ETP48300 C10A1 Mini MCP 4M + ETP48300 C10A1 Mini MCP 4M +


1 4200002140 JKB561 UNIVBINUS New System Mini MCP COC392 CMBTSNIPERBNIPEJOMPONGAN New System Mini MCP CR MAPPING 08.11.2020
Belting + Bracket Bracket

ETP 48300 C10 OD 3M2B Shoto 6-FMX- ETP 48300 C10 OD 3M2B Shoto 6-FMX-
2 4000019197 SKB896 GUNUNGJAYACISAAT New System OD JSX920 CIGANJURJAGAKARSA New System CR MAPPING 27.11.2020
100 + 2 Cage 100 + 2 Cage

Upgrade Module dan R4830N3 1M1B Shoto 6-FMX-100 + 1 R4830N3 1M1B Shoto 6-FMX-100 + 1
3 4000019216 BKX240 JLPERUMGRAMATAMANSARI JSX920 CIGANJURJAGAKARSA Upgrade Module dan battery CR MAPPING 27.11.2020