8 5 5
12-14 0.22 1.72 1.9 324.29 0.10 0.049 1140.00 1139.00 0.03 63.50 1.57 0.334 0.48 0.16
3 5
14-15 0.37 1.56 1.9 324.43 0.03 0.049 1139.00 1138.75 0.03 39.91 0.63 0.334 0.30 0.10
2 5
6-15 0.37 0.63 1.0 338.21 0.05 0.049 1142.00 1139.00 0.03 37.12 8.08 0.334 1.09 0.36
0 5
15-16 0.00 0.00 0.0 0.00 0.00 0.049 0.00 0.00 0.03 0.00 0.00 0.334 0.00 0.00
0 5
17-16 0.37 0.55 0.9 339.57 0.09 0.049 1147.00 1137.00 0.03 42.98 23.2 0.334 1.85 0.62
23
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
1 5 7
18-19 0.37 0.42 0.7 341.52 0.07 0.049 1140.00 1135.00 0.03 37.30 13.4 0.334 1.40 0.47
9 5 0
22-16 0.22 3.44 3.6 301.33 0.08 0.049 1138.00 1137.00 0.03 89.24 1.12 0.334 0.40 0.14
6 5
16-19 0.37 0.64 1.0 338.19 0.09 0.049 1137.00 1135.00 0.03 40.72 4.91 0.334 0.85 0.28
0 5
21-20 0.37 0.52 0.8 340.03 0.09 0.049 1136.00 1133.00 0.03 40.58 7.39 0.334 1.04 0.35
8 5
19-20 0.37 0.84 1.2 334.97 0.05 0.049 1135.00 1133.00 0.03 41.74 4.79 0.334 0.84 0.28
1 5
22-23 0.37 0.46 0.8 340.89 0.05 0.049 1137.00 1133.00 0.03 42.37 9.44 0.334 1.18 0.39
3 5
20-23 0.28 1.86 2.1 321.29 0.06 0.049 1133.00 1132.00 0.03 57.24 1.75 0.334 0.51 0.17
5 5
24-25 1.99 1.9 323.50 0.10 0.049 1158.00 1152.00 0.03 21.02 28.5 0.334 2.04 0.68
9 5 4
25-26 0.22 1.26 1.4 331.03 0.12 0.049 1155.00 1149.00 0.03 82.58 7.27 0.334 1.03 0.34
7 5
24
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
28-30 1291.6 2232.4 3524.1 0.75 0.20 0.40 171.80 1180.00 1141.00
3 7 0
32-33 3811.8 3811.8 0.75 0.20 0.75 8.00 144.75 1166.00 1163.00 1163.00 1141.00
0 0
33-30 426.30 426.30 0.75 0.20 0.75 8.00 21.15 1140.25 1140.00 1140.00 1139.80
30-26 229.96 229.96 0.75 0.20 0.75 8.00 14.00 1140.25 1140.00 1140.00 1139.80
26-35 516.30 516.30 0.75 0.20 0.75 8.00 30.87 1138.50 1138.00 1138.00 1134.00
40-35 598.84 598.84 0.75 0.20 0.75 8.00 35.34 1139.25 1139.00 1139.00 1133.00
37-38 2567.0 2567.0 0.75 0.20 0.75 8.00 77.21 1139.50 1139.00 1133.00 1128.00
6 6
38-39 1007.8 1007.8 0.75 0.20 0.75 8.00 55.28 1126.25 1126.00 1126.00 1125.75
3 3
40-39 2451.0 2451.0 0.75 0.20 0.75 8.00 64.48 1138.25 1138.00 1138.00 1128.00
2 2
39-46 354.78 354.78 0.75 0.20 0.75 8.00 19.85 1128.25 1128.00 1128.00 1127.00
41-42 319.42 319.42 0.75 0.20 0.75 8.00 20.14 1132.00 1131.00 1131.00 1130.00
43-42 596.99 596.99 0.75 0.20 0.75 8.00 34.93 1131.50 1131.00 1131.00 1129.00
42-45 2918.1 2918.1 0.75 0.20 0.75 8.00 77.92 1131.00 1130.00 1130.00 1125.00
25
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
9 9
44-45 934.89 934.89 0.75 0.20 0.75 8.00 25.87 1124.25 1124.00 1124.00 1123.00
32-33 0.14 1.50 1.6 328.55 0.26 0.049 1163.00 1141.00 0.03 121.85 18.0 0.334 1.63 0.54
4 5 5
33-30 0.37 0.86 1.2 334.81 0.03 0.049 1140.00 1139.80 0.03 16.88 1.18 0.334 0.42 0.14
2 5
30-26 0.37 0.74 1.1 336.64 0.02 0.049 1140.00 1139.80 0.03 28.50 0.70 0.334 0.32 0.11
0 5
26
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
26-35 0.28 0.45 0.7 342.40 0.04 0.049 1138.00 1134.00 0.03 44.80 8.93 0.334 1.14 0.38
4 5
40-35 0.37 0.39 0.7 342.00 0.04 0.049 1139.00 1133.00 0.03 38.48 15.5 0.334 1.51 0.50
6 5 9
37-38 0.28 1.46 1.7 327.08 0.17 0.049 1133.00 1128.00 0.03 92.30 5.42 0.334 0.89 0.30
4 5
38-39 0.37 3.38 3.7 300.23 0.06 0.049 1126.00 1125.75 0.03 48.33 0.52 0.334 0.28 0.09
5 5
40-39 0.37 0.73 1.0 336.79 0.17 0.049 1138.00 1128.00 0.03 65.45 15.2 0.334 1.50 0.50
9 5 8
39-46 0.37 0.42 0.7 341.54 0.03 0.049 1128.00 1127.00 0.03 23.42 4.27 0.334 0.79 0.26
9 5
41-42 0.22 0.42 0.6 343.96 0.02 0.049 1131.00 1130.00 0.03 22.77 4.39 0.334 0.80 0.27
4 5
43-42 0.28 0.63 0.9 339.64 0.04 0.049 1131.00 1129.00 0.03 33.46 5.98 0.334 0.94 0.31
1 5
42-45 0.22 1.41 1.6 328.75 0.20 0.049 1130.00 1125.00 0.03 84.70 5.90 0.334 0.93 0.31
3 5
44-45 0.3670 0.595 0.9 338.82 0.07 0.049 1124.00 1123.00 0.03 27.35 3.66 0.334 0.73 0.24
7 3 6 5
27
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
El diseño de los pozos y tubería debe hacerse teniendo en cuanta los siguientes criterios:
A. Áreas Tributarias
El área tributaria en un tramo se hará sumando el área del tramo considerado con las
áreas tributarias de los tramos anteriores.
B. Diámetros Mínimos
• El diámetro mínimos las tuberías que unen los tragantes con los pozos de registro
serán de 18 pulgadas.
28
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
A= 24707.37m2
2. Coeficiente de Escorrentía:
Es el coeficiente de escorrentía calculado anteriormente para la revisión del tramo 1-47
C=0.20
3. Tiempo critico:
Tc= 4.38min (Tiempo más largo para llegar al tragante en 2, calculado con anterioridad en
la sección de tragantes)
4. Intensidad
Utilizando la ecuación de la Intensidad ya conocida y con los datos obtenidos:
I= 7346.394.38+4.38=292.74 mmh
Se obtuvo una pendiente negativa, lo que indica que para que el sistema funcione por
gravedad, no es posible utilizar la pendiente del terreno natural.
29
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
8. Pendiente de la Invertida
La elevación inicial y final de la Invertida se obtiene restando del terreno natural la
profundidad del pozo inicial y final, respectivamente. Luego la diferencia de elevaciones se
divide entre la longitud de la tubería y se obtiene la pendiente que esta tendrá.
Elev ini=1147-1.8= 1145.2m
Elev Final=1148-3.25=1144.75m
SI=1145.2-1144.7558*100=0.78%
Ya que está pendiente cumple con la norma, continuamos con los siguientes cálculos, caso
contrario se debería cambiar la profundidad de los pozos hasta lograr un pendiente que
cumpla.
9. Diámetro
A= 0.2917m2 y R=0.1524
Donde:
• R es el radio hidráulico,
• S es la pendiente de la parte invertida de la tubería y
• N es el coeficiente de rugosidad del material utilizado (concreto).
Vll=10.035 *0.15242/30.781001/2=1.6754ms
Vr/Vll=1.1187
31
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
47-2 24707. 24707. 0.20 0.20 4.3 4.38 292.74 0.402 58 1147 1148 -
37 37 8 1.7
2
2-3 24707. 3795.1 28502. 0.20 0.75 0.27 7.0 7.03 264.73 0.573 52 1148 1142 11.
37 7 54 3 54
3-4 24707. 4579.1 29286. 0.20 0.75 0.29 7.0 0.17 7.21 263.07 0.612 53 1142 1145 -
37 7 54 3 5.6
6
4-5 24707. 5251.1 29958. 0.20 0.75 0.30 7.0 0.51 7.55 259.90 0.641 26 1145 1144 3.8
37 7 54 3 5
5-6 24707. 5800.1 30507. 0.20 0.75 0.30 7.0 0.62 7.66 258.88 0.668 24 1144 1141 12.
37 7 54 3 50
6-15 24707. 27652. 52359. 0.20 0.75 0.49 7.0 0.72 7.76 257.99 1.840 34 1141 1139 5.8
37 31 68 3 8
14- 3046.4 3046.4 0.75 0.75 1.9 1.93 324.29 0.206 22 1139. 1139 2.2
15 0 0 3 5 7
32
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
15- 24707. 31554. 56262. 0.20 0.75 0.51 7.6 0.11 7.77 257.86 2.049 43 1139 1137 4.6
16 37 71 08 6 5
25- 5779.5 5779.5 0.75 0.75 1.9 1.99 323.50 0.390 70 1153 1137 22.
26 3 3 9 86
33- 3811.8 3811.8 0.75 0.75 2.5 2.54 315.84 0.251 13 1141 1139 15.
30 0 0 4 58
30- 3524.1 4238.1 7762.2 0.40 0.75 0.59 2.5 0.05 2.59 315.22 0.402 26 1139 1137 7.6
26 0 0 0 4 9
26- 5779.5 2380.9 8160.4 0.20 0.75 0.36 2.5 0.10 2.68 313.91 0.256 18 1137 1134 16.
34 3 0 3 9 67
16- 24707. 34217. 58924. 0.20 0.75 0.52 7.6 0.17 7.83 257.35 2.188 40 1137 1135 5.0
19 37 60 97 6 0
19- 24707. 61083. 85791. 0.20 0.75 0.59 7.8 0.14 7.96 256.13 3.611 42 1135 1133 4.7
20 37 85 22 3 6
20- 24707. 62300. 87008. 0.20 0.75 0.59 7.9 0.14 8.10 254.90 3.658 40 1133 1132. 1.2
23 37 92 29 6 5 5
23- 24707. 63212. 87919. 0.20 0.75 0.60 8.1 0.13 8.23 253.77 3.690 29 1132. 1134 -
34 37 38 75 0 5 5.1
7
34- 30486. 64681. 95168. 0.20 0.75 0.57 8.2 0.10 8.33 252.88 3.836 27 1134 1131 11.
35 90 82 72 3 11
35- 30486. 65280. 95767. 0.20 0.75 0.57 8.3 0.10 8.43 252.02 3.854 14 1131 1130. 0.7
33
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
41 90 66 56 3 9 1
41- 30486. 65280. 95767. 0.20 0.75 0.57 8.4 0.06 8.49 251.5 3.854 31 1130. 1129 6.1
42 90 66 56 3 9 3
42- 30486. 66197. 96683. 0.20 0.75 0.58 8.4 0.10 8.59 250.6 3.881 84 1129 1124 5.9
45 90 07 97 9 5
45- 30486. 70050. 100537 0.20 0.75 0.58 8.5 0.29 8.88 248.2 4.042 43 1124 1128 -
46 90 15 .05 9 9.3
0
38- 2567.0 2567.0 0.75 0.75 1.7 1.74 327.1 0.175 49 1127 1128 -
39 6 6 4 2.0
4
39- 7585.1 7585.1 0.75 0.75 1.7 0.50 2.24 320.0 0.506 24 1128 1128. -
46 4 4 4 5 2.0
8
Tram INI Fin E E S θ(pul θ( n Área( R(m) Vll(m Qll(m3/s Qp/Qll V/VL Y/D V(m/
o INI(m) Fin(m) (%) g) m) m2) /s) ) L s)
47-2 2.4 3.9 1144.5 1144.14 0.78 24 0.6 0.01 0.2917 0.15 1.676 0.489018 0.821696 1.11 0.69 1.9
9 1 5 24 4 2 81 87 7
2-3 4 2.6 1143.9 1139.43 8.75 30 0.7 0.01 0.4558 0.19 6.528 2.975927 0.192443 0.77 0.29 5
9 8 6 5 05 9 55 75 47 9
34
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
3-4 2.6 6.3 1139.4 1138.73 1.32 30 0.7 0.01 0.4558 0.19 2.536 1.156190 0.529389 1.02 0.52 2.6
4 8 6 5 05 6 54 88 12 6
4-5 2.6 2.6 1142.4 1141.43 3.85 30 0.7 0.01 0.4558 0.19 4.328 1.973020 0.324921 0.89 0.39 3.9
4 8 6 5 05 6 75 81 54 4
5-6 4.5 2.6 1139.4 1138.43 4.37 30 0.7 0.01 0.4558 0.19 4.616 2.104298 0.317521 0.88 0.38 4.1
9 8 6 5 05 7 55 86 97 9
6-15 3.4 2.7 1137.5 1136.28 3.82 36 0.9 0.01 0.6564 0.22 4.873 3.198899 0.575319 1.03 0.54 5.0
9 6 1 5 86 7 04 42 56 5
14- 2.3 2.3 1137.2 1136.74 2.27 18 0.4 0.01 0.1641 0.11 2.367 0.388414 0.529895 0.63 0.21 1.5
15 4 3 6 5 43 1 4 61 3
15- 3.9 2.9 1135.0 1134.08 2.33 36 0.9 0.01 0.6564 0.22 3.800 2.494790 0.821337 1.11 0.69 4.2
16 9 6 1 5 86 9 54 2 65 1
25- 8.5 2.7 1144.5 1134.28 14.5 36 0.9 0.01 0.6564 0.22 9.520 6.249126 0.062331 0.56 0.17 5
26 6 9 1 5 86 9 98 68 37 3
33- 2.6 2.4 1138.3 1136.59 14.0 24 0.6 0.01 0.2917 0.15 7.121 2.077520 0.120727 0.66 0.11 4.7
30 9 2 1 5 24 7 73 93 09 7
30- 2.4 2.4 1136.5 1134.59 7.69 24 0.6 0.01 0.2917 0.15 5.275 1.538933 0.261375 0.84 0.34 4.4
26 9 1 5 24 5 84 58 17 9
26- 3.3 2.6 1133.7 1131.43 12.7 30 0.7 0.01 0.4558 0.19 7.889 3.596217 0.071323 0.57 0.18 4.6
34 4 8 8 6 5 05 8 85 68 93 1
16- 3.4 2.7 1133.5 1132.28 3.25 36 0.9 0.01 0.6564 0.22 4.493 2.949579 0.741722 1.09 0.64 4.9
19 9 6 1 5 86 8 47 19 54 2
19- 3.8 2.9 1131.2 1130.13 2.62 42 1.0 0.01 0.8934 0.26 4.470 3.993602 0.904204 1.13 0.74 5
20 3 3 7 5 67 2 05 58 17 2
20- 2.9 3.5 1130.1 1129.03 2.75 42 1.0 0.01 0.8934 0.26 4.580 4.092224 0.893970 1.13 0.73 5
35
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
23 3 3 7 5 67 6 36 58 08 8
23- 3.6 5.7 1128.8 1128.28 2.07 48 1.2 0.01 1.1669 0.30 4.343 5.067746 0.728183 1.09 0.63 4.7
34 8 1 2 5 48 1 79 74 13 4
34- 5.7 3.2 1128.2 1127.78 1.85 48 1.2 0.01 1.1669 0.30 4.108 4.794478 0.800067 1.11 0.67 4.6
35 8 1 2 5 48 9 78 3 15 7
35- 3.2 3.3 1127.7 1127.58 1.43 48 1.2 0.01 1.1669 0.30 3.608 4.211038 0.915304 1.13 0.75 4.1
41 8 1 2 5 48 9 97 11 34
41- 4.2 3.0 1126.6 1125.98 2.26 48 1.2 0.01 1.1669 0.30 4.537 5.294274 0.728028 1.09 0.63 5.0
42 8 1 2 5 48 2 49 23 13 4
42- 6.2 3.0 1122.7 1120.98 2.14 48 1.2 0.01 1.1669 0.30 4.419 5.157448 0.752505 1.09 0.64 4.9
45 8 1 2 5 48 9 39 66 8 8
45- 3.0 7.7 1120.9 1120.28 1.63 48 1.2 0.01 1.1669 0.30 3.852 4.495241 0.899265 1.13 0.74 4.4
46 8 1 2 5 48 4 96 14 17 2
38- 2.3 3.7 1124.7 1124.29 0.92 18 0.4 0.01 0.1641 0.11 1.504 0.246905 0.708482 1.08 0.62 1.6
39 4 3 6 5 43 7 51 4 1
39- 3.7 5.5 1124.2 1123.04 5.21 18 0.4 0.01 0.1641 0.11 3.583 0.587991 0.859885 1.12 0.71 4.0
46 9 3 6 5 43 3 5 03 43 4
36
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Conclusiones y Recomendaciones
• El numero de tragantes depende del área de terreno que tributara a cada uno de
ellos, y la colocación de estos debe ser en puntos estratégicos ya que ponerlos en
lugares donde realmente no se necesitan viene en detrimento de la economía, que es
uno de los elementos más importantes a tomar en cuanta cuando se diseña un
sistema de alcantarillado.
• Para estos sistemas se puede utilizar tubería de concreto o de PVC considerando que
existe diámetros funcionales, la decisión va depender del lugar y la presión externa
a la cual están expuestos los mismos, además de un análisis de costos ya que
siempre se busca que la infraestructura sea lo más económica posible; pero en
nuestro medio lo más común es usar tuberías de concreto
37
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
• El agua se debe dirigir hacia al punto más bajo del la urbanización o lugar y de ahí
llevarla hacia un campo de infiltración, una quebrada, rio o un pozo de
almacenamiento para reutilizarla. Si la misma se va a devolver hacia una quebrada o
rio esta debe estar en las mejores condiciones para no contaminar el estado natural
de los mismos.
38
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Anexos
39
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
40
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
41
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
43
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
44
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
45
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
46
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
47
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
48
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
49
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
50
Proyecto: Alcantarillado Pluvial Ingeniería Sanitaria II
Ordenamiento de Valores
51