ISKAN CONTRACTING Co.

LLC
Shuttering for soffits of Dome

Mosque at Bausher 14th April 2011

Sr. No. Description Unit Qty Rate Amount

Formwork for Semicircular Dome of Diameter 6.1 metres 6.1

Surface area 0.5 3.14 9.3025 58.4197

MATERIALS

1 Main support for dome shuttering comprise of 18 mm


plywood cut into arc shape and joined together by
50 x 50mm white wood pieces and covered by two layers
of 4mm plywood
3.14 6.1 19.154
Perimeter of dome = 3.14 x 6.1 = 19.154 say 20m. Say 20.000

If 400mm spacing is kept between main runners


No of pieces of runners = 20/0.4 = 50 20.000 0.4 50.000

Length of each piece = 12.6m say 12.3m considering congetion


at apex

Considering 2.4m length of plywood,5.5 pieces will be


required to cover 1 length of the runner

Total plywood pieces reqd.= 50 x 5.5 = 275 Nos. 50.000 5.500 275.000

2 No.of 18mm thick plywood ( 5 pieces /ply ) of width 240mm

275/5.5 = 92 Nos. say 65 Nos.


No 55 10.500 577.500

3 Miranti wood frame work 50 x 100 at 400 x 400 c/c

Perimeter of dome = 20 m 20.000


Height covered
1m 3.14 5.6 17.584 140.672
2m 3.14 5.1 16.014 128.112
3m 4.14 4.6 19.044 152.352
4m 5.14 4.1 21.074 168.592
Total length 589.728
850.000

Total length 400 m


Say 400 x 0.05 x 0.1 x 35.29 = 123.5 cft. C ft. 14.99825 8.000 119.986

Miscellaneous timber 200.000


Cover at the appex 100.000

3 Two layers of 4mm thick ply for bottom

101/2.88 x 2 = 70 Nos No 45.8193725 2.800 128.294

4 Nails & screws Item 60.000

5 Nut bolts
101/0.4x0.4 = 631 No 400.91951 1.000 400.920

6 Labour

Workshop 4C x 10 days Manday 45.8193725 15.000 687.291

Site 8C x 110 days Manday 68.7290588 15.000 1,030.936

Removal 6C x 5days Manday 34.3645294 15.000 515.468

7 Machines

2MC x 5 days x 10Hr MC Hr 57.2742157 3.000 171.823

8 Transportation Item 100.000

9 RMD scaffolding & support work M2 57.8469578 15.000 867.704

10 Crane for liftind Item 1,000.000

Total for 58.4197 m2 5,959.921

5,959.921
Rate/m2 102.019
Say 103.000

ISKAN CONTRACTING Co. LLC


Shuttering for soffits of Dome

Mosque at Bausher 14th April 2011

Sr. No. Description Unit Qty Rate Amount

Formwork for Semicircular Dome of Diameter 6.1 metres 6

Surface area 0.5 3.14 9 56.52

MATERIALS
1 Main support for dome shuttering comprise of 18 mm
plywood cut into arc shape and joined together by
50 x 50mm white wood pieces and covered by two layers
of 4mm plywood
3.14 6 18.840
Perimeter of dome = 3.14 x 6.1 = 19.154 say 20m. Say 19.000

If 400mm spacing is kept between main runners


No of pieces of runners = 20/0.4 = 50 19.000 0.4 47.500

Length of each piece = 12.6m say 12.3m considering congetion


at apex

Considering 2.4m length of plywood,5.5 pieces will be


required to cover 1 length of the runner

Total plywood pieces reqd.= 50 x 5.5 = 275 Nos. 47.500 5.500 261.250

2 No.of 18mm thick plywood ( 5 pieces /ply ) of width 240mm

275/5.5 = 92 Nos. say 65 Nos.


No 52.25 10.500 548.625

3 Miranti wood frame work 50 x 100 at 400 x 400 c/c

Perimeter of dome = 20 m 19.000


Height covered
1m 3.14 5.5 17.270 138.160
2m 3.14 5 15.700 125.600

Total length 263.760


140.000

Total length 400 m


Say 400 x 0.05 x 0.1 x 35.29 = 123.5 cft. C ft. 2.4703 8.000 19.762

Miscellaneous timber 200.000

Cover at the appex 100.000

3 Two layers of 4mm thick ply for bottom

101/2.88 x 2 = 70 Nos No 44.3294118 2.800 124.122

4 Nails & screws Item 60.000

5 Nut bolts
101/0.4x0.4 = 631 No 387.882353 1.000 387.882

6 Labour

Workshop 4C x 10 days Manday 44.3294118 15.000 664.941


Site 8C x 110 days Manday 66.4941176 15.000 997.412

Removal 6C x 5days Manday 33.2470588 15.000 498.706

7 Machines

2MC x 5 days x 10Hr MC Hr 55.4117647 3.000 166.235

8 Transportation Item 100.000

9 RMD scaffolding & support work M2 55.9658824 15.000 839.488

10 Crane for liftind Item 500.000

Total for 56.52 m2 5,207.174

5,207.174
Rate/m2 92.130
Say 93.000
ISKAN CONTRACTING Co. LLC
Shuttering for soffits of Dome

NATIONAL DEFENCE COLLEGE - BAF Rev.18TH October -09

Sr. No. Description Unit Qty Rate Amount

Formwork for Semicircular Dome of Diameter 8 metres

Surface area 0.5 3.14 64 100.48

MATERIALS

1 Main support for dome shuttering comprise of 18 mm


plywood cut into arc shape and joined together by
50 x 50mm white wood pieces and covered by two layers
of 4mm plywood

Perimeter of dome = 3.14 x 8 = 25.12 say 26m.

If 400mm spacing is kept between main runners


No of pieces of runners = 26/0.4 = 65

Length of each piece = 12.6m say 12.3m considering congetion


at apex

Considering 2.4m length of plywood,5.5 pieces will be


required to cover 1 length of the runner

Total plywood pieces reqd.= 65 x 5.5 = 358 Nos.

2 No.of 18mm thick plywood ( 5 pieces /ply ) of width 240mm

358/5.5 = 92 Nos. say 65 Nos. No 65 10.500 682.500

3 Miranti wood frame work 50 x 100 at 400 x 400 c/c

Perimeter of dome 25.5m.


Height covered
23.5 x 8 -- 3.14 x 7.5 1m
20.5 x 8 -- 3.14 x 6.5 2m
27.5 x 8 -- 3.14 x 5.5 3m
14.3 x 6 -- 3.14 x 4.5 4m

Total length 658 m


Say 700 x 0.05 x 0.1 x 35.29 = 123.5 cft. C ft. 130 8.000 1,040.000

Miscellaneous timber 200.000

Cover at the appex 100.000


3 Two layers of 4mm thick ply for bottom

101/2.88 x 2 = 70 Nos No 80 2.800 224.000

4 Nails & screws Item 60.000

5 Nut bolts
101/0.4x0.4 = 631 No 700 1.000 700.000

6 Labour

Workshop 4C x 10 days Manday 80 15.000 1,200.000

Site 8C x 110 days Manday 120 15.000 1,800.000

Removal 6C x 5days Manday 60 15.000 900.000

7 Machines

2MC x 5 days x 10Hr MC Hr 100 3.000 300.000

8 Transportation Item 100.000

9 RMD scaffolding & support work M2 101 15.000 1,515.000

10 Crane for liftind Item 1,000.000

Total for 100.48 m2 9,139.000

9,139.000
Rate/m2 90.953
Say 91.000