Vous êtes sur la page 1sur 5

It Works!

Risk Management on an IS Project

Joseph A. Lukas, PMP, PE

Introduction turing facilities, upgrades to production equipment, new or reno-


vated office areas, and storage facilities.
Risk management is the process of identifying potential project The business case for the new CMS software was productivity sav-
risks, assessing the probability and severity of risk events, and plan- ings in managing the capital budget for the company. CMS re-
ning responses for the most important risk events. People tend to placed over ten obsolete systems in use at various plant sites. These
relate only negative events to the term risk. However, risk includes legacy systems were only accessible by a few administrative per-
all uncertainty on a project and includes both the positive (oppor- sonnel, did not interface with each other and used old software that
tunities) and negatives (threats). was no longer supported. In addition, the legacy systems did not
This paper describes the successful use of risk management on an provide online access to project information for most users and had
information systems (IS) project to create a new capital manage- very limited reporting capability.
ment system (CMS) for a Fortune 500 company. This IS project was The new CMS software provides about 200 data fields for each
done to create a new, customized intranet-based software package capital project including project description, justification category,
that will be used for managing the capital budget and expenditures business case data, budgets, actual costs, key schedule dates, proj-
for the company. The client sponsor’s most important project ob- ect team members, project status and project performance mea-
jective was completing the project within budget, followed by func- sures. Actual projects costs are uploaded from existing cost systems
tionality and then schedule. The presentation will describe how risk used at the various plant sites. The software also provides summary
management was a major part of the detailed project plan and level information that can be rolled up by business unit or plant site.
helped ensure project success. CMS includes standard reports that can be run by project, by busi-
This paper explains the specific risk identification technique used ness unit, plant site or rolled up for the entire company. The system
by the project team. Each project risk was described using a standard includes various levels of security to limit access to project data, and
sentence format describing the cause, risk event and consequence. provides the ability to search the database for multiple selected
The team then used qualitative risk analysis to better understand the criteria (such as for a specific justification category like capitalized
potential of each risk event. The scales used to assign a value for maintenance projects being planned for the next year).
probability and risk impact for each risk event will be reviewed. The resource plan for this IS project was contracting design and
Using these numbers, an expected value was calculated to determine programming to a software vendor. The project team was lead by
which risk events warranted specific risk response planning. an experienced IS project manager from the client company. The
The presentation will cover risk response planning, which was team also included the database manager and a few key users of the
done as part of the project plan. For all major risks, mitigation existing capital budget systems. Once the software contractor was
plans were prepared to reduce the likelihood of threats and to max- selected during project requirements definition, the team was ex-
imize the likelihood of opportunities. Contingency plans were also panded to include the contractor project manager and a lead tech-
prepared for the major risks. The spreadsheets developed on this nical consultant. Once the project was fully defined and approved,
project to document the risk processes used will be reviewed. The the contractor finalized the project price and added programmers
talk will conclude with a discussion on the use of risk monitoring to the project team. An experienced project management coach with
and control on the project. This included a status review of all risk an extensive background in the use of risk management and earned
events as part of the weekly project team meeting. The talk will pro- value assisted the team from project initiation to completion.
vide ideas on how to apply risk management to your projects!

The Risk Management Process


Project Background
Risk is a frequent occurrence in all aspects of our lives. People tend
This IS project provided a new customized intranet-based soft- to relate only negative events to the term risk. However, risk in-
ware package to manage the capital budget and expenditures for a cludes all uncertainty on a project, both the positive and the nega-
Fortune 500 company with multiple manufacturing plants around tive. Risk management is the process of identifying potential proj-
the world. Capital projects include things such as new manufac- ect risks, assessing the probability and severity of risk events, and

Proceedings of the Project Management Institute Annual Seminars & Symposium


October 3–10, 2002 • San Antonio,Texas, USA
Exhibit 1. Identified Risks on the CMS Project

Risk CAUSE RISK EVENT CONSEQUENCE


# due to <cause> <risk event> could occur resulting in <consequence>
The many job opportunities for top-
The loss of key project personnel Higher costs and a longer schedule
1 notch programmers
A time & material contract with the Cost increases due to
A higher project cost
2 software vendor underestimates
The database manager having
A lack of needed functionality with
multiple job assignments and a lack Missing key project requirements
the new system
3 of time for the CMS project
Increases in cost due to scope
Late changes in requirements A higher project cost
4 changes
A lack of space to support CMS on
Other systems projects underway The need to purchase a new server
5 existing servers
the obsolete legacy cost systems in The inability to automatically feed Extra manual work each month to
6 use at different plant sites actual cost data to CMS load actual cost data
The inconsistent use of data fields Extra manual work (and costs) to
The inability to automatically
with the existing capital budget move existing project data to the
transfer existing project data to CMS
7 systems new system
Poor data quality because of
System launch without the
A lack of training resources untrained users entering incomplete
necessary training materials
8 data

planning responses to the most important project risks. The goal of • Risk monitoring and control. Keeping track of major potential
risk management is to identify all project risks and develop strate- risks, implementing the risk response plan when risk events do
gies to maximize the effects of potential opportunities and signifi- occur, and watching for any new risks.
cantly reduce or eliminate the potential impact of threats.
Risk Identification
Companies that consistently excel in project delivery, typically
have a well-documented project process in use, which includes risk Risk identification involves information-gathering techniques that
management. An excellent reference on the project risk management determine which risks may affect the project and the characteris-
process is A Guide to the Project Management Body of Knowledge tics of each risk event. Risk characteristics include the possible fre-
(PMBOK® Guide), published by the Project Management Institute. quency of the risk event, the range of outcomes, the type of risk, im-
The material presented in this article is consistent with the pacts if the risk event occurs and symptoms of the risk event. Many
PMBOK® Guide, which describes the generally accepted project different techniques are available for identification of project risks.
management knowledge. However, generally accepted doesn’t These include the following:
mean that the knowledge and practices should be uniformly applied Brainstorming. The free flow of ideas used to generate a listing
on all projects. The project team is responsible for determining of potential risk events. The key to brainstorming is to not prejudge
the appropriate tools and techniques to apply on a project. For ex- any idea until after completion of the brainstorming session.
ample, the risk management plan for construction of a multibillion- Phrases to avoid during brainstorming include: “that can’t happen”
dollar chemical plant would be more extensive than the risk man- and “what a dumb idea.”
agement plan for a simple office renovation. The risk management Checklists. A listing of risk events typically encountered for a spe-
processes are as follows: cific type or class of projects. The project team reviews the check-
• Risk Management Planning. Deciding how to approach and plan list when starting a new project to identify specific risk events that
the risk management activities for the project. may occur. Checklists can be organized by project phase, major de-
• Risk identification. Determining which risks may affect the proj- liverables or by impacts to the project.
ect and understanding the characteristics of the risk events. Interviews. Discussions with project team members and other
• Risk analysis. Using qualitative and/or quantitative techniques stakeholders can help identify risks not identified during normal
to understand the probability and severity of each risk event, in planning activities. A good source of risk information is from peo-
order to prioritize the risk events based on impacts to the project ple who have done similar projects in the past.
objectives. Flowcharting. Diagramming techniques displaying how various
• Risk response planning. Determining actions that the project elements of a project are related. This illustrates how risk events and
team can take for each major risk event, in order to maximize any causes relate to create potential risk impacts and help the team
opportunities and minimize threats to the project objectives. better understand causes and effects of risks.

Proceedings of the Project Management Institute Annual Seminars & Symposium


October 3–10, 2002 • San Antonio,Texas, USA
Identifying Risks on the CMS Project Exhibit 2. Risk Probability Scale Used by the CMS
Team to Determine for Each Project Risk the Level of
To help the CMS project team focus on risk events, a technique was Probability
used to describe each risk by listing the risk cause, risk event, and
consequence. This technique was introduced in an excellent article Probability Description
titled “Project Risks, Identifying Causes, Risks and Effects” by David
Hillson, PMP. This article was published in the September 2000 1.0 Certain to Occur
issue of PM Network.
A common error during risk identification is not differentiating 0.8 Highly Likely
between risk causes, risk events, and consequences (also called im-
pacts or effects). This failure can dilute the risk identification 0.6 Likely
process by not providing focus on actual risk events. Risk events
have one unique feature, and that is uncertainty! 0.4 Low Likelihood
A risk cause is a definite event or circumstance that exists. For ex-
ample, purchasing a special piece of equipment from a foreign 0.2 Very Unlikely
supplier would be a risk cause if the only alternative were buying
the equipment from the foreign supplier due to patents. The risk 0.0 No Probability of Occurring
event could be exchange rate fluctuations or poor communica-
tions due to language barriers.
The consequences are the results that will occur if the risk event For the CMS project, the team decided on a simple probability
happens. For the example above, if the exchange rate does fluctu- scale as detailed in Exhibit 2.
ate, it will have an impact on the project cost. Keep in mind this im- Impact (Consequences) Scale
pact could be favorable! If the foreign currency drops relative to the
U.S. dollar, this becomes an opportunity for the project team. Basically, there are only four possible consequences to any risk event
A good technique to use when doing risk identification is to ex- on any project. They are cost, schedule, quality and/or functional-
press each project risk as a sentence covering the cause, risk event, ity impacts. In this definition, quality can cover a variety of miscel-
and consequence. A suggested format is: “Due to <cause>, <risk laneous impacts, including how well the product works and safety.
event> could occur, resulting in <consequence>” On any project, it is vital for the project team to understand what is
An example would be “Due to purchase of the equipment from an most important to the client. This is essential knowledge so the
overseas vendor, exchange rate fluctuations could occur, resulting in a team can accurately access the impact of any risk event on the proj-
cost impact to the project budget.”Another example would be “Due to ect. For example, if schedule is not critical to the client, then a risk
sharing a senior programmer between two projects, a work overload event with a schedule impact would have a lower impact rating.
could occur, resulting in a schedule delay on one or both projects.” On the CMS project money was limited, so the most critical im-
The CMS project team used this technique to identify potential pact was cost. The team needed to complete the project within or
risk events. A brainstorming session was held with the entire team, below the allocated budget. Functionality and quality were second
and a listing of risk events was developed. Then the team used the in importance, since it was necessary to provide the data fields and
risk cause, risk event, and consequence technique to fully describe information needed by Project Managers and management. Also,
each risk. For example, in Exhibit 1 Risk #3 reads: “Due to the the system had to be user friendly to ensure it was accepted and
database manager having multiple jobs, missing key project re- used. Schedule was the least important driver. The desire was to im-
quirements could occur, resulting in a lack of needed functionality plement CMS in January 2002 since that was the time period of
with the new system.” Risk #1 reads: “Due to the many job oppor- lowest system use. However, a delay was not a significant problem
tunities for top-notch programmers, the loss of key project per- since the legacy systems could continue to be used until the new sys-
sonnel could occur, resulting in higher costs and a longer schedule.” tem got up and running.
In order to keep the Exhibit 1 to a reasonable size, not all identified For the CMS project, the team used a simple consequence (im-
risks on the CMS project are listed. pact) scale as detailed in Exhibit 3. The highest impact value is
chosen if any of the criteria is met for that value. For example, if the
risk event had a very high cost impact, the impact value was a 10
Qualitative Risk Analysis on the CMS Project even if there were no functionality, quality or schedule issues.
Calculating Expected Value for Each Risk
Once the risk identification process was completed, the project
team used a qualitative risk analysis process to understand the like- Each identified risk event on the CMS project was assigned a proba-
lihood (probability) and consequence (severity or impact) of each bility and impact value using the Exhibits 2 and 3. An expected value
risk event. This was done to identify those risks that required risk was then calculated for each risk event using the following formula:
response planning. The technique the team used is from the Expected Value (EV) = Probability x Impact Rating
PMBOK® Guide, and also from an excellent article titled “Qualita-
tive Risk Assessment” by Roger Graves. This article was published Expected value provides a scale to assess the importance of each
in the October 2000 issue of PM Network. risk event relative to other risk events. Using the probability and

Proceedings of the Project Management Institute Annual Seminars & Symposium


October 3–10, 2002 • San Antonio,Texas, USA
Exhibit 3. Project Impact Scale Used on the CMS Project Shows That Schedule Was not a Major Project Driver

Impact
Value Cost Schedule Functionality Quality
10 very high impact - major issue major issue
8 high impact - medium issue medium issue
6 medium impact major impact minor issue minor issue
4 low impact medium impact very small issue very small issue
2 - low impact - -
0 - - - -

Exhibit 4.The CMS Project Risks Expected Values Helped Team Members Focus on the Most Important Risks

Risk RISK EVENT Probability Impact Expected


# (0 - 1.0) (0 - 10) Value
1 The loss of key project personnel 0.4 10.0 4.0
Cost increases due to
2 underestimates 0.5 8.0 4.0
3 Missing key project requirements 0.9 10.0 9.0
Increases in cost due to scope
4 changes 0.2 9.0 1.8
A lack of space to support CMS on
5 existing servers 0.7 9.0 6.3
The inability to automatically
transfer existing project data to CMS
6 0.6 9.0 5.4
The inability to automatically feed
7 actual cost data to PIMS 0.5 10.0 5.0
System launch without the
8 necessary training materials 0.8 7.0 5.6

impact scales defined by the CMS project team, the maximum ex- Transference is shifting the risk event impact to a third party
pected value a risk event could have is 10 (1.0 probability x 10 impact). along with ownership of the risk response. Transferring the risk
The CMS project team decided that risk events with an expected simply gives another party responsibility for the risk but the risk
value over 5.0 warranted specific risk response planning, and risk isn’t eliminated. Transference is most effective in dealing with fi-
events below 5.0 deserved watching, but not necessarily specific action. nancial risk exposure. However, risk transfer almost always in-
Exhibit 4 shows the assigned probability, impact and expected value volves payment of a risk premium to the party taking on the risk.
for each risk event on the CMS project. For simplicity, not all identi- Examples of transference include insurance, warranties and fixed
fied risk events on the CMS project are shown in Exhibit 4. price contracts.
Mitigation is reducing the expected value of a risk event by re-
ducing the probability of occurrence and/or the risk event value. It
Risk Response Planning looks to change conditions so that the probability of the risk event
occurring is reduced.
Risk response planning is the process of developing plans and ac- An example of mitigation to prevent missing a schedule com-
tions to respond to specific risk events. The effectiveness of risk re- pletion date is adding more resources. Mitigation also looks to re-
sponse planning will greatly influence how much the risk level de- duce the risk impact. An example of this is airplanes that have re-
creases as the project continues. The risk response techniques com- dundant hydraulic systems to greatly reduce the impact of a failure
monly used are described below. of any one hydraulic system.
Avoidance is changing the project plan to eliminate either the risk Acceptance as a risk response technique is where the project
event or the impact. However, keep in mind that the project team team has decided not to change the project plan to deal with the
can never eliminate all risk events! An example of avoidance is risk—or more likely, is unable to identify any other suitable re-
adopting a familiar approach instead of a new and untried innov- sponse strategy. Acceptance can be either passive or active. The ac-
ative approach. Another example of avoidance is selecting a site for tive acceptance response is developing a contingency plan in case the
a new shopping mall in a town with a friendly town planning board risk event occurs. An example of active acceptance is developing an
where quick approval of building plans occur. alternative schedule plan to deal with late delivery of key equipment.

Proceedings of the Project Management Institute Annual Seminars & Symposium


October 3–10, 2002 • San Antonio,Texas, USA
Exhibit 5. Sample Mitigation and Contingency Plans on the CMS Project

Risk RISK EVENT Probability Impact Expected Mitigation Plan Contingency Plan
# (0 - 1.0) (0 - 10) Value

* Include in the resource plan a


detailed estimate of activities and * If problem persists for more than 2
Missing key project
hours needed by key resources weeks, elevate issue to project
requirements
* Get management commitment to sponsors
dedicate key personnel to this project
3 0.9 10.0 9.0
A lack of space to support CMS * Get commitment from systems * Include $25k in project budget for
5 on existing servers 0.7 9.0 6.3 support for space required server
System launch without the * Get management commitment to * Investigate vendor training
necessary training materials dedicate key personnel to this project companies to prepare materials
8 0.8 7.0 5.6

The passive acceptance response would be doing nothing until the Conclusion
risk event occurs.
Risk Response Planning on the CMS Project Successful project teams include risk management as part of their
project plan. The probability of success on any project is much
Exhibit 5 shows the risk planning worksheet used by the CMS proj- higher when the project team follows a structured risk management
ect team for some representative risk events. Exhibit 5 only shows process. On the Capital Management System (CMS) IS project,
a few representative examples from the CMS project. use of risk management helped ensure successful completion of the
Mitigation was the biggest response technique used by the CMS project.
team, and this technique looks to reduce the expected value of the
risk event by reducing either or both the probability and impact. It References
makes sense that if a risk has high likelihood of occurring, the Graves, Roger. 2000. Qualitative Risk Assessment. PM Network (Octo-
team won’t just sit idle, but will try to intervene to reduce the prob- ber), pp. 61–66.
ability of the risk event. Likewise, if the consequences of the risk Hillson, David. 2000. Project Risks—Identifying Causes, Risks, and Ef-
event are high, the team will look for methods to reduce the impact. fects. PM Network (September): pp. 48–51.
In addition to mitigation planning, the project team also considered Lukas, Joseph. 1995. Managing Risks on Capital Projects. AACE Trans-
contingency plans in case the risk event did occur. This allows a actions.
team to quickly respond to any risk event that does occur. The Lukas, Joseph. 2001. Manage Project Risks with Success. Inside Project
spreadsheet in Exhibit 5 includes columns for mitigation and con- Management (November), pp. 1–5.
McKim, Robert. 1992. Risk Management—Back to Basics. Cost Engi-
tingency plans, along with columns for responsible person and sta-
neering (December), pp. 7–12.
tus. The project team reviewed the risk spreadsheet at the weekly
Project Management Institute Standards Committee. 2000. A Guide to
team meetings. the Project Management Body of Knowledge. PMBOK® Guide. 2000 Edition.
Newtown Square, PA: Project Management Institute.
Risk Response Monitoring and Control Royer, Paul. 2000. Risk Management: The Undiscovered Dimension of
Project Management. PM Network (September), pp. 31–39.
Note that probability and impact are not fixed during the project
life! As the project team implements actions to mitigate risk prob-
abilities and impacts, the associated values should drop. This means
the expected value should also decrease, reducing the overall risk
level on the project.
For example, in Exhibit 5, Risk Event #3 (missing key project re-
quirements) has a high probability and impact. The high probability
(0.9) resulted from the database manager holding multiple jobs. The
mitigation plan was getting management commitment to dedicate
the database manager to the CMS project and finding another per-
son to pick up her other job responsibilities. Once this happened,
the probability dropped from 0.9 down to 0.4. In addition, once the
project requirements were totally defined, the impact dropped
from 10 down to 4. This means the expected value of Risk Event #3
dropped from 9.0 down to 1.6, which is a very low risk event value.
This is the goal of the project team—to reduce the expected value
of risks and to increase the expected value of opportunities.

Proceedings of the Project Management Institute Annual Seminars & Symposium

Previous Menu
October 3–10, 2002 • San Antonio,Texas, USA

Vous aimerez peut-être aussi