Level Three
______________________________________________________________________________________
Course Title: IT and Project Management
COMP 1305
Page 1 of 4
APPROVED
(b) Critically evaluate the impact each of the following techniques on the
duration of a project:
2. Six Sigma is described as "a comprehensive and flexible system for achieving,
sustaining and maximizing business success."
(a) Projects that use Six Sigma normally follow a five-phase improvement
process called DMAIC. Describe each of the five phases in detail.
[10 marks]
(b) The target for Six Sigma is 3.4 defects per million opportunities.
Explain the mathematical basis of this figure.
[8 marks]
(c) What additional concepts does Six Sigma include that are not in "Total
Quality Management" or "Business Process Engineering"?
[7 marks]
(b) Conflicts between the project team staff often arise during a project.
What techniques can the project manager adopt for dealing with these
conflicts if they threaten the success of the project?
[10 marks]
______________________________________________________________________________________
Course Title: IT and Project Management
COMP 1305
Page 2 of 4
APPROVED
(a) Project managers often recommend that people take specific training
courses to improve individual and team development. Why is it
usually considered important that training is provided in a just-in-time
fashion?
[8 marks]
(b) Myers-Briggs Type Indicator (MBTI) and the Wilson Learning Styles
Profile are two methods for determining personality preferences in
teams. Critically evaluate ONE of these methods in detail as a basis
for team selection.
[7 marks]
• Brainstorming
• The Delphi technique
• SWOT analysis.
[9 marks]
• Contingency plans
• Fallback plans
• Contingency reserves
______________________________________________________________________________________
Course Title: IT and Project Management
COMP 1305
Page 3 of 4
APPROVED
(c) Describe and evaluate the range of software that can be used to assist
in project procurement management.
[8 marks]
______________________________________________________________________________________
Course Title: IT and Project Management
COMP 1305
Page 4 of 4