Vous êtes sur la page 1sur 24

------------c-H-A-p-T-E-R-ll

Pipe Racks

A pipe rack is the main artery of a process unit. It mentation diagram issues covers only commodity, line
connectS all equipment with lines that cannot run number, and preliminary sizes,
through adjacent areas, Because it is located in the Process flow diagrams prOVide insight to operating
middle of most plants, the pipe rack must be erected temperatures and identify the need for insulation,
first, before it becomes obstructed by rows of equip- Once the routing diagram is complete, the develop-
n\':'nt, The corresponding piping drawings are also re- ment of rack Width, bent spaCing, and numbers of
quired early for the same reason, Pipe racks ~an"y levels and elevations may proceed,
process and utility piping and may also include instru-
ment and electrical cable trays as well as equipment
Bent Spacing
mounted over ,,: of these, This vital area requires
considerable planning and coordination with other A pipe bent consists of a vertical column or columns
technology groups regarding construction because and a horizontal structural member or members that
costs are so high, carry piping systems, usually above headroom, The
This chapter explains what is required to finalize line sizes that are installed in the rack establish the
the pipe rack width, number of levels and elevations, bent spaCing. Exhibit 11-2 is a typical pipe span chart
and bent spacing and addresses pipe flexibility and and shows how far a particular line can span on the
access and maintenance concerns for each item lo- basis of size, schedule, liqUid or vapor, and insulated
cated within the pipe rack area, or bare pipe, Pipe racks are tailored to a specific plant;
The primary data required for the detailed develop- pipe sizes in chemical plants are smaller than those
ment of a pipe rack includes the follOWing found in refinery units If a plant requires a 16-ft
(4,900-mm) spacing, the variation in Exhibit 11-3 al-
• Plot plan, lows for a 32-ft (9,700-mm) spaCing by adding inter-
• Piping and instrumentation diagrams, mediate bents supported from spandrels Spandrels
• Plant layout specification, are horizontal structural members located along the
longitudinal centerline that are used for structural sta-
• Client specification,
bility, pipe suppOrt, or intermediate pipe bents, Dou-
• Construction materials, bling the column spacing as shown in 2A of Exhibit
• Fireproofing requirements, 11-3 may be reqUired to cross roadways or avoid un-
derground obstructions, The civil and structural engi-
neers should be consulted to review the economics of
ESTABLISHING WIDTH, BENT SPACING, the approach
AND ELEVATIONS Setting the width of the pipe rack may then pro-
ceed, With the routing diagram, a dimensioned cross
The first step in the development of any pipe rack is section is developed at the bent that will carry the
the generation of a line-routing diagram, shown in most piping, which is bent No 12 in the example
Exhibit 11-1, A line-routing diagram is a schematic rep- shown in Exhibit 11-4, Usually, pipe racks carry pro-
resentation of all process piping systems drawn on a cess lines on the lower level or levels, and the utility
copy of the plot plan, Although it disregards exact lines on the top level Instrument and electrical trays
locations, elevations, or interferences, it locates the are integrated on the utility level if space permits or
most congested piping bent in the pipe rack. Csually, on a separate level above all pipe levels, Any pipe rack
the information available on early piping and instru- design should prOVide for 20% future growth When

261
262
EXHIBIT 11-1 Line-Routing Diagram

,.....------ - --.....,.--,,~r-----­ -------

~.o~

I
.e-1.'"
_E: ·1oe
I
P-U>4-. I
I &.?U7
_! -'2'2.~
~~.
E:=1!S .
_..I-..zor
o.,d'
D-21"

_---.I:-~.A-
~

e- -22(4- - - - - - , I) -ZIZ
I
C.-2,? ___ c-'l!>7 I
I
I-toJ
I r--z.!>J
e-~,O
F-~.lL-
e--'ll~ -
e--ZI7 Eo..z.1 'Z
0-'20'2_ c-'J..L
I
T-Z~
I
_1-20'2
-- -- I
Process Plant Layout and Piping Design
263

EXHIBIT 11-2 Basic Pipe Span Table

Vapor Line Liquid Line


Insulation (Span) Insulation (Span) Bare Pipe (Span)
0
Size Schedule Corrosion 351 0 to 601 0 to 351 to 601 0 to Empty Water Filled Size
(inches) (inches) Allowance To 3500 F 600 0 F 750' F To 350' F 6000 F 750' F (to 350' F) (to 350 0 F) (inches)

3/4 40 005 12 11 8 12 10 14 13 3/4


1 40 005 14 13 10 14 12 9 16 14 1
1 1/2 40 005 18 14 14 1~ 15 12 19 Ie 1 1/2
2 40 010 18 16 II I~ I'; 11 21 18 2
21/2 40 010 23 19 16 19 18 15 2'; 2] 2 li2
3 40 010 24 21 18 21 19 16 26 22 3
4 40 010 -r , 25 22 24 23 19 29 25 4
6 40 010 33 31 28 29 r 25 34 29 6
8 40 0.10 39 36 33 33 32 29 40 33 8
10 40 010 44 42 39 3- 35 34 46 38 10
12 3/8 w 010 4~ 45 42 39 38 36 49 40 12
14 318 w 0.10 49 47 44 40 39 37 52 41 14
16 318 w 010 53 50 4"'7 42 4I 39 55 43 16
18 318 w 010 56 54 50 44 43 40 59 45 18
20 318 w 0.10 59 57 53 46 45 41 62 46 20
24 3/8 w 010 65 62 58 48 47 43 68 49 24
3/4 80 010 12 10 11 10 6 14 13 3/4
1 80 0.10 14 12 10 13 12 9 16 14 I
I 1/2 80 0.10 17 16 lq 16 15 13 10 17 I 112
2 80 010 19 17 14 18 16 13 2I 19
2 1/2 80 010 22 20 18 20 19 1- 23 21 2 112
3 80 010 24 22 20 22 21 19 2'; 23 3
80 010 2-:" 26 23 25 24 22 29 26
6 80 010 34 32 30 31 29 28 35 31 6
8 112 "'. 010 39 r 35 35 33 32 40 36 8
10 1/2 w 010 44 42 39 38 37 35 45 39 10
12 1/2 w 010 47 45 43 41 40 38 49 42 12
14 112 w 0.10 50 48 4" 42 41 40 ';1 44 14
16 112 w 010 53 "1 49 44 43 42 55 46 16
18 1/2 w 010 57 55 52 47 46 44 59 48 18
20 112 w 010 59 49 47 46 62 49 20
24
1
1/2 w
XXS
0.10
025
65
14
"7
63
13
""
60
10
52
13
50
12
49
10
68
15
52
14
24
1
1 1/2 XXS 025 17 16 14 16 15 14 18 17 1 112
2 XXS 0.25 20 18 15 18 ]7 15 21 19 2
21/2 160 025 21 19 17 19 18 16 23 21 21/2
3 160 025 24 22 20 22 21 19 25 23 3
4 120 025 27 26 23 25 24 22 29 26 4
6 80 0.25 33 31 28 28 27 26 35 29 6
8 112 w 025 38 34 33 32 30 40 34 8 8
10 1/2 w 025 43 41 38 36 35 33 45 37 10
12 1/2 w 025 47 45 41 38 3- 35 49 39 12
14 1/2 w 025 49 47 44 39 38 37 52 40 14
16 1/2 w 025 52 50 48 41 40 39 55 42 16
18 1/2 w 025 56 53 50 43 42 40 59 47 18
20 1/2 w 025 59 56 53 45 44 42 62 45 20
24 1/2 w 025 64 60 58 4- 46 45 68 48 24

PIpe Racks
264
EXHIBIT 11-3
Pipe RacJc Column
Spacing

EXHmIT 11-4
A Pipe Rack Cross Section
(at Column 12)

Process Plant Layout and Piping Design


265

f5flf~~~
EXHIBIT 11-5
Pipe Rack Composite

hJ ~y~ eleG:rtzw:=d..

I
~l..JN&$

'-----~--+--~4:iJL-

the electrical conduit trays are located on the tOp level ft (6,100 mm) rather than 19 ft 3 in (5,850 mm). To
and a row of motOr-driven pumps is located beneath illustrate, if the pipe requires a much greater area in
the rack at grade, a 6-in (lSO-mm) slot should be pro- the rack, the designer would work with the structural
vided to allow the conduit to run in the most direct engineers to determine whether the pipe rack should
manner and avoid running to the outside of the rack be rwo 30-ft (9,150-mm) wide levels or three 20-ft
and back to the pumps. This feature is illustrated in (6,l00-mm) wide levels This decision affects the cost
Exhibit l1-S Once future rack growth and conduit of the structure and pipe and mu:;t be made carefully.
have been allowed for in the plan, the spaCing may be After the bent spacing, rack Width, and number of
set with the line spacing chart in Exhibit 11-6. levels are established, the elevation of the levels must
When flanges or flanged valves are reqUired on rwo be set. As discussed in Chapter 2, the plant layout
adjacent lines, the flanges are staggered as depicted in designer must know the minimum clearances to set
Exhibit 11-7. Thermal expanSion or contraction must the elevations. Plant roads, type of mobile equipment,
be accommodated, as shown in Exhibit 11-8. When all and equipment located beneath the pipe rack can in-
the distances have been established berween all lines fluence the pipe rack elevation. Usually, space is al-
on each level, including allowances for future growth lowed below the pipe rack for equipment, with a mini-
and conduit, the only remaining dimension to be set is mum clearance of 10 ft (3,050 mm)
the distance from the first line in the rack to the verti- The next factor to consider is the dimension be-
cal column centerline. Column sizes are furnished by rween the bottom of a line in the rack and the bottom
the civil/structural engineers. of a branch as it leaves the rack. For example, if a
The last step is to add up all the dimensions and review of the largest lines in the entire pipe rack
round off to the next whole number-for example, 20 indicates that there are rwo or three large-diameter

ptpeRacks
266
EXHmIT 11-6 line Spacing Chan

l..l1-,Je- t70#~GC- ?I>~~


",:le- I l~ '2 ~ 8 10 It. IA ICo Ie> t:; '24 I I~ 'Z.
4 4 ~ e> 10 11 14 I~ I~ 1t> 1'2.4
I i
..,
"
1 1 l 1 ~ ~ 10 1'2 17 14 Ie;, I~ 18 1 l l
,
?
1 1 ~ ~ 10 1'2. I~ 14' I~ J(i, l8
IYt 1 1 1 e, ~ 10 1"2. I? 14 1;- I(p I~ 1 'j
1 ~ 10 II I~ 14 117 I~ Ie. to
'2
?
1 1 1 e. ~ II 1'2 I'.:> 14 II? 1& I")
I b ~ \0 II I? 14 17 I~ 11 I~
i "1
1
8
t>
~
~
'0
II
'I
~
I~

~ 1~
14 Ie;. 11 Ie tl
I~ 11 I~ 'Z.I
UJ
N
4 8> ~ 10 1'2 I? 14 I~ I" Ii I'to 9 10 11 ,~
14 It? 1(# Ie> ,~
'Zt
~ CD 10 II I;' 14 Ie; 11 11 19 'ZI 12 I~ It; ,(, '1 I~ '20 z?
l1J
"2
J
8 1"2 14 1'7
1t7
,(;,

11
I!!J I!> I~ 1.'2. " I? IA. I~

Ir,. 11 Ie>
I i Ib 'Z.o 1,1 14
10 ,~ I~ I~ '21 1? I~ 'Z' 'Z:z. ~

~ 1'2 Ii 18 'ZO 10 'Z'Z Z4 I~ I~ 1.0 'tt 'Z? ~

1'Z4
~
14 10) ~o '2.1 'Z2 '2.1 'Z"Z. t.? 14- Ur:>

$~~ -zz ~ ze;,


I~ ZI ~z 2~ z17 1,1
r; I~
I-J1IN.
1~ Z4 ~ ~ ~ ~
4
'20 '2S> 'q 'Z1 'Z.~

Z4 ~ .,!

bj~;. ~P'AC.I~~ 1~ ~ Ot-J t?f P\~ f;> r~GE: -+ 1;:017.


rz'Dl/Il.J7
· ~r L.I~E; WIn-! lc>~ ~ioJGC DIDl.AE~> flt--JO D1:::U~ L..1-.lE: ~Z= ~ ee:-L:017
~ To ~Nr;:> ~Tel2'L..\h..Ie-~IZt..IIJE: Dll-.I1E:l-JS>ION-e,.... It-J It-.JCl.1E:5.
• WJu'SiT D1...-1~~lot-J To ~rr '1-.J"?ULc.T'o!'J Tl-l~E?7.
# ~UlATI:; -::r'L:lC1IoJG 'W-I~E; p1f'E: IZtJC.K '2F&.. ~6-re I? uI.AIT~.
• t.r?JU~il-'1~ To ~I-.J~ ~ ~~L E':'><p'pl-..J;'IOt-...l t72 coN'ftZtlC.fON ~i.J?T re
MAI7E:.

EXHmIT 11-7
line Spacing

Process Plant Layout and Piping Design


267
EXHIBIT 11-8
Planning for Line Growth

EXHIBIT 11-9
Large-Diameter Lines

eND VIEW

E:LEVATIO~ I

~De VIEW

Pipe Racks
268

...o...
o

...

Process Pla----:-:---
ntLa"o ~-
" ut and p'p . Design
I mg
269

EXHmIT 11·11
Pipe Rack Meter Runs

lines (e.g., 18,20, or 24 in) and the remaining lines are is an example of a typical layout.
12 in, the exit level above and below the rack can be 3 A common arrangement of a standard process unit
ft (915 mm). The dimension from the end of a 90° pipe rack is one in which the process lines are on the
bun-wdd elbow to the centerline of a 12-in line is 18 lower level or levels. The utility piping is on the top
in (457 mm). Exhibit 11-9 illustrates how to handle the level, which carries piping Electrical and instrument
large-diameter lines by using a 45° elbow or trimming cable trays are located on the top level with the utility
an elbow to a more shallow angle. If the instrument piping or on a separate level above the utility piping,
and electrical conduit are installed on a separate level, depending on the extent of cable tray area required.
the estimated dimensions of each tray must be ob- The plant layout designer must consult the electrical
tained from the instrument and electrical engineers to and instrument engineers early in the pipe rack layout
ensure that adequate space is prOVided. to establish these requirements.
The design of the pipe rack is now complete with When locating lines in the rack, the plant layout
the exception of installing equipment over the rack. designer should run the largest lines near the outside
where possible to reduce the overall load on the sup-
porting beams Meter runs should be installed directly
SElTING LINE, VALVE, AND next to the columns so that access is available by porta-
INSTRUMENT LOCATIONS ble ladder or mobile platform, as shown in Exhibit
11-11. Meter runs are located in the pipe rack only
Many factors must be conSidered when locating each when absolutely necessary.
line, valve, and instrument in a pipe rack. Exhibit 11-10 Many relief headers must be located above the top
270

~I.~
-tti EXHIBIT 11-12
Relief Header Location

I!~

EXHIBIT 11-13 Alternative Pipe Rack Expansion EXHIBIT 11-14 Hose Station at a Pipe Rack Column

f---+-h--+-----:l

level of the rack to allow the line to drain to the blow-


dOV'lTl drum. The designer should avoid locating the
line over the centerline of the column for support so
that the columns can be extended for future rack ex- dead spaces. The designer can minimize runs in the
pansion. Exhibit 11-12 shows a suggested location for rack by consulting with the adjacent-area designers to
the relief header that does not impede future expan- identify which lines can run within the areas. Because
sion. the development of a pipe rack often includes swap-
Shut-off valves at utility headers are located inside ping lines, it is advised that the designer draw the lines
the rack area in the horizontal position, directly above lightly until satisfied with the design. Once the layout
the header if room permits. Operating valves must be is optimized, the line definition carl be finalized.
accessible from platforms or by chain operators. The A pipe rack composite is shown in Exhibit 11-5.
location of the valve must also permit the chain to fall This view highlights features mentioned previously
free of obstructions that would hamper operation. An and clarifies additional considerations. For example,
additional 20% of space must be allowed for future the width of the access way is determined by the space
pipe rack growth. An alternative approach to such ex- needed to maintain the equipment located at grade
pansion is shown in Exhibit 11-13 below the pipe rack. For process or COSt reasons, shell
Because space in the pipe rack is limited once the and tube exchangers may be located under a pipe rack
design is set, it is important to route lines to avoid in certain process units. Allowances must be made to

Process Phlnt Layout and Piping Design


271

maintain such units (e,g" providing a hitch pOint over


the channel end to facilitate its removal), Once again, EXHIBIT 11·15 Battery Limit Valving: Single-Level Rack
(ProceSS/Off-Site Common Elevation)
it is extremely important to know exact Iv what kind of
mobile handling equipment the plant will use,
The vertical drop of lines outside the rack, although
usually 2 IT (610 mm), is once again set by the average
line size in the unit. If the average line size is 2 in, a 12-
in (300-mm) drop may be sufficient. This view also
shows how the electrical conduit can be run directly
to the pump starter switch,
Exhibit 11-14 shows a typical arrangement for a
hose station, Battery limit valving for a single-level
pipe rack is shown in Exhibit 11-15, The valves are
staggered on either side of the catwalk, and hand-
wheel extension stems are furnished when necessary
to facilitate operation, Exhibit 11-16 also displays a
single-level rack. Here, however, an elevation change
is required between the process unit and the off-site pL~
pipe rack. This design has the block valves installed in
the vertical portion of the line, which allows for rela-
tive ease of operation,
Exhibit 11-17 illustrates a two-level process unit
pipe rack; the elevation change to the off-site area is
either above or below the process unit pipe rack,

PIPE FlEXIBILIlY AND SUPPORTS

Although conducting the final stress analysis is the re-


sponsibility of the mechanical or stress engineer, the
pipe rack designer makes preliminary calculations us-
ing relevant books and nomograms to ensure that the
design will not require major rework during the for-
mal Stress check. Exhibit 11-18 highlights the steps
involved in making a preliminary fleXibility check,
which are discussed in the following seaions,

Establishing potential flexibility problems The lines


that would most likely require expansion loops
should be defined, Steam headers in the top level of
the pipe rack are such examples,

Pipe Racks
272

EXHIBIT 11-16
Banery limit Valving:
Single-Level Rack
(Process/Off-Site
Elevation Change)

Process Plant Layout and Piping Design


273

EXHIBIT 11-17
Battery limit Valving:
Two-Level Rack
( Process/Off-Site
Elevation Change)

A
I \ I I
w.w

Pipe Racks
274

EXHmIT 11-18
Flexibility Check Steps

to'~c? ~ 4t;o"
e,".e.e;, e ~~O"
& I •• co:, e. ,;,0"

~IfP 1: F~-rD~LI~ fbT~Ni1AL ~~UT( e~e=M?

MUL.1JPly U'erf'G'e:Nf 0/ ~~oJ ~ ~rJ Of LI~~

~f 1I: ra:' BA..A l"-l;: kl N~ §I7oWTH fc1.Z TH~F; klye2

I 1_1 \ I I rly
Tg'( toN a.\o:z. I tJ C?JJEt2 "?F i.J "H;

mr 1!I'. t?t:T~1 "-J[:- wHerHe:tz ONE ~ rt?!b1"f--


WI L. L- :e:u FfICE:;

Process Plant Layout and Piptng Design


275

EXHIBIT 11·19
Pipe Rack Anchor Bent
PI r.> I toJ~ A " I -~-
1-l~E-
- - - \
~
- - - -
~I' ·rr

Determining line growth The gWl.vth of such utility two anchor points approximately one-quarter of the
headers should be determined by multiplying the co- distance from each end of the header should be tried.
efficient of expansion by the length of the line. The Using the nomograms, the designer can calculate the
coefficient of expansion is based on a particular mate- amount of expansion leg required to satisfy all flexibil-
rial operating at a specific temperature. Upset temper- ity requirements.
atures take precedence over operating temperatures.
Arranging lines in proper sequence The line that
Determining whether one anchor point will suffice requires the largest leg must be located on the outside
Assuming that an anchor is located in the center of the of the loop. Placing the headers along one side of the
header, the designer should calculate the grmvth of pipe rack allows the expansion loops to sit with a
.arious branches to determine whether they have slight overhang along the adjacent side of the pipe
enough flexibility to absorb the header gro\V-th. If not, rack Exhibit 11·19 shows such an arrangement. As a

Pipe Racks
276
EXHIBIT 11-20
Steam line Dr~p Legs

EXHmIT 11-21
[& Proper Line Support

~
\
el~T

"-.~~ UIJe-
EXHmIT 11-22 Intermediate Pipe Support
an adjacent line or column, because it will aa as a lint'
stop and could cause a problem. Enough space must
be proVided for the line to move its maximum
distance and still have an ample clearance of 3 in
(75 mm).
Exhibit 11-21 shows the correct way to support a
line that has exceeded its allowable span. A common
mistake is to extend the 10-in process line over the
rack bent and cap it, when the line should have been
run as if a suPPOrt problem did not exist. A smaller
result of imposing stop loads on a particular bent, piece of pipe or dummy leg could then be welded to
bracing may be required to grade, prohibiting the lo- the elbow for support (a hole should not be cut in the
cation of any equipment in that particular bay. A process line).
means of removing condensate bUild-up must be pro- Exhibit 11-22 shows how larger lines in a pipe rack
vided on either side of the expansion loop. The most are used to suppOrt a group of smaller lines that may
common way to accomplish this is to add drip legs and nOt be adequately supported because of the bent spac-
traps, as shown in Exhibit 11-20. ing. The uninsulated line is U-bolted to the supporting
Header growth causes another problem that is of- steel; the insulated line has its shoe welded to the
ten not as obvious. The line spacing chart may have steel. The smaller lines then rest on the steel. When an
been used to set distances between lines, or lines may insulated line is used for support, the growth of th(
have been set close to a column Exhibit 11-8 reveals line at the proposed suPPOrt pOint must be checked.
that the movement of a line must not be restricted by Its growth could become restriaed by this type of

Process Plant Layout and Piping Design


277
EXHIBIT 11-23
Pipe Rack Spandrel
Location

EXHIBIT 11-24
Pipe Rack Spandrel
Variations

suPPOrt, and it may be better to use anOther line for member for the spandrel support. The spandrel also
this application. has an embedded steel member that is bolted to the
column and eventually grouted in. An installation se-
quence for a precast pipe rack is also shown in Exhibit
STRUCTURAL CONSIDERATIONS 11-25
Such equipment as drums and deaerators is often
Most lines require support when leaving or entering a located above pipe rack columns. To avoid wasting
pipe rack Structural members called spandrels are the valuable rack space with the large support columns,
most common means of satisfying this requirement the inside face of the pipe rack column must line up
After all the lines have been run in the pipe rack, the with the inside face of the equipment suPPOrt column,
plant layout designer must begin to locate the span- as shown in Exhibit 11-26. This approach also allows
drels necessary to support all of these lines. Exhibit the feed-water outlet piping to run vertically down to
11-23 shows how the requirement can be handled. If the pump before the expansion loop is added.
the structural engineers require additional spandrels Fireproofing of pipe rack columns is shown in Ex-
for stability of the pipe rack, they should bring this hibit 11-27 If hydrocarbons are prevalent, it is com-
requirement to the attention of the plant layout de- mon to fireproof the columns to a level just below the
signer. Exhibit 11-24 shows some variations of span· lower rack support beam. If air coolers or other
drel design equipment is located above a pipe rack, the fireproof-
The plant layout designer should be aware that pre- ing is extended to the equipment support beam. This
cast concrete pipe racks require structural members issue must be reviewed with the client; allowances
that are much larger than most designs Exhibit 11-25 may need to be made for as much as 4 in (100 mm) of
illustrates a precast column with an embedded steel fireproofing.

PtpeRacks
278

EXHmIT 11·25
Precast Concrete Pipe
Rack Considerations

I
I
L

. ' 6'
..~.'"
, ..;..

~,'

..
.'
~
.
t-

.'

.--- ---,
I I

a. Precast Concrete Pipe Rack

b. Installation Sequence

Process Plant Layout and Piping Design


279
EXHIBIT 11-26
Equipment Support
Column Location

EXHIBIT 11-27
Fireproofing
Requirements

ptpeRacks
280
EXHIBIT 11-28
90° Pipe Rack Turns

EXHIBIT 11·29
Rack Intersection

a. Rack Intersection Layout

OTHER CONSIDERATIONS on the left side of the rack must remain constant as
long as flat turns are used. A different elevation must
Occasionally, a situation arises in which a flat-turn be used at a 90° turn in the rack if the sequence must
pipe rack may be employed. This often happens near a change, as shown on the right side of the diagram.
dead-end area where the potential for problems is This approach must be well thought out before it is
minimal. As shown in Exhibit 11-28, the line sequence used.

Process Plant Layout and Piping Design


281
EXHIBIT 11-29
lUck Intersection (Com)
r---
. or:-
- .- ,~.------ J

/ - - -
I
I 77
'i I I
--b
I
I
'2
1
J I 7
I .J... - - I

C
't'

Wezc,~§! ~,
I

I
I
I
1
.J
I
~ ·ij..... ~
'j
H'
b. Rack Intersection Detail

The secondary pipe rack intersection is shown in


Exhibit 11-29. There is a right and a wrong way to set EXHIBIT 11-30 Pipe lUck Additions
this location. Although it may seem more uniform to
set the secondary rack directly south of the main
north/south rack during the plot plan development
stage, Exhibit 11-29 also clearly shows why this should D
be avoided The lines heading north off the main east!
west rack restrict the lines from the south from en-
tering this common area. Therefore, the secondary
rack should be shifted east one bay to eliminate the
problem,
Alternative pipe rack eX'Pansion of the individual
levels can be accomplished by adding a cantilever
beam as required on the outside of the column. The
only problem with this approach is that, if not planned
for, the venical risers commonly found outside the
pipe rack use a considerable amount of the space of I I
the extension, as shown in Exhibit 11-13-
Pipe rack additions are shown in Exhibit 11-30. I i
Area A shows a standard two-level pipe rack, as
planned. Because it is always possible for the pipe rack
Uoooooo
I
= =t--------®
to be expanded in the future, the area over the
columns must be kept free of piping and conduit. The
future expanSion may include another new level (B),
an air cooler (C), or a series of shell and tube exchang-
erS (D). The preferred location of a relief header
A
above a pipe rack is illustrated in Exhibit 11-12.
Lighting panels and welding receptacles also must

PtpeRaas
282

EXHIBIT 11-31
lighting Panels and
Welding Receptacles

,,1" I II
.,.& .~

." ':>" .•

...... .
~ '.

... ',

LI6~JlNG! t:7A~eL..
(~U\..Ag 'F !:H~f)

Process Plant Layout and Piping Design


283

EXHIBIT 11-32
Operator Access

<'
£--
--~,.~
----""'-'~-

be planned for during the early stages of a pipe rack the designer should avoid blocking access from under
layout. They are mounted direaly on pipe rack the pipe rack to adjacent equipment areas by leaving
columns; their location must be recorded on the ap- clear space, as illustrated in Exhibit 11-32.
plicable documents. Electrical engineers designate Overall pipe rack design must meet the current
where the regular and emergency panels are located; needs of a client as well as any expansion plans with·
construction personnel selea the preferred location out making major modifications to existing facilities.
for the welding receptacles (see Exhibit 11-31). When Available space in the pipe rack must be considered
locating piping manifolds, control stations, instru- valuable and used to the utmost advantage of present
ments, and pull boxes along the pipe rack columns, and future needs.

PipeRadls

Vous aimerez peut-être aussi