Experimental Programme
Schedule B – Compensation
FOR
Page 1 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
TABLE OF CONTENT
1. INTRODUCTION
1.1 ABBREVIATIONS
2. INDIRECT COSTS
2.1. INDIRECT COSTS - INTRODUCTION
2.2 INDIRECT COSTS - GENERAL PRICING PREAMBLES
2.3 INDIRECT COSTS - DEFINITIONS
2.4 CONTENT OF LUMP SUMS FOR INDIRECT COSTS
2.5 INDIRECT COSTS - ADJUSTMENT MECHANISM
3. DIRECT PRICES
3.1 INTRODUCTION
3.2 CONTENT OF RATES FOR DIRECT WORK
3.3 RATES TO INCLUDE
6. STRUCTURAL STEELWORKS
6.1 REFERENCE SPECIFICATIONS & DRAWINGS
6.2 STRUCTURAL STEELWORK
6.3 ERECTION OF PIPE SUPPORTS
8. MECHANICAL EQUIPMENT
8.1 REFERENCE SPECIFICATIONS
8.2 SPECIFIC CHARGES FOR THE INSTALLATION OF EQUIPMENT
8.3 VERTICAL EQUIPMENT
8.4 HORIZONTAL EQUIPMENT
8.5 EQUIPMENT REQUIRING ASSEMBLY
8.6 INTERNAL FITTINGS
8.7 PUMPS AND COMPRESSORS
8.8 PACKAGES
Page 2 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
10. PAINTING
10.1 PAINTING – SPECIFIC CHARGES
10.2 PAINTING – PAINTING WORK CLASSES
10.3 INCLUSIONS & EXCLUSIONS
10.4 METHOD OF MEASUREMENT
11. INSULATION
11.1 INSULATION - CHARGES EXCLUDED/INCLUDED
11.2 INSULATION - METHOD OF MEASURMENT
11.3 INSULATION - CLASSES
11.4 INSULATION WORK - SPECIFIC CHARGES
12. FIREPROOFING
12.1 FIREPROOFING - SPECIFIC CHARGES
12.2 FIREPROOFING - METHOD OF MEASUREMENT
PRICE TABLES
Page 3 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
1. INTRODUCTION
This schedule B contains the Price List Guides and Price Lists applicable to the CONTRACT.
The lump sums, unit rates, day-works and percentages contained in the Schedule B are to be
fully inclusive and represent the total reimbursement the CONTRACTOR will receive for
complying with and fulfilling the obligations contained in the Contract and for the satisfactory
execution of the WORK.
The CONTRACT currency will be US Dollars.
The lump sums, unit rates, day-works and percentage shall be fixed and not subject to
adjustment for duration of the CONTRACT.
Scope of WORK of CONTRACTOR includes the following Areas of the OFFSHORE FACILITY:
Page 4 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Volume
D3 = Cubic decimeter
M3 = Cubic meter
Weight
KG = kilogram
TN = tons
Abbreviations are valid irrespective of whether upper case or lower case letters are used.
NOTE
1. By extension, SIMOPS means also all situations when two or more contractors are
working in the same location and at the same time.
Page 5 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
2. INDIRECT COSTS
For the pricing of CONTRACTOR’s Indirect Costs the CONTRACTOR is referred to the
following documents enclosed herewith:
Page 6 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 7 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
2.3.3 Demobilization
Demobilization is defined as those activities required to demobilize CONTRACTOR’s labor,
materials, equipment, temporary production base and camp facility from SITE, (including those
activities required to similarly fully demobilize the CONTRACTOR’s SUB-CONTRACTORS)
and restore the CONTRACTOR’s area to a condition previously agreed in writing with the
COMPANY.
2.3.4 Prices for demobilization
Prices for Demobilization shall include:
o Costs associated with a complete clean up of the SITE.
o Costs associated with the return of any surplus COMPANY supplied material to
COMPANY’s warehouse.
o Costs associated with the demobilization of CONTRACTOR’s direct and indirect
labor and staff.
o Costs associated with the removal from SITE of CONTRACTOR’s materials,
construction equipment and temporary construction and facilities
o Costs associated with a complete clean up of CONTRACTOR’s area and reinstating
the said area to a condition previously agreed in writing with COMPANY.
2.3.5 Payment for demobilization
The lump sum price for demobilization shall be paid in a single payment to CONTRACTOR
when activities required for demobilization all WORK shall be complete and the
CONTRACTOR shall have received the COMPANY’s approved and signed last MECHANICAL
ACCEPTANCE CERTIFICATE issued by the COMPANY as defined in the CONTRACT.
In the event of the CONTRACTOR implementing guarantee work, no mobilization and
demobilization lump sum shall apply. CONTRACTOR shall not assume that SITE facilities will
be available to the CONTRACTOR for its temporary construction facilities, camp
accommodation facilities and the like in implementing such work.
2.4 CONTENT OF LUMP SUMS FOR INDIRECT COSTS
The following activities and services shall be included inside the lump sums for Indirect Costs.
The following list shall not be considered conclusive:
Page 8 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Cost for providing facilities for use by COMPANY and COMPANY appointed third parties
during its inspection of the execution of work at any CONTRACTOR offsite facilities.
• Cost of providing progress and planning reports and other such reports and other such
reports and certificates required by the CONTRACT, and attendance by appropriate
CONTRACTOR’s personnel at meetings required by the CONTRACT or as directed by
COMPANY.
• Cost of interfacing with and working in close proximity with Other Contractors of
COMPANY and re-sequencing CONTRACTOR’s activities, as required, to avoid
disrupting COMPANY’s Other Contractors who may be working on the SITE concurrent
with the CONTRACTOR.
• Cost of interfacing with the Regulatory Authorities and for complying with the
requirements of the Regulatory Authorities including training and examinations of
CONTRACTOR’s personnel to meet Regulatory Authority requirements for supervision of
work (including RoK “Blue Book”)
• Cost of preparation of Welding Procedure Specifications and obtaining COMPANY
approval
• Cost of promptly making good damages to existing structures, roads, fences and any
other work constructed, fully or partially, by Other Contractors, which are to be retained,
caused by or attributable to the actions or the omissions of the CONTRACTOR
• Cost for the impact on the program and cost of time lost and/or inefficiency due to
inclement weather and for all other periods of non productive time of labor and
construction plant for which the COMPANY is not responsible including mechanical
breakdown of plant and equipment; industrial disputes; and attendance of
CONTRACTOR’s personnel at tool box meetings and induction and training courses,
COMPANY instituted safety meetings, idle time and travel time.
• Cost of preparing any necessary field sketches, fabrication drawings, engineering
calculations, crane lift studies and details of work and “red line” mark ups for as built
documentation.
• Cost of compilation of mechanical completion dossiers for staged completion of the
WORK as defined by COMPANY.
• Cost of any insurances required to be provided by the CONTRACTOR, whether under
this CONTRACT and/or by government or local laws, regulations or decree.
• Costs for preparing and working to CONTRACTOR’s safety plan.
• Costs for constructability, accessibility and other studies required to optimize the WORK
and improve the PROJECT SCHEDULE.
Operational activities connected with the above listed activities and services shall be included in the
Unit Rates for the Direct WORK.
Page 9 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 10 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
3. DIRECT PRICES
3.1 INTRODUCTION
For the pricing of Direct Prices (whether on unit rates, day-works or lump sum) CONTRACTOR
is referred to the following documents enclosed herewith:
• The descriptions attached to the respective items within the Price List Guides (Sect. 4
through 12 here below) are intended to be sufficient only for identification of an item of
work. The descriptions do not provide exhaustive detailing of each and every operation
required to carry out the WORK. For the full obligations of each item the CONTRACTOR is
Page 11 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
referred to the documents forming the CONTRACT. The unit rate entered by the
CONTRACTOR against each respective item in the Price List shall be deemed to be a fully
inclusive rate for the finished work described in the respective item including matters set
out in these pricing preambles and including everything which is contingent to and
indispensable in the construction and completion of the WORK to be carried out under the
CONTRACT, and shall be deemed to include for CONTRACTOR’s acceptance of that part
of WORK previously performed by COMPANY’s other contractors. Unless COPMANY is
notified in writing to the contrary within ten (10) days, CONTRACTOR is deemed to have
warranted aforesaid WORK as if performed directly by CONTRACTOR.
• Notwithstanding the omission from an item description in the Price List Guides (Sect. 4
through 12 here below) of an individual operation or operation considered necessary for
the execution and completion of item, the cost of such operation shall be deemed to be
included in the applicable item in the Price List, and the CONTRACTOR shall be deemed
to have made allowance for the cost of such operations in each applicable item. No claim
will be accepted on the grounds of defective description or omissions that further
operations other than those described are required.
• Where the specific charges/method of measurement state that the unit rate for an item
shall include for work which will not be separately measured or paid for, then the extent of
the included work within the unit rate shall be assessed by the CONTRACTOR and no
claim for additional cost will be entertained by the COMPANY should be extent of the
included work actually executed, vary from that assessed by the CONTRACTOR.
• CONTRACTOR shall be deemed to have allowed for checking of drawing dimensions and
any and all applicable dimensions prior to commencing work. CONTRACTOR shall further
be responsible for checking documentation issued to him by COMPANY and shall draw
the attention of the COMPANY to any discrepancies or omissions therein within ten (10)
working days of COMPANY’s issue to the CONTRACTOR of documentation or revisions to
and/or supplements to documentation. COMPANY will not be liable in respect of costs or
schedule impact incurred by the CONTRACTOR due to errors, conflicts omissions in
drawings, other documents or dimensions the effects of which were avoidable had the
CONTRACTOR checked such documents and dimensions beforehand and notified the
COMPANY within the timeframe stipulated above.
• Where proprietary names or products are quoted in an item in the Price List Guides (Sect.
4 through 12 here below) such proprietary names or products shall be taken as indicating
a required class of quality of finished work. The proprietary name or product may only be
changed by the CONTRACTOR with prior approval in writing of the COMPANY.
• Except as provided in Section 15 “Payment Rules”, the rates shall apply equally to
executing work in large or small quantities, in difficult or easy situations, in any sequence
and at grade or any elevation above the ground unless stated to the contrary in the
CONTRACT and no claim will be allowed which arises form the proportion of the finished
work actually falling into these categories. In the course of the development of the
construction drawings, the proportion and complexity of the various operations included
within the items described in the Price List Guides (Sect. 4 through 12 here below) may
vary from the proportions or complexity which may have been inferred from the
CONTRACT drawings or from the CONTRACTOR’s assessment of the proportions and
complexity. The unit rates are deemed to include provisions for all risk and all advantages
that may arise from any such changes in proportions and complexity and thus unit rates
shall apply equally to the tender quantities and the finished quantities of work.
Page 12 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• The rates apply equally to executing the WORK at any time prior to completion irrespective
of whether the various work items have programmed continuity or not, or performed in a
different season, or in a different proportions in different seasons and/or weather
conditions, or performed in different sequences, from that initially envisaged in the
CONTRACT. No claims will be accepted by the COMPANY for remobilization of labor or
equipment, additional access and the like, as full entitlement under the CONTRACT shall
be deemed to have been made by application of the relevant unit rates. No claims will be
accepted by the COMPANY for schedule extension, as CONTRACTOR shall be deemed
to have included in CONTRACTOR’S schedule full allowance for any and all such
eventualities.
• The rates and prices shall include for liaison with COMPANY and the COMPANY’s Other
Contractors and the Regulatory Authorities, and obtaining COMPANY and Regulatory
Authorities approval at all stages according to the requirements of the CONTRACT.
When the CONTRACTOR is required by the CONTRACT to seek approval, the
CONTRACTOR shall do so in writing at least seven (7) working days before such approval
is required.
• The CONTRACTOR shall be deemed to have satisfied himself as to the correct meaning
of every item description in the Price List Guides and of the completeness of his unit rate
or price for the work described therein. No claim for additional payment, as a consequence
of any error or misunderstanding on the part the CONTRACTOR to fully determine the
scope of work and his CONTRACT obligations with regard to a Price List Guide item
description, will be considered by the COMPANY
• The quantities indicated in the Price List are approximate only and are not to be taken as
final quantities of work to be executed for any Price List item. The range of work may vary
to the extent that new items and/or sections may be added to the Price List and existing
items or sections may not be used. Any variations, omissions or additions shall be dealt
with in accordance with CONTRACT. Save as provided in Section 5, remuneration for the
Unit Rates for Direct WORK shall remain valid regardless of any variation between the
estimated and actual quantities of work executed against the unit rates, and no variation of
the items or quantities give in the Price List shall in any way affect the validity of the
relevant price in the Price List.
• The quantities contained within the Price List shall not be used for the purpose of ordering
any materials that CONTRACTOR is required to provide under the CONTRACT except as
provided herein. CONTRACTOR shall order CONTRACTOR supplied material on the
basis of the identification of materials for Hook Up as provided inside the “Approved For
Page 13 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• The quantities of work actually executed in accordance with the CONTRACT shall be
measured or calculated in accordance with the method of measurement defined in the
Pricing List Guides (Sect. 4 through 12 here below). COMPANY computer programs for
the re-measurement of work shall be used where possible. Quantities not detailed on
drawings or derived from computer programs shall be determined by joint measurement by
the CONTRACTOR and the COMPANY. No allowance shall be made for waste in the re-
measurement of the quantities. The CONTRACTOR shall be deemed to have included in
the Price List for Indirect Costs for the provision of personnel and other recourses
necessary for the re-measurement of the WORK and CONTRACTOR’s commercial
administration of the CONTRACT.
• Except as provided in Section 15 “Payment Rules”, the amounts of money to be paid to the
CONTRACTOR for unit rate measured work in accordance with the CONTRACT, shall be
the product of the total quantities of work correctly executed by the CONTRACTOR, in
accordance with the CONTRACT drawings and specifications and measured in
accordance with the applicable method of measurement, and the pertinent total unit rates
defined in the Price Lists.
Works rejected by COMPANY for reasons ascribable to CONTRACTOR shall not be
computed and taken into account (not even provisionally), regardless of the progress
reached at the time of COMPANY’s rejection.
In the event that works already progressed and taken into account, at any stage of
progress, are subsequently rejected by COMPANY for reasons ascribable to
CONTRACTOR, all the related quantities and compensation already taken into account
shall be nullified and the Payment Certificate shall be amended to reflect such
adjustments.
Compliance with CONTRACT drawings and technical specifications and quantity
assurance requirements.
The prices in the Price List are deemed to Include for the execution of the WORK and the
supply of materials (where specified as CONTRACTOR supplied in the CONTRACT), strictly in
accordance with the CONTRACT drawings and specifications.
3.3 RATES TO INCLUDE
The unit rates included in the Price List for Direct Costs and referred to in this document shall
include, along with the other CONTRACT provisions, for costs in connection with the complete
performance of the WORK described in the respective Price List Guides descriptions including,
but not limited to, the following:
• Cost of skilled, semi-skilled and unskilled labor for trades up to and including the level of
working foreman.
• Salaries, wages, bonuses, allowances, fringe benefits, incentive payments, overtime and
shift payments, offshore rotations for travelling personnel, local travelling time and fares
(in particular: to and from the Crew Change Facility), public holiday entitlement, paid
holiday, sick pay, insurances, pensions, recruitment, passports, visas, residence and
work permits, training and other emoluments, contributions, taxes, levies or expenses
that CONTRACTOR may make in respect of labor in accordance with national or local
agreements or with statutory provisions.
Page 14 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Cost of providing construction equipment and plant (delivery point: the ONSHORE
SUPPORT BASE in Kuryk) of adequate type, quality and quantity for the execution of the
WORK (including ensuring certification remains valid) including maintaining and repairing
the plant and equipment, road tax, insurance and providing sufficient spare parts, fuel,
fuel oil, lubricants, other consumables and any tackle normally associated with the
equipment and sufficient contingency for the equipment to ensure work continuity.
• Cost of providing and replacing “small tools” and Personal Protection Equipment (PPE)
required for trades.
• Cost of providing cranes, crane mats lifting equipment, lifting/spreader beams, slings and
shackles and other ancillaries and sufficient contingency for the equipment to ensure
work continuity. Delivery point: the ONSHORE SUPPORT BASE in Kuryk.
• Cost of transporting labor, plant and materials to and from the ONSHORE SUPPORT
BASE in Kuryk, and then around the OFFSHORE SITE including travel allowances and
expenses and the traveling time of personnel to and from their temporary
accommodation and the SITE including complying with the COMPANY’s SITE security
regulations and SITE transportation regulations. Only cost of transporting labor, plant and
materials from the ONSHORE SUPPORT BASE to the OFFSHORE SITE and vice-versa
shall not be included in the unit rates quoted by CONTRACTOR.
• Costs of utilities (power distribution, water) for SITE construction and fabrication activities
including connections thereto.
Page 15 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Cost of working in accordance with any applicable COMPANY Work Permit Procedure
and any and all limitations imposed by SIMOPS.
• Cost of quality assurance and quality control and the provision of as-built drawings,
certificates, reports, chemical analysis, test certificates and the like, and other
documentation as required by the CONTRACT or the statutory authorities.
• Cost of implementing “material identification and traceability” for materials supplied
and/or incorporated by the CONTRACTOR during all phases of the WORK, as may be
required by the CONTRACT.
• Cost of implementing technology / knowledge transfer and Local Content commitments in
accordance with the CONTRACT requirements.
• Cost of testing of materials, welding procedure qualifications, welder qualifications and
work in accordance with the CONTRACT including the provision of necessary testing
equipment and facilities, and the submission to the COMPANY and the Regulatory
Authorities (as applicable) of the appropriate test or calibration certificates. Provision of
samples where required by the CONTRACT.
• Cost of performing Non Destructive Examination (NDE)
• Cost of collecting up scrap, recoverable and surplus material and delivering same to the
CONTRACTOR’s and/or the COMPANY’s designated storage points
• Cost of making good or reworking any item not executed in accordance with the
CONTRACT.
• Cost for protecting, preserving and maintaining the WORK at all stages as required or as
inferred by the CONTRACTOR including the provision of sufficient watching, flood
lighting, general lighting, fire fighting capabilities, general security and weather protection
to avoid damage to the WORK and delay in the execution of the WORK. This cost
includes preservation of COMPANY supplied equipment and material in accordance with
manufacturers’ recommendations and/or as specified in the CONTRACT. Preservation of
COMPANY Provided Items after their installation shall be performed by COMPANY.
• Cost of increasing the number and/or capacity of CONTRACTOR’s labor and
construction plant as applicable, and/or execution of weekday, weekend or holiday
overtime and shift working where necessary to complete the construction work in
accordance with the current program in the PROJECT SCHEDULE (or as revised from
time to time with COMPANY’s agreement) except where liability for the delay in the
PROJECT SCHEDULE does not lie with CONTRACTOR under the provisions of this
CONTRACT.
• Cost of keeping the SITE clear of rubbish, cleaning up upon completion of the WORK
and at all times removing rubbish and waste material to RoK approved disposal areas
Page 16 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Costs for providing free access to the WORK for COMPANY personnel.
Page 17 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
4. CIVIL WORKS
Specification reference:
KE01.A0.000.KD.C.SP.0001.000 Specification for Site Preparation, Construction of
Roads and Earthworks.
4.1 BACKFILLING
4.1.1 Backfilling - Specific Charges
The unit rates for backfilling are inclusive of the work necessary to go from an excavated or
existing site condition to backfilled condition.
Charges excluded:
• None
Charges included:
• The volume of fills, by type of material , shall be measured according to the cross-
section method, or another method previously approved by the COMPANY. The volumes
shall be calculated on the basis of the elevations specified on the topographic survey or
site survey of areas prepared by other contractors and of the design elevations found on
the AFC drawings.
4.2 AREA FINISH
Specification reference:
KE01.A0.000.KD.C.SP.0001.000 Specification for Site Preparation, Construction of
Roads and Earthworks
KE01.B0.000.KD.C.SP.0002.000 Specification for Concrete Materials and Construction of
Concrete Structures, Foundations and Paving
4.2.1 Area Finish - Specific Charges
Page 18 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
CE 301 – 304 The unit rates for area finish are inclusive of the work necessary to go from a
construction site to an area in final finish.
Charges excluded:
• None
Charges included:
• Charges for excavation or backfill to bring the area to final grade
• Charges for finish grading of the site including the shaping of the ditch along side
the roads
• Charges for shaping of the surfaces, sides and/or slopes.
• Charges for grassing includes maintenance up to sprouting
4.2.2 Area Finish - Method of Measurement
a. Finish Grading (C E 301)
• Area shall be calculated from the dimensions shown on the AFC drawings
b. Pedestrian Stone Walkways (C E 302)
• Area shall be calculated from the dimensions shown on the AFC drawings
4.3 TRENCHING
Specification Reference:
KE01.B0.000.KD.C.SP.0003.000 Specification for Drainage Materials and Construction
KE01.00.000.KD.E.SF.0020.000 Project Specification for Electrical Installation and
Testing
KE01.B0.000.KD.I.SF. 0001.000 Instrument Installation and Testing Procedural
Specification – Offshore Facilities
Drawing Reference:
KE01.B0.675.KD.C.DD. 0011.001/5 Miscellaneous Details
KE01.00.000.KD.E.DS. 0014.001 Configuration of Directly Buried Cables
KE01.00.000.KD.E.DS. 0015.001 Cable Route Marker Post & Sign Plate Details
KE01.00.000.KD.E.DS. 0016.001 Typical Cable Duct Bank Under Roads
KE01.A0.000.KD.I.DS. 0004.000 Cable Trench in Non-paved Areas (042/175)
KE01.A0.000.KD.I.DS. 0004.000 Cable Trench in Paved Areas (043/175)
KE01.A0.000.KD.I.DS. 0004.000 Cable Route Marker Posts (044/175)
4.3.1 Trenching - Specific Charges
C E 501 – 505 The unit rates for trenching are inclusive of the work necessary to go
from existing site conditions to an installed underground cables and
under roadway duct-ways.
Charges excluded:
• Trenching for underground piping
• Installation f the cables in the trenches or piping in the ducts
• Sybase, wedge chipping and wear course for roads and paving
Page 19 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Charges included:
• Charges for preparation of site, e.g. excavation
• Charges for finishing the site, e.g. backfilling (including sand and other fills)
• Charges for of protective tiles, warning tape and cable route marker posts and
signs
Page 20 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• The gate opening will be measured from the centerline of the posts on either side
of the gate
b) Gates
• Gates shall be evaluated at a lump sum price for each type
Page 21 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
5. SCAFFOLDING
5.1 GENERAL
Scaffolding shall be erected in accordance to the reference procedure:
GE00-DHS-H20-SP-0001-000 Scaffolding Specification
The Unit Rates for scaffolding works shall allow for the provision of access to the WORKS
including erecting, maintaining, and dismantling of scaffolding.
Charges excluded:
• Supply of materials
5.2 SPECIFIC CHARGES FOR SCAFFOLDING
The Unit rates for provision of Scaffolding shall include, but shall not be limited to the following:
o Cost of complying with pricing preambles included in the CONTRACT
o All costs associated with the design of Scaffolding in accordance with HSE procedures
and the CONTRACT requirements and/or applicable law
o Any required site measurement
o Transport, erection, maintenance, and removal
o Toe boards, guard rails and decking
o All necessary ladders, ledgers, transoms, bracing, ties, anchorages, clips, base plates
or boards
o The preparation of a safety procedure for the installation, use, dismantling of
scaffolding
o Provision and maintenance of a scaffolding tag system
o Rubber lined wheels with locking facilities for mobile scaffold
o Any required protection against contact with electrical supply
o Any other protection required by HSE plan and procedures and the CONTRACT
requirements and / or applicable law.
Scaffolding will paid in accordance with the rates and prices entered in the Contract on the
following basis:
70% on completion of erection (scaffold ready for use)
30% on completion of dismantling
5.3 METHOD OF MEASUREMENT FOR SCAFFOLDING
o Scaffold
Scaffolds are classified and grouped into heights of every 6 m above commencement
level. The working area of platforms are measured in square meters at each level within
the particular group of a given height range.
Platforms at levels of 6m, 12 m, 18 m, are considering as pertaining to the nearest group
downwards.
Page 22 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
The area of the working platform (plan of scaffold) is determined by the design norms in
relation to the safety and stability of the scaffold.
o Mobile Scaffold
Mobile scaffolds shall be numbered as per the Price List description.
The area of the working platform (plan of scaffold) is determined by the design norms in
relation to the safety and stability of the scaffold.
o Platform Scaffold
Platform scaffold shall be measured in square meters on plan at any elevations.
o Barrier
Barriers shall be measured in linear meters stating the height of the barrier and number of
rails.
o Protective Panels / Sheeting
Protective panels / sheeting shall be measured in cubic meters stating the type of
materials to be used, the lighting system, ventilation and heating system, PA/GA system
included inside the enclosed environment defined by the scaffold.
Lap and joints shall be deemed to be included
o Scaffold to convex / concave surfaces
CONTRACTOR shall prepare a proposal for a lump sum price for such type of scaffold on
the basis of available rates for other types of scaffolds. Price shall be agreed before
commencement of erection.
o Scaffolding for load bearing purposes
CONTRACTOR shall prepare a proposal for a lump sum price for such type of scaffold on
the basis of available rates for other types of scaffolds. Price shall be agreed before
commencement of erection.
Page 23 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
6. STRUCTURAL STEELWORKS
6.1 Reference Specifications & Drawings
KE01.A0.000.KD.C.SP.0008.000 Specification for Erecting of Structural Steelwork
KE01-A0-650-KD-C-DD-0007-003 Typical Ladder Details
KE01-A0-650-KD-C-DD-0007-004 Typical Stair Details
KE01-A0-650-KD-C-DD-0007-005 Typical Handrail and Gate Details
KE01-A0-650-KD-C-DD-0007-006 Typical Circular Platform Details
6.2 STRUCTURAL STEELWORK
6.2.1 Structural Steelworks - Specific Charges
Charges excluded:
• Supply of materials
• Prefabrication of structural steel
• Pipe-rack and building structural steel includes those items identified on structural drawings
and identified as light, medium and heavy steel
• Miscellaneous structural as access related items that are prefabricated by other contractors
• Charges for the assembly and erection of prefabricated steelworks
• Charges for leveling material and temporary restraints
• Charges for the supply and installation of installation accessories (e.g. slings)
• Charges for installation of fastening devices/erection aids (e.g. pad-eyes for ladders)
• Charges for fastening of the works to masonry, concrete or steel structure by welding,
bolting, etc.
• Charges for cutting, drilling, welding and bolting to achieve fitment
• Charges for any cutting, trimming or adding penetrations in the grating
• Charges for assembly and installation of prefabricated miscellaneous steelwork e.g.
handrails, stairs and ladders.
6.2.2 Structural Steelworks - Method of Measurement
• The weight of a piece is calculated based on the nit weight of the primary member
times its end-to-end length
Page 24 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• The weight shall not include the weight of stiffeners and other appurtenance (e.g.
padeyes, brackets)
• The weight shall not include a reduction for any penetrations
• The area of grating shall be calculated based on the outside dimensions
• The area of granting shall not include a reduction for any penetrations
• The length of stairways, landings, walkways, handrails shall be based on the end-
to-end center line dimension
• The length of ladders shall be based on the end-to-end center line dimension
6.3 ERECTION OF PIPE SUPPORTS
6.3.1 Erection of Pipe Supports – Specific Charges
Charges excluded:
• Supply of materials
• Prefabrication of support
Charges included:
• unit rates shall be inclusive of work required to erect pipe supports
Page 25 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Chemical cleaning
Charges Included
• Temporary storage of fabricated pipe-work in an approved lay down area and the
provision of end caps and pallets, in accordance with the specification
• Spool tagging, identification and protection
Page 26 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Threaded pipe-work
Charges included:
• fittings and flanges, including handling in any location is to be included in the linear rate for
pipe-work (fittings and flanges are not measured separately)
• valves, strainers, filters, in-line equipment etc. including handling, placing and aligning etc.
• any screwed or bolted joints up to and including 1½" diameter made to a boss or similar
connecting item to process pipe-work, either during or post mechanical construction, for instrument
insert items.
7.4.2 Handle and Erect Small-bore Pipe-work - Method of Measurement
• Linear meters of small bore piping will be measured from end to end including flanges
and fittings as per ISO
7.5 HANDLE & ERECT FABRICATED SPOOLS BETWEEN / OUTSIDES PIPE-RACKS
7.5.1 Handle & Erect Fabricated Spools Between/Outsides Pipe-racks - Specific Charges
Charges exclude (items included elsewhere):
• installation of control/motorized valves
• installation of safety valves
Page 27 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• threaded piping
Charges include:
• work required to complete the installation of pipe, fabricated spools and in-
line items
• Piping unit rate will be measured for each diameter group through the
center line of the pipe including fittings, flanges and in-line items as per ISO.
7.6 WELDING OF CARBON STEEL PIPING
7.6.1 Welding of Carbon Steel Piping – Specific Charges
Charges excluded (items included elsewhere):
• None
Charges included:
• Unit Rates are inclusive of work required to make welded joints
• Weld ‘O-lets including cutting and preparation of the main pipe, alignment
and making of the joint between the O-let and main
• non destructive testing
• stress relieving
7.6.2 Welding of Carbon Steel Piping – Method of Measurement
• Small bore socket and butt weld joints are numbered with reference to the
pipe diameter
• Large bore butt weld joints are enumerated with reference to the pipe
material, diameter and wall thickness
• where a butt weld joint is executed to small bore pipe-work, charges shall
be equivalent socket weld rate plus 20%
• The welding of a slip on flange for each diameter of pipe shall be paid at
the unit rate of a butt weld for pipe of STD wall thickness
• The welding of O-lets/half couplings are enumerated stating the material
and branch diameter
Page 28 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• cleaning and preparation of pipe, cutting to length, tapering, beveling, setting up,
aligning, orientating, jigging, making joint, tack welding, temporary jointing, final
welding of any wall thickness or rating
• weld O-lets including cutting and preparation of the main pipe, alignment and making
of the joint between the O-let and main
• non destructive testing
• stress relieving
7.7.2 Welding of Alloy Steel Piping – Method of Measurement
• Small bore socket and butt weld joints are enumerated with reference to the pipe
diameter
• Large bore butt weld joints are enumerated with reference to the pipe material, diameter
and wall thickness
• In circumstances where a butt weld joint is executed to small bore pipe-work the charges
shall be the equivalent socket weld rate plus 20%
• The welding of a slip on flange for each diameter of pipe shall be paid at the unit rate of
a butt weld for pipe of STD wall thickness
• The welding of O-lets/half couplings are enumerated stating the material and branch
diameter
• In circumstances where a reinforcing/ compensating plate is required the Charges shall
be paid at an addition of 20% to the rate for a welded branch joint of the same pipe
diameter and wall thickness
• In circumstances where an angled welded branch joint is executed the Charges shall be
paid at an addition of 40% to the rate for a welded branch joint of the same pipe
diameter and wall thickness
Page 29 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Straight length of pipes in excess of 6 meters will be based on a weld every 6meters
without re-measure
• Enumeration will include only welds properly recorded on the engineering isometric
drawings
• Bolted joints shall include for cleaning, preparation and dressing of flange
faces; installation of gaskets or ring type joints, nuts, bolts and washers, spacers,
blinds, orifice plates etc.; final adjustment and tightening of the joint
• the work required to complete test, test documentation and sign-off of pipe-work
• Preparation of test packs from P&I diagrams
• The planning and progressive execution of testing operations to meet the testing
priorities of COMPANY and/or to support pre-commissioning activities
• Providing adequate test valves complete with supporting documentation and test
certificates
• Pre-flushing of pipe-work prior to testing for removal of debris
• The provision, installation and subsequent removal of test equipment (pumps, gauges,
recorders etc.) manifolds and hoses.
• The removal and reinstallation of in-line equipment and instruments
• Supply and installation of spool pieces for testing across in-line instruments and control
valves removed testing purposes
Page 30 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Provision, installation and subsequent removal of stud bolts, bolts, special bolts, nuts,
blanks, blinds, spades, caps, plugs, strainers, additional temporary valves and/or safety
valves and necessary temporary gaskets
• Supply and installation of bolts for testing including bolts to be installed at flanges which
have to be split for testing (e.g. control valves test limits etc.)
• Necessary disconnection of flanges and subsequent re-jointing
• Provision of testing water
• Provision of air where required
• Provision of N2 where required
• Filling up and subsequent draining and disposal of test water
• Venting of lines during filing and drainage
Page 31 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Straight length of pipes in excess of 6 meters will be based on a weld every 6 meters
without re-measure
Page 32 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
7.11 VALVES
7.11.1 Valves - Specific Charges
Charges excluded (items included elsewhere):
• Jointing activities (welding or bolted joints) are measured separately
Charges included:
• work required for the installation of safety and self regulating valves,
instrument valves and instrumentation in-line
• handling of valves and instrumentation items including lifting to required
locations
• cleaning and preparation of flanges prior to fitment of valves and instruments
Page 33 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
8. MECHANICAL EQUIPMENT
8.1 REFERENCE SPECIFICATIONS
KE01-00-000-KD-V-SS-0001-000 Specification for Surface Preparation and External Coating
KE01-00-000-KD-V-SS-0005-000 Welding of Structural Steel for Packages and Equipment
8.2 SPECIFIC CHARGES FOR THE INSTALLATION OF EQUIPMENT
The unit rates for the installation of equipment shall include, but not be limited to, the following:
• Charges for necessary cranes, lifting frames, spreaders, eyes, hooks, wires, shackles,
slings, ropes and other rigging equipment.
• Charges for rigging studies and calculations for lifts
• Charges for checking of levels and elevations prior to erection and in particular the
positions and levels of foundations and main structures
• Charges for checking location and elevation of anchor bolts, removing protective covers
to anchor bolts, greasing anchor bolts and trial fitting nuts prior to equipment erection
• Charges for checking the dimensional correctness of the bolt hole positions of items of
equipment that require to be mated and bolted together prior to final positioning of the
equipment
• Charges for multiple handling of equipment to be welded or bolted on site
• Charges for removal and disposal of any temporary protection, framing, transportation
saddles, bracing and packing
• Charges for erection, alignment, plumbing and leveling of equipment in final position
including any limitations placed upon erection as a consequence of restricted access
and workspace
• Charges for shims and leveling plates and setting to correct elevation, centre line and
orientation
• Charges for installation of sliding plates
• Charges for erection and fixing of accessories and ancillary items normally provided with
the equipment but packed separately for transportation and checking of internals where
existing
• Charges for installation and tightening of nuts, washers and other holding down devices
• Charges for internal cleaning of equipment to ensure removal of debris
• Charges for opening nozzles, manholes etc., service gaskets and to ensure that access
ways have been correctly mounted and closed
• Welding and testing of equipment supplied in two or more Sections at site. Welding
procedures (WPS, WPQ & PQP) shall be provided by the vendor/supplier.
• Charges for hydraulic and pneumatic testing of equipment shall include for the provision
of necessary consumables, labour, material, equipment, temporary gaskets and other
apparatus for setting up and carrying out the complete test and cleaning away on
completion under the supervision of a vendor/supplier.
• Charges for collection from the transport barge or vessel.
Page 34 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Installation of platforms, stairs, handrails and ladders (not supplied by equipment vendor)
Charges included:
• work necessary to collect for COMPANY delivery point to a completed
assembled and erected component.
• erection of vertical equipment including accessories supplied in one section of
any weight and/or shape e.g. columns, reactors, accumulators, vessels, separators,
heat exchangers, ejectors and other similar equipment.
• Installation of platforms, stairs handrails and ladders (not supplied by equipment vendor)
Charges included:
• work necessary to collect from COMPANY delivery point to a completed
assembled and erected component
• erection of horizontal equipment including accessories supplied in one section
of any weight and/or shape e.g. columns, reactors, accumulators, vessels, separators,
heat exchangers, ejectors and other similar equipment
• Installation of platforms, stairs, handrails and ladders supplied by equipment
vendor.
8.5 EQUIPMENT REQUIRING ASSEMBLY
8.5.1 Equipment Requiring Assembly - Specific Charges
Charges excluded (item included elsewhere):
• Grouting of base-plates
• Installation of platforms, stairs, handrails and ladders(not supplied by
equipment vendor)
Charges included:
• work necessary to collect from COMPANY delivery point to a completed
assembled and erected component .
• Charges for installation of vertical and horizontal equipment including
accessories supplied in two or more sections of any weight and/or shape to be welded
Page 35 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 36 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Grouting of base-plates
• Installation of platforms, stairs, handrails and ladders (not supplied by
equipment vendor)
Page 37 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Charges included:
• work necessary to collect from COMPANY delivery point to a completed
assembled and erected package
• installation of packages supplied prefabricated as single modules
• installation of packages supplied prefabricated in two or more modules
requiring direct interconnection by bolting and/or welding
• installation of packages supplied prefabricated in two or more modules
• installation of packages supplied in two or more modules
• installation of packages supplied as loose materials (Note: Package- type units
are defined as those items which arrive at site as one or more pre-assembled skids
ready for erection )
• alignment and plumbing of the skid or equipment in final position
• welding including NDE under the supervision of Vendor/ Supplier
• Nuts, bolts, washers, gaskets or ring type joints for flanged pipe-work shall be
provided by vendor/ supplier
Page 38 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 39 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
10. PAINTING
Reference specification:
KE01-B0-000-KD-V-SP-5003-000 Offshore Coating Systems Specification
The purpose of this document is to define the costs which are deemed to be included in the
unit rates for the Direct Costs and to define the method of measurement.
10.1 Painting – Specific Charges
The rates shall exclude the following:
o none
• Items not in the Scope of WORK
o Internal coatings of steel tanks
o application of equipment identification panels, labeling and lettering to pipe-
work, flow direction arrows to pipe-work and product color banding
10.2 Painting – Painting Work Classes
The painting work is divided by the various types of surface preparation and according to each
painting system. Winter grade quality paint products shall be included, to optimize painting
activities at site.
10.3 PAINTING – INCLUSIONS & EXCLUSIONS
The unit rates shall include, but not be limited to, the following:
o supply of all materials
o application of all coats required for the coating system
o prequalification tests
o repair work to previously blasted, primed or painted surfaces to ensure the integrity of
the finished painting system
o preparation of surfaces including blasting, washing, solvent wipe or tool cleaning and
the application including but not limited to brushing, roller, or spraying
o working around obstructions, projections, beams etc.
o protection of items not to be coated, such as flange faces, etc.
o work to wide or narrow widths and curved or flat surfaces
o coating weld location on underground piping
o transportation and handling of material to/from galvanizing facility
o application to the irregular surface of solid chequer plate flooring and for painting all
surfaces and all edges
o application to the full girth of all members of rigid open grate flooring
o Repairs to CONTRACTOR applied coatings shall be deemed to be included in the
rates. The rates shall include any costs associated with repairs to painting damage not
specifically attributable to COMPANY
Page 40 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 41 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
11. INSULATION
The purpose of this document is to define the costs which are deemed to be included in the
unit rates for the Direct Costs and to define the method of measurement.
11.1 INSULATION - CHARGES EXCLUDED:
The unit rates shall exclude the following:
• none
11.2 INSULATION - METHOD OF MEASURMENT
The method of measurement for each class of work and work element is described hereafter.
11.3 INSULATION - CLASSES
Enclosure is the terminology used in KE01-00-000-KD-V-SS-002-000, also generally called
flange or valve boxes. The thickness would be same thickness of the insulation on the line for
which it is provided .
The price list for insulation work is divided by the various types of insulation and different
thicknesses into the following classes:
• Acoustic insulation
• Cold insulation
• Cold insulation incorporating Acoustic Insulation
Page 42 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• insulation of entire line including pipe, jacketed pipe, fittings, valves, tracers, etc. and
equipment
• aluminum or stainless steel jacketing as required
• checking and cleaning surfaces prior to installation of insulation
• support rings if required including the supply and installation of material for fixing
cladding to the support ring
• fixings and fastenings including but not be limited to: tape, ware, adhesives, sealant,
jointing material and ancillary material
• taping, wiring, banding, fixing, sealing and jointing including necessary overlapping of
material
• forming of laps, welts, cut-outs, recesses, ends, etc.
• insulation of nozzles, manholes, manhole covers, pipe collars, pockets, blanked off
branches, projections and the provision of removable covers , etc. of equipment
• provision of the required thickness of insulation in more than one layer where required.
• provision of any masking or similar special pieces
• execution of special shapes e.g. curve, conical or spherical
• provision of materials for removable sections of insulation where required, such as
boxes and covers to valves, flanges, etc. including trial erection, subsequent dismantling,
identification, storage and final erection. Works will include for correctly terminating (e.g.
end stops) the insulation and cladding adjacent to removable sections
• sealing, pointing, trowelling smooth chamfered and sealed edges and the like and
generally ensuring a sound and watertight seal to joints
• ring spacers, expansion, contraction and proprietary joints
• protection of the work including covering unfinished insulation, taking necessary
precautions against damage to painted surfaces, and providing adequate temporary
weatherproofing when work is not being performed.
• insulating of vessels inside the skirt
• ensuring that nameplates, code inspection plates, stamping, etc. are visible or suitably
marked and identified after insulation is applied.
• Jacketing for hot, cold and acoustic applications may be either aluminum or stainless
steel (refer Spec KE01-00-000-KD-V-SS-0002-000 sect. 6.4.1.2)
• Jacketing for personnel protection (PG and PP) applications is stainless steel
perforated sheeting, (refer Spec KE01-00-000-KD-V-SS-0002-000 sect. 5.1.4.) except
when it incorporates hot or acoustic cladding in which case it shall revert to item above
Page 43 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Cold insulation will be cellular glass (foam glass) (ref Spec KE01-00-000-KD-V-SS-
0002-000 sect. 6.2.1). PIR/PUR may be used for class CC & CA applications with
COMPANY approval only
• Hot insulation and Acoustic Porous Layer will be stone wool (ref Spec KE01-00-000-
KD-V-SS-0002-000 Annex 5,54.2)
11.4.3 Insulation Works - Method of Measurement
Insulation of Pipe-work, Valves and Small Components
• Work shall be measured based on the external diameter of the pipe times the effective
length
• There will be no increase in the diameter to account for the small components in the
line
• Effective length will be calculated using the center line length shown on the piping
isometrics
• The effective length will exclude equipment but will include valves, flanges, fittings and
other small components
Page 44 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
12. FIREPROOFING
12.1 FIREPROOFING - SPECIFIC CHARGES
Reference Specification:
KE-A0-000.KD.C.SP.0005.000
KE.B0.000.KD.H.SF.5001.000 Fireproofing Functional Specification
Charges excluded (included elsewhere):
• none
Rates and prices are fully inclusive for the supply and installation of required fireproofing works
including, but not limited to, the following:-:
• Supply of all materials
• Protection of machinery, equipment, instruments and/or piping already installed
• Fixing of the welded wire fabric by means of tying wires
• Plates, rod pieces and/or chairs for fixing the reinforcement to the metal
• Formwork
• Casting and vibration of concrete
• Sealant over fireproofing
12.2 FIREPROOFING - METHOD OF MEASUREMENT
• Area shall be calculated based on the perimeter of the structural steel primary
member times the length
• Area shall be calculated based on the vessel skirt area (inside and outside of
skirts, as required
• Area calculated shall not include any deductions for openings
• Area calculated shall not include any increase for bolts, nuts, washers, stiffeners,
brackets
Volume of fireproofing will be calculated on the design thickness times the area.
Page 45 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• The descriptions attached to the respective items within the Price List Guides are intended
to be sufficient only for identification of an item of work. The descriptions do not provide
exhaustive detailing of each and every operation required to carry out the WORK. For the
full obligations of each item the CONTRACTOR is referred to the documents forming the
CONTRACT. The unit rate entered by the CONTRACTOR against each respective item in
the Price List shall be deemed to be a fully inclusive rate for the finished work described in
the respective item including matters set out in these pricing preambles and including
everything which is contingent to and indispensable in the construction and completion of
the WORK to be carried out under the CONTRACT, and shall be deemed to include for
CONTRACTOR’s acceptance of that part of WORK previously performed by COMPANY’s
other contractors. Unless COPMANY is notified in writing to the contrary within ten (10)
days, CONTRACTOR is deemed to have warranted aforesaid WORK as if performed
directly by CONTRACTOR.
Page 46 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Notwithstanding the omission from an item description in the Price List Guides of an
individual operation or operation considered necessary for the execution and completion of
item, the cost of such operation shall be deemed to be included in the applicable item in
the Price List, and the CONTRACOTR shall be deemed to have made allowance for the
cost of such operations in each applicable item. No claim will be accepted on the grounds
of defective description or omissions that further operations other than those described are
required.
• Where the specific charges/method of measurement state that the unit rate for an item
shall include for work which will not be separately measured or paid for, then the extent of
the included work within the unit rate shall be assessed by the CONTRACTOR and no
claim for additional cost will be entertained by the COMPANY should be extent of the
included work actually executed, vary from that assessed by the CONTRACTOR.
• CONTRACTOR shall be deemed to have allowed for checking of drawing dimensions and
any and all applicable dimensions prior to commencing work. CONTRACTOR shall further
be responsible for checking documentation issued to him by COMPANY and shall draw
the attention of the COMPANY to any discrepancies or omissions therein within ten (10)
working days of COMPANY’s issue to the CONTRACTOR of documentation or revisions to
and/or supplements to documentation. COMPANY will not be liable in respect of costs or
schedule impact incurred by the CONTRACTOR due to errors, conflicts omissions in
drawings, other documents or dimensions the effects of which were avoidable had the
CONTRACTOR checked such documents and dimensions beforehand and notified the
COMPANY within the timeframe stipulated above.
• Where proprietary names or products are quoted in an item in the Price List Guides such
proprietary names or products shall be taken as indicating a required class of quality of
finished work. The proprietary name or product may only be changed by the
CONTRACTOR with prior approval in writing of the COMPANY.
• Except as provided in Section 15 “Payment Rules”, the rates shall apply equally to
executing work in large or small quantities, in difficult or easy situations, in any sequence
and at grade or any elevation above the ground unless stated to the contrary in the
CONTRACT and no claim will be allowed which arises form the proportion of the finished
work actually falling into these categories. In the course of the development of the
construction drawings, the proportion and complexity of the various operations included
within the items described in the Price List Guides may vary from the proportions or
complexity which may have been inferred from the CONTRACT drawings or from the
CONTRACTOR’s assessment of the proportions and complexity. The unit rates are
deemed to include provisions for all risk and all advantages that may arise from any such
changes in proportions and complexity and thus unit rates shall apply equally to the tender
quantities and the finished quantities of work.
• The rates apply equally to executing the WORK at any time prior to completion irrespective
of whether the various work items have programmed continuity or not, or performed in a
different season, or in a different proportions in different seasons and/or weather
conditions, or performed in different sequences, from that initially envisaged in the
CONTRACT. No claims will be accepted by the COMPANY for remobilization of labour or
equipment, additional access and the like, as full entitlement under the CONTRACT shall
be deemed to have been made by application of the relevant unit rates. No claims will be
accepted by the COMPANY for schedule extension, as CONTRACTOR shall be deemed
to have included in CONTRACTOR’S schedule full allowance for any and all such
eventualities.
Page 47 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• The rates and prices shall include for liaison with COMPANY and the COMPANY’s Other
Contractors and the Regulatory Authorities, and obtaining COMPANY and Regulatory
Authorities approval at all stages according to the requirements of the CONTRACT.
• When the CONTRACTOR is require by the CONTRACT to seek approval, the
CONTRACTOR shall do so in writing at least seven (7) working days before such approval
is required.
• The CONTRACTOR shall be deemed to have satisfied himself as to the correct meaning
of every item description in the Price List Guides and of the completeness of his unit rate
or price for the work described therein. No claim for additional payment, as a consequence
of any error or misunderstanding on the part the CONTRACTOR to fully determine the
scope of work and his CONTRACT obligations with regard to a Price List Guide item
description, will be considered by the COMPANY
• The quantities indicated in the Price List are approximate only and are not to be taken as
final quantities of work to be executed for any Price List item. The range of work may vary
to the extent that new items and/or sections may be added to the Price List and existing
items or sections may not be used. Any variations, omissions or additions shall be dealt
with in accordance with CONTRACT. Save as provided in Section 5, remuneration for the
unit rates work shall remain valid regardless of any variation between the estimated and
actual quantities of work executed against the unit rates, and no variation of the items or
quantities give in the Price List shall in any way affect the validity of the relevant price in
the Price List.
• The quantities contained within the Price List shall not be used for the purpose of ordering
any materials that CONTRACTOR is required to provide under the CONTRACT except as
provided herein. The CONTRACTOR shall order CONTRACTOR supplied material based
on “Approved For Construction” (AFC) documents issued by Company.
• The quantities of work actually executed in accordance with the CONTRACT shall be
measured or calculated in accordance with the method of measurement defined in the
Pricing List Guides. COMPANY computer programs for the re-measurement of work shall
be used where possible. Quantities not detailed on drawings or derived from computer
programs shall be determined by joint measurement by the CONTRACTOR and the
COMPANY. No allowance shall be made for waste in the re-measurement of the
quantities. The CONTRACTOR shall be deemed to have included in the Price List for
Indirect Costs for the provision of personnel and other recourses necessary for the re-
measurement of the WORK and CONTRACTOR’s commercial administration of the
CONTRACT.
Page 48 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Except as provided in Section 15 “Payment Rules”, the amounts of money to be paid to the
CONTRACTOR for unit rate measured work in accordance with the CONTRACT, shall be
the product of the total quantities of work correctly executed by the CONTRACTOR, in
accordance with the CONTRACT drawings and specifications and measured in
accordance with the applicable method of measurement, and the pertinent total unit rates
defined in the Price Lists.
• Works rejected by COMPANY for reasons ascribable to CONTRACTOR shall not be
computed and taken into account (not even provisionally), regardless of the progress
reached at the time of COMPANY’s rejection.
• In the event that works already progressed and taken into account, at any stage of
progress, are subsequently rejected by COMPANY for reasons ascribable to
CONTRACTOR, all the related quantities and compensation already taken into account
shall be nullified and the Payment Certificate as detailed in Section 7 shall be amended to
reflect such adjustments.
Compliance with CONTRACT drawings and technical specifications and quantity assurance
requirements.
The prices in the Price List are deemed to Include for the execution of the WORK and the
supply of materials (where specified as CONTRACTOR supplied in the CONTRACT), strictly in
accordance with the CONTRACT drawings and specifications.
13.3 RATES TO INCLUDE
The unit rates included in the Price List for Direct Costs and referred to in this document shall
include, along with the other CONTRACT provisions, for costs in connection with the complete
performance of the WORK described in the respective Price List Guides descriptions including,
but not limited to, the following:
• Cost of skilled, semi-skilled and unskilled labor for trades up to and including the level of
working foreman
• Salaries, wages, bonuses, allowances, fringe benefits, incentive payments, overtime and
shift payments, offshore rotations for 49raveling personnel, local 49raveling time and
fares (in particular: to and from the Crew Change Facility), public holiday entitlement,
paid holiday, sick pay, insurances, pensions, recruitment, passports, visas, residence
and work permits, training and other emoluments, contributions, taxes, levies or
expenses that CONTRACTOR may make in respect of labour in accordance with
national or local agreements or with statutory provisions.
• Cost of providing construction equipment and plant (delivery point: the ONSHORE
SUPPORT BASE in Kuryk) of adequate type, quality and quantity for the execution of the
WORK (including ensuring remains valid) including maintaining and repairing the plant
and equipment, road tax, insurance and providing sufficient spare parts, fuel, fuel oil,
lubricants, other consumables and any tackle normally associated with the equipment
and sufficient contingency for the equipment to ensure work continuity.
• Cost of providing and replacing “small tools” required for trades.
• Cost of providing cranes, crane mats lifting equipment, lifting/spreader beams, slings and
shackles and other ancillaries and sufficient contingency for the equipment to ensure
work continuity. Delivery point: the ONSHORE SUPPORT BASE in Kuryk.
• Cost of materials required for the WORK, unless started to the contrary in the
CONTRACT, including any necessary insurance, packing for transport, transportation up
to the ONSHORE SUPPORT BASE in Kuryk, customs duties and clearances, off loading,
Page 49 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
handling and waste (COMPANY supplied materials are separately addressed in the
CONTRACT).
• Cost of consumables including but not limited to nails, wood spreader, ties, stake-brace,
studs, wire clamps, wing nut, plate washer, spacers, polyethylene sheets, waterproof
paper, wet burlap. Hessian cloth, welding electrodes, fluxes, compressed air, oxygen,
and other gases, temporary supporting materials and fastenings, wood, water cleaning
materials, clothes, sponges, degreasants, blasting materials, solvents, brushes, etc.
• Cost of transporting labour, plant and materials to and from the ONSHORE SUPPORT
BASE in Kuryk, and then around the OFFSHORE SITE including travel allowances and
expenses and the traveling time of personnel to and from their temporary
accommodation and the SITE including complying with the COMPANY’s SITE security
regulations and SITE transportation regulations
• Costs of electrical power, lighting – including workface lifting – compressed air and water
for SITE construction and fabrication activities including connections thereto.
Page 50 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Cost of working in accordance with any applicable COMPANY Work Permit Procedure
and any and all limitations imposed by SIMOPS.
• Cost of complying with government and local regulations pertaining to the SITE and
payments of fines for breaches found by Regulatory Authorities.
• Cost of quality assurance and quality control and the provision of as-built drawings,
certificates, reports, chemical analysis, test certificates and the like, and other
documentation as required by the CONTRACT or the statutory authorities.
Page 51 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• Cost of promptly making good damages to existing structures, roads, fences and any
other work constructed, fully or partially, by Other Contractors, which are to be retained,
caused by or attributable to the actions or the omissions of the CONTRACTOR
• Cost of making good or reworking any item not executed in accordance with the
CONTRACT
• Cost for protecting, preserving and maintaining the WORK at all stages as required or as
inferred by the CONTRACTOR including the provision of sufficient watching, flood
lighting, general lighting, fire fighting capabilities, general security and weather protection
to avoid damage to the WORK and delay in the execution of the WORK. This cost
includes preservation of COMPANY supplied equipment and material in accordance with
manufacturers’ recommendations and/or as specified in the CONTRACT.
• Cost for the impact on the program and cost of time lost and/or inefficiency due to
inclement weather and for all other periods of non productive time of labour and
construction plant for which the COMPANY is not responsible including mechanical
breakdown of plant and equipment; industrial disputes; and attendance of
CONTRACTOR’s personnel at tool box meetings and induction and training courses,
COMPANY instituted safety meetings, idle time and travel time.
• Cost of increasing the number and/or capacity of CONTRACTOR’s labor and
construction plant as applicable, and/or execution of weekday, weekend or holiday
overtime and shift working where necessary to complete the construction work in
accordance with the current program in the PROJECT SCHEDULE (or as revised from
time to time with COMPANY’s agreement) except where liability for the delay in the
PROJECT SCHEDULE does not lie with CONTRACTOR under the provisions of this
CONTRACT.
• Cost of keeping the SITE clear of rubbish, cleaning up upon completion of the WORK
and at all times removing rubbish and waste material to RoK approved disposal areas
Page 52 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Day-work rates shall be used in case any part of the WORK cannot be performed on the basis
of Unit Rates and there is no possibility to establish new Unit Rates on the basis of existing
ones. In such case, COMPANY will issue an Instruction in order that certain parts of the
WORK are executed on a Day-work basis.
COMPANY will then instruct CONTRACTOR to prepare an estimate of the number of days,
number and type of equipment, category of personnel that are necessary to execute the work.
Prior to CONTRACTOR commencing such work, COMPANY and CONTRACTOR shall agree
on this base estimate.
In addition, COMPANY may request CONTRACTOR for a period after Pre-Commissioning
primarily of any system to provide labor and construction plant and equipment on a “as
required” basis to assist COMPANY generally in connection with the PROJECT and in
particular to provide resources to assist COMPANY during the Commissioning of the
completed system.
Work performed on Day-works (irrespective of the timing thereof) shall be excluded from the
adjustment mechanism for overall remuneration by element for items performed using Unit
Rates.
CONTRACTOR shall prepare his labor/discipline estimate at least two days in advance and
notify the relevant discipline supervisor of the COMPANY on a daily basis of CONTRACTOR
personnel who will be working on a Day-work basis. CONTRACTOR shall further notify the
relevant supervisor of the COMPANY about changes in CONTRACTOR’s personnel, who will
be working on a Day-work basis. The latest updated information shall correctly cross check
with the Daily Labor and the Daily Plant and Equipment Record Sheets.
CONTRACTOR shall submit on a daily basis Daily Record Sheets in duplicate for each activity,
which COMPANY has instructed to be carried out on a Day-work basis.
The Daily Record Sheet shall identify:
• Reference to COMPANY Instruction
• activities being carried out with a full and accurate description including its location
• Name and craft level of each of CONTRACTOR personnel engaged
• Their badges and trade discipline
• Actual hours spent and locations
Page 53 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
weekly report period (or such as COMPANY may instruct). CONTRACTOR shall submit the
complete and fully priced Day-works Sheet to the COMPANY REPRESENTATIVE for
COMPANY’s counter-signature and approval. CONTRACTOR shall attach to each priced Day-
work Sheet the applicable Daily Record Sheets, previously approved by the relevant
COMPANY Supervisor, together with the applicable originals of the invoices for materials.
Payment of Day-works will only be approved following the submission by CONTRACTOR to
COMPANY of correctly completed, fully priced Day-work Sheets signed by the COMPANY
REPRESENTATIVE.
Although the COMPANY may at times instruct CONTRACTOR labor working on Day-work,
with such instruction conveyed through the CONTRACTOR supervision, CONTRACTOR shall
understand that his responsibilities for his labor, plant and equipment and activities performed
thereby are entirely unchanged. Statutory requirements including the safety of
CONTRACTOR’s labor, plant and equipment, civil and penal liabilities remain at the sole
responsibility of CONTRACTOR.
13.5 DAY-WORKS
A list of personnel and construction plant and equipment is included in Table 5 of the Unit Price
List. CONTRACTOR may add items in the Unit Price List in order to include items of personnel
and construction plant and equipment more appropriate to his intended execution of the scope
of WORK of the CONTRACT.
13.5.1 Classification of Day-works
Day-works carried out either during construction or after the Handover to Commissioning of
each system will fall under the following categories:
• Labor
• Plant / Equipment
• Supply of Materials / Services
13.5.2 Specific Charges for Day-works
• Labor
Rates included in Table 5 are deemed to be inclusive of any overtime or out of work time
working hours, inclusive of Indirect Costs inferred as required in the Sect. 2 hereof. Day-
works shall, on a general basis, be carried out within daytime hours from 6:00 to 18:00 and
up to 7 (seven) days a week. However the Day-works can be carried out at any time
outside daytime hours if COMPANY deems it necessary at the same Day-work rates.
Skilled personnel shall be fluent in English with a minimum of 5 (five) years working
experience in his appropriate trade.
The rates for labor shall include for, but not be limited to, the following:
o Management, supervision (above foreman level) and administration, save where
CONTRACTOR is solely providing Assistance to Commissioning, where COMPANY
and CONTRACTOR shall agree appropriate non direct labor and foremen personnel
payment (i.e. the management, supervision above foreman level and administration
who may be compensated on Day-work)
o Basic salaries (basic wage, contingency allowance, seniority, condition money, piece
work, production bonus and further specially agreed rates, overtime working hours,
national insurance, etc
Page 54 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
o Payroll burdens (annual leave, national holidays and weekend holidays, bonuses,
seniority, training board levies, redundancy payments, pensions, insurances in
accordance with the requirements of the CONTRACT and/or the applicable law,
absence due to sickness or accident, absence for study purposes, for workers
meetings, time lost due to inclement weather
o Social and assistance charges (all contributions to pension funds, unemployment
funds, etc)
o Travelling time and expenses between the home base / temporary accommodation
and the ONSHORE SUPPORT BASE and for complying with SITE security, including
entry and exit from the SITE, together with and periodic leave and rotational leave
allowance
o Safety and welfare facilities
o Mobilization and demobilization costs for substitute or replacement personnel
o Any additional subsistence and accommodation expenses
o Protective clothing and environmental protective clothing and safety requirements
o Charges for small tools
o Charges for consumables and minor construction supplies / erection accessories
o CONTRACTOR’s Indirect Costs (in accordance with the CONTRACT parameters)
including CONTRACTOR’s overhead and profit
o All other liabilities and obligations whatsoever as per the CONTRACT and applicable
law.
• Plant and Equipment
Plant and Equipment Rates shall apply to CONTRACTOR’s plant and equipment already
at the OFFSHORE SITE. The rates shall exclude the cost of the drivers, operators and
attendants, which will be priced separately at the appropriate rates inside the Day-work
Rates for Labor.
Payment for plant and equipment on Day-work rates shall be only made for the actual
productive hours worked by the item of plant and equipment. Mobilization / demobilization
of plant and equipment to the ONSHORE SUPPORT BASE is deemed to be included in
the Day-work Rates (i.e. chargeable time commences at the specific Day-works work
location). Transport from the ONSHORE SUPPORT BASE to the OFFSHORE SITE will be
performed by COMPANY.
The rates stated in the Day-works Rates shall be deemed to be applicable to any hours of
the 24 hour day, or any day of the week/month.
Equipment mobilized under an Instruction to carry out Day-works, shall be compensated
at:
o hourly rates for up to 12 hours per day
o daily rates for up to 4 days per week
o weekly rates for up to 18 days per month
The list of plant and equipment is a selection only of construction plants and equipment and is
not meant to be either comprehensive or particular to the CONTRACTOR’s plant and
equipment. Consequently, CONTRACTOR may add to the items in the Price List. Any item not
Page 55 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
listed but related to an item in the agreed list shall subsequently deemed to be small tool,
construction supplies and consumables and as such shall be deemed to be included for in the
applicable Day-work Rate.
The Day-work Rates for Plant and Equipment shall include for, but not be limited to, the
following:
o Charges for road tax, insurance (in accordance with the requirements of the
CONTRACT and/or applicable law) fuel, lubricants and consumables
o Maintenance and repair (including those carried out by the operator or driver or
CONTRACTOR’s own fitters or CONTRACTOR’s plant repair and maintenance
organization)
o Any tackle normally associated with the equipment (ropes, pulley blocks, slings, hooks,
etc)
o CONTRACTOR’s Indirect Costs (in accordance with the CONTRACT parameters)
including CONTRACTOR’s overheads and profit
o Spare parts
o All other liabilities and obligations whatsoever as per the CONTRACT and applicable
law.
• Supply of Materials and / or subcontracted services/works
In case of supply of materials and/or services that are not within the CONTRACTOR’s
scope of supply and which are requested by COMPANY, CONTRACTOR shall evaluate
the number of days required and the personnel involved in the supply of these materials
and/or services. Their payment shall be in accordance with the Day-work Rates for
Management, Engineering, Construction and Administration Personnel. CONTRACTOR
shall submit such evaluation to COMPANY REPRESENTATIVE for approval. COMPANY
REPRESENTATIVE will review, correct if necessary, sign and return the evaluation
assessment to CONTRACTOR.
The price of the materials to be supplied by CONTRACTOR, in this case, shall be agreed
by COMPANY prior to issue of the purchase order. Payment for such materials will be
based on the net documented cost (including delivery costs) incurred plus the applicable
mark-up stated below, consistent with the material price agreed with the COMPANY, once
the materials are incorporated into the WORK, in accordance with the CONTRACT
provisions for payment.
The net price of materials shall not include import duties or taxes, and if these are
unavoidably incurred, they will be reimbursed to CONTRACTOR at cost (i.e. without
application of any mark-up).
The following mark-up shall be fully inclusive of all other costs associated with supply of
materials including but not limited to Overhead and Profit:
Mark-up: 15 % (fifteen percent)
In case of services provided by a THIRD PARTY or of works performed by a
Subcontractor, these shall occur only in the event that a variation to the WORK is
instructed by COMPANY which necessitates the use of a specialist lower tier
subcontractor not envisaged at CONTRACT award stage and for which no applicable Unit
Page 56 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
rate exist or can be agreed. The price of such services shall be agreed by COMPANY prior
to CONTRACTOR contracting with such THIRD PARTY and the net documented cost plus
the applicable mark-up stated below, consistent with the services price agreed with the
COMPANY, once the services have been performed, shall be paid to CONTRACTOR in
accordance with the CONTRACT provisions for payment. Such services shall be paid as if
such THIRD PARTY was CONTRACTOR’s subcontractor. The above provisions shall not
be applicable to subcontractors whose employment is envisaged at CONTRACT award
stage. Any Day-work carried out by such subcontractors of CONTRACTOR shall be
subject to this procedure and will be paid for the Day-work rates included in the
CONTRACT.
The following mark-up shall be fully inclusive of all other costs associated with supply of
services including but not limited to Overhead and Profit:
Mark-up: 15 % (fifteen percent)
13.5.3 Method of Measurement for Day-works
• Labor
Payment shall only be made for productive hours actually worked by CONTRACTOR’s
labor, in accordance with the authorization mechanism in this document and as recorded
on the relevant Daily Record Sheet and approved by the relevant authorized COMPANY
supervisor.
Foremen shall be paid for in similar manner to the other personnel being paid for at Day-
work rates. The cost of supervision above foreman level, for personnel being paid at Day-
work rates, is deemed to be included in the Unit Rate for Day-works and consequently no
separate payment shall be made for Supervision.
• Plant and Equipment
Payment shall only be made for productive hours actually worked by CONTRACTOR’s
plant and equipment, in accordance with the authorization mechanism in this document
and as recorded on the relevant Daily Record Sheet and approved by the relevant
authorized COMPANY supervisor.
• Miscellaneous Support Services
If instructed by COMPANY, CONTRACTOR shall provide Miscellaneous Support Services
on an ad hoc basis and CONTRACTOR shall be reimbursed for on a net documented cost
basis plus percentage mark-up as defined in Attachment 1 hereto.
The net price of services shall not include import duties or taxes, and if these are
unavoidably incurred, they will be reimbursed to CONTRACTOR at cost.
All CONTRACTOR’s invoices for reimbursement for agreed Miscellaneous Support
Services shall be presented with a certified copy of the original invoice.
Page 57 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 58 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 59 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
Page 60 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
15.2.2 The CONTRACTOR shall prepare within seven (7) working days of each agreed monthly cut-
off date, a complete and comprehensive financial statement of the WORK executed to the cut
off date, complementing the CONTRACTOR’s monthly report.
15.2.3 The CONTRACTOR shall submit the statement to COMPANY at SITE in one original and two
copies together with an electronic copy in a format agreed with the COMPANY. Pages of the
statement shall be sequentially numbered, signed on each page by the CONTRACTOR and
shall be sectionalized as described below.
15.2.4 The financial statement shall be accompanied by each of the following documents, where
applicable:
• Indirect Costs - A schedule of the facilities provided by the CONTRACTOR in
accordance with lump sum portion of the Price List for Indirect Costs and a contractual evaluation of
same. The schedule shall take the form of a cumulative valuation, such that it will ultimately constitute
the final account of the lump sum portion of Indirect Costs.
• Direct Costs - Detailed measurement sheets and priced billing of work which is the
subject of unit rates. COMPANY computer programmes for the measurement of completed work shall
be used where possible. The actual quantities of work completed shall have been subject to the prior
agreement and signature of the COMPANY REPRESENTATIVE. The measurement and billing shall
take the form of a cumulative valuation, such that it will ultimately constitute the final account of
measured work of the unit rate portion. Progress reports shall state the percentage complete of WORK
for the period and cumulative valuation of the unit rate portion of WORK based on CONTRACTOR’s
estimated bill of quantity quantities where the drawings are issued or COMPANY’s preliminary
quantities for the balance, where such quantities are not yet finalised.
• In respect lump sum portion of the direct cost WORK (if any are agreed between
COMPANY and CONTRACTOR during the duration of the CONTRACT), progress reports shall record
the percentage complete of work in accordance with the COMPANY agreed weighting mechanism.
The CONTRACTOR shall similarly record the progress complete of any COMPANY approved Variation
Order, a copy of the executed front sheet of which should be incorporated in the statement. The
percentage complete shall have been subject to the prior agreement and signature of the COMPANY
REPRESENTATIVE. The CONTRACTOR’s billing shall take the form of a cumulative valuation, such
that it will ultimately constitute the final account of lump sum work (including Variation Orders, as
applicable).
• Day-works costs: A list of Field Instructions and the like issued by COMPANY and the
amounts being claimed for by the CONTRACTOR against each Field Instruction. Each Field Instruction
shall be fully substantiated by a measurement of the work executed, Day-work Sheets or invoices as
applicable. Field Instructions shall be priced in accordance with the Unit Rates wherever possible or as
pre-agreed Lump Sum and by exception using Day-works. Field Instructions shall be listed and
approved as a VARIATION ORDER prior to being submitted for payment.
• Fully complete and priced Day-work Sheets with supporting Record Sheets and original
material invoices. The Record Sheets shall have been previously agreed and signed by COMPANY
REPRESENTATIVE and the Day-work Sheets shall have been previously approved and signed by the
COMPANY REPRESENTATIVE. Day-work Sheets shall refer to a Field Instruction No. issued by
COMPANY. The Day-work billing shall take the form of a cumulative valuation, such that it will
ultimately constitute the final account of reimbursable work of the Day-work portion.
• Original material invoices of any material purchased by the CONTRACTOR on the
instructions in writing of COMPANY (not included in an applicable unit rate). The material invoice shall
refer to a Field Instruction No. issued by COMPANY.
Page 61 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
• The valuation of any THIRD PARTY Services provided to the CONTRACTOR (offset) or
by the CONTRACTOR in accordance with PRE.GC.CC.8020. The invoice for the THIRD PARTY
Service shall refer to a Field Instruction No issued by COMPANY.
• Any credits that are due from the CONTRACTOR to the COMPANY or back-charges
from the COMPANY to the CONTRACTOR
15.2.5 Each of the items stated in 6.4 shall be separately totaled by the CONTRACTOR and the totals
of each carried to a statement summary. Each statement submission shall bear the
CONTRACTOR’s full title and address, place of registration and be serially numbered and
dated, and refer to both the Contract No. and the time period for which the submission is being
made, in accordance with the provisions of the CONTRACT. COMPANY will review the
CONTRACTOR’s statement and determine the amount which in the opinion of the COMPANY
is due from the COMPANY to the CONTRACTOR, making amendments where required to the
statement. The COMPANY will return such amended statement (as applicable) to the
CONTRACTOR, for the CONTRACTOR to issue, without delay, a credit note to the
COMPANY, reflecting the COMPANY’s notified valuation position, together with an amended
CONTRACTOR period/cumulative invoice, in order to regularize payment
COMPANY will prepare a Payment Certificate recording the amount which in the opinion of the
COMPANY is due from the COMPANY to the CONTRACTOR. The Payment Certificate shall
record the gross value of work completed to the cut off date, the amount of retention withheld,
the value of previous payments and the net amount due to the CONTRACTOR for the current
period, allowing for any back-charge. The Payment Certificate shall be signed by the
CONTRACTOR and COMPANY. The statement and the signed Payment Certificate shall be
presented together with the CONTRACTOR’s signed invoice, in the same amount as the
Payment Certificate, to the COMPANY REPRESENTATIVE for forwarding to COMPANY’S
Accounts Department.
15.2.6 Failure to observe the above requirements may lead to delays in agreement of the amount of
the statement, issue of the signed Payment Certificate, and processing of the
CONTRACTOR's invoice and credit note, and invoice payment by the COMPANY.
Page 62 of 63
Kashagan Field Development Experimental Programme
Contract No: 2009-0363
Hook-Up, Pre-Commissioning & Commissioning Assistance
Schedule B – Compensation
PRICE TABLES
Table 0 GRAND TOTAL
Table 1 INDIRECT COSTS
Table 2 DIRECT COSTS – TRAIN 2 PIPE-RACKS & MODULES
Table 3 DIRECT COSTS – RISER ISLAND
Table 4 OPTIONAL WORKS – ISLAND A
Table 5 DAY-WORK RATES
Table 6 SUMMARY OF PROVISIONAL ITEMS
Table 7 MOB / DEMOB MILESTONE PAYMENTS
Page 63 of 63