3. EQUIPMENT TAG NO :
I)The refinery area sirens were not available as job was going on vide cold work
permit no. 00270 dated 17/03/2011.
(Signature of Officer-in-
charge)
Name: DC Baruah
Designation: M (EM)
6. ANALYSIS OF FAILURE :
The earlier Fire Siren system was based on timer circuits, the variation of time
was found during the daily test run and during Mock Drills in all the Siren
operating modes i.e., All Clear/Test, Major Fire and Disaster. Based on the report
on “audibility of Sirens in NRL and NRMT area dated 11-09-2006”, the
requirement of New Electronic Siren Panel was proposed. The New Electronic
Siren Panel was commissioned on 09-02-2011. The commissioning report is
enclosed in Annexure-1.
During the commissioning of New Electronic Siren Panel it was observed that in
the siren distribution system, numbers of sirens of different locations are connected
in parallel loop (Layout of old siren distribution system attached in Annexure-2).
The disadvantage of this system are:
A. Fault propagates from one faulty siren to the other connected sirens in
parallel loop.
B. Checking of individual siren not possible without taking shutdown of the
complete loop.
C. Fault troubleshooting was time consuming.
D. No protection available in the load side.
E. Siren distribution system was not done in a sequential manner.
F. Colour coding of the cables in the MDF (located in EPABX) was not
done.
G. The positive of the 48 VDC was connected directly to the individual
siren’s outgoing, due to which manual tracing of the positive voltage
cables required to be done.
Sequence of Events:
II) Cold permit no. 00270 was issued from F&S Deptt. dated 17/3/2011 at
10:00 HRS up to 16:45 HRS.
III) The checking of the siren motors was carried out w.r.t. permit no 00270
(F&S). & the same informed to all concerned via mail dated 17.3.2011 at
9.13 HRS (as attached in annexure 4).
IV) The non functioning sirens were thoroughly checked one by one in the
following locations as provided in TABLE 1:
TABLE 1
Sl No ADMIN
LOCATIONS ETP SS#5 SS#2 OIL LPG LG
BUILDING
1 Disconnection of Done Done Done Done Done Done
Power Cable
2 Voltage Injected Done Done Done Done Done Done
3 Voltage measured at 52 VDC 52 VDC 52 VDC 52 VDC 52 VDC 52 VDC
MDF side
4 Voltage measured at 45 VDC 45 VDC 45 VDC 45 VDC 45 VDC 45 VDC
field side
5 Simulation of 48 Done Done Done Done Done Done
VDC control
contatctor
6 Result of simulation Contactor Contactor Contactor Contactor Contactor Contactor
of 48 VDC control pick up pick up pick up pick up pick up pick up
contatctor found OK found OK found OK found OK found OK found OK
7 Simulation of 230 Done Done Done Done Done Done
VAC power
contatctor
8 Result of simulation Contactor Contactor Contactor Contactor Contactor Contactor
of 230 VAC control pick up pick up pick up pick up pick up pick up
contatctor found OK found OK found OK found OK found OK found OK
9 Reconnection of Done Done Done Done Done Done
power cable
10 Control circuir Done Done Done Done Done Done
normalization in field
side
TABLE 2
XVI) The cold permit no 00270 was extended up to 21:00 HRS on17/03/2011 at
16:50 HRS.
XVII) Process of migration to the new siren distribution system initiated as per
table 3.
Sl ADMIN
LOCATIONS
No ADMIN Building NRMT
CPP SS#4 LPG LG
Building Electronic MCC Room
siren
1 Identification of Done Done Done Done Done Done
outgoing pair cable
2 Krone Point 02B0901 02B0901 02A0406 02A0507 01D0203 01D0409
3 Colour of the outgoing Green/Red Orange/Red Blue/Red Orange/Red Black/Green Green/Red
cables
4 Tagging of the outgoing Done Done Done Done Done Done
cables
5 Voltage measurement -52VDC -52VDC -52VDC -52VDC -52VDC -52VDC
before disconnection
6 Voltage measurement 0V 0V 0V 0V 0V 0V
after disconnection of
the outgoing cables
7 Voltage measurement at 0V 0V 0V 0V 0V 0V
Krone point
8 Clamping of the Contactor Contactor Contactor Contactor Contactor Contactor
outgoing cables with the pick up pick up pick up pick up pick up pick up
cables of the new found OK found OK found OK found OK found OK found OK
system
9 Field side isolation done Done Done Done Done Done Done
10 Simulation of 48 VDC Done Done Done Done Done Done
control contatctor from
EPABX end
11 Result of simulation of Contactor Contactor Contactor Contactor Contactor Contactor
48 VDC control pick up pick up pick up pick up pick up pick up
contatctor found OK found OK found OK found OK found OK found OK
12 Reconnection Done Done Done Done Done Done
Sl NRMT
LOCATIONS FIRE &
No Control OIL SS#5 SS#2 ETP
SAFETY
Room
1 Identification of Done Done Done Done Done Done
outgoing pair cable
2 Krone Point 01C1008 02B0201 01A1010 01A0506 02A0910 01B0310
3 Colour of the outgoing Green/Yellow Blue/White Grey/ Blue/ Grey/Red Grey/Red
cables Yellow Red
4 Tagging of the outgoing Done Done Done Done Done Done
cables
5 Voltage measurement -52VDC -52VDC -52VDC -52VDC -52VDC -52VDC
before disconnection
6 Voltage measurement 0V 0V 0V 0V 0V 0V
after disconnection of
the outgoing cables
7 Voltage measurement at 0V 0V 0V 0V 0V 0V
Krone point
8 Clamping of the Contactor Contactor Contactor Contactor Contactor Contactor
outgoing cables with the pick up found pick up pick up pick up pick up pick up
cables of the new OK found OK found OK found OK found OK found OK
system
9 Field side isolation done Done Done Done Done Done Done
10 Simulation of 48 VDC Done Done Done Done Done Done
control contatctor from
EPABX end
11 Result of simulation of Contactor Contactor Contactor Contactor Contactor Contactor
48 VDC control pick up found pick up pick up pick up pick up pick up
contatctor OK found OK found OK found OK found OK found OK
12 Reconnection Done Done Done Done Done Done
TABLE 3
XVIII) Admin Building Electronic siren was manually checked from Fire &
Safety.
XIX) The whole system was functionality was checked on 18-03-2011 morning
during daily checking of sirens from Fire & Safety Deptt.
9. RECOMMENDATION/APPROVAL:
Signature of HOD
Name:
Designation: