Académique Documents
Professionnel Documents
Culture Documents
Installation Verification
Table of Contents
Topic Page
CHAPTER 1: RBS 2106/2206 OVERVIEW...........................................1
EXERCISE 1...................................................................................................................1
a) True
b) False
2. In the following figure, draw the paths of the cooling air from
each of the three fans in the combined climate unit of the RBS
2106.
3. The following figure shows the power system for which RBS?
Answer: _________________________________________
Answer: _________________________________________
a) G9deht_3.6(5)\a
b) F9de_2.4 (E-GSM) and F18d_2.4 (GSM 1800)
c) F9de_2.8 (E-GSM) and F18d_2.8 (GSM 1800)
d) F9det_2.6 (E-GSM) and F18dt_2.6 (GSM 1800)
CHAPTER 3: SAFETY PRECAUTIONS AND TEST TOOLS
EXERCISE 3
1. The following figure is the symbol for what (circle the correct
answer)?
Preparation
In the following exercise, you will be verifying the previously
installed RBS antenna system for a given site. The exercise will
cover Distance To Fault (DTF) and Standing Wave Radio (SWR)
tests and related procedures.
Procedure
1. Locate the correct procedures for verifying the antenna system
in the manual(s).
2. Review the Work Order (following page) and test preconditions.
3. Follow the Work Process precisely, and conduct both DTF and
SWR tests.
4. After completing the antenna system tests, complete the Test
Record and Checklist. Make sure the instructor sees your results.
5. Be prepared to discuss your results at the end of this exercise.
Work Order General Information
Work area: DALLAS 01
Cause of this Work Order: Newly-installed RBS antenna system
needs to be tested for proper
installation.
Identification
Work Order Id: DLS 78241
Work Order Issued by: OMC Department
Change status (Time):
Site id: D01
Site name: DALLAS 400
Work order priority: P1
Alarm time:
Alarm slogan:
Fault code subsystem:
Work Order History
Work Order escalated from: N/A
Comments: Perform DTF, SWR and other
applicable tests as necessary.
Task Description
Trouble ticket: -90324
Task title: ANTENNA SYSTEM TESTS
Time
First start (Time):
Last start (Time):
Finished at the latest (Time):
Reporting Results
How to report results: Immediately complete Test Record
and Checklist, and submit to OMC.
References
System documentation:
Alarm Printout:
Check the following: OK
1. Are all outdoor antenna system connectors covered with sealing tape?
2. Is the Test Record completed?
3. Is the Site Installation Documentation complete with the Test Record and Test
Record supplements (if necessary)?
Exercise 5.1 will be for the RBS 2106; Exercise 5.2 will be for the
RBS 2206. The instructor will assign you/your team to the RBS
model you will be verifying. If there is time allowed, you will be
conducting installation verifications on both models.
Preparation
The following resources/tools will be needed to complete this
exercise:
• Multimeter
• ESD wrist strap
• Operation and Maintenance Terminal (OMT)
• System Verification Set (OMT software, interface cable, and
manual)
• Diskette (for IDB back-up)
• Work Order (located on the following page)
• Completed “Test Record for Antenna System Tests”
(Exercise 4)
• Test Record for Stand Alone Tests (located on the second to
the last page of Exercise 5.1)
• Checklist (located on the last page of Exercise 5.1)
• RBS 2106 Installation and Integration Manual, which includes:
– Preconditions
– Work Process (flowchart)
– Installation verification procedures
Procedure
1. Locate the correct procedures for verifying the RBS 2106 site
installation in the Installation and Integration manual.
2. Review the Work Order (following page) and verify preconditions.
3. Follow the Work Process precisely, and conduct all procedures and
installation verifications.
4. After completing the antenna system tests, complete the Test
Record and Checklist. Make sure the instructor sees your results.
5. Be prepared to discuss your results at the end of this exercise.
Test Record
Checklist Check the following:
2. Is the Local indicator on the DXU off (or flashing if no PCM link is connected)?
3. Are all other indicators on the DXU off?
4. Are the Local indicators on all dTRUs off (or flashing if no PCM link is
connected)?
9. Has all installation verification equipment been disconnected from the RBS?
11. Are the inside and the outside of the cabinet free of damage?
Preparation
In the following exercise, you will be integrating the RBS with the
BSC and then testing to verify the integration. The exercise will
cover bringing the RBS into service and making test calls on the
air interface. The instructor will assign you/your team to the RBS
model you will be integrating/testing.
• TEMS
• Laptop/PC with TEMS software
• Work Order (located after the Procedure section)
• Completed “Test Record for Antenna System Tests”
(Exercise 4)
• Completed “Test Record for Site Installation Tests” (Exercise
5.1 or 5.2)
• Test Record for RBS Site Integration (located after the Work
Order)
• Checklist (located on the second to the last page of this exercise)
• Network Element Acceptance Certificate (located on the last
page of this exercise)
• RBS 2106 and 2206 Installation and Integration Manuals,
which include:
– Preconditions at the RBS and the BSC
– Work Process (flowchart)
– Installation verification procedures
Procedure
1. Locate the correct procedures for verifying the RBS site integration
in the Installation and Integration manual for your assigned RBS.
2. Review the Work Order (following page) and installation
verification preconditions.
3. Follow the Work Process precisely, and conduct all site integration
tests.
4. After completing the site integration tests, complete the Test
Record, Checklist, and the Network Element Acceptance
Certificate. Make sure the instructor sees your results.
5. Be prepared to discuss your results at the end of this exercise.
Work Order General Information
Work area: DALLAS 01
Cause of this Work Order: Newly-installed and verifyed RBS
needs to be integrated with the BSC
and test calls made.
Identification
Work Order Id: DLS 78243
Work Order Issued by: OMC Department
Change status (Time):
Site id: D01
Site name: DALLAS 400
Work order priority: P1
Alarm time:
Alarm slogan:
Fault code subsystem:
Work Order History
Work Order escalated from: N/A
Comments: Perform all necessary tests to verify
RBS is integrated correctly.
Task Description
Trouble ticket: -90327
Task title: SITE INTEGRATION
Time
First start (Time):
Last start (Time):
Finished at the latest (Time):
Reporting Results
How to report results: Immediately complete Test Record,
Checklist, and Network Element
Acceptance Certificate, and submit to
OMC.
References
System documentation:
Alarm Printout:
Test Record
Checklist Check the following:
3. Has all installation verification equipment been disconnected from the RBS?
5. Are the inside and the outside of the cabinet free of damage?
Answer: ______________________________________
______________________________________
Answer: ______________________________________
___________________________________
___
EXERCISE 7.2
In the following exercise, perform the corrective
action on the assigned RBS: