Académique Documents
Professionnel Documents
Culture Documents
Estimating is the most important of the practical aspects of construction management, and the subject
deserves the closest attention of one aspiring to a career in the profession. It is a comparatively simple
subject to understand; however, as it brings one up against practical work, methods and procedure,
knowledge of it cannot be acquired without close application.
. Purpose of Estimating:
To give a reasonably accurate idea of the cost
An estimate is necessary to give the owner a reasonably accurate idea of the cost to help him decide whether
the work can be undertaken as proposed or needs to be curtailed or abandoned, depending upon the
availability of funds and prospective direct and indirect benefits. For government works proper sanction has to
be obtained for allocating the required amount. Works are often let out on a lump sum basis, in which case the
Estimator must be in a position to know exactly how much expenditure he is going to incur on them
1. Estimating Materials
From the estimate of a work it is possible to determine what materials and in what quantities will be required
for the work so that the arrangements to procure them can be made.
2. Estimating Labor
The number and kind of workers of different categories who will have to be employed to complete the work in
the specified time can be found out from the estimate.
3. Estimating Plant
An estimate will help in determining amount and kind of equipment needed to complete the work.
4. Estimating Time
The estimate of a work and the past experience enable one to estimate quite closely the length of time
required to complete an item of work or the work as a whole.
Whereas the importance of knowing the probable cost needs no emphasis, estimating materials, labor, plant
and time is immensely useful in planning and execution of any work.
1. Approximate Estimates
An approximate estimate is an approximate or rough estimate prepared to obtain an approximate cost in a
short time. For certain purposes the use of such methods is justified.
2. Detailed Estimate
A detailed estimate of the cost of a project is prepared by determining the quantities and costs of everything
that a contractor is required to provide and do for the satisfactory completion of the work. It is the best and
most reliable form of estimate. A detailed estimate may be prepared in the following two ways:
(a). Unit quantity method
(b). Total quantity method.
The total quantities of each kind or class of material or labor are found and multiplied by their individual unit
cost. Similarly, the cost of plant, overhead expenses and profit are determined. The costs of all the five sub-
heads are summed up to give the estimated cost of the item of work. For example, the cost of brickwork in a
building would be determined as below:
I ( i ) Cost of Materials at the source $
Bricks $
Sand $
Cement $
Water $
(ii) Cost of Handling and transporting
$
above materials
II Cost of Labor, both skilled and unskilled $
III Cost of plant $
IV Overheads $
V Profit $
Total Cost of Brickwork $
. Qualifications of an Estimator
A good estimator should possess the following quantifications:
1. A thorough understanding of architectural drawings.
2. A sound knowledge of building materials, construction methods and customs prevailing in the trade.
3. A fund of information collected or gained through experience in construction work, relating to materials
required, hourly output of workers and plant, overhead expenses and costs of all kinds.
4. An understanding of a good method of preparing an estimate.
5. A systematic and orderly mind.
6. Ability to do careful and accurate calculations.
7.Ability to collect, classify and evaluate data that would be useful in estimating.
Good instruction or careful and thorough study of a standard book will help a beginner to become a good
estimator. He must, however, try to develop all the above mentioned qualities while obtaining practical
experience.
• Observation
• Comparison of observation with some desired standard
• Corrective action to take if necessary.
A construction cost control system should enable a manager to observe current cost levels, compare them
with a standard plan or norm, and institute corrective action to to keep cost within acceptable bounds.
Most construction cost control systems have an inordinately long response time. Even the best cost control
system would provide information on what was happening last week or last month. Since, in construction
projects some activities might finish in a week or a month, then nothing could be done if the performance of
such activities was reported to overrun estimates of respective costs.
3 of 10
One of the unique Construction Software that provides a futuristic construction cost control tool for
construction management is the CFF3 for cash flow forecasting. Version three has taken into consideration
the possible deviations from estimates of cost as well as cash in patterns and provided a means to return
back to the original estimate by damping out these deviations through the remaining period of construction.
Updated estimates are provided each time an actual figure is added such that the end cost remain same as
was originally estimated. It provides an excellent guide for managers through the construction project to
capture the best possible actions in each period activities. Labor rate and efficiency constitute the core of
Quantitative Scheduling which is highly recommended if cost minimization in respect of productivity rates is
sought.
Also Construction Cost is directly related to Material price, Material usage and waste, Fixed and varied
overhead expenditure. These are the areas where managers should seek action for future adjustments in
order to get back to original estimate or practically as near as possible.
The linked bar chart shows the links between an activity and its preceding activities which have to be
complete before this activity can start.
The bar charts are also useful for calculating the resources required for the project. To add the resources to
each activity and total them vertically is called a resource aggregation. Bar charts and resource aggregation
charts are useful for estimating the work content in terms of man-hours and machine hours.
2- Network Analysis and Critical Path Method
Practically network analysis offers little more than a linked bar chart, though its protagonists claim, with some
justification, that the self contained steps of a network are more applicable to complex operations than the bar
chart, and that the greater rigor imposed by the logic diagram produces more realistic models of the proposed
work. The steps in producing a network are:
- Listing of activities
- Producing a network showing the logical relationship between activities.
- Assessing the duration of each activity, producing a schedule, and determining the start and finish times of
each activity and the available float
- Assessing the required resources.
There are now two popular forms of network analysis in construction management practice, activity on the
arrow and activity on the node, the latter now usually called a precedence diagram. Each of these approaches
offers virtually the same facilities and it seems largely a matter of preference which is used.
3- Line of Balance
The line of Balance is a planning technique for repetitive work. The principles employed are taken from the
planning and control of manufacturing processes greatly modified by E. G. Trimple. The basis of the technique
is to find the required resources for each stage or operation so that the following stages are not interfered with
and the target output can be achieved. The line of balance technique has been applied in construction work
mainly to house building and to a lesser extent to jetty work and in conjunction with networks to road works.
4- Q Scheduling
The Q Scheduling is a new technique, though getting rapid popularity among contracting firms. It is the only
scheduling technique that reveals a relation between the sequence of doing a job and the cost to be incurred.
The Q schedule is similar to the Line of Balance with some modifications made by A. R. A. Z. A in 2004, to
allow for a varying volume of repetitive activities at different segments or locations of the construction project,
thus the model produced is closer to reality. The following example explains the technique.
4 of 10
Having a project site with three buildings A, B, C with following quantities
Average daily
Activity unit Building A Building B Building C
output
Excavation m3 20 60 20 40
Foundations m3 15 30 15 15
Backfilling m3 30 30 60 60
Note: Above quantities are chosen for illustration purpose and may not reflect a practical construction case.
There are six possible arrangements for doing the job in respect of location sequence with the constraint of
ensuring a continuous flow of work for each activity so that no idle time for employed crews might be
encountered, and no allowance for more than one activity to take place simultaneously at one location:
• A - B - C,
• A - C - B,
• B - A - C,
• B - C - A,
• C - A - B,
• C-B-A
C 2 1 2
Alternative 1 gives a total duration of 10 working B 1 1 2
days A 3 2 1
Days 1 2 3 4 5 6 7 8 9 10
B 1 1 2
C 2 1 2
Alternative 2 gives a total duration of 10 working days
A 3 2 1
Days 1 2 3 4 5 6 7 8 9 10
C 2 1 2
A 3 2 1
Alternative 3 gives a total duration of 9 working days
B 1 1 2
Days 1 2 3 4 5 6 7 8 9 10
A 3 2 1
C 2 1 2
Alternative 4 gives a total duration of 10 working days B 1 1 2
Days 1 2 3 4 5 6 7 8 9 10
B 1 1 2
A 3 2 1
C 2 1 2
Alternative 5 gives a total duration of 10 working days
Days 1 2 3 4 5 6 7 8 9 10
A 3 2 2
B 1 1 1
Alternative 6 gives a total duration of 10 working days
C 2 1 2
Days 1 2 3 4 5 6 7 8 9 10
The example shows that alternative 3 can produce a saving of 10% relative to other alternatives, either in
output rates if duration is kept same, or in total duration and subsequently in overheads and supervision
costs. Actually Q Scheduling software picks up alternative 3 as the most economic sequence and considers
other alternatives as having additional cost of 11.11% proportional to the most economic alternative.
However, with a construction project having four locations there would be twenty four possible alternatives,
and for a five location project there would be 120 alternatives. For a project with ten locations there would be
three million, six hundred twenty eight thousand, and eight hundred alternatives to consider.
Q Scheduling software is currently limited to consider up 5 locations; i.e. 120 alternatives so that it can work
on normal computers - Pentium II and above. It can be used efficiently for small to medium projects. However,
for the time being large projects can use Q Scheduling first by integrating segments together so that a
maximum total of five segments is there, then considering each segment as a separate construction project.
Thus a twenty five location project can be handled.
5 of 10
Quality Management
. Quality Control
Quality is defined as 'fitness to purpose', i.e. providing a product (a building) which provides an appropriate
quality for the purpose for which it is intended. The price to be paid for a building is a reflection of the
expectations of quality - A cheaper building probably uses inferior materials and is likely to be less attractive
and less durable. The quality is also related to the timing of when it is delivered.
Quality control in the construction industry can be looked at as having three elements:
Like most other aspects of construction management quality control has to be planned. Planning seeks 'order'
and a quality control system for a construction project reflects this sense of order. It may be seen to be in five
basic stages:
• Failure costs: The costs of demolishing and rebuilding, the cost of production time, delays to other
gangs
• Appraisal costs: The cost of inspection and testing.
• Prevention costs: The costs of providing better designs, more training to reduce failure costs, more
maintenance.
. Quality Assurance QA
Quality assurance is a mechanism for ensuring that the construction process takes place within the
framework of a quality management system. This suggests that quality assurance defines the organization
structure, tasks and duties for implementing quality management.
In 1987, the Building research establishment surveyed the quality problems on Britain's construction sites.
They found that half of the faults were design related, and 40% of the problems arose from faulty construction.
10% were product failing.
Design faults
Construction faults
Miles was assigned the task of purchasing the materials to permit this. Often he was unable to obtain
the specific material or component specified by the designer, so Miles reasoned, "if I can not obtain
the product, I must obtain an alternative which performs the same function". Where alternatives were
found they were tested and approved by the designer.
Miles observed that many of the substitutes were providing equal or better performance at a lower
cost and from this evolved the first definition of value engineering.
• . Value Engineering Definition
• It is an organized approach to providing the necessary functions at the lowest cost
From the beginning the concept of value engineering was seen to be cost validation exercise, which
did not affect the quality of the product. The straight omission of an enhancement or finish would not
be considered value engineering. This led to the second definition :
The following tasks are undertaken by Quantity Surveyors, and are involved in value engineering
practice:
7 of 10
Construction safety
Unfortunately the construction industry has become stereotyped as an accident prone industry, in fact only
mining and fishing industries have higher fatalities. Depressingly, the accident rates experienced closely
correlate to the level of activity within the industry, indicating that when work load is high, safety tends to
receive less attention.
It is argued that construction management must have a prime concern for safety and therefore should have a
moral, economic, and legal commitment to ensure workplace safety on sites. However the responsibility for
safety must commence upstream of the construction phase of a project; architects and engineers must have
the technical knowledge to design buildings which can be safely constructed, as well as a commitment to safe
working conditions for site workers.
. Construction Safety costs
To many managers who have been brought up to the importance of construction scheduling, and controlling
costs, the economic aspect of safety is the most forceful. In construction the costs associated with an accident
can be immense. For material losses in which no injury occurs the accounting of loss can be easily assessed;
but where human loss is concerned, the costing becomes more difficult since life or a physical facility cannot
crudely be financially evaluated, yet it has been widely recognized that monetary compensation to either the
injured party or relatives in the event of fatality has to be paid.
Most compensation payments are paid by the contractor's insurance company. Insurance companies will base
their premiums upon historical evidence and a poor safety record will inevitably be reflected in insurance
premiums.
Contractors should give careful thought to the role of the full time safety officer. Two basic concepts exist
about this role:
In general the role of the safety officer shall consist of the following duties:
8 of 10
• Providing information to sites on accidents that have happened elsewhere on similar sites to help
generate safety consciousness within working sites.
Construction Risks
(Quoted from a Study by the National Economic Development Office, London)
The construction risks can be broadly grouped under the following categories:
. Technical Risks
• Incomplete design.
• Inadequate site investigation.
• Uncertainty over the source and availability of materials.
• Appropriateness of specifications.
. Logistical Risks
• Availability of resources - particularly construction equipments, spare parts, fuel and labor.
• Availability of sufficient transportation facilities.
. Construction Risks
. Financial Risks
• Inflation.
• Availability and fluctuation in foreign exchange.
• Delay in Payment.
• Repatriation of funds.
• Local taxes.
. Political Risks
There is no consensus in the literature on the identification of factors which affect stipulated, planned or
achieved construction times of buildings. One reason for this is that researchers have largely viewed the
subject from diverse prospective. Such view points include identification of discrete factors which affect
productivity on site and taking a systems view of the construction process and end product.
The following factors have been traced to be the construction time influencing factors, with different weights
assigned to them by each individual planner.
. Delay Factors pertinent to Clients
• Weather
• Regulations
• Statutory undertakes ( water, gas, etc..)
10 of 10